ALLIED GOLD ANNOUNCES THIRD QUARTER 2024 RESULTS: IMPLEMENTING OPERATIONAL IMPROVEMENTS, SECURING KEY REGULATORY APPROVALS, ADVANCING DEVELOPMENT AT KURMUK AND SADIOLA, AND STRENGTHENING FINANCIAL FLEXIBILITY THROUGH STRATEGIC INITIATIVES
Allied Gold reported Q3 2024 production of 85,147 ounces, consistent with previous quarters. Year-to-date production reached 258,459 ounces, nearly 10,000 ounces higher than 2023. The company expects Q4 production of 98,000-102,000 ounces, projecting full-year production of 360,000-367,000 ounces. Q3 financial results showed a net loss of $108.0 million, while adjusted net earnings were $50.6 million. The company secured key regulatory approvals in Mali, including permit renewals for Sadiola mine and Korali-Sud property. The Kurmuk Gold Project continues to advance with $47.6 million invested year-to-date, remaining on track despite revised 2024 capital expenditure estimates of $100 million.
Allied Gold ha riportato una produzione di 85.147 once nel terzo trimestre del 2024, in linea con i trimestri precedenti. La produzione dall'inizio dell'anno ha raggiunto 258.459 once, quasi 10.000 once in più rispetto al 2023. L'azienda prevede una produzione per il quarto trimestre tra 98.000 e 102.000 once, proiettando una produzione annuale di 360.000-367.000 once. I risultati finanziari del terzo trimestre hanno mostrato una perdita netta di 108,0 milioni di dollari, mentre gli utili netti rettificati ammontano a 50,6 milioni di dollari. L'azienda ha ottenuto approvazioni regolatorie chiave in Mali, comprese le rinnovo dei permessi per la miniera di Sadiola e la proprietà di Korali-Sud. Il Progetto Aurifero Kurmuk continua a progredire con 47,6 milioni di dollari investiti dall'inizio dell'anno, mantenendosi in linea nonostante le stime riviste delle spese in conto capitale del 2024 di 100 milioni di dollari.
Allied Gold reportó una producción de 85.147 onzas en el tercer trimestre de 2024, consistente con trimestres anteriores. La producción acumulada hasta la fecha alcanzó las 258.459 onzas, casi 10.000 onzas más que en 2023. La compañía espera una producción para el cuarto trimestre de entre 98.000 y 102.000 onzas, proyectando una producción anual de 360.000-367.000 onzas. Los resultados financieros del tercer trimestre mostraron una pérdida neta de 108,0 millones de dólares, mientras que las ganancias netas ajustadas fueron de 50,6 millones de dólares. La empresa obtuvo importantes aprobaciones regulatorias en Malí, incluyendo la renovación de permisos para la mina de Sadiola y la propiedad de Korali-Sud. El Proyecto de Oro Kurmuk sigue avanzando con 47,6 millones de dólares invertidos hasta la fecha, manteniéndose en camino a pesar de las revisiones en las estimaciones de gastos de capital para 2024 de 100 millones de dólares.
Allied Gold는 2024년 3분기 생산량이 85,147온스로 이전 분기들과 일치한다고 보고했습니다. 연간 생산량은 258,459온스로 2023년보다 거의 10,000온스 더 많습니다. 회사는 4분기 생산량을 98,000-102,000온스로 예상하며, 연간 생산량을 360,000-367,000온스로 예측하고 있습니다. 3분기 재무 결과는 1억 8백만 달러의 순손실을 보였고, 조정된 순이익은 5,060만 달러였습니다. 회사는 말리에서 사디올라 광산과 코랄리-수드 부지의 허가 갱신을 포함한 주요 규제 승인을 확보했습니다. 쿰룩 금 프로젝트는 연초까지 4,760만 달러가 투자되며 순조롭게 진행되고 있으며, 2024년 자본 지출 추정치가 1억 달러로 수정되었음에도 불구하고 계획대로 진행되고 있습니다.
Allied Gold a rapporté une production de 85.147 onces au troisième trimestre 2024, constante par rapport aux trimestres précédents. La production depuis le début de l'année a atteint 258.459 onces, soit près de 10.000 onces de plus qu'en 2023. La société s'attend à une production au quatrième trimestre de 98.000 à 102.000 onces, projetant une production annuelle de 360.000 à 367.000 onces. Les résultats financiers du troisième trimestre ont montré une perte nette de 108,0 millions de dollars, tandis que les bénéfices nets ajustés étaient de 50,6 millions de dollars. L'entreprise a obtenu des approbations réglementaires clés au Mali, notamment des renouvellements de permis pour la mine de Sadiola et la propriété de Korali-Sud. Le Projet d'Or Kurmuk continue de progresser avec 47,6 millions de dollars investis jusqu'à présent, restant sur la bonne voie malgré les révisions des estimations de dépenses en capital de 100 millions de dollars pour 2024.
Allied Gold berichtete von einer Produktion von 85.147 Unzen im dritten Quartal 2024, was mit den vorherigen Quartalen übereinstimmt. Die bis dato erreichte Produktion betrug 258.459 Unzen, fast 10.000 Unzen mehr als im Jahr 2023. Das Unternehmen erwartet im vierten Quartal eine Produktion von 98.000-102.000 Unzen und prognostiziert eine Jahresproduktion von 360.000-367.000 Unzen. Die finanziellen Ergebnisse des dritten Quartals zeigten einen Nettoverlust von 108,0 Millionen Dollar, während der bereinigte Nettogewinn 50,6 Millionen Dollar betrug. Das Unternehmen hat wichtige aufsichtsrechtliche Genehmigungen in Mali erhalten, darunter die Genehmigungsverlängerungen für die Mine Sadiola und das Grundstück Korali-Sud. Das Kurmuk Gold Projekt schreitet mit einer Investition von 47,6 Millionen Dollar seit Jahresbeginn voran, bleibt trotz überarbeiteter Kostenschätzungen für 2024 in Höhe von 100 Millionen Dollar auf Kurs.
- Year-to-date gold production increased by 4% to 258,459 ounces compared to 2023
- Strong Q4 production guidance of 98,000-102,000 ounces
- Adjusted EBITDA of $52.1 million showing significant increase from prior year
- Operating cash flow before tax and working capital reached $87.2 million
- Secured C$221 million through public offering and $53 million gold streaming agreement
- Q3 net loss of $108.0 million ($0.43 per share)
- Higher AISC costs expected by approximately $200 per oz above previous guidance
- Reduced 2024 Kurmuk capital expenditure from $155M to $100M with payments deferred to 2025
- Higher Q3 costs due to administrative delays at Korali-Sud
- Temporary production suspension at Korali-Sud due to permitting issues
Production in the third quarter included minimal contribution from Korali-Sud (previously referred to as Diba) at the Sadiola mine. Korali-Sud, a higher-grade oxide ore body, was expected to represent a significant component of the Company's production at Sadiola for 2024 and 2025, displacing some of the lower-grade ore originally planned to be fed through the plant. It is now expected to represent a significant component of production for the fourth quarter of 2024, continuing through 2025 and early 2026. This is anticipated to improve both production and cost efficiency. In the second quarter, the Company began operations and stockpiling from Korali-Sud, although operations were suspended early in the third quarter, as the Company was required to complete the permitting process for Korali-Sud under the new 2023 Mining Code. Now fully permitted, the Company has begun processing stockpiled material and broader production activities. Korali-Sud is planned as a bridge between current operations at Sadiola and the completion of the first phase expansion, which will allow the plant to process more of the fresh ore. This first phase expansion commenced in the fourth quarter of 2024 and is expected to be completed by the fourth quarter of 2025, which will allow for sustainable production at Sadiola of at least 200,000 ounces per year. Lastly, the Company continued to drill other areas of oxide mineralization at Sadiola, including Sekekoto West, FE4, FE2.5 and Tambali South, so that they can serve as backup ore feed for Korali-Sud, as the first phase expansion is completed.
Production exceeded sales of 78,939 ounces in the period due to the timing of shipments in relation to gold pours, particularly at Korali-Sud. AISC(1) per ounce, which is calculated on an ounce sold versus produced basis, was impacted by certain expenditures being divided by a lower denominator, which is expected to normalize in the fourth quarter. Total cost of sales, cash costs(1) and AISC(1) per gold ounce sold were
Cost improvements are expected for the remainder of the year. At Sadiola, which will meaningfully impact the consolidated result, this will be achieved through the increased production resulting from the inclusion of oxide ore from Korali-Sud in addition to other operational improvements. Further, as expected and guided, Bonikro's sustaining capital and AISC(1) in the third quarter were impacted by capitalized stripping at PB5. The stripping activities being carried out during the year, and the expected ramp-up of stripping activities in the fourth quarter, will improve production and costs for the next few years, as high-grade ore will be exposed while significantly lower waste removal is planned.
The Company estimates production in the fourth quarter of 98,000 ounces to 102,000 ounces, making it the highest production quarter of the year and comfortably corroborating the Company's position that the production platform of the Company's current operations is in the 375,000-400,000 range, as previously disclosed. Mostly, production increases in the fourth quarter are attributable to more fulsome contributions to production from Korali-Sud which has had a nominal contribution to production year-to-date. Estimated production for the fourth quarter also accounts for reduced throughput when processing ores from Korali-Sud, as a result of clay content in those ores. Presently, ores from Korali-Sud are processed separately from ores from Sadiola under a tolling arrangement given different ownership of Sadiola and Korali-Sud. The Company is seeking approval from mining authorities to blend ores from the two deposits thereby optimizing throughput and production. The foregoing production profile is before any capital programs that will result in a step increase in production, notably from Kurmuk and the Sadiola expansion.
THIRD QUARTER HIGHLIGHTS
Financial Results
- Third quarter net loss(2) was
or$108.0 million per share basic and diluted.$(0.43) - Adjusted third quarter net earnings(1)(2) of
or$50.6 million per share basic and diluted, primarily reflecting adjustments for non-recurring items related to the$0.20 Mali agreement (discussed below), tax adjustments, and unrealized losses on the revaluation of financial instruments. - EBITDA(1) for the three months ended September 30, 2024 was a loss of
, an improvement over last year.$69.1 million - Adjusted EBITDA(1) was
representing a significant increase from the prior year comparative period. The Company's strong Adjusted EBITDA(1) demonstrates its strong cash-flow generating ability and continued operational efficiency.$52.1 million - Operating cash flow before income tax paid and movements in working capital was
, up significantly from the comparative prior period.$87.2 million - Net cash generated from operating activities for the three months ended September 30, 2024 was
. This compares to an inflow of$72.6 million in the prior year comparative quarter. Current period cash from operating activities was positively impacted by higher realized gold prices and proceeds of the stream with Triple Flag that closed during the third quarter. Working capital impact was modest for the quarter, with mostly offsetting decreases due to the buildup of prepaid balances, VAT, stockpiles and finished goods inventory, and increases due to general timing of accounts payable.$2.2 million - Cash and cash equivalents totaled
as of September 30, 2024. Cash balances increased significantly subsequent to quarter end with gross proceeds of approximately C$95.4 million $221 million received during October.
Operational Improvements and Significant Developments
Throughout 2024 and continuing in the third quarter, management made a series of improvements to its operational improvement plans to ensure a materially stronger fourth quarter and to position the Company to achieve its 2025 objectives and beyond, effectively strengthening and de-risking the production platform moving forward. These actions include:
- Mining, Processing, Exploration and Administrative Improvements: The Company has been progressing to an operationally focused approach to the business and has implemented a series of improvements and optimizations, that once again support a strong fourth quarter and beyond. These include:
- Increases in mining and waste movement to achieve spatial compliance and access higher-grade ores, resulting in a lower-than-planned cost per ton.
- Processing plant optimizations have increased total tonnes milled across all operations throughout the year, which is expected to continue through the fourth quarter. Notably, operations in Côte d'Ivoire achieved substantial gains, with third-quarter milling rates up
15% at Agbaou and39% at Bonikro compared to the first quarter. - Consolidating and integrating critical activities, such as contract mining services awarded to Mota-Engil, a leading global mining and construction organization. Consolidating mining services with a well-capitalized partner is expected to enhance consistency, reliability, and to improve logistics and supply chain expertise, including customs and importation.
- Exploration initiatives aimed at extending mine life, focusing on expanding the Mineral Reserves of oxide ore at Sadiola and advancing exploration at several high-quality targets within the Kurmuk project.
- Leadership Strengthened to Drive Operational Performance:
- The Company has appointed Johannes Stoltz as Chief Operating Officer, leveraging his 28 years of mining experience and deep knowledge of Allied's operations. Johannes' transition into the role has been occurring since the beginning of 2024, and he has been primarily responsible for optimizations and improvements initiated to improve operations from early this year, making strong progress toward achieving sustainable and predictable production goals starting in the third quarter. This appointment is part of an orderly succession plan that had begun at the beginning of the year as his predecessor was nearing retirement, and the company having determined that for its optimizations plan, and having improved its plant functions, a focus on mining was critical and its head of operations should be a qualified mining engineer.
- Allied has strengthened its Board of Directors by adding a new Board Member, Oumar Toguyeni. Mr. Toguyeni is a highly experienced global mining executive, with over 35 years of mining expertise. His career has included senior leadership positions at major international mining companies such as BHP, Alcoa Inc., IAMGOLD Corporation, and he has also recently been appointed to the Board of Directors of Hummingbird Resources. He very recently joined the board of that company in connection with the restructuring and recapitalization of the company initiated, and financially supported, by its largest shareholder. Beginning his career as an exploration geologist, Mr. Toguyeni has gained extensive experience in
Europe ,North and South America , theCaribbean , and particularly inWest Africa , where he is based. His executive career includes senior operational and sustainability positions inMali the result of which, together with his in country relationships, will assist in management of and board oversight over the Company's in country efforts. Fluent in English and French, he brings a wealth of international experience and insight to the Board. He is a geologist and also holds a Master of Business Administration degree. - The Company is further consolidating its management into its head office in
Toronto , rationalizing legacy offices throughout the organization. - Adoption of a governance approach aligned with best practices established by public companies, emphasizing rigorous risk management and sustainability practices.
- Securing Fiscal and Regulatory Framework in
Mali : During the third quarter, the Company entered into a definitive protocol agreement (the "Agreement") with the Government ofMali (the "State"), providing for renewal of the exploitation permit for Sadiola, advancement of the nearby Korali-Sud property including the issuance of a definitive exploitation permit for large-scale mining and processing of mined ore at the Sadiola plant, and the fiscal and regulatory framework for the phased expansion of the operations. Subsequent to the Agreement, other producers in the country reached similar arrangements with the State. The Agreement establishes a strong foundation for certainty and consistency, and leads to the Company continuing to operate in-country and able to pursue growth plans that result in stronger production and cash flow. The Agreement provides several benefits for the Company, setting the stage for advancing the Company's operational and expansion plans:- Permit Renewals: The Exploitation Permit for the Sadiola Gold Mine has been renewed for ten years, and allows for further renewals after the initial ten-year term until all Mineral Reserves are depleted. This renewal enables operational continuity and supports the Company's phased expansion plan, which provide for the realization of Sadiola's inherent value.
- Fiscal and Regulatory Stability: The Agreement provides fiscal and regulatory stability, in which royalties align with the new mining code, although also provides for derogations from certain royalties. The derogations have substantial financial value, as compared to the mining code itself. In addition, the Company's ownership of Sadiola remains at
80% , with the State owning a carried20% (the State's ownership of Korali-Sud will be increased to35% whereas the Company will retain65% ) and maintain rights to fiscal stability, mediation and arbitration. As the Company was the first to complete negotiations and discussions culminating in the Agreement, the Company also secured a most-favoured-nations right which allows for it to claim any right or benefit settled with other companies operating in-country. This framework supports the phased expansion at Sadiola, fostering increased production and cash flow and creating a foundation for optimization projects to enhance recoveries and throughput. - Approval of Korali-Sud: Korali-Sud represents significant value and offers near-term production and cash flow, advancing strategic goals at Sadiola.
- Potential Upside through Joint Ventures: The Company believes that entering into the Agreement has certain qualitative benefits which include increased goodwill which applies, in addition to other areas, to the pursuit of other in-country mining opportunities with the recently formed State mining company. These include nearby deposits which would benefit Sadiola.
- Tax Stability: Under the Agreement,
Mali has agreed to abandon all outstanding claims related to the Company's customs, income and other tax matters up to the date of the Agreement, offering a clean slate for tax-related matters moving forward.
- Kurmuk Progress: During the quarter, Allied continued the advancement of the Kurmuk Gold Project, progressing earthworks, camp construction, and supply chain activities according to schedule, including key agreements aimed at securing cost-effective operations. A signed 20-year Power Purchase Agreement with Ethiopian Electric Power ensures sustainable energy for Kurmuk at a fixed rate of
US per kWh, positioning it as one of the lowest-cost operations globally. Additionally, following a broad and competitive process, Allied selected Mota-Engil Group as its mining contractor, with preparations underway for mining operations to begin mid-2025. Mota-Engil, a multinational engineering and construction leader with nearly 80 years of expertise across$0.04 Europe ,Africa , andLatin America , will bring vital experience to Kurmuk, supporting commercial production goals by mid-2026. This selection aligns with Allied's strategic assessment of its West African operations and the performance of existing mining contractors on-site. Year-to-date, has been invested in the project, excluding capitalized borrowing interest under IFRS. Fourth-quarter expenditures are expected to increase as construction activities continue to ramp-up. The project remains on track on physical progress, however 2024 capital expenditures are now expected to be approximately$47.6 million excluding capitalized interest, below the original estimate of$100 million . The difference is mostly the result of detailed and optimized execution planning, favorable contract negotiations which lowered upfront payments, preference for local contractor deployment with lower mobilization costs, and optimization of certain earthworks. Some of these payments have been deferred into the first half of 2025, and consequently, the project remains on budget.$155 million - Executing Financial Strategy: Allied continued to enhance financial flexibility to support growth plans this quarter through an overnight public offering for
C and a$221 million gold streaming agreement with Triple Flag Precious Metals Corp. The Company is also in advanced discussions for a$53 million gold stream on Kurmuk, covering approximately$150 -$175 million 6% -7% of its production, with a step-down to4% -5% , and a gold prepay package. These initiatives validate significant opportunities across the asset portfolio and demonstrate Allied's ability to attract substantial investment at a low cost of capital, enhancing financial flexibility and accelerating cash flows.$75 million
Operational Results and Outlook
As previously disclosed, production is expected to be back-end weighted, with quarter-over-quarter variances driven by mine sequencing, access to higher grades per the mining plan, and the implementation of operational improvements. Third-quarter results and year-to-date production were impacted by temporary suspension related to permitting in accessing higher-grade ore at the Korali-Sud (Diba) property, as well as previously disclosed power issues in Côte d'Ivoire.
For three months ended September 30, | For nine months ended September 30, | YTD Percentage | |||
2024 | 2023 | 2024 | 2023 | Improvement | |
Gold Ounces Produced | 85,147 | 84,473 | 258,459 | 249,062 | 4 % |
- Fourth Quarter Expectations:
- The Company expects production in the fourth quarter of 98,000-102,000 oz, making it the highest production quarter of the year.
- Run-rate production is expected to comfortably support the Company's platform within the 375,000–400,000 oz range, as previously disclosed, even before the impact of capital programs anticipated to drive a step increase in production, particularly from Kurmuk and the Sadiola expansion.
- 2024 Production Expectations:
- Full-year production is expected to be 360,000–367,000 oz, an increase of approximately 20,000 oz at the midpoint, or over
5% from 2023 production levels.
- Full-year production is expected to be 360,000–367,000 oz, an increase of approximately 20,000 oz at the midpoint, or over
- Cost Expectations:
- Costs for the first half of the year were in line with expectations, and with anticipated strong production in the second half, full-year costs were initially projected within the guided range.
- However, challenges encountered during the third quarter, along with the updated full-year production expectation and anticipated effects of
Mali 's 2023 Mining Code, are expected to increase full-year AISC(1) costs by approximately per oz relative to prior expectations.$200 - Expenses are expected to continue trending lower through the remainder of the year, with quarter-over-quarter savings and improvements anticipated alongside a significant increase in fourth quarter production. As costs decrease and production rises, the per-ounce cost of general and administrative expenses is projected to decline at an even greater rate.
Advancement of Key Growth Initiatives
Kurmuk Development
The Company continues to make substantial progress on the Kurmuk Project, achieving key milestones to date, including:
- Successful completion of early works and project setup
- Completion and filling of the construction water dam
- Substantial completion of key engineering packages
- Procurement of major services and critical equipment
- Final negotiations of key construction contracts in preparation for the fourth-quarter construction ramp-up
- Establishment of the starter camp and advanced construction of the main camp
- Initiation and steady progress on plant site and general facility earthworks
The mining contract for Kurmuk has been awarded to Mota-Engil, a Portuguese-based engineering and construction company with demonstrated competency and robust financial capacity, following a comprehensive tendering process conducted by the Company. The award will advance pioneering earthworks at an early stage, allow sufficient time for the importation and mobilization of equipment well ahead of the timeframe when mining will begin, and also allow for the early establishment of infrastructure, support and training of personnel.
Year-to-date,
- Further progress on earthworks, including main water dam excavations
- Ramp-up of concrete, batch plant, and civil activities
- Start of steel fabrication and other construction activities
- Advancement of main camp construction
- Procurement of other services and supplies
The Company remains on track with the physical progress of the Kurmuk Project; however, capital expenditures are lower than the original estimate for the year. Full-year direct project cash flow spending (excluding capitalized interest) is now expected to be approximately
The Kurmuk Project's development plan involves a total capital investment of approximately
Exploration efforts have also been positive, particularly at the Tsenge gold prospect, confirming high prospectivity and reinforcing Allied's goal of significant Mineral Resource growth. These advancements underscore Allied's commitment to establishing Kurmuk as a major gold mineral province in
With Kurmuk fully permitted, licensed, and progressing on plan and on budget, the Company remains well-positioned to achieve first production in mid-2026, delivering long-term value to stakeholders. Continued updates will be provided as construction and exploration activities advance in line with the project's objectives.
Sadiola Protocol Agreement and Phased Expansion
During the third quarter, the Company entered into a definitive protocol agreement (the "Agreement") with the Government of
The Agreement also provides for certain payments to the State. On October 12, 2024 the Company made an initial upfront payment, and the Company intends to make an additional and final payment by March 31, 2025 from cash flows. In addition, the Company also settled certain tax and other obligations. In accordance with accounting standards, all amounts were expensed during the quarter. The aforementioned items resulted in an impact to current income tax expense of
Present efforts have focused on increasing the inventory of oxide and fresh ores, significantly optimizing mining and processing, conducting several technical studies on processing fresh ores through existing facilities, and planning the development of a new plant for processing fresh ore exclusively. This includes implementing enhancements to existing facilities to benefit both the current plant and the planned new plant.
Meaningful improvements in production are targeted in the short term through the contribution from high-grade oxide ores from various sources, with the objective to support production levels between 200,000 and 230,000 ounces per year in the next two years, reduce AISC(1), increase revenue, and provide robust cash flows in 2024 and 2025 to support development projects across the Company.
The discovery of additional economic oxide mineralization has the potential to improve upon these targets. Exploration activities, resource modeling, and engineering studies are in progress for several areas and new discoveries of oxide ore, including those at S12, Sekekoto West, FE4, and Tambali South, among others. These developments are a key part of the Company's strategy, allowing for the optimized utilization of existing resources and infrastructure, further contributing to production and cost improvements for the next several years, and providing mine plan flexibility with more areas for mining.
The aforementioned approach will enable the mine to continue producing at elevated levels while incurring lower near-term capital costs. Following this period, with the commissioning of the Phase 1 Expansion, the Sadiola Gold Mine is expected to support an average production level between 200,000 and 230,000 ounces per year through 2028, although by processing more fresh ore with higher grades and lower recoveries. This strategy not only optimizes the use of existing Mineral Resources but also aligns with our commitment to extend the life of the mine and enhance its profitability.
Project pre-construction activities for the Phase 1 Expansion are progressing well, and with the Agreement now in place, formal modifications to the existing plant are expected to begin in the fourth quarter and extend into 2025. Allied expects to invest approximately
The Phase 2 Expansion, planned as a new processing plant to be built beginning in late 2026 and dedicated to processing fresh rock and oxides at a rate of up to 10 Mt per year, targeted to start in the second-half of 2028, is expected to increase production to an average of 400,000 ounces per year for the first four years and 300,000 ounces per year on average for the mine's 19-year life, with AISC(1) expected to decrease to below
While the investment in the Sadiola Gold Mine Expansion Project is delineated in phases for planning purposes, it is critical to recognize that these phases are part of an integrated development effort aimed at significantly increasing the Sadiola Gold Mine's production, enhancing its profitability and longevity, and reaffirming the commitment to the Company's stakeholders. This is demonstrated by the over
Further, the Company is investigating the merits of a more progressive expansion of the existing plant beyond the year 2025, with the objective to target similar ultimate production levels at improved capital intensity.
The Company is also advancing opportunities for optimization of the Sadiola Gold Mine Expansion Projects, including metallurgical test work and a pre-feasibility study to potentially increase recoveries by over 10 percentage points through the use of flotation and concentrate leaching. This study, supported by the Company's phased investment, seeks to improve the project's financial performance significantly. With this long-term and value-focused strategy, the Company is well-positioned to affirm that the advancement of the Sadiola Gold Mine Project is proceeding as planned, reinforcing Allied's commitment to operational excellence and long-term value creation.
Financing Strategy
The Company's ability to unlock significant value from its expanding mineral inventory is supported by the financial flexibility needed to fund optimizations and growth initiatives. While Allied expects to finance much of this through cash flows based on recent gold prices, it is strategically enhancing its capital structure with a combination of financing options.
Recently, Allied raised approximately
Allied's recent
The prepay facility will accelerate cash flows with a built-in gold price hedge, supporting Kurmuk's anticipated mid-2026 construction timeline and balancing capital requirements. Allied's strengthened financial position also provides flexibility to reinvest operational cash flows into potential Sadiola expansions, maximizing asset value and shareholder returns.
Sustainability
- The Company did not report any significant Environmental Incidents for the three and nine months ended September 30, 2024.
- For the quarter ended September 30, 2024, the Company reported three Lost Time Injuries ("LTI"), resulting in a Lost Time Injury Rate ("LTIR") of 0.75(4).
OPERATING RESULTS SUMMARY
For three months ended September 30, | For nine months ended September 30, | |||
2024 | 2023 | 2024 | 2023 | |
Gold ounces | ||||
Production | 85,147 | 84,473 | 258,459 | 249,062 |
Sales | 78,939 | 91,164 | 248,686 | 250,012 |
Per Gold Ounce Sold | ||||
Total Cost of Sales | $ 1,750 | $ 1,593 | $ 1,635 | $ 1,587 |
Cash Costs(1) | $ 1,514 | $ 1,424 | $ 1,419 | $ 1,426 |
AISC(1) | $ 1,811 | $ 1,546 | $ 1,619 | $ 1,561 |
Average revenue per ounce | $ 2,390 | $ 1,935 | $ 2,247 | $ 1,901 |
Average market price per ounce* | $ 2,474 | $ 1,928 | $ 2,299 | $ 1,930 |
*Average market prices based on the LMBA PM Fix Price |
Sadiola
For the three months ended September 30, 2024, Sadiola produced 39,138 ounces of gold, compared to the 43,525 ounces produced in the comparative prior year quarter. Production in the third quarter included minimal contribution from Korali-Sud at the Sadiola mine. Korali-Sud, an oxide, higher-grade ore body, that was expected to represent a significant component of the Company's production at Sadiola, displacing some of the lower-grade ore originally planned to be fed through the plant for 2024 and 2025, is now expected to represent a significant component of production for the fourth quarter of 2024, continuing through 2025 and early 2026. This is expected to improve both production and cost efficiency. Ore from Korali-Sud was exposed and made available for mining as planned in late June, to commence industrial-scale tests at the Sadiola plant. These tests were aimed at confirming and optimizing processing parameters. As a result, limited quantities of ore were processed during the second quarter to conduct these tests and assess the plant's behavior and controls, particularly for the higher-grade ores, and these tests were successful. The plant trial yielded production at better-than-expected grades. Production from Korali-Sud has recommenced, at better grades and recoveries than expected, now that the Company has received the necessary authorizations for processing Korali-Sud ore at Sadiola. Operations were suspended early in the third quarter, as the Company was required to complete the permitting process for the ore body under the new 2023 Mining Code. Now that it is fully permitted, the Company has begun processing stockpiled material and broader production activities.
Ongoing exploration at Sekekoto West, FE4, and Tambali South aims to expand near-surface oxide gold resources, supporting short-term production growth and cash flow. During the third quarter, Sadiola increased total tonnes mined to accelerate waste stripping and enhance oxide availability for operational flexibility in 2025. Concurrently, plant automation enabled record tonnes milled, positioning the Company to recover from the oxide shortages stemming from earlier Korali-Sud delays.
Gold sales for the current quarter were lower than production, solely resulting from timing of shipments and consequent sales.
Given the overall economic position of the
During the third quarter, exploratory and resource drilling programs were conducted on the Sadiola mining license. A total of 180 holes were drilled, covering 21,706 meters, with five exploration drill rigs. Drilling efforts were focused on the Sekekoto West, FE2.5, and Borokone prospects, as well as the Tambali deposit, with expanded programs on these sites during the quarter.
Exploratory drilling at Sekekoto West continues to extend strike length; while the area is closed off to the south, it remains open to the north along 50-meter spaced drill lines. Additional exploratory and resource drilling is planned in this area for the fourth quarter, following the end of the wet season. At FE2.5, infill resource drilling on 25-meter centers was completed on the central part of the eastern trend, and initial exploratory drilling was conducted along a second, parallel trend on the western contact. Deeper drilling in fresh rock has intersected sulphide mineralization in silicified and vein-impure carbonates, though at lower gold grades.
At Tambali, resource drilling for shallow sulphides continued on the deposit's eastern flank. Mineralization has now been traced to the edge of the waste dump separating the Sadiola main pit and Tambali pits, presenting an opportunity to connect these zones with previously drilled areas in the Sadiola deposit hanging wall. Toward the end of the quarter, a coring rig was deployed for a round of resource core drilling to further define the sulphide resource at Tambali.
Finally, at Borokone, the first intersections of oxide mineralization were encountered, with further exploratory drilling scheduled for 2025.
Bonikro
Bonikro produced 27,369 ounces of gold during the three months ended September 30, 2024, compared with 23,628 ounces produced in the comparable quarter of the previous year. Third-quarter production represented a meaningful increase over both the second and first quarters, as the challenges and impact of in-country power issues were mitigated, and the stockpile was drawn down, providing greater flexibility and availability of ore for processing.
The sequential increase in gold production over the second and first quarters of 2024 was driven by high-grade ore from Stage 1, increased waste mining from Stages 3 and 5 to ensure a sustainable ore supply to the plant, stable ore supply with recoveries above plan, and increased plant throughput due to skill training and leadership changes. Furthermore, the stripping of Pushback 5 ("PB5") during 2024 will expose higher-grade material for 2025 and 2026. Although the 2024 cost profile reflects these activities, they are expected to significantly reduce the mine-site AISC(1) to below
Several additional opportunities to optimize the plant are being pursued, including operational and maintenance improvements, comminution circuit optimization, increased gravity gold recovery, and better slurry density and viscosity control practices. Several of these initiatives have already been implemented or are under study, and they will ultimately lead to improvements in mill rates, as well as greater predictability of throughput and recoveries. During the second quarter, the sizing screen panels were modified from 40mm to 35mm, improving the mill rate by nearly
At Bonikro, expected cost reductions are to be achieved through the normalization of production with the more self-reliant power strategy. However, as expected and guided, Bonikro's sustaining capital and AISC(1) in the third quarter were impacted by capitalized stripping at PB5. The stripping activities being carried out during the year, and the expected ramp-up of stripping activities in the fourth quarter, will improve production and costs for the next few years, as high-grade ore will be exposed while significantly lower waste removal is planned. The classification of stripping costs to sustaining capital was changed in the fourth quarter of 2023, with first production from the pushback achieved in that quarter. Prior year comparative costs associated with PB5, which did not have any ore production in the third quarter of 2023, were deemed as expansionary capital and consequently did not impact AISC(1). Further, the increase in DDA from the comparative prior quarter is related to amortization of the PB5 expansionary deferred stripping, which commenced in the fourth quarter of 2023.
During the third quarter, gold sales were slightly lower than production due to timing of production and shipments.
During the quarter, resource and exploration drilling was conducted on the Company's mining and exploration licenses, with the following activity:
- Hire Mining License: 231 holes, totaling 12,696 meters
- Oume Exploration License: 66 holes, totaling 10,283 meters
At the Hire mine, core drilling was completed to the WSW of the Agbalé prospect, expected to be processed at Agbaou, and beneath the Akissi-So waste rock dump. Gold intersections in fresh rock suggest the likely presence of a linking mineralized structure between the Akissi-So and Agbalé deposits. Additional infill drilling is planned to further test this area with the aim of connecting these mineralized zones and expanding the resource. Three rigs were also active around the Assondji-So ROM pad, identifying a 300-meter strike of mineralization, which will be the focus of both exploratory and resource infill drilling in the fourth quarter.
At the Oume Project, drilling progressed at the Dougbafla West and North deposits, with infill drilling focused on upgrading inferred resources to indicated resources. Work at Dougbafla West concentrated on the oxide portion of the resource, while at Dougbafla North, core drilling and structural geological analysis enhanced understanding of mineralization geometry, informing resource estimation wireframing.
Additionally, target generation continued on the broader Hire mining license, with field teams actively exploring the Ditula prospect.
Agbaou
Agbaou produced 18,640 ounces of gold during the three months ended September 30, 2024, compared to 17,320 ounces in the corresponding quarter of the previous year. The increase is modest in relation to the comparative quarter but more significant when compared to the second quarter, as the impact of in-country grid power issues had been mitigated. During the third quarter, the mine demonstrated its operational mining capacity, with total tonnes mined continuing to increase, enabling the Company to expose all ore planned for 2024. Additionally, fleet performance improved due to the implementation of short-term interval controls. In terms of plant and processing, the mine achieved record throughput as a result of successful fragmentation strategies. Oxide ore feed is also ahead of schedule from Chapelle and Agbalé.
With most mine pits nearing the end of their pushback cycles, improvements in stripping ratios, ore mined, and grades have been observed, with expectations for continued enhancements in the upcoming quarters. In particular, the upcoming mining sequence at South Sat 3, Agbalé, Chapelle and WP7 will result in increased grades, contributing to the expected strong second-half production as guided. The completion of mining oxides and transitional ore across all pits has led to a shift towards a higher proportion of fresh material mining, contributing to reduced mining rates.
Gold sales during the quarter were generally in line with production.
Costs for the third quarter were impacted by the inclusion of Agbalé ounces, and in particular the costs of sustaining capital expenditures related to its development, which are disproportionate to the production levels. However, with the Côte D'Ivoire mines now being with the same contractor, the Company expects synergies and the reduction of costs going forward. At Agbaou, expected cost reductions are to be achieved through the normalization of production after the aforementioned contractor changeover in the first quarter, process optimizations, and the normalization of the power matters. The Company has also kicked-off a further cost reduction project with the objective to reduce AISC.
The blend ratio feeding the Agbaou plant remains critical with quality oxide ore, which resulted in accelerating the mining plan of Agbalé Phase 2 into production, which has continuously delivered on grade, and has provided significant flexibility in the first quarter for the Agbaou plant blended ore requirements.
The Company is focused on extending the life of its mines in Côte d'Ivoire through strategic exploration and resource management, with new life-of-mine planning at Agbaou supporting total gold production of over 465,000 ounces through 2028 at a mine-site AISC(1) below
During the third quarter, the Company conducted resource and exploration drilling on the Agbaou mining license, with 17 holes totaling 2,358 meters.
At Agbaou, infill drilling at the North Pit Extension was ongoing at quarter end. Initial core drilling at the Agbaou South prospect has concluded, with final assays received, and a second phase is planned to further evaluate the prospect.
The exploration work and focus at both Agbaou and Bonikro continue to align with the Company's strategic aim to establish a sustainable production platform of 180,000 to 200,000 oz per annum over a mine life of more than 10 years.
For three months ended September 30, 2024 | Production Gold | Sales Gold | Cost of Sales Per | Cash Cost(1) Per | AISC(1) Per Gold |
Sadiola Gold Mine | 39,138 | 35,289 | $ 1,588 | $ 1,522 | $ 1,793 |
Bonikro Gold Mine | 27,369 | 25,457 | $ 1,451 | $ 940 | $ 1,318 |
Agbaou Gold Mine | 18,640 | 18,193 | $ 2,485 | $ 2,300 | $ 2,537 |
Total | 85,147 | 78,939 | $ 1,750 | $ 1,514 | $ 1,811 |
FINANCIAL SUMMARY AND KEY STATISTICS
Key financial operating statistics for the third quarter 2024 are outlined in the following tables.
(In thousands of US Dollars, except for shares and | For three months ended September 30, | For nine months ended September 30, | ||
2024 | 2023 | 2024 | 2023 | |
Revenue | $ 188,855 | $ 176,685 | $ 559,536 | $ 476,017 |
Cost of sales, excluding depreciation, depletion | (122,583) | (134,343) | (363,789) | (368,197) |
Gross profit excluding depreciation and | $ 66,272 | $ 42,342 | $ 195,747 | $ 107,820 |
DDA | (15,596) | (10,884) | (42,735) | (28,597) |
Gross profit | $ 50,676 | $ 31,458 | $ 153,012 | $ 79,223 |
General and administrative expenses | $ (16,307) | $ (15,440) | $ (45,708) | $ (37,338) |
Gain (loss) on revaluation of call and put options | — | (16,337) | — | (21,883) |
Loss on revaluation of financial instruments and | (5,835) | (240) | (9,717) | (2,053) |
Other losses | (113,239) | (147,259) | (120,868) | (146,872) |
Net loss before finance costs and income tax | $ (84,705) | $ (167,437) | $ (23,281) | $ (148,542) |
Finance income (costs) | 441 | (4,559) | (12,278) | (17,271) |
Net loss before income tax | (84,264) | (171,996) | (35,559) | (165,813) |
Current income tax expense | $ (38,141) | $ (27,187) | $ (65,521) | $ (47,110) |
Deferred income tax (expense) recovery | (4,755) | 9,798 | (10,503) | 8,115 |
Net loss and total comprehensive loss for the | $ (127,160) | $ (189,385) | $ (111,583) | $ (204,808) |
(Loss) earnings and total comprehensive (loss) | ||||
Shareholders of the Company | $ (107,965) | $ (194,641) | $ (105,352) | $ (213,927) |
Non-controlling interests | (19,195) | 5,256 | (6,231) | 9,119 |
Net loss and total comprehensive loss for the | $ (127,160) | $ (189,385) | $ (111,583) | $ (204,808) |
Net loss per share attributable to shareholders of | ||||
Basic and Diluted | $ (0.43) | $ (0.98) | $ (0.42) | $ (1.14) |
(In thousands of US Dollars, except per share | For three months ended September 30, | For nine months ended September 30, | ||
2024 | 2023 | 2024 | 2023 | |
Net Loss attributable to Shareholders of the | $ (107,965) | $ (194,641) | $ (105,352) | $ (213,927) |
Net Loss attributable to Shareholders of the | $ (0.43) | $ (0.98) | $ (0.42) | $ (1.14) |
(Gain) loss on revaluation of call and put options | — | 16,337 | — | 21,883 |
Loss on revaluation of financial instrument | 5,835 | 240 | 9,717 | 2,053 |
Foreign exchange | 1,634 | (1,188) | 2,466 | 370 |
Share-based compensation | 818 | 1,566 | 4,956 | 5,253 |
| 112,905 | 4,441 | 117,868 | 845 |
Tax adjustments | 37,344 | 9,409 | 37,695 | 9,409 |
Total increase to Attributable Net Earnings | $ 158,536 | $ 196,920 | $ 172,702 | $ 205,928 |
Total increase to Attributable Net Earnings | $ 0.63 | $ 0.99 | $ 0.69 | $ 1.10 |
Adjusted Net Earnings (Loss)(1) | $ 50,571 | $ 2,279 | $ 67,350 | $ (7,999) |
Adjusted Net Earnings (Loss)(1) per Share | $ 0.20 | $ 0.01 | $ 0.27 | $ (0.05) |
Third Quarter 2024 Conference Call
The Company will host a conference call and webcast on Friday, November 8, 2024 at 9:00 a.m. ET.
Toll-free dial-in number ( | 1-800-898-3989 |
Local dial-in number: | 416-406-0743 |
Toll Free ( | 00-80042228835 |
Participant passcode: | 5324345# |
Webcast: |
Conference Call Replay
Toll-free dial-in number ( | 1-800-408-3053 |
Local dial-in number: | 905-694-9451 |
Passcode: | 6354190# |
The conference call replay will be available from 12:00 p.m. EST on November 8, 2024, until 11:59 p.m. ET on December 8, 2024.
Qualified Persons
Except as otherwise disclosed, all scientific and technical information contained in this press release has been reviewed and approved by Sébastien Bernier, P.Geo (Vice President, Technical Services). Mr. Bernier is an employee of Allied and a "Qualified Person" as defined by Canadian Securities Administrators' National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").
About Allied Gold Corporation
Allied Gold is a Canadian-based gold producer with a significant growth profile and mineral endowment which operates a portfolio of three producing assets and development projects located in Côte d'Ivoire,
END NOTES
(1) | This is a non-GAAP financial performance measure. Refer to the Non-GAAP Financial Performance Measures section at |
(2) | Net earnings and adjustments to net earnings represent amounts attributable to Allied Corporate equity holders. |
(3) | The Government of |
(4) | Calculated on a 1,000,000 exposure-hour basis. |
(5) | Historically, Cost of sales was presented inclusive of DA. Cost of sales is the sum of mine production costs, royalties, and |
NON-GAAP FINANCIAL PERFORMANCE MEASURES
The Company has included certain non-GAAP financial performance measures to supplement its Condensed Consolidated Interim Financial Statements, which are presented in accordance with IFRS, including the following:
- Cash costs per gold ounce sold;
- AISC per gold ounce sold;
- Gross profit excluding DA;
- Sustaining, Expansionary and Exploration Capital Expenditures;
- Adjusted Net Earnings (Loss) and Adjusted Net Earnings (Loss) per share; and
- EBITDA and Adjusted EBITDA
The Company believes that these measures, together with measures determined in accordance with IFRS, provide investors with an improved ability to evaluate the underlying performance of the Company.
Non-GAAP financial performance measures, including cash costs, AISC, Gross profit excluding DA, Sustaining, Expansionary and Exploration Capital Expenditures, Adjusted Net Earnings (Loss), Adjusted Net Earnings (Loss) per Share, EBITDA and Adjusted EBITDA, do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies. Non-GAAP financial performance measures intend to provide additional information, and should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS and are not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.
Management's determination of the components of non-GAAP financial performance measures and other financial measures are evaluated on a periodic basis, influenced by new items and transactions, a review of investor uses and new regulations as applicable. Any changes to the measures are described and retrospectively applied, as applicable. Subtotals and per unit measures may not calculate based on amounts presented in the following tables due to rounding.
The measures of cash costs and AISC, along with revenue from sales, are considered to be key indicators of a Company's ability to generate operating earnings and cash flows from its mining operations. This data is furnished to provide additional information and is a non-GAAP financial performance measure.
CASH COSTS PER GOLD OUNCE SOLD
Cash costs include mine site operating costs such as mining, processing, administration, production taxes and royalties which are not based on sales or taxable income calculations. Cash costs exclude DA, exploration costs, accretion and amortization of reclamation and remediation, and capital, development and exploration spend. Cash costs include only items directly related to each mine site, and do not include any cost associated with the general corporate overhead structure.
The Company discloses cash costs because it understands that certain investors use this information to determine the Company's ability to generate earnings and cash flows for use in investing and other activities. The Company believes that conventional measures of performance prepared in accordance with IFRS do not fully illustrate the ability of its operating mines to generate cash flows. The most directly comparable IFRS measure is cost of sales. As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.
Cash costs are computed on a weighted average basis, with the aforementioned costs, net of by-product revenue credits from sales of silver, being the numerator in the calculation, divided by gold ounces sold.
AISC PER GOLD OUNCE SOLD
AISC figures are calculated generally in accordance with a standard developed by the World Gold Council ("WGC"), a non-regulatory, market development organization for the gold industry. Adoption of the standard is voluntary, and the standard is an attempt to create uniformity and a standard amongst the industry and those that adopt it. Nonetheless, the cost measures presented herein may not be comparable to other similarly titled measures of other companies. The Company is not a member of the WGC at this time.
AISC include cash costs (as defined above), mine sustaining capital expenditures (including stripping), sustaining mine-site exploration and evaluation expensed and capitalized, and accretion and amortization of reclamation and remediation. AISC exclude capital expenditures attributable to projects or mine expansions, exploration and evaluation costs attributable to growth projects, DA, income tax payments, borrowing costs and dividend payments. AISC include only items directly related to each mine site, and do not include any cost associated with the general corporate overhead structure. As a result, Total AISC represent the weighted average of the three operating mines, and not a consolidated total for the Company. Consequently, this measure is not representative of all of the Company's cash expenditures.
Sustaining capital expenditures are expenditures that do not increase annual gold ounce production at a mine site and excludes all expenditures at the Company's development projects as well as certain expenditures at the Company's operating sites that are deemed expansionary in nature, such as the Sadiola Phased Expansion, the construction and development of Kurmuk and the PB5 pushback at Bonikro. Exploration capital expenditures represent exploration spend that has met criteria for capitalization under IFRS.
The Company discloses AISC, as it believes that the measure provides useful information and assists investors in understanding total sustaining expenditures of producing and selling gold from current operations, and evaluating the Company's operating performance and its ability to generate cash flow. The most directly comparable IFRS measure is cost of sales. As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.
AISC are computed on a weighted average basis, with the aforementioned costs, net of by-product revenue credits from sales of silver, being the numerator in the calculation, divided by gold ounces sold.
The following tables provide detailed reconciliations from total costs of sales to cash costs(1) and AISC(1). Subtotals and per unit measures may not calculate based on amounts presented in the following tables due to rounding.
(In thousands of US Dollars, unless | For three months ended September 30, 2024 | For three months ended September 30, 2023 | ||||||
Bonikro | Agbaou | Sadiola | Total | Bonikro | Agbaou | Sadiola | Total | |
Cost of Sales, excluding DA | $ 24,646 | $ 43,291 | $ 54,646 | $ 122,583 | $ 24,532 | $ 34,914 | $ 74,896 | $ 134,342 |
DA | 12,294 | 1,916 | 1,386 | 15,596 | 8,044 | 900 | 1,940 | 10,884 |
Cost of Sales | $ 36,940 | $ 45,207 | $ 56,032 | $ 138,179 | $ 32,576 | $ 35,814 | $ 76,836 | $ 145,226 |
Cash Cost Adjustments | ||||||||
DA | $ (12,294) | $ (1,916) | $ (1,386) | $ (15,596) | $ (8,044) | $ (900) | $ (1,940) | $ (10,884) |
Exploration Expenses | (586) | (1,638) | (881) | (3,105) | (502) | (2,535) | (2,067) | (5,104) |
Agbaou Contingent Consideration | — | 221 | — | 221 | — | 830 | — | 830 |
Silver by-Product credit | (122) | (39) | (59) | (220) | (123) | (54) | (94) | (271) |
Total Cash Costs(1) | $ 23,938 | $ 41,835 | $ 53,706 | $ 119,479 | $ 23,907 | $ 33,155 | $ 72,735 | $ 129,797 |
AISC(1) Adjustments | ||||||||
Reclamation & Remediation | $ 219 | $ 319 | $ 560 | $ 1,098 | $ 171 | $ 242 | $ 452 | $ 865 |
Exploration Capital | 1,842 | — | — | 1,842 | 296 | — | 560 | 856 |
Exploration Expenses | 586 | 1,638 | 881 | 3,105 | 502 | 2,535 | 2,067 | 5,104 |
Sustaining Capital Expenditures | 6,791 | 2,255 | 8,133 | 17,179 | 1,455 | 1,238 | 1,531 | 4,224 |
IFRS 16 Lease Adjustments | 174 | 109 | — | 283 | — | 55 | — | 55 |
Total AISC(1) | $ 33,550 | $ 46,156 | $ 63,280 | $ 142,986 | $ 26,331 | $ 37,225 | $ 77,345 | $ 140,901 |
Gold Ounces Sold | 25,457 | 18,193 | 35,289 | 78,939 | 21,587 | 18,151 | 51,426 | 91,164 |
Cost of Sales per Gold Ounce Sold | $ 1,451 | $ 2,485 | $ 1,588 | $ 1,750 | $ 1,509 | $ 1,973 | $ 1,494 | $ 1,593 |
Cash Cost(1) per Gold Ounce Sold | $ 940 | $ 2,300 | $ 1,522 | $ 1,514 | $ 1,107 | $ 1,827 | $ 1,414 | $ 1,424 |
AISC(1) per Gold Ounce Sold | $ 1,318 | $ 2,537 | $ 1,793 | $ 1,811 | $ 1,220 | $ 2,051 | $ 1,504 | $ 1,546 |
(In thousands of US Dollars, unless | For nine months ended September 30, 2024 | For nine months ended September 30, 2023 | ||||||
Bonikro | Agbaou | Sadiola | Total | Bonikro | Agbaou | Sadiola | Total | |
Cost of Sales, excluding DA | $ 78,931 | $ 115,239 | $ 169,619 | $ 363,789 | $ 75,144 | $ 105,574 | $ 187,479 | $ 368,197 |
DA | 32,609 | 5,376 | 4,750 | 42,735 | 20,380 | 2,705 | 5,512 | 28,597 |
Cost of Sales | $ 111,540 | $ 120,615 | $ 174,369 | $ 406,524 | $ 95,524 | $ 108,279 | $ 192,991 | $ 396,794 |
Cash Cost Adjustments | ||||||||
DA | $ (32,609) | $ (5,376) | $ (4,750) | $ (42,735) | $ (20,380) | $ (2,705) | $ (5,512) | $ (28,597) |
Exploration Expenses | (973) | (6,509) | (3,507) | (10,989) | (909) | (6,569) | (5,930) | (13,408) |
Agbaou Contingent Consideration | — | 940 | — | 940 | — | 2,430 | — | 2,430 |
Silver by-Product credit | (323) | (131) | (286) | (740) | (350) | (136) | (231) | (717) |
Total Cash Costs(1) | $ 77,635 | $ 109,539 | $ 165,826 | $ 353,000 | $ 73,885 | $ 101,299 | $ 181,318 | $ 356,502 |
AISC(1) Adjustments to Total Cash | ||||||||
Reclamation & Remediation | $ 655 | $ 955 | $ 1,681 | $ 3,291 | $ 514 | $ 724 | $ 1,357 | $ 2,595 |
Exploration Capital | 5,582 | — | — | 5,582 | 1,901 | — | 1,838 | 3,739 |
Exploration Expenses | 973 | 6,509 | 3,507 | 10,989 | 909 | 6,569 | 5,930 | 13,408 |
Sustaining Capital Expenditures | 14,376 | 4,470 | 10,601 | 29,447 | 3,369 | 4,268 | 6,193 | 13,830 |
IFRS 16 Lease Adjustments | 174 | 165 | — | 339 | — | 83 | — | 83 |
Total AISC(1) | $ 99,395 | $ 121,638 | $ 181,615 | $ 402,648 | $ 80,578 | $ 112,943 | $ 196,636 | $ 390,157 |
Gold Ounces Sold | 65,797 | 52,223 | 130,666 | 248,686 | 65,966 | 54,245 | 129,801 | 250,012 |
Cost of Sales per Gold Ounce Sold | $ 1,695 | $ 2,310 | $ 1,334 | $ 1,635 | $ 1,448 | $ 1,996 | $ 1,487 | $ 1,587 |
Cash Cost(1) per Gold Ounce Sold | $ 1,180 | $ 2,098 | $ 1,269 | $ 1,419 | $ 1,120 | $ 1,867 | $ 1,397 | $ 1,426 |
AISC(1) per Gold Ounce Sold | $ 1,511 | $ 2,329 | $ 1,390 | $ 1,619 | $ 1,222 | $ 2,082 | $ 1,515 | $ 1,561 |
GROSS PROFIT EXCLUDING DDA
The Company uses the financial measure "Gross Profit excluding DDA" to supplement information in its financial statements. The Company believes that in addition to conventional measures prepared in accordance with IFRS, the Company and certain investors and analysts use this information to evaluate the Company's performance.
Gross profit excluding DDA is calculated as Gross Profit plus DDA.
The Company discloses Gross Profit excluding DDA because it understands that certain investors use this information to determine the Company's ability to generate earnings and cash flows. The Company believes that conventional measures of performance prepared in accordance with IFRS do not fully illustrate the ability of its operating mines to generate cash flows. The most directly comparable IFRS measure is Gross Profit. As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.
The reconciliation of Gross Profit to Gross Profit Excluding DDA can be found on page 10 of this press release and in Section 1: Highlights and Relevant Updates of the Company's MD&A, under the Summary of Financial Results and Section 4: Review of Operations and Mine Performance, for the relevant mines.
ADJUSTED NET EARNINGS (LOSS) AND ADJUSTED NET EARNINGS (LOSS) PER SHARE
The Company uses the financial measures "Adjusted Net Earnings (Loss)" and the non-GAAP ratio "Adjusted Net Earnings (Loss) per share" to supplement information in its financial statements. The Company believes that in addition to conventional measures prepared in accordance with IFRS, the Company and certain investors and analysts use this information to evaluate the Company's performance.
Adjusted Net Earnings (Loss) and Adjusted Net Earnings (Loss) per share are calculated as Net Earnings (Loss) attributable to Shareholders of the Company, excluding non-recurring items, items not related to a particular periods and/or not directly related to the core mining business such as the following, with notation of Gains (Losses) as they would show up on the financial statements.
- Gains (losses) related to the reverse takeover transaction events and other items,
- Gains (losses) on the revaluation of historical call and put options,
- Unrealized Gains (losses) on financial instruments and embedded derivatives,
- Write-offs (reversals) on mineral interest, exploration and evaluation and other assets,
- Gains (losses) on sale of assets,
- Unrealized foreign exchange gains (losses),
- Share-based (expense) and other share-based compensation,
- Unrealized foreign exchange gains (losses) related to revaluation of deferred income tax asset and liability on non-monetary items,
- Deferred income tax recovery (expense) on the translation of foreign currency inter-corporate debt,
- One-time tax adjustments to historical deferred income tax balances relating to changes in enacted tax rates,
- Non-recurring provisions,
- Any other non-recurring adjustments and the tax impact of any of these adjustments calculated at the statutory effective rate for the same jurisdiction as the adjustment.
Non-recurring adjustments from unusual events or circumstances are reviewed from time to time based on materiality and the nature of the event or circumstance.
Management uses these measures for internal valuation of the core mining performance for the period and to assist with planning and forecasting of future operations. Management believes that the presentation of Adjusted Net Earnings (Loss) and Adjusted Net Earnings (Loss) per share provide useful information to investors because they exclude non-recurring items, items not related to or not indicative of current or future periods' results and/or not directly related to the core mining business and are a better indication of the Company's profitability from operations as evaluated by internal management and the board of directors. The items excluded from the computation of Adjusted Net Earnings (Loss) and Adjusted Net Earnings (Loss) per share, which are otherwise included in the determination of Net Earnings (Loss) and Net Earnings (Loss) per share prepared in accordance with IFRS, are items that the Company does not consider to be meaningful in evaluating the Company's past financial performance or the future prospects and may hinder a comparison of its period-to-period profitability.
The most directly comparable IFRS measure is Net Earnings (Loss). As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.
The reconciliation of Net Loss to attributable to Shareholders of the Company to Adjusted Net Earnings (Loss) can be found on pages 10 and 11 of this press release and in Section 1: Highlights and Relevant Updates of the Company's MD&A, under the Summary of Financial Results.
EBITDA AND ADJUSTED EBITDA
The Company uses the financial measures "EBITDA" and "Adjusted EBITDA" to supplement information in its financial statements. The Company believes that in addition to conventional measures prepared in accordance with IFRS, the Company and certain investors and analysts use this information to evaluate the Company's performance.
EBITDA is calculated as Net Earnings (Loss), plus Finance Costs, DDA, Current income tax expense and Deferred income tax expense. Adjusted EBITDA calculated is further calculated as EBITDA, excluding non-recurring items, items not related to a particular periods and/or not directly related to the core mining business such as the following, with notation of Gains (Losses) as they would show up on the financial statements.
- Gains (losses) on the revaluation of historical call and put options,
- Unrealized Gains (losses) on financial instruments and embedded derivatives,
- Write-offs (reversals) on mineral interest, exploration and evaluation and other assets,
- Gains (losses) on sale of assets,
- Unrealized foreign exchange gains (losses),
- Share-based (expense) and other share-based compensation,
- Unrealized foreign exchange gains (losses) related to revaluation of deferred income tax asset and liability on non-monetary items,
- Non-recurring provisions,
- Non-recurring adjustments from unusual events or circumstances are reviewed from time to time based on materiality and the nature of the event or circumstance.
Management uses these measures for internal valuation of the cash flow generation ability of the period and to assist with planning and forecasting of future operations. Management believes that the presentation of EBITDA and Adjusted EBITDA provide useful information to investors because they exclude non-recurring items, items not related to or not indicative of current or future periods' results and/or not directly related to the core mining business and are a better indication of the Company's cash flow from operations as evaluated by internal management and the board of directors. The items excluded from the computation of Adjusted EBITDA, which are otherwise included in the determination of Net Earnings (Loss) prepared in accordance with IFRS, are items that the Company does not consider to be meaningful in evaluating the Company's past financial performance or the future prospects and may hinder a comparison of its period-to-period performance comparisons.
The most directly comparable IFRS measure is Net Earnings (Loss). As aforementioned, this non-GAAP measure does not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to similar measures employed by other companies, should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS, and is not necessarily indicative of operating costs, operating earnings or cash flows presented under IFRS.
(In thousands of US Dollars) | For three months ended September 30, | For nine months ended September 30, | ||
2024 | 2023 | 2024 | 2023 | |
Net Loss | $ (127,160) | $ (189,385) | $ (111,583) | $ (204,808) |
Finance (income) costs, net | $ (441) | $ 4,559 | $ 12,278 | $ 17,271 |
DDA | 15,596 | 10,884 | 42,735 | 28,597 |
Current income tax expense | 38,141 | 27,187 | 65,521 | 47,110 |
Deferred income tax (expense) recovery | 4,755 | (9,798) | 10,503 | (8,115) |
EBITDA(1) | $ (69,109) | $ (156,553) | $ 19,454 | $ (119,945) |
(In thousands of US Dollars) | For three months ended September 30, | For nine months ended September 30, | ||
2024 | 2023 | 2024 | 2023 | |
EBITDA(1) | $ (69,109) | $ (156,553) | $ 19,454 | $ (119,945) |
(Gain) loss on revaluation of call and put options | — | 16,337 | — | 21,883 |
Loss on revaluation of financial instrument | 5,835 | 240 | 9,717 | 2,053 |
Impairment of exploration and evaluation asset | — | 19,619 | — | 19,619 |
Foreign exchange | 1,634 | (1,188) | 2,466 | 370 |
Share-based compensation | 818 | 1,566 | 4,956 | 5,253 |
| 112,905 | 4,441 | 117,868 | 845 |
Adjusted EBITDA(1) | $ 52,083 | $ (115,538) | $ 154,461 | $ (69,922) |
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION
This press release contains "forward-looking information" including "future oriented financial information" under applicable Canadian securities legislation. Except for statements of historical fact relating to the Company, information contained herein constitutes forward-looking information, including, but not limited to, any information as to the Company's strategy, objectives, plans or future financial or operating performance. Forward-looking statements are characterized by words such as "plan", "expect", "budget", "target", "project", "intend", "believe", "anticipate", "estimate" and other similar words or negative versions thereof, or statements that certain events or conditions "may", "will", "should", "would" or "could" occur. In particular, forward looking information included in this press release includes, without limitation, statements with respect to:
- the Company's expectations in connection with the production and exploration, development and expansion plans at the Company's projects discussed herein being met;
- the Company's plans to continue building on its base of significant gold production, development-stage properties, exploration properties and land positions in Mali, Côte d'Ivoire and
Ethiopia through optimization initiatives at existing operating mines, development of new mines, the advancement of its exploration properties and, at times, by targeting other consolidation opportunities with a primary focus inAfrica ; - the Company's expectations relating to the performance of its mineral properties;
- the estimation of Mineral Reserves and Mineral Resources;
- the timing and amount of estimated future production;
- the estimation of the life of mine of the Company's projects;
- the timing and amount of estimated future capital and operating costs;
- the costs and timing of exploration and development activities;
- the Company's expectation regarding the timing of feasibility or pre-feasibility studies, conceptual studies or environmental impact assessments;
- the effect of government regulations (or changes thereto) with respect to restrictions on production, export controls, income taxes, expropriation of property, repatriation of profits, environmental legislation, land use, water use, land claims of local people, mine safety and receipt of necessary permits;
- the Company's community relations in the locations where it operates and the further development of the Company's social responsibility programs; and
- the Company's expectations regarding the payment of any future dividends.
Forward-looking information is based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made, and is inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause actual events or results to differ materially from those projected in the forward-looking information. These factors include the Company's dependence on products produced from its key mining assets; fluctuating price of gold; risks relating to the exploration, development and operation of mineral properties, including but not limited to adverse environmental and climatic conditions, unusual and unexpected geologic conditions and equipment failures; risks relating to operating in emerging markets, particularly
Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that could cause actions, events or results to not be as anticipated, estimated or intended. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking information if circumstances or management's estimates, assumptions or opinions should change, except as required by applicable law. The reader is cautioned not to place undue reliance on forward-looking information. The forward-looking information contained herein is presented for the purpose of assisting investors in understanding the Company's expected financial and operational performance and results as at and for the periods ended on the dates presented in the Company's plans and objectives and may not be appropriate for other purposes.
CAUTIONARY NOTE TO U.S. INVESTORS REGARDING ESTIMATES OF MEASURED, INDICATED AND INFERRED RESOURCES
This press release uses the terms "Measured", "Indicated" and "Inferred" Mineral Resources as defined in accordance with NI 43-101.
NOTES ON MINERAL RESERVES AND MINERAL RESOURCES
Mineral Resources are stated effective as at December 31, 2023, reported at a 0.5 g/t cut-off grade, constrained within an
Mineral Reserves are stated effective as at December 31, 2023 and estimated in accordance with CIM Standards and NI 43-101. The Mineral Reserves:
- are inclusive of the Mineral Resources which were converted in line with the material classifications based on the level of confidence within the Mineral Resource estimate;
- reflect that portion of the Mineral Resources which can be economically extracted by open pit methods;
- consider the modifying factors and other parameters, including but not limited to the mining, metallurgical, social, environmental, statutory and financial aspects of the project;
- include an allowance for mining dilution and ore loss; and
- were reported using cut-off grades that vary by ore type due to variations in recoveries and operating costs. The cut-off grades and pit shells were based on a
/ounce gold price, except for the Agbalé pit, which was based on a$1,500 /ounce gold price.$1,800
Mineral Reserve and Mineral Resource estimates are shown on a
The Mineral Resource and Mineral Reserve estimates for each of the Company's mineral properties have been approved by the qualified persons within the meaning of NI 43-101 as set forth below:
Qualified Person of Mineral Reserves | Qualified Person of Mineral Resources |
John Cooke of Allied Gold Corporation, an employee of Allied | Steve Craig of Orelogy Consulting Pty Ltd., an employee of Allied |
Mineral Reserves (Proven and Probable)
The following table sets forth the Mineral Reserve estimates for the Company's mineral properties at December 31, 2023.
Proven Mineral Reserves | Probable Mineral Reserves | Total Mineral Reserves | |||||||
Content | Content | Content | |||||||
Tonnes | Grade | (k | Tonnes | Grade | (k | Tonnes | Grade | (k | |
Sadiola Mine | 18,612 | 0.82 | 492 | 137,174 | 1.57 | 6,907 | 155,786 | 1.48 | 7,399 |
Kurmuk Project | 21,864 | 1.51 | 1,063 | 38,670 | 1.35 | 1,678 | 60,534 | 1.41 | 2,742 |
Bonikro Mine | 4,771 | 0.71 | 108 | 8,900 | 1.62 | 462 | 13,671 | 1.30 | 571 |
Agbaou Mine | 1,815 | 2.01 | 117 | 6,092 | 1.79 | 351 | 7,907 | 1.84 | 469 |
Total Mineral Reserves | 47,061 | 1.18 | 1,782 | 190,836 | 1.53 | 9,399 | 237,897 | 1.46 | 11,180 |
Notes:
- Mineral Reserves are stated effective as at December 31, 2023 and estimated in accordance with CIM Standards and NI 43-101.
- Shown on a
100% basis. - Reflects that portion of the Mineral Resource which can be economically extracted by open pit methods.
- Considers the modifying factors and other parameters, including but not limited to the mining, metallurgical, social, environmental, statutory and financial aspects of the project.
Sadiola Mine:
- Includes an allowance for mining dilution at
8% and ore loss at3% - A base gold price of
/oz was used for the pit optimization, with the selected pit shells using values of$150 0 /oz (revenue factor 0.88) for Sadiola Main and$132 0 /oz (revenue factor 1.00) for FE3, FE4, Diba, Tambali and Sekekoto.$150 0 - The cut-off grades used for Mineral Reserves reporting were informed by a
/oz gold price and vary from 0.31 g/t to 0.73 g/t for different ore types due to differences in recoveries, costs for ore processing and ore haulage.$150 0
Kurmuk Project:
- Includes an allowance for mining dilution at
18% and ore loss at2% - A base gold price of
/oz was used for the pit optimization, with the selected pit shells using values of$150 0 /oz (revenue factor 0.88) for Ashashire and$132 0 /oz (revenue factor 0.96) for Dish Mountain.$144 0 - The cut-off grades used for Mineral Reserves reporting were informed by a
/oz gold price and vary from 0.30 g/t to 0.45 g/t for different ore types due to differences in recoveries, costs for ore processing and ore haulage.$150 0
Bonikro Mine:
- Includes an allowance for mining dilution at
8% and ore loss at5% - A base gold price of
/oz was used for the Mineral Reserves for the Bonikro pit:$150 0- With the selected pit shell using a value of
/oz (revenue factor 0.925).$138 8 - Cut-off grades vary from 0.68 to 0.74 g/t Au for different ore types due to differences in recoveries, costs for ore processing and ore haulage.
- With the selected pit shell using a value of
- A base gold price of
/oz was used for the Mineral Reserves for the Agbalé pit:$180 0- With the selected pit shell using a value of
/oz (revenue factor 1.00).$180 0 - Cut-off grades vary from 0.58 to 1.00 g/t Au for different ore types to the Agbaou processing plant due to differences in recoveries, costs for ore processing and ore haulage
- With the selected pit shell using a value of
Agbaou Mine:
- Includes an allowance for mining dilution at
26% and ore loss at1% - A base gold price of
/oz was used for the Mineral Reserves for the:$150 0- Pit designs (revenue factor 1.00) apart from North Gate (Stage 41) and South Sat (Stage 215) pit designs which used a higher short-term gold price of
/oz and account for 49 koz or$180 010% of the Mineral Reserves. - Cut-off grades which range from 0.49 to 0.74 g/t for different ore types due to differences in recoveries, costs for ore processing and ore haulage.
- Pit designs (revenue factor 1.00) apart from North Gate (Stage 41) and South Sat (Stage 215) pit designs which used a higher short-term gold price of
Mineral Resources (Measured, Indicated, Inferred)
The following table set forth the Measured and Indicated Mineral Resource estimates (inclusive of Mineral Reserves) and for the Company's mineral properties at December 31, 2023.
Measured Mineral Resources | Indicated Mineral Resources | Total Measured and Indicated | |||||||
Content | Content | Content | |||||||
Tonnes | Grade | (k | Tonnes | Grade | (k | Tonnes | Grade | (k | |
Sadiola Mine | 20,079 | 0.86 | 557 | 205,952 | 1.53 | 10,101 | 226,031 | 1.47 | 10,659 |
Kurmuk Project | 20,472 | 1.74 | 1,148 | 37,439 | 1.64 | 1,972 | 57,911 | 1.68 | 3,120 |
Bonikro Mine | 7,033 | 0.98 | 222 | 25,793 | 1.41 | 1,171 | 32,826 | 1.32 | 1,393 |
Agbaou Mine | 2,219 | 2.15 | 154 | 11,130 | 1.96 | 701 | 13,349 | 1.99 | 855 |
Total Mineral Resources (M&I) | 49,804 | 1.30 | 2,081 | 280,315 | 1.55 | 13,945 | 330,118 | 1.51 | 16,027 |
The following table set forth the Inferred Mineral Resource estimates and for the Company's mineral properties at December 31, 2023.
Inferred Mineral Resources | |||
Tonnes | Grade | Content | |
Sadiola Mine | 16,177 | 1.12 | 581 |
Kurmuk Project | 5,980 | 1.62 | 311 |
Bonikro Mine | 19,588 | 1.30 | 816 |
Agbaou Mine | 959 | 1.84 | 57 |
Total Mineral Resources (Inferred) | 42,704 | 1.29 | 1,765 |
Notes:
- Mineral Resources are estimated in accordance with CIM Standards and NI 43-101.
- Shown on a
100% basis. - Are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
- Are listed at 0.5 g/t Au cut-off grade, constrained within an
US /oz pit shell and depleted to 31 December 2023.$180 0 - Rounding of numbers may lead to discrepancies when summing columns.
View original content to download multimedia:https://www.prnewswire.com/news-releases/allied-gold-announces-third-quarter-2024-results-implementing-operational-improvements-securing-key-regulatory-approvals-advancing-development-at-kurmuk-and-sadiola-and-strengthening-financial-flexibility-through-strategic-ini-302299468.html
SOURCE Allied Gold Corporation
FAQ
What was Allied Gold's (AAUCF) Q3 2024 gold production?
What is Allied Gold's (AAUCF) full-year 2024 production guidance?
How much did Allied Gold (AAUCF) invest in the Kurmuk Project year-to-date?