STOCK TITAN

Bitdeer Announces March 2025 Production and Operations Update

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Very Positive)
Tags

Bitdeer Technologies Group (NASDAQ: BTDR) reported significant operational progress in March 2025. The company completed mass production of 3.8 EH/s SEALMINER A1 mining rigs, with 2.8 EH/s already energized, increasing self-mining hashrate to 11.5 EH/s.

Key developments include:

  • Self-mined 114 Bitcoins in March 2025
  • Launched SEALMINER A2 Pro series with 14.9 J/TH efficiency
  • Obtained regulatory approval for Tydal, Norway site (175 MW)
  • Signed agreement for 50 MW mining datacenter in Ethiopia for $7.5 million
  • Total hash rate under management reached 24.2 EH/s
  • Bitcoin holdings increased to 1,156

The company's infrastructure expansion continues with multiple sites under development, including projects in Bhutan (500 MW), Ohio (525 MW), and Norway (175 MW). Bitdeer also retained Northland Capital Markets as financial advisor for its HPC/AI data center development strategy.

Bitdeer Technologies Group (NASDAQ: BTDR) ha riportato progressi operativi significativi a marzo 2025. L'azienda ha completato la produzione di massa di 3.8 EH/s dei minatori SEALMINER A1, con 2.8 EH/s già attivi, aumentando il tasso di hash self-mining a 11.5 EH/s.

Sviluppi chiave includono:

  • 114 Bitcoin auto-minati a marzo 2025
  • Lancio della serie SEALMINER A2 Pro con efficienza di 14.9 J/TH
  • Ottenuta l'approvazione normativa per il sito di Tydal, in Norvegia (175 MW)
  • Firmato un accordo per un datacenter minerario da 50 MW in Etiopia per 7.5 milioni di dollari
  • Il tasso di hash totale sotto gestione ha raggiunto i 24.2 EH/s
  • Le riserve di Bitcoin sono aumentate a 1,156

L'espansione delle infrastrutture dell'azienda continua con più siti in fase di sviluppo, inclusi progetti in Bhutan (500 MW), Ohio (525 MW) e Norvegia (175 MW). Bitdeer ha anche mantenuto Northland Capital Markets come consulente finanziario per la sua strategia di sviluppo di centri dati HPC/AI.

Bitdeer Technologies Group (NASDAQ: BTDR) reportó avances operativos significativos en marzo de 2025. La compañía completó la producción en masa de 3.8 EH/s de los equipos de minería SEALMINER A1, con 2.8 EH/s ya energizados, aumentando la tasa de hash de auto-minado a 11.5 EH/s.

Los desarrollos clave incluyen:

  • 114 Bitcoins auto-minados en marzo de 2025
  • Lanzamiento de la serie SEALMINER A2 Pro con eficiencia de 14.9 J/TH
  • Obtención de aprobación regulatoria para el sitio de Tydal, Noruega (175 MW)
  • Firma de un acuerdo para un centro de datos de minería de 50 MW en Etiopía por 7.5 millones de dólares
  • La tasa total de hash bajo gestión alcanzó 24.2 EH/s
  • Las reservas de Bitcoin aumentaron a 1,156

La expansión de la infraestructura de la empresa continúa con múltiples sitios en desarrollo, incluidos proyectos en Bután (500 MW), Ohio (525 MW) y Noruega (175 MW). Bitdeer también retuvo a Northland Capital Markets como asesor financiero para su estrategia de desarrollo de centros de datos HPC/AI.

Bitdeer Technologies Group (NASDAQ: BTDR)는 2025년 3월에 중요한 운영 진전을 보고했습니다. 이 회사는 3.8 EH/s의 SEALMINER A1 채굴 장비의 대량 생산을 완료했으며, 2.8 EH/s가 이미 가동 중으로, 자가 채굴 해시레이트를 11.5 EH/s로 증가시켰습니다.

주요 개발 사항은 다음과 같습니다:

  • 2025년 3월에 114 비트코인을 자가 채굴
  • 14.9 J/TH 효율성을 가진 SEALMINER A2 Pro 시리즈 출시
  • 노르웨이 타이달 사이트(175 MW)에 대한 규제 승인 획득
  • 에티오피아에 50 MW 채굴 데이터 센터를 위해 750만 달러에 계약 체결
  • 관리 중인 총 해시레이트가 24.2 EH/s에 도달
  • 비트코인 보유량이 1,156으로 증가

회사의 인프라 확장은 부탄(500 MW), 오하이오(525 MW), 노르웨이(175 MW) 등 여러 개발 중인 사이트와 함께 계속되고 있습니다. Bitdeer는 또한 HPC/AI 데이터 센터 개발 전략을 위한 재무 고문으로 Northland Capital Markets를 유지했습니다.

Bitdeer Technologies Group (NASDAQ: BTDR) a signalé des progrès opérationnels significatifs en mars 2025. L'entreprise a achevé la production de masse de rigs de minage SEALMINER A1 à 3,8 EH/s, avec 2,8 EH/s déjà activés, augmentant le taux de hashage en auto-minage à 11,5 EH/s.

Les développements clés incluent:

  • 114 Bitcoins auto-minés en mars 2025
  • Lancement de la série SEALMINER A2 Pro avec une efficacité de 14,9 J/TH
  • Obtention de l'approbation réglementaire pour le site de Tydal, en Norvège (175 MW)
  • Signature d'un accord pour un centre de données de minage de 50 MW en Éthiopie pour 7,5 millions de dollars
  • Le taux de hash total sous gestion a atteint 24,2 EH/s
  • Les avoirs en Bitcoin ont augmenté à 1 156

L'expansion des infrastructures de l'entreprise se poursuit avec plusieurs sites en développement, y compris des projets au Bhoutan (500 MW), dans l'Ohio (525 MW) et en Norvège (175 MW). Bitdeer a également retenu Northland Capital Markets comme conseiller financier pour sa stratégie de développement de centres de données HPC/AI.

Bitdeer Technologies Group (NASDAQ: BTDR) berichtete im März 2025 über bedeutende betriebliche Fortschritte. Das Unternehmen hat die Massenproduktion von 3,8 EH/s SEALMINER A1 Mining-Rigs abgeschlossen, wobei bereits 2,8 EH/s in Betrieb sind, wodurch die Self-Mining-Hashrate auf 11,5 EH/s gesteigert wurde.

Wichtige Entwicklungen umfassen:

  • Im März 2025 wurden 114 Bitcoins selbst geschürft
  • Einführung der SEALMINER A2 Pro-Serie mit einer Effizienz von 14,9 J/TH
  • Regulatorische Genehmigung für den Standort Tydal, Norwegen (175 MW) erhalten
  • Vertrag über ein 50 MW Mining-Datacenter in Äthiopien für 7,5 Millionen Dollar unterzeichnet
  • Die gesamte unter Verwaltung stehende Hashrate erreichte 24,2 EH/s
  • Die Bitcoin-Bestände erhöhten sich auf 1.156

Die Infrastrukturexpansion des Unternehmens geht mit mehreren in Entwicklung befindlichen Standorten weiter, darunter Projekte in Bhutan (500 MW), Ohio (525 MW) und Norwegen (175 MW). Bitdeer hat auch Northland Capital Markets als Finanzberater für seine HPC/AI-Datenzentrum-Entwicklungsstrategie beauftragt.

Positive
  • Completed mass production of 3.8 EH/s SEALMINER A1 rigs with 2.8 EH/s already energized
  • Total hash rate under management increased to 24.2 EH/s from 20.9 EH/s in February
  • Bitcoin holdings grew to 1,156 from 1,039 in February
  • Secured regulatory approval for 175 MW Tydal, Norway facility
  • SEALMINER A3 achieved improved efficiency of 9.7 J/TH at chip level
Negative
  • Paused SEALMINER A2 wafer capacity disclosures due to market uncertainty and slowdown in mining rig demand
  • Monthly Bitcoin production decreased significantly year-over-year (114 vs 294 in March 2024)
  • Hosting hashrate declined year-over-year from 14.1 EH/s to 12.1 EH/s

Insights

Bitdeer's March operational update demonstrates strong execution on multiple fronts that enhance the company's competitive positioning. The completion of mass production and energization of 2.8 EH/s of SEALMINER A1 rigs has immediately boosted self-mining capacity to 11.5 EH/s (up 28% from February), resulting in 114 Bitcoins mined. This operational expansion has allowed Bitdeer to increase Bitcoin holdings to 1,156, representing a meaningful treasury growth of 11.3% month-over-month.

The company's infrastructure development deserves particular attention. The regulatory approval for the 175 MW Tydal, Norway facility unlocks significant near-term capacity expansion with 70 MW ready for imminent energization. Combined with ongoing construction across global sites totaling 1,794 MW in pipeline capacity, Bitdeer is positioning itself as a major player in industrial-scale Bitcoin mining infrastructure. The $7.5 million acquisition in Ethiopia secures low-cost power at approximately $0.036/kWh with a 4-year PPA, potentially improving gross mining margins.

The technological roadmap shows progressive efficiency improvements from the current SEALMINER A2 Pro's 14.9 J/TH to the SEALMINER A3's 9.7 J/TH and the planned SEALMINER A4's 5 J/TH. These efficiency gains should significantly reduce operational costs per Bitcoin mined. The strategic engagement with Northland Capital Markets to develop the HPC/AI data center business represents a promising diversification strategy that leverages Bitdeer's core competencies in managing power-intensive computing infrastructure.

Bitdeer's operational metrics reveal compelling technical progress in both mining efficiency and hashrate expansion. The company's total hashrate under management reached 24.2 EH/s, representing a 15.8% increase from February and now comprising approximately 3% of Bitcoin's total network hashrate. The self-mining capacity increase to 11.5 EH/s positions Bitdeer among the top-tier public miners by proprietary hashrate.

The SEALMINER product line demonstrates an aggressive technology roadmap that follows the industry's efficiency curve. The newly launched A2 Pro series at 14.9 J/TH brings competitive efficiency to market, while the development progress on SEALMINER A3 (9.7 J/TH) and SEALMINER A4 (5 J/TH) indicates Bitdeer's commitment to maintaining technological leadership. These efficiency improvements directly translate to mining profitability, particularly important given the recent Bitcoin halving event.

Bitdeer's infrastructure strategy shows sophisticated geographical diversification across North America, Europe, and Asia. The 500 MW Bhutan facility and newly acquired 50 MW Ethiopia operation secure access to low-cost renewable power sources, a crucial competitive advantage in mining economics. The company's decision to pause SEALMINER A2 wafer capacity disclosures reflects pragmatic adjustment to current market conditions characterized by reduced mining rig demand. However, the continued sales of approximately 0.3 EH/s of SEALMINER A2 units to external customers in March demonstrates maintained demand for Bitdeer's hardware despite market headwinds.

-- Completed mass production of SEALMINER A1s and 2.8 EH/s energized
-- Regulatory approval for Tydal, Norway site finalized
-- Retained Northland Capital Markets (“Northland”) to act as financial advisor for its HPC/AI data center development strategy

SINGAPORE, April 09, 2025 (GLOBE NEWSWIRE) -- Bitdeer Technologies Group (NASDAQ: BTDR) (“Bitdeer” or the “Company”), a world-leading technology company for blockchain and high-performance computing, today announced its unaudited mining and operations updates for March 2025.

Operational Update

  • Self-mined Bitcoin: 114 Bitcoins.
  • Mining Rig Manufacturing and R&D:
    • SEALMINER A1:
      • Completed mass production of approximately 3.8 EH/s of mining rigs.
      • 2.8 EH/s are energized, 0.6 EH/s have been delivered for installation, 0.3 EH/s are in-transit to the Company’s datacenters, with remaining to be delivered in April.
    • SEALMINER A2:
      • Wafer capacity disclosures will be paused temporarily. This decision was the result of a comprehensive consideration for maximizing the Company’s shareholders’ value. These disclosures were previously provided to assist potential mining rig buyers in making informed decisions. However, due to the current market uncertainty and the significant slowdown in mining rig demand, disclosure of total capacity is not currently useful. The Company’s self-mining hashrate forecast increased slightly this month and Bitdeer remains confident that the previously predicted hashrate targets in the second half of 2025 are achievable, on schedule, and can potentially exceed the Company’s expectations.
      • 0.8 EH/s of mining rigs have been shipped to customers and the Company’s own datacenters for self-mining, 0.4 EH/s have been manufactured and are ready for shipment and 1 EH/s are being assembled.
      • Sales of SEALMINER A2 are ongoing, ~0.3 EH/s of miners have been shipped to customers in March.
      • Launched SEALMINER A2 Pro series on March 17, 2025, featuring air-cooling (SEALMINER A2 Pro Air) and hydro-cooling (SEALMINER A2 Pro Hyd) models with a power efficiency ratio of 14.9 J/TH. The SEALMINER A2 Pro Air delivers up to 270 TH/s, while the SEALMINER A2 Pro Hyd reaches 530 TH/s, both with advanced efficiency, stability, and noise reduction. SEALMINER A2 Pro will be another commercialized product that is currently open for external sales.
    • SEALMINER A3:
      • SEAL03 sample wafers achieved an energy efficiency of 9.7 J/TH at the chip level during chip verification and prototype testing while running at low voltage, ultra power-saving mode. More risk wafers will be delivered in April for further testing and mass production ready R&D.
    • SEALMINER A4:
      • SEAL04 R&D remains on track to achieve an expected chip efficiency of approximately 5 J/TH with anticipated initial tape-out in Q4 2025.
  • HPC/AI:
    • Bitdeer has now formalized an engagement with Northland Capital Markets (“Northland”) to act as financial advisor for its HPC/AI data center development strategy.  Northland will assist Bitdeer with existing negotiations with potential development partners and provide guidance regarding capital providers.
    • Discussions are ongoing with multiple development partners and potential end users for selected large scale sites in U.S. for HPC/AI clouding business.
    • GB200 NVL72 reservations open – deployment is on schedule for 2025.
  • Hosting:
    • Client-hosted mining rigs increased by 3,000 units or 0.6 EH/s in March 2025, due to existing customers increasing hosted mining rigs.
  • Infrastructure:
    • Tydal, Norway: Regulatory approval has been obtained, with 70 MW set for energization and commissioning in early April and the remaining 105 MW scheduled for completion by mid-2025.
    • Rockdale, Texas, USA: 1.4 EH/s of SEALMINER A1 hydro mining rigs have been energized into 100 MW hydro-cooling conversion.
    • Clarington Phase 2, Ohio, USA: 304 MW land lease agreement signed and negotiating with regional utility.
    • Jigmeling, Bhutan: All electrical equipment has been delivered and is being installed, with completion and energization in Q2 2025 on track (see Infrastructure Construction Update section below for further details).
    • Oromia Region, Ethiopia: In early April, Bitdeer signed an SPA and a turnkey agreement for the acquisition and construction of a 50 MW mining datacenter in Ethiopia for US$7.5 million, including a local company with a mining permit, a 33kV substation connection, and a 4-year Power Purchase Agreement (PPA) with Ethiopian Electric Power Company. The Company is collaborating with an EPC contractor with specialized experience in Bitcoin mining and targeting energization by Q4 2025.

Management Commentary

“We achieved significant operational progress in March,” stated Matt Kong, Chief Business Officer at Bitdeer. “First, we completed mass production of 3.8 EH/s our SEALMINER A1 mining rigs and energized 2.8 EH/s, increasing our self-mining hashrate to 11.5 EH/s at the end of March with the remaining to be installed and turned on in April. Second, we launched the SEALMINER A2 Pro series Bitcoin mining rigs, delivering an efficiency of 14.9 J/TH. Finally, we obtained regulatory approval for Phase 1 and 2 of our Tydal, Norway site and we expect to energize more than 600 MW of power capacity over the next few months, including our Bhutan site.”

Production and Operations Summary

MetricsMar 2025Feb 2025Mar 2024
Total hash rate under management1 (EH/s)24.220.922.5
- Proprietary hash rate12.19.48.4
• Self-mining11.59.06.7
• Cloud Hash Rate--1.7
• Delivered but not hashing0.60.40.0
- Hosting12.111.514.1
Mining rigs under management175,000163,000226,000
- Self-owned297,00088,00086,000
- Hosted78,00075,000140,000
Bitcoins mined (self-mining only)114110294
Bitcoin held31,1561,03958


1
Total hash rate under management as of March 31, 2025 across the Company’s primary business lines: Self-mining, Cloud Hash Rate, and Hosting.

  • Self-mining refers to cryptocurrency mining for the Company’s own account, which allows it to directly capture the high appreciation potential of cryptocurrency.
  • Cloud Hash Rate offers hash rate subscription plans and shares mining income with customers under certain arrangements. The Cloud Hash Rate stated above reflects the contracted hash rate with customers at month-end.
  • Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services for efficient cryptocurrency mining.

2 Self-owned mining machines are for the Company’s self-mining business and Cloud Hash Rate business.
3 Bitcoins held do not include the Bitcoins from deposits of the customers.

Infrastructure Construction Update

Rockdale, Texas – 100 MW Hydro-cooling conversion energization commenced:

  • All cooling system delivered and installed.
  • Approximately 1.4 EH/s of SEALMINER A1 hydro mining rigs have been energized.
  • Energization in accordance with the phase of delivery of mining rigs.

Tydal, Norway175 MW site expansion anticipated to be fully energized by mid-2025:

  • Regulatory approval has been obtained.
  • 70 MW will be ready for energization and commissioning in early April, with the remaining 105 MW to be commissioned by mid-2025.
  • Installation of the transformers has been completed, with the delivery and installation of electrical equipment currently in progress. Additionally, the procurement and delivery of containers and hydro-cooling systems are underway, and drainage systems construction is ongoing.

Massillon, Ohio – 221 MW site construction has begun ahead of schedule:

  • Substation construction is underway and is expected to be completed in Q3 2025.
  • Building design is completed and construction has begun earlier than expected, estimated to be completed in phases between Q3 and Q4 2025.
  • Estimated energization is expected to be completed in phases over Q3 and Q4 2025.

Clarington Phase 2, Ohio – 304 MW: Signed lease agreement with the landlord and negotiating with regional utility.

Jigmeling, Bhutan – 500 MW site is progressing well and is expected to be energized in phases beginning in April through June 2025:

  • All electrical equipment has been delivered and is currently being installed, with completion expected by Q2 2025.
  • The first main 132kV transformer has been powered on. The second main 132kV transformer is expected to be powered on in April 2025.
  • Construction of the 220kV substation is underway and is expected to be completed by Q2 2025.
  • Delivery of containers and hydro-cooling systems are in progress and is expected to be completed in phases by Q2 2025.

Fox Creek, Alberta – 101 MW site acquired in Alberta, sitting on 19 acres, is fully licensed and permitted:

  • Acquisition includes all permits and licenses to construct an on-site natural gas power plant, as well as approval for a 99 MW grid interconnection with Alberta Electric System Operator (“AESO”).
  • Bitdeer will develop and construct the power plant in partnership with a leading engineering, procurement and construction (“EPC”) company and is expected to be energized by Q4 2026.

Oromia Region, Ethiopia – Signed an SPA and a turnkey agreement for the acquisition and construction of a 50 MW Bitcoin mining project in Ethiopia for US$7.5 million:

  • Acquisition includes local Ethiopian company with a mining permit, connected to a neighboring transmission substation at 33kV interconnection.
  • This local Ethiopian company has signed a Power Purchase Agreement (PPA) with Ethiopian Electric Power Company for a duration of 4 years at an electricity price of approximately US$0.036/ kWh.
  • Bitdeer is working closely with an EPC contractor with specialized experience in Bitcoin mining and this mining project is expected to be energized in Q4 2025.
Site / LocationCapacity (MW)StatusTiming4
Electrical capacity   
- Rockdale, Texas563OnlineCompleted
- Knoxville, Tennessee86OnlineCompleted
- Wenatchee, Washington13OnlineCompleted
- Molde, Norway84OnlineCompleted
- Tydal, Norway50OnlineCompleted
- Gedu, Bhutan100OnlineCompleted
Total electrical capacity8955  
Pipeline capacity   
- Tydal, Norway Phase 170In progressApril 2025
- Tydal, Norway Phase 2105In progressMid 2025
- Massillon, Ohio221In progressQ3-Q4 2025
- Clarington, Ohio Phase 1266In progressQ3 2025
- Clarington, Ohio Phase 2304Pending approvalEstimate 2026
- Jigmeling, Bhutan500In progressQ2 2025
- Rockdale, Texas179In planningEstimate 2026
- Alberta, Canada99In planningQ4 2026
- Oromia Region, Ethiopia50In planningQ4 2025
Total pipeline capacity1,794  
Total global electrical capacity2,689  


4
Indicative timing. All timing references are to calendar quarters and years.
5 Figures may not add up due to rounding.

Upcoming Conferences and Events

  • April 8 – 9, 2025: Jones Healthcare and Technology Innovation Conference in Las Vegas, Nevada
  • April 16, 2025: Jefferies Power x Coin Virtual Conference
  • May 14 – 15, 2025: Macquarie Asia Conference 2025 in Hong Kong
  • May 19 – 20, 2025: Barclay 15th Annual Emerging Payments and Fintech Forum in New York City
  • May 20, 2025: Benchmark Virtual Digital Asset Seminar
  • May 21 – 22, 2025: B. Riley 25th Annual Investor Conference in Marina Del Rey, California
  • May 28, 2025: Orange Group & Blockware Sell-side and Buy-side Conference in Las Vegas, Nevada

About Bitdeer Technologies Group

Bitdeer is a world-leading technology company for Bitcoin mining. Bitdeer is committed to providing comprehensive Bitcoin mining solutions for its customers. The Company handles complex processes involved in computing such as equipment procurement, transport logistics, datacenter design and construction, equipment management, and daily operations. The Company also offers advanced cloud capabilities to customers with high demand for artificial intelligence. Headquartered in Singapore, Bitdeer has deployed datacenters in the United States, Norway, and Bhutan. To learn more, visit https://ir.bitdeer.com/ or follow Bitdeer on X @ BitdeerOfficial and LinkedIn @ Bitdeer Group.

Investors and others should note that Bitdeer may announce material information using its website and/or on its accounts on social media platforms, including X, formerly known as Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages investors and others to review the information it posts on the social media and other communication channels listed on its website.

Forward-Looking Statements

Statements in this press release about future expectations, plans, and prospects, as well as any other statements regarding matters that are not historical facts, may constitute “forward-looking statements” within the meaning of The Private Securities Litigation Reform Act of 1995. The words “anticipate,” “look forward to,” “believe,” “continue,” “could,” “estimate,” “expect,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “should,” “target,” “will,” “would” and similar expressions are intended to identify forward-looking statements, although not all forward-looking statements contain these identifying words. Actual results may differ materially from those indicated by such forward-looking statements as a result of various important factors, including factors discussed in the section entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as well as discussions of potential risks, uncertainties, and other important factors in Bitdeer’s subsequent filings with the U.S. Securities and Exchange Commission. Any forward-looking statements contained in this press release speak only as of the date hereof. Bitdeer specifically disclaims any obligation to update any forward-looking statement, whether due to new information, future events, or otherwise. Readers should not rely upon the information on this page as current or accurate after its publication date.

For investor and media inquiries, please contact:

Investor Relations
Orange Group
Yujia Zhai
bitdeerIR@orangegroupadvisors.com

Public Relations
BlocksBridge Consulting
Nishant Sharma
bitdeer@blocksbridge.com


FAQ

What was Bitdeer's (BTDR) Bitcoin production in March 2025?

Bitdeer self-mined 114 Bitcoins in March 2025, compared to 110 in February 2025.

How much hashrate does Bitdeer (BTDR) have under management as of March 2025?

Bitdeer managed 24.2 EH/s total hashrate, including 12.1 EH/s proprietary and 12.1 EH/s hosting hashrate.

What are the specifications of Bitdeer's new SEALMINER A2 Pro series?

The SEALMINER A2 Pro series features 14.9 J/TH efficiency, with Air model delivering 270 TH/s and Hydro model reaching 530 TH/s.

How many Bitcoins does Bitdeer (BTDR) hold as of March 2025?

Bitdeer held 1,156 Bitcoins as of March 2025, up from 1,039 in February 2025.

What is Bitdeer's (BTDR) total planned global electrical capacity?

Bitdeer's total global electrical capacity is 2,689 MW, including 895 MW current capacity and 1,794 MW pipeline capacity.
Bitdeer Technologies Group

NASDAQ:BTDR

BTDR Rankings

BTDR Latest News

BTDR Stock Data

1.51B
82.62M
40.77%
22.62%
8.77%
Software - Application
Technology
Link
Singapore
Singapore