Bitdeer Announces November 2024 Production and Operations Update
Bitdeer Technologies Group (NASDAQ: BTDR) released its November 2024 operations update, highlighting significant expansion plans. The company expects to achieve ~35 EH/s of SEALMINER A2 mass production through Q3 2025, up from 18 EH/s. An initial allocation of ~30,000 units (~7 EH/s) has been fully reserved by customers.
Key operational metrics include 150 self-mined Bitcoins and a total hash rate under management of 20.7 EH/s. The company closed a US$400 million convertible note offering to accelerate SEALMINER development. Infrastructure developments include 1.1 GW of new power capacity scheduled for 2025, with major projects in Norway, Texas, Ohio, and Bhutan progressing.
Bitdeer Technologies Group (NASDAQ: BTDR) ha pubblicato il suo aggiornamento operativo di novembre 2024, evidenziando importanti piani di espansione. L'azienda prevede di raggiungere circa 35 EH/s di produzione di massa con SEALMINER A2 entro il terzo trimestre del 2025, rispetto ai 18 EH/s attuali. Un'allocazione iniziale di circa 30.000 unità (circa 7 EH/s) è stata completamente riservata dai clienti.
I principali indicatori operativi includono 150 Bitcoin auto-minati e un tasso di hash totale sotto gestione di 20,7 EH/s. L'azienda ha chiuso un'offerta di nota convertibile da 400 milioni di dollari per accelerare lo sviluppo di SEALMINER. Gli sviluppi infrastrutturali includono 1,1 GW di nuova capacità energetica prevista per il 2025, con progetti significativi in Norvegia, Texas, Ohio e Bhutan in fase di avanzamento.
Bitdeer Technologies Group (NASDAQ: BTDR) publicó su actualización de operaciones de noviembre de 2024, destacando planes de expansión significativos. La empresa espera alcanzar aproximadamente 35 EH/s de producción masiva del SEALMINER A2 para el tercer trimestre de 2025, un aumento desde los 18 EH/s actuales. Una asignación inicial de aproximadamente 30,000 unidades (aproximadamente 7 EH/s) ha sido completamente reservada por los clientes.
Los principales indicadores operativos incluyen 150 Bitcoins auto-minados y una tasa de hash total bajo gestión de 20.7 EH/s. La empresa cerró una oferta de notas convertibles de 400 millones de dólares para acelerar el desarrollo de SEALMINER. Los desarrollos de infraestructura incluyen 1.1 GW de nueva capacidad de energía programada para 2025, con importantes proyectos en Noruega, Texas, Ohio y Bután en progreso.
Bitdeer Technologies Group (NASDAQ: BTDR)는 2024년 11월 운영 업데이트를 발표하며 중요한 확장 계획을 강조했습니다. 회사는 2025년 3분기까지 SEALMINER A2의 대량 생산을 통해 약 35 EH/s를 달성할 것으로 예상하며, 이는 현재의 18 EH/s에서 증가한 수치입니다. 약 30,000대(약 7 EH/s)의 초기 할당량이 고객에 의해 완전히 예약되었습니다.
주요 운영 지표에는 150개의 자산굴착 비트코인과 관리자 하시레이트 총 계수인 20.7 EH/s가 포함됩니다. 회사는 SEALMINER 개발을 가속화하기 위해 4억 달러의 전환사채 발행을 완료했습니다. 인프라 개발에는 2025년을 목표로 하는 1.1GW의 새로운 전력 용량이 포함되어 있으며, 노르웨이, 텍사스, 오하이오 및 부탄에서 주요 프로젝트가 진행되고 있습니다.
Bitdeer Technologies Group (NASDAQ: BTDR) a publié sa mise à jour opérationnelle de novembre 2024, mettant en avant d'importants plans d'expansion. L'entreprise s'attend à atteindre environ 35 EH/s de production de masse avec le SEALMINER A2 d'ici le troisième trimestre 2025, en hausse par rapport à 18 EH/s. Une allocation initiale d'environ 30 000 unités (environ 7 EH/s) a été entièrement réservée par des clients.
Les principaux indicateurs opérationnels comprennent 150 Bitcoins minés par soi-même et un taux de hachage total sous gestion de 20,7 EH/s. L'entreprise a clôturé une offre de billets convertibles de 400 millions de dollars pour accélérer le développement du SEALMINER. Les développements d'infrastructure incluent 1,1 GW de nouvelle capacité énergétique prévue pour 2025, avec des projets majeurs en Norvège, au Texas, en Ohio et au Bhoutan en cours.
Bitdeer Technologies Group (NASDAQ: BTDR) hat sein Betriebsupdate für November 2024 veröffentlicht und dabei bedeutende Expansionspläne hervorgehoben. Das Unternehmen erwartet, bis zum dritten Quartal 2025 etwa 35 EH/s an Massenproduktion des SEALMINER A2 zu erreichen, ein Anstieg von 18 EH/s. Eine anfängliche Zuteilung von etwa 30.000 Einheiten (ca. 7 EH/s) wurde von Kunden vollständig reserviert.
Zu den wichtigsten betrieblichen Kennzahlen gehören 150 selbstgebaute Bitcoins und eine Gesamt-Hashrate unter Verwaltung von 20,7 EH/s. Das Unternehmen hat ein Angebot von wandelbaren Anleihen in Höhe von 400 Millionen US-Dollar abgeschlossen, um die Entwicklung von SEALMINER zu beschleunigen. Zu den Infrastrukturentwicklungen gehören 1,1 GW neuer Leistungsfähigkeit, die für 2025 geplant sind, mit wichtigen Projekten in Norwegen, Texas, Ohio und Bhutan, die fortschreiten.
- Secured increased SEALMINER A2 production capacity from 18 EH/s to 35 EH/s
- Initial allocation of ~30,000 SEALMINER A2 units fully reserved by customers
- Successfully closed US$400 million convertible note offering
- Total hash rate under management increased to 20.7 EH/s from 18.0 EH/s in October
- Bitcoin holdings increased to 344 from 337 in October
- Monthly Bitcoin production decreased to 150 from 174 in October
- Tydal, Norway Phase 1 expansion facing delays due to regulatory approval issues
- Rockdale, Texas cooling system installation delayed by one month due to dock workers strike
Insights
This operational update reveals significant expansion and strategic positioning in the crypto mining sector. Key highlights include: secured wafer capacity for 35 EH/s of SEALMINER A2 production (up from 18 EH/s), full reservation of initial 30,000 units for external sale and successful closing of a
Monthly performance metrics show relative stability in proprietary hash rate at 8.8 EH/s and moderate Bitcoin production of 150 BTC. The expansion of hosting services by 2.6 EH/s indicates strong market demand. The diversification into AI cloud services with NVIDIA H200 deployment and geographical expansion demonstrates strategic adaptation to emerging tech trends.
The company's infrastructure development strategy is comprehensive and well-distributed geographically. The Rockdale facility's hydro-cooling conversion, though slightly delayed, represents technological advancement in cooling efficiency. The Bhutan facility (500 MW) and Norway expansion (175 MW) demonstrate strategic positioning in regions with favorable power costs. The total pipeline capacity of 1,645 MW represents significant growth potential.
Notable is the diversification of power sources and locations, reducing geographical and regulatory risks. The planned expansion across multiple sites indicates careful capacity scaling, with attention to power infrastructure and cooling solutions. The integration of AI capabilities in datacenters shows forward-thinking infrastructure planning beyond just crypto mining.
- Anticipated ~35 EH/s of SEALMINER A2 Mass Production through Q3 2025
- 1.1 GW of New Power Capacity On Track to Come Online in 2025
- Closed US
SINGAPORE, Dec. 05, 2024 (GLOBE NEWSWIRE) -- Bitdeer Technologies Group (NASDAQ: BTDR) (“Bitdeer” or the “Company”), a world-leading technology company for blockchain and high-performance computing, today announced its unaudited mining and operations updates for November 2024.
Operational Update
- Self-mined Bitcoin: 150 Bitcoins.
- Mining Rig Manufacturing and R&D:
- SEALMINER A1: Mass production of approximately 3.7 EH/s of mining rigs is on track with 0.1 EH/s powered on, 0.4 EH/s delivered for installation, 0.3 EH/s in-transit to data centers and 2.6 EH/s in production.
- SEALMINER A2:
- Secured wafer capacity as of this report date is expected to generate approximately 35 EH/s hashrate in 2025, increased from 18 EH/s.
- Initial allocation of ~30,000 units (~7 EH/s out of the 35 EH/s) of SEALMINER A2s for external sale has been fully reserved by customers. This allocation is subject to further increase depending on market conditions.
- HPC/AI:
- Discussions are ongoing with multiple development partners and potential end users for selected sites.
- Bitdeer AI cloud services deployed an early batch of NVIDIA H200 in the Company’s Tier 3 datacenter.
- Expanded AI cloud services to United States and Holland. AI cloud services are now hosted from Singapore, Canada, United States and Holland.
- Hosting:
- Client-hosted machines increased by 11,000 units or 2.6 EH/s.
- Infrastructure:
- Tydal, Norway, 40 MW phase 1 expansion was expected to be ready for use by December 2024. Energization pending regulatory approval.
- Rockdale, Texas, USA, 100MW hydro-cooling conversion is on track for phased completion during Q1 2025.
- Jigmeling, Bhutan, 500 MW construction is on track with the primary substation expected to be completed by Q1 2025.
- 1.1 GW of new power capacity is on track to come online in 2025.
Management Commentary
“2025 is going to be a transformative year for Bitdeer,” stated Linghui Kong, Chief Business Officer of Bitdeer. “The launch of our SEALMINER A2 last month has generated tremendous interest. Our initial plan of selling ~30,000 units to external customers has been fully reserved by customers, signaling the industry’s strong demand for cutting-edge technology and a diversified supply chain. Further, at the end of November, we increased our SEALMINER A2 production through Q3 2025 to 35 EH/s, up from 18 EH/s, based on the secured wafer capacity, significantly increasing our ability to ramp our self-mining hashrate and sales inventory.”
Mr. Kong continued, “Further, we are extremely pleased with the closing of our US
Production and Operations Summary
Metrics | Nov 2024 | Oct 2024 | Nov 2023 |
Total hash rate under management1 (EH/s) | 20.7 | 18.0 | 21.1 |
- Proprietary hash rate | 8.8 | 8.7 | 8.7 |
• Self-mining | 8.2 | 8.4 | 7.1 |
• Cloud Hash Rate | 0.2 | 0.3 | 1.6 |
• Delivered but not hashing | 0.4 | - | - |
- Hosting | 11.9 | 9.3 | 12.4 |
Mining machines under management | 178,000 | 168,000 | 220,000 |
- Self-owned2 | 86,000 | 87,000 | 92,000 |
- Hosted | 92,000 | 81,000 | 128,000 |
Bitcoins mined (self-mining only) | 150 | 174 | 403 |
Bitcoins held3 | 443 | 372 | 28 |
1 Total hash rate under management as of November 30, 2024 across the Company’s three primary business lines: Self-mining, Cloud Hash Rate, and Hosting.
- Self-mining refers to cryptocurrency mining for the Company’s own account, which allows it to directly capture the high appreciation potential of cryptocurrency.
- Cloud Hash Rate offers hash rate subscription plans and shares mining income with customers under certain arrangements. The Cloud Hash Rate stated above reflects the contracted hash rate with customers at month-end. However, throughout the month, the Cloud Hash Rate may transition to Self-mining hash rate if customers opt to not make their monthly electricity payments for various reasons.
- Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services for efficient cryptocurrency mining.
2 Self-owned mining machines are for the Company’s self-mining business and Cloud Hash Rate business.
3 Bitcoins held do not include the Bitcoins from deposits of the customers.
Infrastructure Construction Update
Rockdale, Texas - 100 MW Hydro-cooling conversion underway:
- Demolition work completed.
- Cooling system will be delivered and installed in phases from Q4 2024 to Q1 2025.
- Due to supply chain delays from the US dock workers strike in early October, the expected phased energization timeline is expected to occur one month later, now between January and March 2025.
Tydal, Norway - 175 MW site expansion is progressing well, with several key milestones achieved:
- Buildings and groundwork completed, along with the construction of the transformer foundation and housing.
- Orders for transformer and electrical equipment have been placed, with delivery and installation currently in progress. Additionally, the procurement and delivery of containers and hydro-cooling systems are underway, and drainage systems construction is ongoing.
- Construction of the substation completed.
- Tydal, Norway Phase 1 of 40 MW Expansion had been expected to be ready for use by December 2024 but could be delayed for a few months due to regulatory approval application issues, which are now under close monitoring of the management team. Energization of the full 175 MW site is reasonably expected to be no later than mid-2025.
Massillon, Ohio - 221 MW site is also making progress:
- Substation conceptual design is completed and long lead-time electrical equipment for the substation have been ordered.
- Engineering, Procurement, and Construction (EPC) contractor has been selected for the substation construction.
- Civil work is ongoing, with the majority expected to be completed by the end of Q4 2024 or Q1 2025.
- Building design is completed, and construction is anticipated to begin in Q4 2024, earlier than expected.
- Estimated energization timeline remains on track for mid-to-late 2025.
Jigmeling, Bhutan - 500MW site is progressing well, with the following key milestones achieved:
- Civil work is finished. Construction of transformer and container foundations is in progress and will be completed in phases, with the last phase expected by the end of February 2025.
- 132kv/140MW and 220kv/360MW substation designs are completed with construction anticipated to be ready by the end of Q1 2025.
- Orders for the procurement of transformers and electrical equipment have been placed, with delivery and installation work to be completed in phases over the next two quarters.
- Procurement and delivery of containers and hydro-cooling systems are in progress, with completion in phases by the end of Q1 2025.
Site / Location | Capacity (MW) | Status | Timing4 |
Electrical capacity | |||
- Rockdale, Texas | 563 | Online | Completed |
- Knoxville, Tennessee | 86 | Online | Completed |
- Wenatchee, Washington | 13 | Online | Completed |
- Molde, Norway | 84 | Online | Completed |
- Tydal, Norway | 50 | Online | Completed |
- Gedu, Bhutan | 100 | Online | Completed |
Total electrical capacity | 8955 | ||
Pipeline capacity | |||
- Tydal, Norway Phase 1 | 40 | In progress | Pending Regulatory Approval |
- Tydal, Norway Phase 2 | 135 | In progress | Mid 2025 |
- Massillon, Ohio | 221 | In progress | Mid-to-late 2025 |
- Clarington, Ohio Phase 1 | 266 | In progress | Q3 2025 |
- Clarington, Ohio Phase 2 | 304 | Pending approval | Estimate 2026 |
- Jigmeling, Bhutan | 500 | In progress | Mid-to-late 2025 |
- Rockdale, Texas | 179 | In planning | Estimate 2026 |
Total pipeline capacity | 1,645 | ||
Total global electrical capacity | 2,540 | ||
4 Indicative timing. All timing references are to calendar quarters and years.
5 Figures may not add up due to rounding.
Upcoming Conferences and Events
- December 4, 2024: B. Riley Crypto & Energy Infrastructure Conference in New York City
- January 14-17, 2025: 27th Annual Needham Growth Conference
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company for blockchain and high-performance computing. Bitdeer is committed to providing comprehensive computing solutions for its customers. The Company handles complex processes involved in computing such as equipment procurement, transport logistics, datacenter design and construction, equipment management, and daily operations. The Company also offers advanced cloud capabilities to customers with high demand for artificial intelligence. Headquartered in Singapore, Bitdeer has deployed datacenters in the United States, Norway, and Bhutan. To learn more, visit https://ir.bitdeer.com/ or follow Bitdeer on X @ BitdeerOfficial and LinkedIn @ Bitdeer Group.
Investors and others should note that Bitdeer may announce material information using its website and/or on its accounts on social media platforms, including X, formerly known as Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages investors and others to review the information it posts on the social media and other communication channels listed on its website.
Forward-Looking Statements
Statements in this press release about future expectations, plans, and prospects, as well as any other statements regarding matters that are not historical facts, may constitute “forward-looking statements” within the meaning of The Private Securities Litigation Reform Act of 1995. The words “anticipate,” “look forward to,” “believe,” “continue,” “could,” “estimate,” “expect,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “should,” “target,” “will,” “would” and similar expressions are intended to identify forward-looking statements, although not all forward-looking statements contain these identifying words. Actual results may differ materially from those indicated by such forward-looking statements as a result of various important factors, including factors discussed in the section entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as well as discussions of potential risks, uncertainties, and other important factors in Bitdeer’s subsequent filings with the U.S. Securities and Exchange Commission. Any forward-looking statements contained in this press release speak only as of the date hereof. Bitdeer specifically disclaims any obligation to update any forward-looking statement, whether due to new information, future events, or otherwise. Readers should not rely upon the information on this page as current or accurate after its publication date.
For investor and media inquiries, please contact:
Investor Relations
Orange Group
Yujia Zhai
bitdeerIR@orangegroupadvisors.com
Public Relations
BlocksBridge Consulting
Nishant Sharma
bitdeer@blocksbridge.com
FAQ
What is Bitdeer's (BTDR) expected SEALMINER A2 production capacity through Q3 2025?
How many Bitcoins did Bitdeer (BTDR) mine in November 2024?
What was the size of Bitdeer's (BTDR) convertible note offering in November 2024?