STOCK TITAN

TeraWulf Announces May 2024 Production and Operations Update

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags
Rhea-AI Summary

TeraWulf, a bitcoin mining company, announced its May 2024 production update.

The company mined 186 bitcoin, averaging 6 bitcoin per day. May marked the first full month after the April halving event, which reduced block rewards.

TeraWulf's self-mining capacity reached 8.0 EH/s, an 82% year-over-year increase.

The average power cost per bitcoin mined was $31,239, based on a $0.039/kWh rate.

Construction of Building 4 at Lake Mariner, which will house 10,000 S21 and S21 Pro miners, is set for completion in June 2024, expected to boost capacity to over 10.0 EH/s in the second half of 2024.

The company is also advancing a 2.0 MW AI/HPC pilot at Lake Mariner with next-gen GPU technology and SOC 2 standards.

Positive
  • Self-mining capacity increased by 82% year-over-year, reaching 8.0 EH/s.
  • Mined 186 bitcoin in May 2024, averaging 6 bitcoin per day.
  • Construction of Building 4 on track, expected to boost capacity to over 10.0 EH/s in the second half of 2024.
  • AI/HPC pilot at Lake Mariner advancing with next-gen GPU technology and SOC 2 standards.
  • 95% zero-carbon energy powering bitcoin mining operations.
Negative
  • Average power cost per bitcoin mined increased to $31,239 in May 2024, up from $16,659 in April 2024.
  • Nautilus facility experienced temporary performance issues in early May due to breaker trips and fan blade installation.

Insights

TeraWulf reported achieving an 82% year-over-year increase in their self-mining capacity, reaching 8.0 EH/s. This substantial growth highlights their ability to scale operations efficiently. However, it's important to note the increased power cost per bitcoin, which averaged $31,239 in May. This is significantly higher than the previous month, influenced by reduced block rewards post-halving. For retail investors, understanding the dynamics of Bitcoin halving is essential. Halving reduces the rewards for mining, which can increase costs and reduce profitability unless offset by higher Bitcoin prices or improved efficiency. The operational efficiency of 95% of the installed nameplate capacity is commendable and indicates robust management of their mining infrastructure. The growth trajectory, with Building 4 expected to add significant capacity by the second half of 2024, is a positive signal for future scalability.

Overall, the financial outlook appears mixed. While operational capacity is growing, high power costs need careful monitoring. Investors should watch how TeraWulf manages these costs and the impact of future bitcoin prices on profitability.

From a technology perspective, TeraWulf's advancements in their AI/HPC pilot are noteworthy. The pilot is designed to support next-generation GPU technology and meet SOC 2 standards, emphasizing data security. This positions TeraWulf not just as a bitcoin miner but as a player in the high-performance computing (HPC) space, potentially diversifying its revenue streams. The infrastructure allowing up to 8 nodes per rack with over 100 kW per rack power density is impressive, as is the integration of liquid cooling technology. These features are critical for tackling the heat and power challenges associated with HPC and AI workloads. For retail investors, this diversification is worth watching as it could reduce dependency on bitcoin mining alone and mitigate risks associated with cryptocurrency volatility.

In summary, the technological investments enhance TeraWulf's positioning in the digital infrastructure space, offering potential for long-term growth beyond just cryptocurrency mining.

The market context in which TeraWulf operates is important for evaluating its business potential. The company benefits from its vertically integrated and zero-carbon energy approach, appealing to the environmentally conscious segment of investors. The completion of Building 4 and the commencement of Building 5 indicate a clear pathway to increased capacity. However, the market is rife with volatility and bitcoin’s price fluctuations can significantly impact TeraWulf's earnings. The halving event has already increased operational costs, which will pressurize margins if bitcoin prices do not rise correspondingly. Investors should consider the broader market trends, including regulatory changes and energy costs, which could affect TeraWulf’s operations. Participation in industry conferences suggests a proactive engagement with stakeholders, which could foster positive investor sentiment.

Ultimately, while TeraWulf's expansion plans are promising, market volatility and rising costs present challenges that need to be closely monitored.

8.0 EH/s of installed and operational self-mining capacity, up 82% Y-o-Y

Building 4 at Lake Mariner scheduled for completion in June, paving the way to >10.0 EH/s in 2H 2024

AI/HPC digital infrastructure pilot advancing at Lake Mariner with innovative features and a strong focus on data security

Releases latest construction update video on the Company’s YouTube channel here

EASTON, Md., June 04, 2024 (GLOBE NEWSWIRE) -- TeraWulf Inc. (Nasdaq: WULF) (“TeraWulf” or the “Company”), owners and operators of vertically integrated, domestic bitcoin mining facilities powered by 95% zero-carbon energy, today provided an unaudited monthly production and operations update for May 2024.

May 2024 Production and Operations Highlights

  • Self-Mined Bitcoin: Mined 186 bitcoin in May, reflecting the first full month of reduced block rewards following the April Halving event, with an average production rate of approximately 6.0 bitcoin per day.
  • Power cost: Averaged $31,239 per bitcoin self-mined in May, reflecting an approximate rate of $0.039/kWh and excluding the benefit of expected demand response or ancillary services proceeds.
  • Operating Capacity: TeraWulf's installed and operational self-mining capacity reached approximately 8.0 EH/s, representing an 82% year-over-year increase.
  • AI/HPC Pilot: Advancing 2.0 MW AI pilot at Lake Mariner, designed to accommodate next generation GPU technology and meet SOC 2 standards.
Key Metrics 1May 2024April 2024
Bitcoin Self-Mined Lake Mariner144259
Bitcoin Self-Mined Nautilus24276
Value per Bitcoin Self-Mined 3$65, 094$66, 322
Power Cost per Bitcoin Self-Mined$31,239$16,659
Avg. Operating Hash Rate (EH/s) 47.67.8
Nameplate Miner Efficiency (J/TH) 524.624.6


Management Commentary

“During May, the Company mined 186 bitcoin, equivalent to approximately 6 bitcoin per day,” said Sean Farrell, SVP of Operations at TeraWulf.

“The Lake Mariner team is making remarkable progress on Building 4, which is scheduled to complete construction in June and will house approximately 10,000 of Bitmain’s latest generations of S21 and S21 Pro miners. Once online, Building 4 is expected to increase our total operating capacity to above 10.0 EH/s,” continued Farrell. “Looking ahead, we have already optimized a 50 MW modular building with local key contractors for Building 5, which is currently anticipated to be online in Q1 2025.”

Production and Operations Update

As of May 31, 2024, TeraWulf's operational infrastructure capacity comprised 160 MW at the Lake Mariner facility and 50 MW at the Nautilus facility, with the company's total self-mining hash rate at approximately 8.0 EH/s. On average, TeraWulf's miners continue to operate at 95% of installed nameplate capacity, consistent with the Company’s prior monthly performance. In early May, the Nautilus facility experienced a temporary performance reduction caused by intermittent breaker trips and the installation of low-noise fan blades, which has been addressed. Also, during May the Lake Mariner team focused on optimizing the performance of Building 3 by leveraging valuable data gathered from higher temperature operations.

Construction of Building 4 (35 MW) at the Lake Mariner facility remains on track for completion in June 2024, which is expected to further increase TeraWulf’s total operational capacity to more than 10.0 EH/s. For a more in-depth look at Building 4 as well as an overview of TeraWulf’s future expansion plans, watch the latest construction update video on the Company’s YouTube channel here.

Relating to WULF Compute, progress is underway at Lake Mariner on the previously announced construction of a 2.0 MW AI/HPC digital infrastructure pilot, supporting current and next-generation GPU technology. Key features include:

  • Infrastructure accommodating up to 8 nodes per rack with a power density exceeding 100 kW per rack.
  • Data center racks that incorporate liquid cooling technology, facilitating chilled doors and/or direct liquid-to-chip cooling.
  • Facility design with an emphasis on data security to achieve System and Organization Controls 2 (SOC 2) standards.

Upcoming Industry Events

Various members of the Company’s senior management will be participating in the following upcoming investor and industry conferences:

  • June 25, 2024: Northland Growth Conference 2024, Virtual
  • June 25-26, 2024: Mining Disrupt Conference, Miami, FL
  • July 25-27, 2024: Bitcoin 2024, Nashville, TN

About TeraWulf

TeraWulf owns and operates vertically integrated, environmentally clean bitcoin mining facilities in the United States. Led by an experienced group of energy entrepreneurs, the Company currently has two Bitcoin mining facilities: the wholly owned Lake Mariner facility in New York, and Nautilus Cryptomine facility in Pennsylvania, a joint venture with Cumulus Coin, LLC. TeraWulf generates domestically produced Bitcoin powered by 95% zero carbon energy resources including nuclear, hydro, and solar with a goal of utilizing 100% zero-carbon energy. With a core focus on ESG that ties directly to its business success, TeraWulf expects to provide industry leading mining economics at an industrial scale.

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995, as amended. Such forward-looking statements include statements concerning anticipated future events and expectations that are not historical facts. All statements, other than statements of historical fact, are statements that could be deemed forward-looking statements. In addition, forward-looking statements are typically identified by words such as “plan,” “believe,” “goal,” “target,” “aim,” “expect,” “anticipate,” “intend,” “outlook,” “estimate,” “forecast,” “project,” “continue,” “could,” “may,” “might,” “possible,” “potential,” “predict,” “should,” “would” and other similar words and expressions, although the absence of these words or expressions does not mean that a statement is not forward-looking. Forward-looking statements are based on the current expectations and beliefs of TeraWulf’s management and are inherently subject to a number of factors, risks, uncertainties and assumptions and their potential effects. There can be no assurance that future developments will be those that have been anticipated. Actual results may vary materially from those expressed or implied by forward-looking statements based on a number of factors, risks, uncertainties and assumptions, including, among others: (1) conditions in the cryptocurrency mining industry, including fluctuation in the market pricing of bitcoin and other cryptocurrencies, and the economics of cryptocurrency mining, including as to variables or factors affecting the cost, efficiency and profitability of cryptocurrency mining; (2) competition among the various providers of cryptocurrency mining services; (3) changes in applicable laws, regulations and/or permits affecting TeraWulf’s operations or the industries in which it operates, including regulation regarding power generation, cryptocurrency usage and/or cryptocurrency mining, and/or regulation regarding safety, health, environmental and other matters, which could require significant expenditures; (4) the ability to implement certain business objectives and to timely and cost-effectively execute integrated projects; (5) failure to obtain adequate financing on a timely basis and/or on acceptable terms with regard to growth strategies or operations; (6) loss of public confidence in bitcoin or other cryptocurrencies and the potential for cryptocurrency market manipulation; (7) adverse geopolitical or economic conditions, including a high inflationary environment; (8) the potential of cybercrime, money-laundering, malware infections and phishing and/or loss and interference as a result of equipment malfunction or break-down, physical disaster, data security breach, computer malfunction or sabotage (and the costs associated with any of the foregoing); (9) the availability, delivery schedule and cost of equipment necessary to maintain and grow the business and operations of TeraWulf, including mining equipment and infrastructure equipment meeting the technical or other specifications required to achieve its growth strategy; (10) employment workforce factors, including the loss of key employees; (11) litigation relating to TeraWulf and/or its business; and (12) other risks and uncertainties detailed from time to time in the Company’s filings with the Securities and Exchange Commission (“SEC”). Potential investors, stockholders and other readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they were made. TeraWulf does not assume any obligation to publicly update any forward-looking statement after it was made, whether as a result of new information, future events or otherwise, except as required by law or regulation. Investors are referred to the full discussion of risks and uncertainties associated with forward-looking statements and the discussion of risk factors contained in the Company’s filings with the SEC, which are available at www.sec.gov.

Company Contact:
Jason Assad
Director of Corporate Communications
assad@terawulf.com
(678) 570-6791

_________________

1 The Company’s share of the earnings or losses from operations at the Nautilus Cryptomine facility is reflected within “Equity in net income (loss) of investee, net of tax” in the consolidated statements of operations. Accordingly, operating results of the Nautilus Cryptomine facility are not reflected in revenue, cost of revenue or cost of operations lines in TeraWulf’s consolidated statements of operations. The Company uses these metrics as indictors of operational progress and effectiveness and believes they are useful to investors for the same purposes and to provide comparisons to peer companies. All figures except Bitcoin Self-Mined are estimates and remain subject to standard month-end adjustments.
2 The figures for Bitcoin Self-Mined Nautilus included in the production and operations report for April 2024, previously released on May 2, 2024, have been updated herein.
3 Computed as the weighted-average opening price of bitcoin on each respective day the Bitcoin Self-Mined is earned.
4 While nameplate inventory as of May 31, 2024 for WULF’s two facilities is estimated at 8.0 EH/s, actual monthly hash rate performance depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICS due to adverse weather and ASIC maintenance and repair.
5 Nameplate miner efficiency excludes auxiliary load.


FAQ

What was TeraWulf's bitcoin mining production in May 2024?

TeraWulf mined 186 bitcoin in May 2024, averaging 6 bitcoin per day.

How much did TeraWulf's self-mining capacity increase year-over-year?

TeraWulf's self-mining capacity increased by 82% year-over-year, reaching 8.0 EH/s.

What is the expected increase in TeraWulf's operational capacity in 2024?

TeraWulf's operational capacity is expected to increase to over 10.0 EH/s in the second half of 2024 with the completion of Building 4 at Lake Mariner.

What was the average power cost per bitcoin mined by TeraWulf in May 2024?

The average power cost per bitcoin mined by TeraWulf in May 2024 was $31,239.

What advancements is TeraWulf making in AI/HPC digital infrastructure?

TeraWulf is advancing a 2.0 MW AI/HPC pilot at Lake Mariner, designed to accommodate next-generation GPU technology and meet SOC 2 standards.

TeraWulf Inc.

NASDAQ:WULF

WULF Rankings

WULF Latest News

WULF Stock Data

1.75B
382.60M
26.47%
45.15%
11.64%
Capital Markets
Finance Services
Link
United States of America
EASTON