Arizona Sonoran Cactus Project Standalone PEA Technical Report Reporting Post-Tax NPV8 of US$2.03 Billion and IRR of 24% is now Filed
Arizona Sonoran Copper Company (TSX:ASCU | OTCQX:ASCUF) has filed a technical report for its Cactus Project NI 43-101 Preliminary Economic Assessment (PEA). The PEA outlines a 31-year mine life with an average annual production of 86,000 short tons (172 million pounds) of copper through open pit heap leaching. Key highlights include:
- Post-tax NPV8 of US$2.03 billion
- Internal Rate of Return (IRR) of 24%
- Payback period of 4.9 years
- Initial capital investment of $668 million
- Life of Mine (LoM) Gross Revenue of $20.8 billion
- Cash costs (C1) of $1.82/lb and All-in Sustaining Costs (AISC) of $2.00/lb
The PEA supersedes the previous Pre-Feasibility Study and demonstrates the project's potential in various copper price environments.
Arizona Sonoran Copper Company (TSX:ASCU | OTCQX:ASCUF) ha presentato un rapporto tecnico per il suo Cactus Project NI 43-101 Valutazione Economica Preliminare (PEA). La PEA delinea una durata mineraria di 31 anni con una produzione annuale media di 86.000 tonnellate brevi (172 milioni di libbre) di rame attraverso il processo di lisciviazione in cumulo in miniera aperta. I principali punti salienti includono:
- Valore NPV8 post-tasse di 2,03 miliardi di dollari USA
- Tasso Interno di Rendimento (IRR) del 24%
- Periodo di ammortamento di 4,9 anni
- Investimento iniziale di 668 milioni di dollari
- Entrate lorde della vita mineraria (LoM) di 20,8 miliardi di dollari
- Costi in contante (C1) di 1,82 dollari/lb e Costi Totali Sostenibili (AISC) di 2,00 dollari/lb
La PEA sostituisce il precedente studio di prefattibilità e dimostra il potenziale del progetto in vari scenari di prezzo del rame.
Arizona Sonoran Copper Company (TSX:ASCU | OTCQX:ASCUF) ha presentado un informe técnico para su Cactus Project NI 43-101 Evaluación Económica Preliminar (PEA). La PEA describe una vida útil de mina de 31 años con una producción anual media de 86,000 toneladas cortas (172 millones de libras) de cobre a través de la lixiviación en pilas a cielo abierto. Los aspectos más destacados incluyen:
- NPV8 post-impuesto de 2.03 mil millones de dólares EE. UU.
- Tasa Interna de Retorno (TIR) de 24%
- Periodo de recuperación de 4.9 años
- Inversión de capital inicial de 668 millones de dólares
- Ingresos brutos de la vida útil de la mina (LoM) de 20.8 mil millones de dólares
- Costos de efectivo (C1) de 1.82 dólares/lb y Costos Totales de Sostenibilidad (AISC) de 2.00 dólares/lb
La PEA reemplaza el estudio de prefactibilidad anterior y demuestra el potencial del proyecto en diversos entornos de precios del cobre.
아리조나 소노란 구리 회사 (TSX:ASCU | OTCQX:ASCUF)가 그 하카투스 프로젝트 NI 43-101 초기 경제성 평가 (PEA)에 대한 기술 보고서를 제출했습니다. PEA는 31년의 광산 수명 및 연평균 86,000 단위 톤 (172백만 파운드)의 구리를 오픈 피트 힙 리칭을 통해 생산한다고 설명합니다. 주요 하이라이트는 다음과 같습니다:
- 세후 NPV8의 20억 3천만 달러
- 내부 수익률 (IRR) 24%
- 회수 기간 4.9년
- 초기 자본 투자 6억 6천8백만 달러
- 광산 생애 (LoM) 총 수익 208억 달러
- 현금 비용 (C1) 1.82 달러/파운드 및 모든 유지 비용 (AISC) 2.00 달러/파운드
PEA는 이전의 사전 타당성 연구를 대체하며 다양한 구리 가격 환경에서 프로젝트의 잠재력을 보여줍니다.
Arizona Sonoran Copper Company (TSX:ASCU | OTCQX:ASCUF) a déposé un rapport technique pour son Cactus Project NI 43-101 Évaluation Économique Préliminaire (PEA). La PEA décrit une durée de vie de mine de 31 ans avec une production annuelle moyenne de 86 000 tonnes courtes (172 millions de livres) de cuivre par lixiviation en tas à ciel ouvert. Les points saillants incluent :
- VAN8 après impôts de 2,03 milliards de dollars US
- Taux de Rendement Interne (TRI) de 24%
- Délai de récupération de 4,9 ans
- Investissement initial de 668 millions de dollars
- Revenus bruts de la vie de la mine (LoM) de 20,8 milliards de dollars
- Coûts en espèces (C1) de 1,82 USD/lb et Coûts totaux de maintien (AISC) de 2,00 USD/lb
La PEA remplace l'étude de préfaisabilité précédente et démontre le potentiel du projet dans divers environnements de prix du cuivre.
Die Arizona Sonoran Copper Company (TSX:ASCU | OTCQX:ASCUF) hat einen technischen Bericht für ihr Cactus Project NI 43-101 Vorläufige Wirtschaftlichkeitsanalyse (PEA) eingereicht. Die PEA beschreibt eine lebensdauer der Mine von 31 Jahren mit einer durchschnittlichen Jahresproduktion von 86.000 Kurztonnen (172 Millionen Pfund) Kupfer durch Tagebau-Haufenlixivierung. Zu den wichtigsten Punkten gehören:
- Nach-Steuer NPV8 von 2,03 Milliarden US-Dollar
- Interner Zinsfuß (IRR) von 24%
- Amortisationszeit von 4,9 Jahren
- Anfangsinvestition von 668 Millionen US-Dollar
- Bruttoerträge über die Lebensdauer der Mine (LoM) von 20,8 Milliarden US-Dollar
- Cash-Kosten (C1) von 1,82 USD/lb und All-in-Holding-Kosten (AISC) von 2,00 USD/lb
Die PEA ersetzt die vorherige Machbarkeitsstudie und zeigt das Potenzial des Projekts in verschiedenen Kupferpreisumgebungen.
- Post-tax NPV8 of US$2.03 billion and IRR of 24%, indicating strong project economics
- 31-year mine life with average annual production of 172 million pounds of copper
- Low production costs with C1 cash costs of $1.82/lb and AISC of $2.00/lb
- Life of Mine Gross Revenue of $20.8 billion and Free Cash Flow of $7.295 billion
- 94% of material from open pit mining, suggesting efficient extraction methods
- Initial capital investment of $668 million required for project development
- Payback period of 4.9 years, which may be considered long by some investors
- PEA includes inferred mineral resources, which are considered speculative and may not be economically viable
Highlights from the PEA:
-
Key Performance Indicators at
/lb Copper$3.90 -
Net Present Value (“NPV”) ($2,032 million 8% discount, after-tax) -
24% Internal rate of return (“IRR”, after-tax) - 4.9 years Payback Period
-
development capital including contingency$668 million
-
-
Life of Mine (“LoM”) Gross Revenue of
$20.8 billion -
LoM Free Cash Flow (“FCF”) of
(unlevered)$7,295 million -
Cash costs (C1) of
and All in Sustaining Costs (“AISC”) of$1.82 per pound of copper$2.00 -
Financial and operational executability now through transition to Open Pit operation
-
94% material from open pit mining (Cactus West and Parks/Salyer),6% from the Stockpile and Cactus East underground
-
- 232 million pounds (“lbs”) (116,052 short tons (“st”)) average annual copper cathode production over the first 20 years of operation and a total of 5,339 million lbs (2,669,342 st) of copper cathode produced over the 31-year operating mine life
- Cactus Project is well positioned to add value in a variety of copper price environments
The PEA is preliminary in nature, and it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the project described in the PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.
TABLES 1 and 2 below summarize the key metrics within the PEA and the sensitivities to the copper price, as it relates to revenue, NPV and IRR.
TABLE 1: SUMMARY OF KEY METRICS
Valuation Metrics (Unlevered) |
Unit |
2024 PEA
|
Net Present Value @ |
$ millions |
2,769 |
Net Present Value @ |
$ millions |
2,032 |
Internal Rate of Return (after-tax) |
% |
24.0 |
Payback Period (after-tax) |
# years |
4.9 |
Project Metrics (Imperial) |
Unit |
2024 PEA
|
Construction Period – SXEW plant |
# years |
1.5 - 2 |
Life of Mine |
# years |
31 |
Strip Ratio |
Waste : Feed |
2.3 : 1 |
LoM Mineralized Material Mined |
ktons |
889,004 |
LoM Copper Grade |
% CuT |
0.46 |
LoM Avg Annual Contained Copper Production |
000 tons millions lbs |
86 172 |
LoM Annual Crusher Throughput |
millions tons |
29 |
Annual Copper Production (years 1-20) |
000 tons millions lbs |
116 232 |
Recovery (years 1-20) |
%Cu TSol |
83 |
LoM Recoveries (LOM) |
% Cu TSol |
73 |
LoM Oxide |
% Cu TSol |
92 |
LoM Enriched |
% Cu TSol |
85 |
LoM Primary (conventional leaching) |
% CuT |
25 |
LoM Recovered Copper Cathodes |
K pounds |
5,338,683 |
Initial Capital (including contingency) |
$ millions |
668 |
Sustaining Capital |
$ millions |
1,169 |
Cash Cost (C1)* |
$/lb Cu |
1.82 |
All in Sustaining Cost (AISC)* |
$/lb Cu |
2.00 |
LoM Revenues |
$ millions |
20,821 |
LoM EBITDA |
$ millions |
11,292 |
LoM FCF (unlevered) after tax |
$ millions |
7,295 |
Notes: |
||
*Project operating costs include mine operating, process plant operating, and general and administrative costs (“G&A”). Total production costs include royalty expense. The AISC additionally includes initial Capex, sustaining Capex, reclamation & closure. |
TABLE 2: Report Sensitivities to the Copper Price
Revenue, NPV and IRR Sensitivity Based on Copper Price |
|||||
Metal Price |
Copper Price |
Revenue
( |
NPV, before tax @ |
NPV, after tax @ |
IRR after Tax |
Base Case |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
|
|
|
|
- |
|
|
|
|
|
Quality Assurance and Quality Control Procedures
Skyline Labs is accredited in accordance with the recognized International Standard ISO/IEC 17025:2005. Their quality management system has been certified as conforming to the requirements defined in the International Standard ISO 9001:2015. The standard operating procedure (SOP) used while processing the ASCU samples was to process samples in groups of 20. Each tray consisted of 18 samples with samples No. 1 and No. 10 repeated as duplicates. The results from each tray were analyzed and any variance in the duplicates of more than
The results of these analyses, including the QA/QC checks, were transmitted to a select set of individuals at ASCU and the qualified persons.
Qualified Persons
Each of the persons listed below are authors preparing the PEA and have reviewed and verified the contents of this news release as it relates to their area of responsibilities. By virtue of their education, experience and professional association membership, each of the below listed persons are considered “qualified person" as defined by NI 43-101.
Scientific and technical aspects of this news release have been reviewed and verified by these Qualified Persons listed below and Dan Johnson, ASCU Director of Projects, as defined by National Instrument 43-101.
Project Management, M3 Engineering, John Woodson, PE, SME-RM
Metallurgy, M3 Engineering, Laurie Tahija, QP-MMSA
Mineral Resources, Allan L. Schappert, CPG, SME-RM, ALS Geo Resources LLC
Water and Environmental, R. Douglas Bartlett, CPG, PG. Clear Creek Associates, a subsidiary of Geo-Logic Associates
Mine Planning, Gordon Zurowski, P.Eng., AGP Mining Consultants Inc.
Links from the Press Release:
August 7, 2024: https://arizonasonoran.com/news-releases/arizona-sonoran-standalone-pea-for-cactus-open-pit-project-reports-post-tax-npv8-of-us-2.03-billion-c-2.77-billion-and-irr-of/
SEDAR+: https://www.sedarplus.ca
About Arizona Sonoran Copper Company (www.arizonasonoran.com | www.cactusmine.com)
ASCU’s objective is to become a mid-tier copper producer with low operating costs and to develop the Cactus and Parks/Salyer Projects that could generate robust returns for investors and provide a long term sustainable and responsible operation for the community and all stakeholders. The Company's principal asset is a
Non-IFRS Financial Performance Measures
This news release contains certain non-IFRS measures, including sustaining capital, sustaining costs, EBITDA, C1 cash costs and AISC. The Company believes that these measures, together with measures determined in accordance with IFRS, provide investors with an improved ability to evaluate the underlying performance of the Company. Non-IFRS measures do not have any standardized meaning prescribed under IFRS, and therefore they may not be comparable to similar measures employed by other companies. The data is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.
Forward-Looking Statements
This news release contains “forward-looking statements” and/or “forward-looking information” (collectively, “forward-looking statements”) within the meaning of applicable securities legislation. All statements, other than statements of historical fact, are forward-looking statements. Generally, forward-looking statements can be identified by the use of forward-looking terminology such as “plans”, “expect”, “is expected”, “in order to”, “is focused on” (a future event), “estimates”, “intends”, “anticipates”, “believes” or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, or the negative connotation thereof. In particular, statements regarding ASCU’s future operations, future exploration and development activities or other development plans constitute forward-looking statements. By their nature, statements referring to mineral reserves or mineral resources constitute forward-looking statements. Forward-looking statements in this news release include, but are not limited to statements with respect to the results (if any) of further exploration work to define and expand or upgrade mineral resources and reserves at ASCU’s properties; the anticipated exploration, drilling, development, construction and other activities of ASCU and the result of such activities; the estimates and assumptions underlying the PEA; projected production; sensitivity of the Cactus Project to changes in copper prices; pre-tax and after-tax NPV; after-tax IRR; payback period; LOM estimates; free-cash flows estimates; AISC and cost estimates; expected revenues, EBITDA or recoveries; the ability of exploration work (including drilling) to accurately predict mineralization; the ability of management to understand the geology and potential of the Cactus Project; the focus of the current drilling program at the Cactus Project including the Parks/Salyer deposit and MainSpring property; the impact of transition to open pit operations; the ability to generate additional drill targets; the ability of ASCU to complete its exploration objectives in 2024 in the timing contemplated (if at all); the timing and scope of any future technical reports and studies conducted by ASCU; the ability to realize upon mineralization in a manner that is economic; the impact of bringing the MainSpring property into the mine plan; the ability and timing of ASCU to commence operations (if at all); the robust economics and opportunity represented by the Cactus Project; the expected impact of the Cactus Project on the local economy and stakeholders; and its operations and any other information herein that is not a historical fact.
ASCU considers its assumptions to be reasonable based on information currently available but cautions the reader that their assumptions regarding future events, many of which are beyond the control of the Company, may ultimately prove to be incorrect since they are subject to risks and uncertainties that affect ASCU, its properties and business. Such risks and uncertainties include, but not limited to, the global economic climate, developments in world commodity markets, changes in commodity prices (particularly prices of copper), risks relating to fluctuations in the Canadian dollar and other currencies relative to the US dollar, risks relating to capital market conditions and ASCU’s ability to access capital on terms acceptable to ASCU for the contemplated exploration and development at the Company’s properties, changes in exploration, development or mining plans due to exploration results and changing budget priorities of ASCU or its joint venture partners, the effects of competition in the markets in which ASCU operates, results of further exploration work, the ability to continue exploration and development at ASCU’s properties, errors in geological modelling, changes in any of the assumptions underlying the PEA, the ability to expand operations or complete further exploration activities, the ability to obtain regulatory approvals, the impact of changes in the laws and regulations regulating mining exploration, development, closure, judicial or regulatory judgments and legal proceedings, operational and infrastructure risks and the additional risks described in ASCU’s most recently filed Annual Information Form, annual and interim management’s discussion and analysis, copies of which are available on SEDAR+ (www.sedarplus.ca) under ASCU’s issuer profile. ASCU’s anticipation of and success in managing the foregoing risks could cause actual results to differ materially from what is anticipated in such forward-looking statements.
Although management considers the assumptions contained in forward-looking statements to be reasonable based on information currently available to it based on information available at the date of preparation, those assumptions may prove to be incorrect. There can be no assurance that these forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements and are urged to carefully consider the foregoing factors as well as other uncertainties and risks outlined in ASCU’s public disclosure record.
ASCU disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by law.
View source version on businesswire.com: https://www.businesswire.com/news/home/20240827889941/en/
Alison Dwoskin, Director, Investor Relations
647-233-4348
adwoskin@arizonasonoran.com
George Ogilvie, President, CEO and Director
416-723-0458
gogilvie@arizonasonoran.com
Source: Arizona Sonoran Copper Company Inc.
FAQ
What is the expected annual copper production for the Cactus Project according to the PEA?
What is the estimated Net Present Value (NPV) and Internal Rate of Return (IRR) for ASCUF's Cactus Project?
How much initial capital is required for the Cactus Project development?