Wesdome Announces Third Quarter 2023 Financial Results
- Wesdome Gold Mines Ltd. has reaffirmed its 2023 production guidance, indicating stability and confidence in its operations and future plans.
- The company's payable gold production in Q3 2023 was 27,760 ounces at cash costs per ounce of $1,755 and all-in sustaining costs per ounce of $2,711, reflecting strong financial performance.
- The Q3 2023 net loss of $3.2 million and adjusted net loss of $2.6 million may raise concerns about the company's profitability and financial management.
TORONTO, Nov. 08, 2023 (GLOBE NEWSWIRE) -- Wesdome Gold Mines Ltd. (TSX: WDO) (“Wesdome” or the “Company”) today announces third quarter (“Q3 2023”) financial results. Management will host a conference call tomorrow, Thursday November 9, 2023, at 10:00 a.m. Eastern time to discuss the results. Dial-in details for the call can be found near the end of this press release.
Third Quarter 2023 Highlights
- Payable gold production in the third quarter was 27,760 ounces at cash costs per ounce1 of
$1,755 (US$1,308) and all-in sustaining costs (“AISC”) per ounce 1 of$2,711 (US$2,021) . Q3 was forecasted as the lightest cash flow quarter of the year due to timing of capital outlays and planned downtime at Eagle River. - At Kiena, development of the ramp to the 129-level mining horizon tracked ahead of schedule. Delineation drilling to date has also confirmed the continuity, thickness, and high grade of the A zone at depth, as per the reserve block model.
- Cash margins1 were
$22.2 million , and free cash flow1 was$10.7 million . During the quarter Wesdome received a$12.5 million tax refund. - Quarterly net loss of
$3.2 million ($0.02) per share in the third quarter of 2023 and adjusted net loss1 of$2.6 million ($0.02) per share. Positive operating cash flow of$45.1 million ($0.30 per share). - Available liquidity of
$142.6 million , including$31.6 million in cash and$111 million of undrawn availability under the Company’s revolving credit facility. - Reaffirming consolidated 2023 production guidance of 110,000 to 130,000 ounces as well as cost guidance for cash costs, all-in sustaining costs and capital expenditures.
Anthea Bath, President and CEO, commented, “In the recent quarter, we made solid progress in advancing development and de-risking our future strategic plans. Eagle River reported consistent results after the completion of mill and infrastructure upgrades during an annual shutdown, and Kiena's ramp development remains ahead of schedule, with access to the 129-metre level achieved after quarter end in November. Elevated cost levels during the quarter were due to planned downtime and timing of capital outlays.
Reaching the 129-level metre at Kiena was an important milestone for Wesdome as it will enable access to the higher-grade Deep A zone stopes in the first half of next year. Also, efforts continue to further de-risk our 2024 mine plans, with delineation drilling reinforcing our block model and overall mine strategy. Site preparation for the Presqu’Île ramp portal and related infrastructure is also underway following the receipt of permits at the end of the quarter.
At Eagle River, performance on various fronts continues to exceed budget. An asset optimization initiative is being launched internally to optimize the unit cost structure of the asset with a view to value by investigating alternative mining and material handling methods, cut-off grade levels, and planning methodologies.
We are expecting a strong finish to this year and based on our year-to-date performance, we are well positioned to deliver on the mid-point of production and cost guidance. Looking ahead, preliminary plans for 2024 continue to point to a production and operating cash flow rebound which will support total capital investment levels similar to this year.”
Financial and Operating Highlights
A summary of the Company’s consolidated financial and operating results for the nine months ended September 30, 2023 are presented below:
(in thousands of Canadian dollars, unless otherwise indicated) | Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | ||||
Financial Results | ||||||||
Revenues | 69,696 | 61,823 | 230,952 | 190,448 | ||||
Cost of sales | 71,450 | 56,294 | 216,916 | 152,374 | ||||
Cash margin1 | 22,233 | 16,993 | 85,393 | 69,208 | ||||
Net loss attributable to shareholders | (3,248 | ) | (3,899 | ) | (8,607 | ) | (11,179 | ) |
Net income ($/sh) | (0.02 | ) | (0.03 | ) | (0.06 | ) | (0.08 | ) |
Adjusted attributable net loss1 | (2,573 | ) | (3,899 | ) | (4,330 | ) | (2,329 | ) |
Adjusted attributable net loss1 ($/sh) | (0.02 | ) | (0.03 | ) | (0.03 | ) | (0.02 | ) |
Operating cash flow | 45,076 | 12,945 | 64,175 | 54,939 | ||||
Operating cash flow ($/sh) | 0.30 | 0.09 | 0.44 | 0.39 | ||||
Cash flow from financing activities | (2,370 | ) | 21,961 | 7,367 | 20,128 | |||
Cash flow from investing activities | (33,191 | ) | (33,681 | ) | (73,145 | ) | 107,090 | |
Free cash flow1 | 10,672 | (23,193 | ) | (14,204 | ) | (58,565 | ) | |
Free cash flow1 ($/sh) | 0.07 | (0.16 | ) | (0.10 | ) | (0.41 | ) | |
Operating Results | ||||||||
Gold produced (oz) | 27,760 | 22,883 | 87,119 | 75,734 | ||||
Gold sold (oz) | 27,000 | 27,500 | 89,000 | 81,500 | ||||
Average realized gold price ($/oz) | 2,579 | 2,246 | 2,592 | 2,334 | ||||
Average realized gold price (US$/oz) | 1,923 | 1,720 | 1,926 | 1,819 | ||||
Cash costs1 ($/oz) | 1,755 | 1,628 | 1,633 | 1,485 | ||||
All-in sustaining costs1 ($/oz) | 2,711 | 2,217 | 2,293 | 1,975 | ||||
All-in sustaining costs1 (US$/oz) | 2,021 | 1,698 | 1,704 | 1,539 | ||||
Financial Position | ||||||||
Cash and cash equivalents | 31,582 | 24,741 | 31,582 | 24,741 | ||||
Working capital | (18,839 | ) | (35,457 | ) | (18,839 | ) | (35,457 | ) |
Total assets | 605,364 | 578,762 | 605,364 | 578,762 | ||||
Current liabilities | 87,577 | 93,733 | 87,577 | 93,733 | ||||
Total liabilities | 180,981 | 190,542 | 180,981 | 190.542 | ||||
Notes:
- Refer to the section entitled “Non-IFRS Performance Measures” for the reconciliation of these non-IFRS measurements to the financial statements
Eagle River, Ontario
Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | |
Ore milled (tonnes) | ||||
Eagle River | 55,153 | 52,247 | 167,959 | 165,428 |
Mishi | - | 3,595 | 6,150 | 23,153 |
Total Ore Milled | 55,153 | 55,842 | 174,109 | 188,581 |
Head grade (grams per tonne, “g/t”) | ||||
Eagle River | 11.9 | 10.7 | 12.1 | 10.6 |
Mishi | - | 2.8 | 2.3 | 3.2 |
Total head grade | 11.9 | 10.2 | 12.1 | 9.7 |
Recoveries (%) | ||||
Eagle River | 96.7 | 96.6 | 96.7 | 96.6 |
Mishi | - | 83.0 | 72.5 | 83.5 |
Total Gold recovery | 96.7 | 96.3 | 96.7 | 96.0 |
Gold production (ounces) | ||||
Eagle River | 20,391 | 17,405 | 63,395 | 54,495 |
Mishi | - | 270 | 332 | 2,005 |
Total Gold Production | 20,391 | 17,675 | 63,727 | 56,500 |
Production sold (ounces) | 19,600 | 18,800 | 66,100 | 57,600 |
Production costs per tonne milled1 | 503 | 475 | 485 | 412 |
Cash margin1 ($/oz) | 1,134 | 774 | 1,202 | 966 |
Cash costs1 ($/oz) | 1,442 | 1,473 | 1,380 | 1,377 |
All-in sustaining costs1 ($/oz) | 2,467 | 2,259 | 2,039 | 1,989 |
For the three months ended September 30, 2023 and 2022, production increased by
Q3 2023 cash cost of
Q3 2023 AISC of
Generated
Kiena, Quebec
Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | |
Ore milled (tonnes) | 47,351 | 16,112 | 141,499 | 63,752 |
Head grade (grams per tonne, “g/t”) | 4.9 | 10.2 | 5.2 | 9.5 |
Recoveries (%) | 98.4 | 98.5 | 98.0 | 98.4 |
Gold production (ounces) | 7,369 | 5,208 | 23,392 | 19,234 |
Production sold (ounces) | 7,400 | 8,700 | 22,900 | 23,900 |
Production costs per tonne milled1 | 402 | 869 | 419 | 643 |
Cash margin1 ($/oz) | 0 | 280 | 258 | 568 |
Cash costs1 ($/oz) | 2,585 | 1,963 | 2,365 | 1,746 |
All-in sustaining costs1 ($/oz) | 3,359 | 2,126 | 3,027 | 1,941 |
For the three months ended September 30, 2023 and 2022, production increased by
Q3 2023 cash cost of
Q3 2023 AISC of
Q3 2023 cash margin net AISC1 of negative
Exploration Updates
Eagle River
Recent exploration drilling within the mine diorite, has extended the 300 East Zone to the 1,600 m-level and remains open down plunge.
The drilling has confirmed the continuity of the mineralization at depth, thus suggesting that many other similar parallel zones, such as 808, 811, 818, 711 and 7 East, have this same potential to continue at depth and will be tested with ongoing drilling.
Initial surface and underground exploration drilling, commenced in July 2023 to test the volcanic rocks west of the mine diorite, has returned high grades within 200 metres from surface, while the first underground hole 750 metres down plunge has also intersected similar mineralization. Highlights of the initial surface drilling of the volcanic rocks returned 64.4 g/t Au over 0.4 m core length. These intersections suggest that a newly defined shoot could be located in this area.
Kiena
Underground exploration drilling has been focused on better delineating Kiena Deep A zones in advance of the planned mining. Limited exploration has been completed to extend and better define the deeper portion of the Kiena Deep zones. This drilling will be increased in the future once more optimal drill platforms are established.
Recent surface drilling at the Presqu’ile zone has confirmed not only the continuity of the gold mineralization and the validity of the geologic model, but also the potential for down plunge extensions towards the east. Highlights of recent in-fill drilling include 32.5 g/t over 3.0 m core length. The drilling will be used to convert resources into reserves at year end.
The excavation of an exploration ramp from surface to access the near-surface Presqu’ile Zone will be underway in Q4 2023 now that the necessary permits have been secured.
2023 Outlook
2023 Guidance | YTD 2023 Performance | ||
Gold production | |||
Eagle River | 80,000 – 90,000 ounces | 63,395 ounces | |
Mishi | - | 332 ounces | |
Kiena | 30,000 – 40,000 ounces | 23,392 ounces | |
Total | 110,000 – 130,000 ounces | 87,119 ounces | |
Head grade (g/t Au) | |||
Eagle River | 11.5 – 12.5 | 12.1 | |
Mishi | - | 2.3 | |
Kiena | 3.7 – 4.7 | 5.2 | |
Cash cost per ounce 1 | (US | (US | |
AlSC per ounce 1 | (US | (US |
1 Operating cost per ounce sold and all-in sustaining cost per ounce are non-IFRS measures, please reference the Company’s interim management discussion and analysis for the period ended September 30, 2023
Third Quarter 2023 Conference Call and Webcast
The financial statements and management discussion and analysis will be available on the company’s website at www.wesdome.com and on SEDAR+ www.sedarplus.ca. A conference call and webcast to discuss these results will be held on November 9, at 10:00 am ET.
- Participants may register for the call at the link below to obtain dial in details. Preregistration is required for this event. It is recommended you join 10 minutes prior to the start of the event.
- Participant Registration Link: https://register.vevent.com/register/BI342316b2dae64c7fa72b789b4ffcb8a1
- Webcast Link: https://edge.media-server.com/mmc/p/4bu4ty2t
- The webcast can also be accessed under the news and events section of the company’s website
Technical Disclosure
The technical content of this release has been compiled, reviewed and approved by Frédéric Langevin, Eng, Chief Operating Officer of the Company and Michael Michaud, P.Geo., Vice President, Exploration of the Company and each a "Qualified Person" as defined in National Instrument 43-101 -Standards of Disclosure for Mineral Projects.
Cautionary Note to United States Investors Concerning Estimates of Reserves and Resources
The mineral reserve and resource estimates reported in this news release were prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) as required by Canadian securities regulatory authorities. The United States Securities and Exchange Commission (the “SEC”) applies different standards in order to classify and report mineralization. This news release uses the terms “measured”, “indicated” and “inferred” mineral resources, as required by NI 43-101. Readers are advised that although such terms are recognized and required by Canadian securities regulations, the SEC does not recognize such terms. Canadian standards differ significantly from the requirements of the SEC. Readers are cautioned not to assume that any part or all of the mineral deposits in these categories constitute or will ever be converted into mineral reserves. In addition, “inferred” mineral resources have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource exists, is economically or legally mineable or will ever be upgraded to a higher category of mineral resource.
About Wesdome
Wesdome is a Canadian focused gold producer with two high grade underground assets, the Eagle River mine in Ontario and the recently commissioned Kiena mine in Quebec. The Company’s primary goal is to responsibly leverage this operating platform and high-quality brownfield and greenfield exploration pipeline to build Canada’s next intermediate gold producer. Wesdome trades on the Toronto Stock Exchange under the symbol “WDO,” with a secondary listing on the OTCQX under the symbol “WDOFF.”
For further information, please contact:
Lindsay Carpenter Dunlop
VP Investor Relations
416-360-3743 ext. 2025
invest@wesdome.com
To receive Wesdome’s news releases by email, please register using the Wesdome website at www.wesdome.com
Cautionary Note Regarding Forward-Looking Information and Statements
This news release contains “forward-looking information” which may include, but is not limited to, statements with respect to the future financial or operating performance of the Company and its projects. Often, but not always, forward-looking statements can be identified by the use of words such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or variations (including negative variations) of such words and phrases, or state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Forward-looking statements contained herein are made as of the date of this press release and the Company disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking statements if circumstances, management’s estimates or opinions should change, except as required by securities legislation. Accordingly, the reader is cautioned not to place undue reliance on forward-looking statements. The Company has included in this news release certain non-IFRS performance measures, including, but not limited to, mine operating profit, mining and processing costs and cash costs. Cash costs per ounce reflect actual mine operating costs incurred during the fiscal period divided by the number of ounces produced. These measures are not defined under IFRS and therefore should not be considered in isolation or as an alternative to or more meaningful than, net income (loss) or cash flow from operating activities as determined in accordance with IFRS as an indicator of our financial performance or liquidity. The Company believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate the Company's performance and ability to generate cash flow.
FINANCIAL AND OPERTAIONAL RESULTS | |||||||||||||
Three Months Ended | Six Months Ended | ||||||||||||
June 30, | June 30, | ||||||||||||
2023 | 2022 | 2023 | 2022 | ||||||||||
Operating data | |||||||||||||
Milling (tonnes) | |||||||||||||
Eagle River | 64,672 | 59,964 | 112,805 | 113,181 | |||||||||
Mishi | 0 | 7,685 | 6,150 | 19,558 | |||||||||
Kiena | 51,824 | 26,478 | 94,148 | 47,640 | |||||||||
Throughput 2 | 116,496 | 94,127 | 213,103 | 180,379 | |||||||||
Head grades (g/t) | |||||||||||||
Eagle River | 11.4 | 9.6 | 12.3 | 10.6 | |||||||||
Mishi | 0.0 | 2.8 | 2.3 | 3.3 | |||||||||
Kiena | 5.0 | 10.6 | 5.4 | 9.3 | |||||||||
Recovery (%) | |||||||||||||
Eagle River | 96.5 | 95.6 | 96.7 | 96.6 | |||||||||
Mishi | 0.0 | 81.2 | 72.5 | 83.6 | |||||||||
Kiena | 97.7 | 98.5 | 97.8 | 98.3 | |||||||||
Production (ounces) | |||||||||||||
Eagle River | 22,845 | 17,756 | 43,004 | 37,090 | |||||||||
Mishi | 0 | 570 | 332 | 1,735 | |||||||||
Kiena | 8,147 | 8,914 | 16,024 | 14,026 | |||||||||
Total gold produced 2 | 30,992 | 27,240 | 59,360 | 52,851 | |||||||||
Total gold sales (ounces) | 32,000 | 26,000 | 62,000 | 54,000 | |||||||||
Eagle River Complex (per ounce of gold sold) 1 | |||||||||||||
Average realized price | $ | 2,625 | $ | 2,382 | $ | 2,584 | $ | 2,389 | |||||
Cash costs | 1,526 | 1,395 | 1,353 | 1,330 | |||||||||
Cash margin | $ | 1,099 | $ | 987 | $ | 1,231 | $ | 1,059 | |||||
All-in Sustaining Costs 1 | $ | 2,019 | $ | 1,940 | $ | 1,859 | $ | 1,858 | |||||
Mine operating costs/tonne milled 1 | $ | 503 | $ | 387 | $ | 474 | $ | 386 | |||||
Average 1 USD → CAD exchange rate | 1.3428 | 1.2768 | 1.3477 | 1.2715 | |||||||||
Cash costs per ounce of gold sold (US$) 1 | $ | 1,136 | $ | 1,093 | $ | 1,004 | $ | 1,046 | |||||
All-in Sustaining Costs (US$) 1 | $ | 1,504 | $ | 1,519 | $ | 1,379 | $ | 1,461 | |||||
Kiena Mine (per ounce of gold sold) 1 | |||||||||||||
Average realized price | $ | 2,676 | $ | 2,372 | $ | 2,642 | $ | 2,355 | |||||
Cash costs 3, 5 | 2,257 | 2,018 | 2,261 | 1,622 | |||||||||
Cash margin | $ | 419 | $ | 354 | $ | 381 | $ | 733 | |||||
All-in Sustaining Costs 1 | $ | 2,755 | $ | 2,284 | $ | 2,868 | $ | 1,834 | |||||
Mine operating costs/tonne milled 1 | $ | 379 | $ | 557 | $ | 430 | $ | 567 | |||||
Average 1 USD → CAD exchange rate | 1.3428 | 1.2768 | 1.3477 | 1.2715 | |||||||||
Cash costs per ounce of gold sold (US$) 1 | $ | 1,681 | $ | 1,581 | $ | 1,678 | $ | 1,276 | |||||
All-in Sustaining Costs (US$) 1 | $ | 2,052 | $ | 1,789 | $ | 2,128 | $ | 1,442 | |||||
Financial Data | |||||||||||||
Cash margin 1 | $ | 28,722 | $ | 21,873 | $ | 63,130 | $ | 52,215 | |||||
Net loss | $ | (5,014 | ) | $ | (14,331 | ) | $ | (5,359 | ) | $ | (7,280 | ) | |
Net income (loss) adjusted 1 | $ | (5,014 | ) | $ | (5,481 | ) | $ | (1,757 | ) | $ | 1,570 | ||
Earnings before interest, taxes, depreciation and amortization 1 | $ | 22,020 | $ | 8,844 | $ | 48,144 | $ | 29,494 | |||||
Operating cash flow | $ | 13,979 | $ | 12,101 | $ | 19,099 | $ | 41,994 | |||||
Free cash outflow 1 | $ | (5,279 | ) | $ | (28,576 | ) | $ | (24,876 | ) | $ | (35,372 | ) | |
Per share data | |||||||||||||
Net income | $ | (0.03 | ) | $ | (0.10 | ) | $ | (0.04 | ) | $ | (0.05 | ) | |
Adjusted net income 1 | $ | (0.03 | ) | $ | (0.04 | ) | $ | (0.01 | ) | $ | 0.01 | ||
Operating cash flow 1 | $ | 0.09 | $ | 0.08 | $ | 0.13 | $ | 0.30 | |||||
Free cash flow 1 | $ | (0.04 | ) | $ | (0.20 | ) | $ | (0.17 | ) | $ | (0.25 | ) | |
Wesdome Gold Mines Ltd. | |||||||||
Condensed Interim Statements of Financial Position | |||||||||
(Unaudited, expressed in thousands of Canadian dollars) | |||||||||
As at September 30, 2023 | As at December 31, 2022 | ||||||||
Assets | |||||||||
Current | |||||||||
Cash | $ | 31,582 | $ | 33,185 | |||||
Receivables and prepaids | 9,962 | 12,755 | |||||||
Inventories | 25,636 | 22,119 | |||||||
Income and mining tax receivable | - | 6,494 | |||||||
Share consideration receivable | 1,558 | 2,994 | |||||||
Total current assets | 68,738 | 77,547 | |||||||
Restricted cash | 2,718 | 1,176 | |||||||
Deferred financing costs | 1,014 | 1,411 | |||||||
Mining properties, plant and equipment | 525,649 | 525,860 | |||||||
Exploration properties | 1,339 | 1,139 | |||||||
Marketable securities | 480 | 960 | |||||||
Share consideration receivable | 1,425 | 2,576 | |||||||
Investment in associate | 4,001 | 8,458 | |||||||
Total assets | $ | 605,364 | $ | 619,127 | |||||
Liabilities | |||||||||
Current | |||||||||
Payables and accruals | $ | 43,056 | $ | 54,734 | |||||
Borrowings | 38,766 | 54,697 | |||||||
Income and mining tax payable | 2,317 | - | |||||||
Current portion of lease liabilities | 3,438 | 6,160 | |||||||
Total current liabilities | 87,577 | 115,591 | |||||||
Lease liabilities | 1,453 | 3,126 | |||||||
Deferred income and mining tax liabilities | 72,670 | 82,950 | |||||||
Decommissioning provisions | 19,281 | 18,941 | |||||||
Total liabilities | 180,981 | 220,608 | |||||||
Equity | |||||||||
Equity attributable to owners of the Company | |||||||||
Capital stock | 237,922 | 205,361 | |||||||
Contributed surplus | 9,749 | 7,359 | |||||||
Retained earnings | 178,332 | 186,939 | |||||||
Accumulated other comprehensive loss | (1,620 | ) | (1,140 | ) | |||||
Total equity attributable to owners of the Company | 424,383 | 398,519 | |||||||
Total liabilities and equity | $ | 605,364 | $ | 619,127 | |||||
Wesdome Gold Mines Ltd. | |||||||||||||||
Condensed Interim Statements of Loss and Comprehensive Loss | |||||||||||||||
(Unaudited, expressed in thousands of Canadian dollars except for per share amounts) | |||||||||||||||
Three Months Ended September 30, | Nine Months Ended September 30, | ||||||||||||||
2023 | 2022 | 2023 | 2022 | ||||||||||||
Revenues | $ | 69,696 | $ | 61,823 | $ | 230,952 | $ | 190,448 | |||||||
Cost of sales | (71,450 | ) | (56,294 | ) | (216,916 | ) | (152,374 | ) | |||||||
Gross profit | (1,754 | ) | 5,529 | 14,036 | 38,074 | ||||||||||
Other expenses | |||||||||||||||
Corporate and general | 4,707 | 2,918 | 12,376 | 9,514 | |||||||||||
Stock-based compensation | 328 | 823 | 3,653 | 2,453 | |||||||||||
Retirement costs | - | - | 1,190 | - | |||||||||||
Exploration and evaluation | 2,935 | 5,273 | 5,162 | 12,442 | |||||||||||
(Gain) loss on disposal of mining equipment | (5 | ) | 74 | 312 | 62 | ||||||||||
Total other expenses | 7,965 | 9,088 | 22,693 | 24,471 | |||||||||||
Operating (loss) income | (9,719 | ) | (3,559 | ) | (8,657 | ) | 13,603 | ||||||||
Impairment of investment in associate | (900 | ) | - | (3,600 | ) | (11,800 | ) | ||||||||
Interest expense | (1,114 | ) | (588 | ) | (3,598 | ) | (1,167 | ) | |||||||
Fair value adjustment on share consideration receivable | (1,010 | ) | (1,552 | ) | (2,587 | ) | (7,391 | ) | |||||||
Share of (loss) income of associate | (328 | ) | 155 | (994 | ) | (388 | ) | ||||||||
Accretion of decommissioning provisions | (269 | ) | (239 | ) | (759 | ) | (618 | ) | |||||||
(Loss) gain on dilution of ownership | (91 | ) | (35 | ) | 137 | (669 | ) | ||||||||
Other income (expense) | 363 | (1,420 | ) | 508 | (1,363 | ) | |||||||||
Loss before income and mining taxes | (13,068 | ) | (7,238 | ) | (19,550 | ) | (9,793 | ) | |||||||
Income and mining tax expense (recovery) | |||||||||||||||
Current | (4,202 | ) | 325 | (662 | ) | 4,601 | |||||||||
Deferred | (5,618 | ) | (3,664 | ) | (10,281 | ) | (3,215 | ) | |||||||
Total income and mining tax expense (recovery) | (9,820 | ) | (3,339 | ) | (10,943 | ) | 1,386 | ||||||||
Net loss | $ | (3,248 | ) | $ | (3,899 | ) | $ | (8,607 | ) | $ | (11,179 | ) | |||
Other comprehensive loss | |||||||||||||||
Change in fair value of marketable securities | (120 | ) | (360 | ) | (480 | ) | (1,260 | ) | |||||||
Total comprehensive loss | $ | (3,368 | ) | $ | (4,259 | ) | $ | (9,087 | ) | $ | (12,439 | ) | |||
Loss per share | |||||||||||||||
Basic | $ | (0.02 | ) | $ | (0.03 | ) | $ | (0.06 | ) | $ | (0.08 | ) | |||
Diluted | $ | (0.02 | ) | $ | (0.03 | ) | $ | (0.06 | ) | $ | (0.08 | ) | |||
Weighted average number of common | |||||||||||||||
shares (000s) | |||||||||||||||
Basic | 148,952 | 142,487 | 147,155 | 142,260 | |||||||||||
Diluted | 148,952 | 142,487 | 147,155 | 142,260 | |||||||||||
Wesdome Gold Mines Ltd. | |||||||||||||||||||
Condensed Interim Statements of Changes in Equity | |||||||||||||||||||
(Unaudited, expressed in thousands of Canadian dollars) | |||||||||||||||||||
Accumulated | |||||||||||||||||||
Other | |||||||||||||||||||
Capital | Contributed | Retained | Comprehensive | Total | |||||||||||||||
Stock | Surplus | Earnings | Loss | Equity | |||||||||||||||
Balance, December 31, 2021 | $ | 187,911 | $ | 5,859 | $ | 201,645 | $ | (240 | ) | $ | 395,175 | ||||||||
Net loss for the period ended | |||||||||||||||||||
September 30, 2022 | - | - | (11,179 | ) | - | (11,179 | ) | ||||||||||||
Other comprehensive loss | - | - | - | (1,260 | ) | (1,260 | ) | ||||||||||||
Exercise of options | 3,031 | - | - | - | 3,031 | ||||||||||||||
Value attributed to RSUs exercised | 638 | (638 | ) | - | - | - | |||||||||||||
Stock-based compensation | - | 2,453 | - | - | 2,453 | ||||||||||||||
Balance, September 30, 2022 | $ | 192,753 | $ | 6,501 | $ | 190,466 | $ | (1,500 | ) | $ | 388,220 | ||||||||
Balance, December 31, 2022 | $ | 205,361 | $ | 7,359 | $ | 186,939 | $ | (1,140 | ) | $ | 398,519 | ||||||||
Net loss for the period ended | |||||||||||||||||||
September 30, 2023 | - | - | (8,607 | ) | - | (8,607 | ) | ||||||||||||
At-the-Market offering: | |||||||||||||||||||
Common shares issued for cash | 31,988 | - | - | - | 31,988 | ||||||||||||||
Agents' fees and issuance costs | (1,366 | ) | - | - | - | (1,366 | ) | ||||||||||||
Other comprehensive loss | - | - | - | (480 | ) | (480 | ) | ||||||||||||
Exercise of options | 676 | - | - | - | 676 | ||||||||||||||
Value attributed to options exercised | 276 | (276 | ) | - | - | - | |||||||||||||
Value attributed to RSUs exercised | 616 | (616 | ) | - | - | - | |||||||||||||
Value attributed to PSUs exercised | 371 | (371 | ) | - | - | - | |||||||||||||
Stock-based compensation | - | 3,653 | - | - | 3,653 | ||||||||||||||
Balance, September 30, 2023 | $ | 237,922 | $ | 9,749 | $ | 178,332 | $ | (1,620 | ) | $ | 424,383 |
Wesdome Gold Mines Ltd. | |||||||||||||||||
Condensed Interim Statements of Cash Flows | |||||||||||||||||
(Unaudited, expressed in thousands of Canadian dollars) | |||||||||||||||||
Three Months Ended September 30, | Nine Months Ended September 30, | ||||||||||||||||
2023 | 2022 | 2023 | 2022 | ||||||||||||||
Operating Activities | |||||||||||||||||
Net loss | $ | (3,248 | ) | $ | (3,899 | ) | $ | (8,607 | ) | $ | (11,179 | ) | |||||
Depreciation and depletion | 23,987 | 11,464 | 71,327 | 31,134 | |||||||||||||
Stock-based compensation | 328 | 823 | 3,653 | 2,453 | |||||||||||||
Accretion of decommissioning provisions | 269 | 239 | 759 | 618 | |||||||||||||
Deferred income and mining tax recovery | (5,618 | ) | (3,664 | ) | (10,281 | ) | (3,215 | ) | |||||||||
Amortization of deferred financing cost | 133 | 99 | 397 | 268 | |||||||||||||
Interest expense | 1,114 | 588 | 3,598 | 1,167 | |||||||||||||
(Gain) loss on disposal of mining equipment | (5 | ) | 74 | 312 | 62 | ||||||||||||
Impairment of investment in associate | 900 | - | 3,600 | 11,800 | |||||||||||||
Fair value adjustment on share consideration receivable | 1,010 | 1,552 | 2,587 | 7,391 | |||||||||||||
Share of loss (income) of associate | 328 | (155 | ) | 994 | 388 | ||||||||||||
Loss (gain) on dilution of ownership | 91 | 35 | (137 | ) | 669 | ||||||||||||
Foreign exchange loss (gain) on borrowings | 4 | 1,569 | (3 | ) | 1,460 | ||||||||||||
Net changes in non-cash working capital | 13,275 | 6,978 | (13,498 | ) | 25,884 | ||||||||||||
Mining and income tax refund (paid) | 12,508 | (2,758 | ) | 9,474 | (13,961 | ) | |||||||||||
Net cash from operating activities | 45,076 | 12,945 | 64,175 | 54,939 | |||||||||||||
Financing Activities | |||||||||||||||||
Proceeds from At-the-Market offering | - | - | 31,988 | - | |||||||||||||
Agents' fees and issuance costs | (35 | ) | - | (1,366 | ) | - | |||||||||||
Proceeds from revolving credit facility | 10,000 | 25,928 | 10,000 | 40,884 | |||||||||||||
Repayment of revolving credit facility | (10,013 | ) | - | (25,931 | ) | (14,810 | ) | ||||||||||
Exercise of options | - | - | 676 | 3,031 | |||||||||||||
Repayment of lease liabilities | (1,208 | ) | (2,300 | ) | (4,402 | ) | (6,731 | ) | |||||||||
Deferred financing costs | - | (1,079 | ) | - | (1,079 | ) | |||||||||||
Interest paid | (1,114 | ) | (588 | ) | (3,598 | ) | (1,167 | ) | |||||||||
Net cash (used in) from financing activities | (2,370 | ) | 21,961 | 7,367 | 20,128 | ||||||||||||
Investing Activities | |||||||||||||||||
Additions to mining properties | (31,654 | ) | (11,058 | ) | (72,235 | ) | (24,380 | ) | |||||||||
Additions to mines under development | - | (22,780 | ) | - | (82,393 | ) | |||||||||||
Purchase of exploration property | - | - | (200 | ) | - | ||||||||||||
Funds held against standby letter of credit | (1,542 | ) | (25 | ) | (1,542 | ) | (519 | ) | |||||||||
Proceeds on disposal of mining equipment | 5 | 182 | 832 | 202 | |||||||||||||
Net cash used in investing activities | (33,191 | ) | (33,681 | ) | (73,145 | ) | (107,090 | ) | |||||||||
Increase (decrease) in cash | 9,515 | 1,225 | (1,603 | ) | (32,023 | ) | |||||||||||
Cash - beginning of period | 22,067 | 23,516 | 33,185 | 56,764 | |||||||||||||
Cash - end of period | $ | 31,582 | $ | 24,741 | $ | 31,582 | $ | 24,741 | |||||||||
Cautionary Note Regarding Non-GAAP Financial Measures
Average realized price per ounce of gold sold
Average realized price per ounce of gold sold is a non-IFRS measure and does not constitute a measure recognized by IFRS and does not have a standardized meaning defined by IFRS. Average realized price per ounce of gold sold is calculated by dividing gold sales proceeds received by the Company for the relevant period by the ounces of gold sold. It may not be comparable to information in other gold producers’ reports and filings.
In 000s, except per unit amounts | Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | ||||
Revenues per financial statements | 69,696 | 61,823 | 230,952 | 190,448 | ||||
Silver revenue from mining operations | (77 | ) | (54 | ) | (233 | ) | (203 | ) |
Gold revenue from mining operations (a) | 69,619 | 61,769 | 230,719 | 190,245 | ||||
Ounces of gold sold (b) | 27,000 | 27,500 | 89,000 | 81,500 | ||||
Average realized price gold sold CAD (c) = (a) ÷ (b) | 2,579 | 2,246 | 2,592 | 2,334 | ||||
Average 1 USD → CAD exchange rate (d) | 1.3414 | 1.3056 | 1.3456 | 1.2828 | ||||
Average realized price gold sold USD (c) ÷ (d) | 1,923 | 1,720 | 1,926 | 1,819 | ||||
Cash costs per ounce of gold sold
Cash cost per ounce of gold sold is a non-IFRS performance measure and does not constitute a measure recognized by IFRS and does not have a standardized meaning defined by IFRS, as well it may not be comparable to information in other gold producers’ reports and filings. The Company has included this non-IFRS performance measure throughout this document as Wesdome believes that this generally accepted industry performance measure provides a useful indication of the Company’s operational performance. The Company believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate the Company’s performance and ability to generate cash flow. Accordingly, it is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The following table provides a reconciliation of total cash costs per ounce of gold sold to cost of sales per the financial statements for each of the last eight quarters:
In 000s, except per unit amounts | Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | ||||
Cost of sales per financial statements | 71,450 | 56,294 | 216,916 | 152,374 | ||||
Depletion and depreciation | (23,987 | ) | (11,464 | ) | (71,327 | ) | (31,134 | ) |
Silver revenue from mining operations | (77 | ) | (54 | ) | (233 | ) | (203 | ) |
Cash costs (a) | 47,386 | 44,776 | 145,356 | 121,037 | ||||
Ounces of gold sold (b) | 27,000 | 27,500 | 89,000 | 81,500 | ||||
Cash costs per ounce of gold sold (c) = (a) ÷ (b) | 1,755 | 1,628 | 1,633 | 1,485 | ||||
Average 1 USD → CAD exchange rate (d) | 1.3414 | 1.3056 | 1.3456 | 1.2828 | ||||
Cash costs per ounce of gold sold USD (c) ÷ (d) | 1,308 | 1,247 | 1,214 | 1,158 | ||||
Production costs per tonne milled
Mine-site cost per tonne milled is a non-IFRS performance measure and does not constitute a measure recognized by IFRS and does not have a standardized meaning defined by IFRS, as well it may not be comparable to information in other gold producers’ reports and filings. As illustrated in the table below, this measure is calculated by adjusting cost of sales, as shown in the statements of income for non-cash depletion and depreciation, royalties and inventory level changes and then dividing by tonnes processed through the mill. Management believes that mine-site cost per tonne milled provides additional information regarding the performance of mining operations and allows Management to monitor operating costs on a more consistent basis as the per tonne milled measure reduces the cost variability associated with varying production levels. Management also uses this measure to determine the economic viability of mining blocks. As each mining block is evaluated based on the net realizable value of each tonne mined, the estimated revenue on a per tonne basis must be in excess of the production cost per tonne milled in order to be economically viable. Management is aware that this per tonne milled measure is impacted by fluctuations in throughput and thus uses this evaluation tool in conjunction with production costs prepared in accordance with IFRS. This measure supplements production cost information prepared in accordance with IFRS and allows investors to distinguish between changes in production costs resulting from changes in production versus changes in operating performance.
In 000s, except per unit amounts | Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | ||||
Cost of sales per financial statements | 71,450 | 56,294 | 216,916 | 152,374 | ||||
Depletion and depreciation | (23,987 | ) | (11,464 | ) | (71,327 | ) | (31,134 | ) |
Royalties | (1,029 | ) | (766 | ) | (3,199 | ) | (2,491 | ) |
Inventory adjustments | 384 | (3,518 | ) | 382 | 35 | |||
Mining and processing costs, before inventory adjustments (a) | 46,818 | 40,546 | 142,772 | 118,784 | ||||
Ore milled (tonnes) (b) | 102,505 | 71,954 | 315,608 | 252,333 | ||||
Production costs per tonne milled (a) ÷ (b) | 457 | 563 | 452 | 471 | ||||
Cash margin
Cash margin is a non-IFRS measure and does not constitute a measure recognized by IFRS and does not have a standardized meaning defined by IFRS, as well it may not be comparable to information in other gold producers’ reports and filings. It is calculated as the difference between gold sales revenue from mining operations and cash mine site operating costs (see Cash cost per ounce of gold sold under this Section above) per the Company’s Financial Statements. The Company believes it illustrates the performance of the Company’s operating mines and enables investors to better understand the Company’s performance in comparison to other gold producers who present results on a similar basis.
In 000s, except per unit amounts | Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 |
Gold revenue from mining operations (per above) | 69,619 | 61,769 | 230,719 | 190,245 |
Cash costs (per above) | 47,386 | 44,776 | 145,356 | 121,037 |
Cash margin | 22,233 | 16,993 | 85,363 | 69,208 |
Per ounce of gold sold (Canadian dollar): | ||||
Average realized price (a) | 2,579 | 2,246 | 2,592 | 2,334 |
Cash costs (b) | 1,755 | 1,628 | 1,633 | 1,485 |
Cash margin (a) – (b) | 824 | 618 | 959 | 849 |
All-in sustaining costs
All-in sustaining costs (“AISC”) include mine site operating costs incurred at Wesdome mining operations, sustaining mine capital and development expenditures, mine site exploration expenditures and equipment lease payments related to the mine operations and corporate administration expenses. The Company believes that this measure represents the total costs of producing gold from current operations and provides Wesdome and other stakeholders with additional information that illustrates the Company’s operational performance and ability to generate cash flow. This cost measure seeks to reflect the full cost of gold production from current operations on a per-ounce of gold sold basis. New project and growth capital are not included.
In 000s, except per unit amounts | Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | ||||
Cost of sales, per financial statements | 71,450 | 56,294 | 216,916 | 152,374 | ||||
Depletion and depreciation | (23,987 | ) | (11,464 | ) | (71,327 | ) | (31,134 | ) |
Silver revenue from mining operations | (77 | ) | (54 | ) | (233 | ) | (203 | ) |
Cash costs | 47,386 | 44,776 | 145,356 | 121,037 | ||||
Sustaining mine exploration and development | 9,683 | 5,134 | 27,191 | 15,686 | ||||
Sustaining mine capital equipment | 10,360 | 2,232 | 15,158 | 4,298 | ||||
Tailings management facility | 15 | 3,692 | 29 | 3,897 | ||||
Corporate and general | 4,707 | 2,918 | 12,376 | 9,514 | ||||
Less: Corporate development | (161 | ) | (87 | ) | (402 | ) | (224 | ) |
Payment of lease liabilities | 1,208 | 2,300 | 4,402 | 6,731 | ||||
All-in Sustaining costs (AISC) (a) | 73,198 | 60,965 | 204,110 | 160,939 | ||||
Ounces of gold sold (b) | 27,000 | 27,500 | 89,000 | 81,500 | ||||
AISC (c) = (a) ÷ (b) | 2,711 | 2,217 | 2,293 | 1,975 | ||||
Average 1 USD → CAD exchange rate (d) | 1.3414 | 1.3056 | 1.3456 | 1.2828 | ||||
AISC USD (c) ÷ (d) | 2,021 | 1,698 | 1,704 | 1,539 | ||||
Free cash flow and operating and free cash flow per share
Free cash flow is calculated by taking net cash provided by operating activities less cash used in capital expenditures and lease payments as reported in the Company’s financial statements. Free cash flow per share is calculated by dividing free cash flow by the weighted average number of shares outstanding for the period.
Operating cash flow per share is a non-IFRS measure and does not constitute a measure recognized by IFRS and does not have a standardized meaning defined by IFRS. Operating cash flow per share is calculated by dividing cash flow from operating activities in the Company’s Financial Statements by the weighted average number of shares outstanding for each year. It may not be comparable to information in other gold producers’ reports and filings.
In 000s, except per share amounts | Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | ||||
Net cash provided by operating activities per financial statements (c) | 45,076 | 12,945 | 64,175 | 54,939 | ||||
Sustaining mine exploration and development | (9,683 | ) | (5,134 | ) | (27,191 | ) | (15,686 | ) |
Sustaining mine capital equipment | (10,360 | ) | (2,232 | ) | (15,158 | ) | (4,298 | ) |
Tailings management facility | (15 | ) | (3,692 | ) | (29 | ) | (3,897 | ) |
Ventilation project | - | - | - | (499 | ) | |||
Capitalized development, exploration and evaluation expenditures | - | (5,550 | ) | - | (21,644 | ) | ||
Mines under development capital equipment | - | (17,230 | ) | - | (60,749 | ) | ||
Growth mine exploration and development | (4,111 | ) | - | (12,787 | ) | - | ||
Growth mine capital equipment | (7,485 | ) | - | (17,070 | ) | - | ||
Purchase of mineral properties | - | - | (200 | ) | - | |||
Surface exploration at Eagle River | - | - | - | - | ||||
Funds held against standby letters of credit | (1,542 | ) | - | (1,542 | ) | - | ||
Payment of lease liabilities | (1,208 | ) | (2,300 | ) | (4,402 | ) | (6,731 | ) |
Free cash flows (a) | 10,672 | (23,193 | ) | (14,204 | ) | (58,565 | ) | |
Weighted number of shares (000s) (b) | 148,952 | 142,487 | 147,155 | 142,260 | ||||
Per Share data | ||||||||
Operating cash flow (c) ÷ (b) | 0.30 | 0.09 | 0.44 | 0.39 | ||||
Free cash flow (a) ÷ (b) | 0.07 | (0.16 | ) | (0.10 | ) | (0.41 | ) | |
Net income (adjusted) and Adjusted net income per share
Adjusted net income (loss) and adjusted net income (loss) per share are non-IFRS performance measures and do not constitute a measure recognized by IFRS and do not have standardized meanings defined by IFRS, as well both measures may not be comparable to information in other gold producers’ reports and filings. Adjusted net income (loss) is calculated by removing the one-time gains and losses resulting from the disposition of non-core assets, non-recurring expenses and significant tax adjustments (mining tax recognition and exploration credit refunds) not related to current period’s income, as detailed in the table below. Wesdome discloses this measure, which is based on its financial statements, to assist in the understanding of the Company’s operating results and financial position.
In 000s, except per share amounts | Q3 2023 | Q3 2022 | YTD 2023 | YTD 2022 | ||||
Net (loss) income per financial statements | (3,248 | ) | (3,899 | ) | (8,607 | ) | (11,179 | ) |
Adjustments for: | ||||||||
Impairment of investment in associate | 900 | - | 3,600 | 11,800 | ||||
Retirement costs | - | - | 2,102 | - | ||||
Total adjustments | 900 | - | 5,702 | 11,800 | ||||
Related income tax effect | (225 | ) | - | (1,425 | ) | (2,950 | ) | |
675 | - | 4,277 | 8,850 | |||||
Net (loss) income adjusted (a) | (2,573 | ) | (3,899 | ) | (4,330 | ) | (2,329 | ) |
Weighted number of shares (000s) (b) | 148,952 | 142,487 | 147,155 | 142,260 | ||||
Per Share data | ||||||||
Net adjusted (loss) income (a) ÷ (b) | (0.02 | ) | (0.03 | ) | (0.03 | ) | (0.02 | ) |
PDF available: http://ml.globenewswire.com/Resource/Download/bf6b0cd4-e1fd-4485-ad91-dbc257620e21
FAQ
What are Wesdome Gold Mines Ltd.'s Q3 2023 financial results?
What is Wesdome Gold Mines Ltd.'s 2023 production guidance?
What were Wesdome Gold Mines Ltd.'s Q3 2023 gold production figures?