ARIS MINING INCREASES SEGOVIA GOLD MINERAL RESERVES BY +75% TO 1.3 MOZ AND ANNOUNCES PLANT EXPANSION TO INCREASE PRODUCTION RATE
- None.
- None.
Neil Woodyer, CEO of Aris Mining, commented "We are pleased to announce a
Based on the increased mineral resource and reserve estimates, we are implementing a small-scope project to increase the processing capacity by
Segovia Operations – Maria Dama processing plant expansion
The capacity of the Maria Dama processing plant is currently 2,000 tpd following an expansion project from 1,500 tpd completed in 2022. The plant includes crushing, grinding, gravity concentration, gold flotation and regrind, cyanidation, Merrill-Crowe precipitation, and smelting of the precipitate and gravity concentrate to produce gold-silver doré.
The current project to expand to 3,000 tpd includes a previously purchased ball mill which is already onsite and the re-location and upgrade of the facilities that receive material from our artisanal and small-scale mining partners. The costs for construction are estimated at
Segovia Operations – mineral reserve estimates
Table 1 summarizes the 2023 Mineral Reserve effective September 30, 2023, a comparison to the 2022 Mineral Reserve effective December 31, 2022, and several years of previous mineral reserve estimates.
Effective date | Proven | Probable | Proven & Probable | ||||||
Tonnes | Grade Au | Oz Au | Tonnes | Grade Au | Oz Au | Tonnes | Grade Au | Oz Au | |
(kt) | (g/t) | (koz) | (kt) | (g/t) | (koz) | (kt) | (g/t) | (koz) | |
2023 Mineral Reserve 2022 Mineral Reserve | 1,515 229 | 12.25 10.92 | 597 81 | 2,017 2,132 | 11.16 9.84 | 723 675 | 3,531 2,361 | 11.63 9.95 | 1,320 755 |
Change 2023 to 2022 | +17 % | +565 + | |||||||
31-Dec-2021 | 204 | 12.00 | 78.6 | 2,087 | 9.93 | 666.1 | 2,290 | 10.11 | 744.7 |
31-Dec-2020 | 187 | 13.86 | 83 | 2,009 | 8.51 | 550 | 2,196 | 8.96 | 633 |
31-Dec-2019 | 165 | 16.53 | 88 | 1,820 | 9.96 | 583 | 1,985 | 10.50 | 670 |
31-Dec-2018 | 79 | 11.72 | 30 | 1,862 | 10.99 | 658 | 1,941 | 11.02 | 688 |
31-Dec-2017 | 46 | 45.44 | 68 | 1,613 | 11.42 | 592 | 1,660 | 12.37 | 660 |
Notes:
2023 Mineral Reserve Notes:
Previous Reserve Notes:
|
The significant increase in the 2023 mineral reserve estimate as compared to 2022 is primarily the result of the increase in the measured and indicated mineral resource estimate effective September 30, 2023, as described in the news release of November 2, 2023.
The Segovia Operations' current operating profile within the mineral reserve zones includes owner mining at a rate of 1,050 tpd and partner mining at a rate of 350 tpd. The shallowly dipping, 1.2 m wide veins are first mined by Aris Mining employees using room and pillar and long wall methods to extract around
Aris Mining will file an updated NI 43-101 compliant technical report in support of the 2023 Mineral Reserve and mineral resource estimates for the Segovia Operations on or before December 17, 2023.
Technical Disclosure and Qualified Person
The technical information in this news release was reviewed and approved by Pamela De Mark, P.Geo, Senior Vice President, Geology and Exploration of Aris Mining, who is a Qualified Person as defined by NI 43-101. Ms. De Mark has verified the sampling, analytical, and test data as well as the geological interpretation underlying the information or opinions disclosed in this news release. Ms. De Mark has fully verified the sampling, analytical, and test data as well as the geological interpretation underlying the information or opinions disclosed in this news release by way of analysis of the data and the geological interpretations while preparing the mineral resource estimate and reviewing the mineral reserve estimate.
Unless otherwise indicated, the mineral reserve estimates, scientific disclosure, and technical information included in this news release are based upon information included in the following documents and NI 43-101 compliant technical reports:
- for the mineral reserve estimate effective December 31, 2017, the technical report entitled "NI 43-101 Technical Report, Prefeasibility Study, Segovia Project,
Colombia " dated May 10, 2018 and prepared by SRK Consulting (US), Inc. (SRK); - for the mineral reserve estimate effective December 31, 2018, the technical report entitled "Amended NI 43-101 Technical Report, Prefeasibility Study Update, Segovia Project,
Colombia " dated July 8, 2019 and prepared by SRK; - for the mineral reserve estimate effective December 31, 2019, the technical report entitled "NI 43-101 Technical Report, Prefeasibility Study Update, Segovia Project,
Colombia " dated May 14, 2020 and effective as of December 31, 2019 and prepared by SRK; - for the mineral reserve estimate effective December 31, 2020, the technical report entitled "NI 43-101 Technical Report, Prefeasibility Study Update, Segovia Project, Department of Antioquia,
Colombia " dated May 13, 2021 and effective as of December 31, 2020 and prepared by SRK; - for the mineral reserve estimate effective December 31, 2021, the technical report entitled "NI 43-101 Technical Report, Prefeasibility Study, Segovia Project, Antioquia,
Colombia " dated May 6, 2022 and effective as of December 31, 2021 and prepared by SRK; and - for the mineral resource estimate effective December 31, 2022, the mineral reserve estimates of the Segovia Operations is summarized, derived, or extracted from the news release of the Company dated March 3, 2023.
All of the documents referenced in this news release are available for review on the Company's website at www.aris-mining.com and on the Company's profile on SEDAR+ at www.sedarplus.ca
About Aris Mining
Aris Mining is a gold producer in the
Aris Mining promotes the formalization of artisanal and small-scale mining as this process enables all miners to operate in a legal, safe and responsible manner that protects them and the environment.
Additional information on Aris Mining can be found at www.aris-mining.com, www.sedarplus.ca, and on www.sec.gov.
Forward-Looking Information
This news release contains "forward-looking information" or forward-looking statements" within the meaning of Canadian and
View original content to download multimedia:https://www.prnewswire.com/news-releases/aris-mining-increases-segovia-gold-mineral-reserves-by-75-to-1-3-moz-and-announces-plant-expansion-to-increase-production-rate-301997469.html
SOURCE Aris Mining Corporation
FAQ
What is the company name and ticker symbol of the corporation announcing the updated mineral reserve estimates for its Segovia Operations in Colombia?
When are the updated mineral reserve estimates for the Segovia Operations in Colombia effective?
What is the expected completion timeline and estimated cost of increasing the capacity of the Maria Dama processing plant within the Segovia Operations?
What is the percentage increase in high-grade mineral reserves at the Segovia Operations?