Torex Gold Provides Q4 2024 Update on Media Luna Project
Torex Gold Resources reports 94% completion of its Media Luna Project as of December 31, 2024. The project is on track for first copper concentrate production by end of Q1 2025, with engineering concluded and procurement 99% complete. Underground development is exceeding targets at 1,300 meters per month, with surface construction at 85% completion.
The company expects to achieve the designed mining rate of 7,500 tonnes per day by mid-2026, six months ahead of schedule. Q4 2024 expenditure was approximately $100 million, bringing total annual spend to $449 million. The company forecasts approximately $60 million in non-sustaining capital expenditures for 2025.
Commercial production is expected in early Q2 2025, with the company anticipating a return to positive free cash flow by mid-year. The project's completion includes 100% engineering completion, 99% procurement completion, 90% underground development/construction, and 85% surface construction.
- Project completion at 94% with first copper concentrate production on schedule
- Underground development exceeding targets at 1,300 meters/month vs 1,200 planned
- Mining rate target of 7,500 tonnes/day to be achieved 6 months ahead of schedule
- Expected return to positive free cash flow by mid-2025
- Additional $60 million non-sustaining capital expenditure required in 2025
- Three-month extension of pre-commercial period due to processing plant tie-in delay
- Eight-day temporary suspension of activities in December 2024
Construction substantially complete and first copper concentrate on track for March
(All amounts expressed in U.S. dollars unless otherwise stated)
Toronto, Ontario--(Newsfile Corp. - February 4, 2025) - Torex Gold Resources Inc. (the "Company" or "Torex") (TSX: TXG) provides a Q4 2024 update on the development of its Media Luna Project ("Media Luna"). Unless otherwise stated, progress and milestones referenced in this press release are as of December 31, 2024.
Jody Kuzenko, President & CEO of Torex, stated:
"The Media Luna Project is now in its final months, sitting at
"The tie-ins at the processing plant are on track to commence towards the end of February, with all major deliveries required to support the tie-in period now on site. In Q4, teams were able to take advantage of a planned maintenance period at the process plant and conducted initial synchronization and testing of the variable frequency drives for the ball mill, which we expect will streamline and de-risk the installation process and support efficient commissioning in March.
"Average monthly underground lateral development rates remained ahead of budget at 1,300 meters per month. Definition drilling is also well ahead of plan, with drilling for 2024 stopes completed ahead of schedule, most of the stopes planned to be mined in 2025 drilled off, and drilling for 2026 underway. Our target is to have a minimum of one year of stope inventory on hand going forward. With an excellent head start on both definition drilling and underground development, which will further accelerate in 2025, we now expect to achieve the designed mining rate of 7,500 tonnes per day by mid-2026, six months ahead of the schedule set out in the Technical Report.
"In terms of project capital, Q1 2025 is expected to be the last quarter of material investment in Media Luna and, with commercial production expected in early Q2 2025, we are well-positioned to pivot back to positive free cash flow generation by mid-year. The robust free cash flow anticipated from Morelos places Torex in a solid position to quickly repay the modest level of debt taken on to fund Media Luna, begin returning capital to shareholders, and support increased investment in our plans for continued growth at Morelos and beyond."
CAPITAL EXPENDITURES
During Q4 2024, approximately
As a result of the previously announced rescheduling of the processing plant tie-ins to February (originally November 2024), the pre-commercial period has been extended by approximately three months. As per full-year guidance, the Company is expected to invest approximately
PROJECT COMPLETION
As at year end, overall development of Media Luna was
Progress on the project was halted by the eight-day temporary suspension of activities at Morelos in early December; as a result, the start of the four-week tie-in of the copper ("Cu") and iron sulphide ("FeS") flotation circuits as well as the modifications to the processing plant has shifted from early to late February. First concentrate production is expected at the end of Q1, and the declaration of commercial production shortly thereafter.
Table 1: Media Luna Project - Project Completion (April 1, 2022 through December 31, 2024)
Project To Date Q4 2024 | |
Procurement | |
Engineering | |
Underground development/construction | |
Surface construction (including paste plant) | |
Total Project |
Notes to Table
1) Physical progress measured starting as of April 1, 2022; excludes progress made prior to Board approval on March 31, 2022.
2) Project period is defined as April 1, 2022 through declaration of commercial production.
3) Total Project is weighted average based on activity levels.
Procurement
With procurement for the project
Notable orders completed during Q4 included the remaining electrical houses ("e-houses") for the processing plant, the backup generator for the 230 kV switchyard, slurry pumps, and carbon steel pipe.
Underground Development and Construction
Steady progress continued underground at Media Luna, with
Underground development rates continue to track ahead of plan, with monthly lateral development rates averaging 1,300 metres since July relative to the original budget of 1,200 metres, excluding the impact of the temporary suspension of activities at Morelos in December. With the significant progress made to date on both definition drilling and underground development, the Company now expects mining rates at Media Luna to achieve the designed rate of 7,500 tonnes per day by mid-2026, six months ahead of the schedule set out in the Technical Report.
Construction and commissioning of rock breaker #1 is now complete (Figure 1). Installation of the fire suppression system for the Guajes conveyor commenced, as did installation of the 15 kV electrical cables along the length of the tunnel. Teams also completed the installation of the first vertical pipe for the tailings line and have commenced work on the backup second line, all with a view to derisking paste plant commissioning.
Figure 1: Rock breaker #1 and the grizzly chute have been installed and commissioned.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/239569_e21395b964d8bbf3_001full.jpg
Surface Construction
Surface construction is now
Installation of power infrastructure is now substantially complete, with the low voltage 115 kV system fully energized and operational, and the transmission line between the 230 kV switchyard and substation completed in the quarter (Figure 3). At the switchyard, crews continued to pull cable in the duct banks and trenches and installed battery banks. Additionally, the transformer for the underground control room has now been energized.
On the south side of the Balsas River, construction of the paste plant is advancing well. The elevated floor slab at the filter level has been poured allowing for preparation for the assembly of the main filter presses, and assembly and welding continues on the exterior tanks. Electrical panels are being mounted in the e-house. Steel erection sits at
Figure 2: Pre-commissioning of the ball mill's variable frequency drives took place in December in order to mitigate potential risks during the tie-in period in February.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/239569_e21395b964d8bbf3_002full.jpg
Figure 3: Transmission lines between the 230 kV switchyard (pictured below) and substation were connected in the quarter.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/239569_e21395b964d8bbf3_003full.jpg
Figure 4: Work progressed on the paste plant during the quarter, including continued erection of the binder silo, thickener, and building steel.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/239569_e21395b964d8bbf3_004full.jpg
Operational Readiness
In parallel with development and construction activities, the surface and underground operational readiness plan continues to progress. The operational readiness team continues to develop and advance Standard Operating and Maintenance procedures for the new assets and is tracking to plan at over
Negotiations with the various haulage companies for Cu concentrate transport to port distribution facilities are complete and contracts executed. The Company is also in the final stages of executing contracts for the sale of Cu concentrate to a mix of traders and smelters. Metal payables are in line with that which was incorporated into the most recent Technical Report dated effective March 16, 2022 and filed on March 31, 2022 ("Technical Report").
PROJECT EXECUTION PLAN
Based on progress made to date and a detailed review of both the surface and underground schedules completed late in the quarter, modest updates have been made to the overall project schedule after incorporating the impact of the temporary suspension of activities at Morelos in early December (Figure 5).
More detail on the Media Luna Project, including the Feasibility Study results, can be found in the Technical Report.
Figure 5: Project execution plan for the Media Luna Project.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1863/239569_e21395b964d8bbf3_005full.jpg
ABOUT TOREX GOLD RESOURCES INC.
Torex is an intermediate gold producer based in Canada, engaged in the exploration, development, and operation of its
FOR FURTHER INFORMATION, PLEASE CONTACT:
TOREX GOLD RESOURCES INC.Jody Kuzenko
President and CEO
Direct: (647) 725-9982
jody.kuzenko@torexgold.com
Dan Rollins
Senior Vice President, Corporate Development & Investor Relations
Direct: (647) 260-1503
QUALIFIED PERSON
The technical and scientific information in this press release has been reviewed and approved by Dave Stefanuto, P. Eng, Executive Vice President, Technical Services and Capital Projects of the Company, and a qualified person under National Instrument 43-101.
CAUTIONARY NOTES ON FORWARD-LOOKING STATEMENTS
This press release contains "forward-looking statements" and "forward-looking information" within the meaning of applicable Canadian securities legislation. Forward-looking information includes, but is not limited to, statements that: the Company is well on track to complete the project and produce first copper concentrate by the end of Q1 2025; the tie-ins at the processing plant are on track to commence at the end of February; in Q4, teams were able to take advantage of a planned maintenance period at the process plant and conducted initial synchronization and testing of the variable frequency drives for the ball mill, which we expect will streamline and de-risk the installation process and support efficient commissioning in March; the Company's target is to have a minimum of one year of stope inventory on hand going forward; the Company now expects to achieve the designed mining rate of 7,500 tonnes per day by mid-2026; Q1 2025 is expected to be the last quarter of material investment in Media Luna, with commercial production expected in early Q2 2025; the Company is well-positioned to pivot back to positive free cash flow generation by mid-year; the robust free cash flow anticipated from Morelos places Torex in a solid position to quickly repay the modest level of debt taken on to fund Media Luna, begin returning capital to shareholders, and support increased investment in the Company's plans for continued growth at Morelos and beyond; expenditures in Q1 2025 are expected to be lower than the quarterly spend in 2024 as the project winds down, first copper concentrate production begins, and commercial production is declared shortly thereafter; the Company is expected to invest approximately
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/239569
FAQ
When will Torex Gold (TORXF) begin copper concentrate production at Media Luna?
What is the total capital expenditure for TORXF's Media Luna project in 2024?
When will TORXF's Media Luna project reach commercial production?
What is the targeted mining rate for TORXF's Media Luna project?