Trilogy Metals Announces Positive Study Results for the Bornite Copper Project Located in Alaska, USA
Trilogy Metals (TSX/NYSE: TMQ) announced positive results from its Preliminary Economic Assessment (PEA) for the Bornite copper project in Alaska. The project, owned 50% by Trilogy through Ambler Metals , shows a 17-year mine life with 1.9 billion pounds of copper production.
Key financial metrics include:
- Pre-tax NPV8% of $552.0 million with 23.6% IRR
- After-tax NPV8% of $394.0 million with 20.0% IRR
- Initial capital cost of $503.8 million
- Total capital expenditure of $866.9 million
The PEA envisions a 6,000 tonne-per-day underground mining operation with conventional milling, achieving 90.9% copper recovery. The base case uses a copper price of $4.20/lb. The project has potential to extend the Upper Kobuk Mineral Projects' mine activity beyond 30 years.
Trilogy Metals (TSX/NYSE: TMQ) ha annunciato risultati positivi dalla sua Valutazione Economica Preliminare (PEA) per il progetto di rame Bornite in Alaska. Il progetto, di proprietà al 50% di Trilogy tramite Ambler Metals, mostra una vita mineraria di 17 anni con una produzione di 1,9 miliardi di libbre di rame.
I principali indicatori finanziari includono:
- NPV pre-tasse dell'8% di 552,0 milioni di dollari con un TIR del 23,6%
- NPV dopo-tasse dell'8% di 394,0 milioni di dollari con un TIR del 20,0%
- Costo iniziale del capitale di 503,8 milioni di dollari
- Spesa totale in capitale di 866,9 milioni di dollari
La PEA prevede un operazione mineraria sotterranea da 6.000 tonnellate al giorno con frantumazione convenzionale, raggiungendo un recupero del rame del 90,9%. Il caso base utilizza un prezzo del rame di 4,20 dollari/libbra. Il progetto ha il potenziale per estendere l'attività mineraria dei Progetti Minerari Upper Kobuk oltre i 30 anni.
Trilogy Metals (TSX/NYSE: TMQ) anunció resultados positivos de su Evaluación Económica Preliminar (PEA) para el proyecto de cobre Bornite en Alaska. El proyecto, 50% propiedad de Trilogy a través de Ambler Metals, muestra una vida mina de 17 años con una producción de 1.9 mil millones de libras de cobre.
Los principales indicadores financieros incluyen:
- NPV antes de impuestos del 8% de 552.0 millones de dólares con un TIR del 23.6%
- NPV después de impuestos del 8% de 394.0 millones de dólares con un TIR del 20.0%
- Costo de capital inicial de 503.8 millones de dólares
- Gasto total de capital de 866.9 millones de dólares
La PEA prevé una operación minera subterránea de 6,000 toneladas por día con molienda convencional, logrando un 90.9% de recuperación de cobre. El caso base utiliza un precio de cobre de 4.20 dólares/lb. El proyecto tiene el potencial de extender la actividad minera de los Proyectos Minerales de Upper Kobuk más allá de 30 años.
Trilogy Metals (TSX/NYSE: TMQ)는 알래스카의 Bornite 구리 프로젝트에 대한 예비 경제 평가(PEA)에서 긍정적인 결과를 발표했습니다. 이 프로젝트는 Trilogy가 Ambler Metals를 통해 50% 소유하고 있으며, 17년의 광산 수명과 19억 파운드의 구리 생산량을 보여줍니다.
주요 재무 지표는 다음과 같습니다:
- 세후 NPV8%가 5억 5천2백만 달러, 내부 수익률(IRR) 23.6%
- 세전 NPV8%가 3억 9천4백만 달러, 내부 수익률(IRR) 20.0%
- 초기 자본 비용 5억 3천8백만 달러
- 총 자본 지출 8억 6천9백만 달러
PEA는 일일 6,000톤의 지하 광산 운영을 구상하며, 전통적인 분쇄 방식으로 구리를 90.9% 회수하는 것을 목표로 하고 있습니다. 기준 사례는 구리 가격을 파운드당 4.20달러로 설정하고 있습니다. 이 프로젝트는 Upper Kobuk 광물 프로젝트의 광산 활동을 30년 이상 연장할 잠재력을 가지고 있습니다.
Trilogy Metals (TSX/NYSE: TMQ) a annoncé des résultats positifs pour son Évaluation Économique Préliminaire (PEA) concernant le projet de cuivre Bornite en Alaska. Le projet, détenu à 50 % par Trilogy via Ambler Metals, présente une durée de vie minière de 17 ans avec une production de 1,9 milliard de livres de cuivre.
Les principaux indicateurs financiers comprennent:
- NPV avant impôt de 552 millions de dollars à 8 % avec un TRI de 23,6 %
- NPV après impôt de 394 millions de dollars à 8 % avec un TRI de 20,0 %
- Coût du capital initial de 503,8 millions de dollars
- Dépenses totales en capital de 866,9 millions de dollars
La PEA envisage une opération minière souterraine de 6 000 tonnes par jour avec un traitement conventionnel, atteignant une récupération de cuivre de 90,9 %. Le cas de base utilise un prix du cuivre de 4,20 $/lb. Le projet a le potentiel d'étendre l'activité minière des Projets Minéraux Upper Kobuk au-delà de 30 ans.
Trilogy Metals (TSX/NYSE: TMQ) hat positive Ergebnisse aus ihrer vorläufigen Wirtschaftlichkeitsanalyse (PEA) für das Bornite-Kupferprojekt in Alaska bekannt gegeben. Das Projekt gehört zu 50 % Trilogy über Ambler Metals und weist eine Bergbaulebensdauer von 17 Jahren mit einer Produktion von 1,9 Milliarden Pfund Kupfer auf.
Die wichtigsten finanziellen Kennzahlen umfassen:
- Netto-Barwert (NPV) vor Steuern von 552 Millionen US-Dollar bei 8 % mit einer internen Rendite (IRR) von 23,6 %
- Netto-Barwert (NPV) nach Steuern von 394 Millionen US-Dollar bei 8 % mit einer internen Rendite (IRR) von 20,0 %
- Anfängliche Investitionskosten von 503,8 Millionen US-Dollar
- Gesamtkapitalaufwand von 866,9 Millionen US-Dollar
Die PEA sieht einen unterirdischen Bergbaubetrieb mit 6.000 Tonnen pro Tag mit konventioneller Verarbeitung vor, was eine Kupfergewinnung von 90,9 % erreicht. Der Basisfall verwendet einen Kupferpreis von 4,20 US-Dollar pro Pfund. Das Projekt hat das Potenzial, die Bergbautätigkeiten der Upper Kobuk Mineral Projects über 30 Jahre hinaus zu verlängern.
- Strong project economics with $394M after-tax NPV8% and 20% IRR
- Significant production of 1.9 billion pounds of copper over 17-year mine life
- High copper recovery rate of 90.9%
- Potential to extend mine activity beyond 30 years
- High initial capital requirement of $503.8M
- Relatively long payback period of 4.4 years post-tax
- Project based on Inferred resources, considered too speculative for reserve classification
- High all-in cost of $3.35/lb Cu
Insights
The Bornite PEA reveals compelling economics with an after-tax NPV8% of
The capital structure is well-defined, requiring
The resource base is substantial, with 208.9Mt of Inferred resources at
This PEA strengthens TMQ's position in the copper market at a important time. The project's 30+ year potential mine life through UKMP integration provides exceptional long-term optionality as global copper demand rises for energy transition. The conservative
Trilogy Metals will host a conference call on January 15, 2025 at 1:00pm Pacific Time or 4:00pm Eastern Time to discuss these results.
Please use this link to access the live webcast of the conference call:
https://www.c-meeting.com/web3/joinTo/38ZLQJQ93P2A84/ZgO5Nop1EQzwZllpJru9iA
Or by phone:
Highlights of the Bornite PEA
- 1.9 billion pounds of copper over 17-year mine life
- Potential to extend mine activity for the Upper Kobuk Mineral Projects ("UKMP") to over 30 years
- Pre-tax Net Present Value ("NPV")
8% of and an Internal Rate of Return ("IRR") of$552.0 million 23.6% - After-tax NPV
8% of and after-tax IRR of$394.0 million 20.0%
The PEA is preliminary in nature and includes Inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the PEA will be realized.
The Bornite PEA describes the technical and economic viability of establishing an underground mining operation for a 6,000 tonne-per-day operation with a 17-year mine life. The PEA assumes re-purposing the infrastructure described in the Company's current Feasibility Study for the Arctic Project for use with the Bornite Project once the Arctic deposit has been depleted. The Feasibility Study for the Arctic Project can be accessed under the Company's profile on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov/edgar. The base case scenario for the Bornite PEA utilizes a long-term metal price of
Tony Giardini, President and Chief Executive Officer of Trilogy Metals commented, "Although we believe that further exploration along the 100km volcanogenic massive sulphide belt will extend the mine life of the Arctic Project beyond the 13 years established by the current Arctic Feasibility Study, the Bornite PEA study shows it is possible, with existing known resources, to continue mine activity at the UKMP beyond 30 years."
The salient details of the Bornite PEA are displayed in the tables below.
Table 1. Metal Production and Assumed Metal Prices
Annual Payable Metals Production | |
Copper ('000 lb) | 109,061 |
Metal Price | |
Copper ($/lb) | 4.20 |
Table 2. Operating and Capital Costs
Operating Costs | |
Mining ($/t milled) | 42.66 |
Processing ($/t milled) | 24.82 |
G&A ($/t milled) | 31.44 |
Total Operating Cost ($/t milled) | 98.91 |
Capital Expenditures | |
Initial Capital ($ million) | 503.8 |
Sustaining Capital ($ million) | 363.1 |
Total Capex ($ million) | 866.9 |
Mine Closure & Reclamation ($ million) | 81.2 |
Table 3. Financial Results
Financial Summary | |
Pre-tax Cash Flow ($ million) | 1,582.2 |
After-tax Cash Flow ($ million) | 1,219.0 |
Pre-tax NPV | 552.0 |
After-tax NPV | 394.0 |
Cash Cost ($/lb Cu payable) | 2.76 |
All-in Cost ($/lb Cu payable) | 3.35 |
Pre-tax IRR (%) | 23.6 |
Pre-tax Payback Period (years) | 4.0 |
Post-tax IRR (%) | 20.0 |
Post-tax Payback Period (years) | 4.4 |
Table 4. Mineral Resources for the Bornite Deposit
Class | Type/Area | Cut-off (Cu %) | Tonnes | Average Grade | Contained Metal |
Inferred | In-Pit | 0.50 | 170.4 | 1.15 | 4,303 |
Outside-Pit South Reef | 1.45 | 27.5 | 2.78 | 1,687 | |
Outside-Pit Ruby Zone | 1.79 | 10.4 | 2.28 | 521 | |
Underground Development | 0.70 | 0.7 | 0.98 | 16 | |
Total Inferred | 208.9 | 1.42 | 6,527 |
Note: | (1) | The effective date of the mineral resource is January 15, 2025. The QP for the mineral resource is Mr. Henry Kim, P.Geo., an employee of Wood. |
(2) | Mineral resources are prepared in accordance with CIM Definition Standards and the CIM Best Practice Guidelines. | |
(3) | Mineral resources are not mineral reserves and do not have demonstrated economic viability. Inferred mineral resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the Inferred mineral resources will ever be upgraded to a higher category. | |
(4) | Mineral resources are constrained by: an open pit shell at a cut-off grade of | |
(5) | Underground development material uses a marginal cut-off of | |
(6) | Figures may not sum due to rounding. | |
(7) | The mineral resource estimates are shown on a |
The South Reef includes a relatively high-grade mineralized zone that would be amendable to underground mining methods should a decision be made not to mine the mineral resources by open pit methods. Table 5 illustrates the portions of the South Reef at a higher cut-off grade (sensitivity to cut-off grade), representing an opportunity that could be considered for mining of this material using only underground mining methods which is illustrated in the PEA.
Table 5. Portions of South Reef Mineral Resource Amenable to Underground Mining
Class | Type/Area | Cut-off (Cu %) | Tonnes | Average Grade | Contained Metal |
Inferred | In-Pit South Reef1 | 1.45 | 14.2 | 2.80 | 876 |
Outside-Pit South Reef2 | 1.45 | 27.5 | 2.78 | 1,687 | |
Total South Reef | 41.7 | 2.79 | 2,563 |
Note: | (1) | Subset of the mineral resource using a higher cut-off to what was used in Table 4 and is not additive to the in-pit mineral resource reported in Table 4. |
(2) | Restatement of the mineral resources outside of the pit as reported in Table 5 and is not additive to Table 4. |
Table 6. Subset of the Mineral Resources Included in the Underground LOM Plan
Class | Tonnes | Average Grade | Contained Metal |
Inferred | 36.9 | 2.61 | 2,125 |
Note: | (1) | Mineral resources within the mine plan were estimated using sublevel stoping underground mining method and includes variable dilution and a mining recovery of |
(2) | Mineral resources are not mineral reserves and do not have demonstrated economic viability. | |
(3) | Input assumptions used to determine mineable stope shapes include a Cu price of | |
(4) | Production stope cut-off of |
Trilogy Metals engaged independent consultants, Wood Canada Limited ("Wood"), Ausenco Engineering Canada ULC ("Ausenco"), SRK Consulting (
The Bornite PEA forecasts total payable production to be 1.9 billion pounds of copper over a 17-year mine life. More importantly, the Bornite PEA demonstrates the ability to extend mine activity at the UKMP to over 30 years. The Bornite PEA does not incorporate any closure cost synergies for the Arctic Project which may be significant.
The Bornite PEA is based on a 6,000 tonne-per-day underground mining operation with conventional milling and flotation process that results in the production of copper concentrate. Based on the Bornite PEA level metallurgical work on the sulphide mineralization, the average recoveries are projected to be
Initial capital expenditure is
There has been no material change to the mineral resource estimates for the Bornite Project as reported in the Company's previous technical reports entitled "NI 43-101 Technical Report on the Mineral Resource Update of the Bornite Project, Northwest,
PEA Contributors
The Bornite PEA was prepared by the contributors listed below, each of whom is a Qualified Person under NI 43-101.
Qualified Person | Company | Scope of Responsibility |
Lewis Kitchen, P.Eng, Senior Mine Engineer | Wood | Mining, capital and operating costs and financial modeling |
Henry Kim, P.Geo, Principal Resource Geologist | Wood | Geology and mineral resources |
Kevin Murray, P.Eng, Process Lead | Ausenco | Process design and capital and operating costs |
Calvin Boese, P.Eng, Principal Consultant, Geotechnical | SRK | Geotechnical, tailings and capital and operating costs |
Dan Mackie, P.Geo, Principal Consultant, Hydrogeologist | SRK | Hydrogeology, hydrology and capital and operating costs |
Jeff Austin, P.Eng, President | Int Met | Metallurgical testing |
Jack DiMarchi, CPG, Principal | Core | Environment and permitting |
Data Verification
Messrs. Kim and Boese have visited the site of the Bornite Project. The Bornite PEA Contributors have had discussions with relevant site personnel and Company management and have reviewed supporting documentation including initial source documents. Additional information on data verification can be found in the Bornite technical report which will be available under the Company's profile on SEDAR+ at www.sedarplus.ca within 45 days of this news release.
Qualified Persons
The Bornite PEA contributors prepared or supervised the preparation of the information that forms the basis of the Bornite PEA disclosure in this news release and have approved its dissemination.
Richard Gosse, P.Geo., Vice President, Exploration for Trilogy Metals, is a Qualified Person as defined by NI 43-101. Mr. Gosse has reviewed and approved the scientific and technical information in this news release.
Conference Call
The conference call to discuss results of the Bornite PEA will be held on January 15, 2025 at 1:00pm Pacific Time or 4:00pm Eastern Time.
Participants can access the Company's presentation by a live webcast of the conference call at the following link or phone numbers:
https://www.c-meeting.com/web3/joinTo/38ZLQJQ93P2A84/ZgO5Nop1EQzwZllpJru9iA
International Toll: +1-647-484-8814
There will be a question-and-answer session following the presentation. A replay of this conference call will be available on the Company's website at www.trilogymetals.com.
About Trilogy Metals
Trilogy Metals Inc. is a metal exploration and development company which holds a 50 percent interest in Ambler Metals LLC, which has a 100 percent interest in the Upper Kobuk Mineral Projects in northwestern
Cautionary Note Regarding Forward-Looking Statements
This news release includes certain "forward-looking information" and "forward-looking statements" (collectively "forward-looking statements") within the meaning of applicable Canadian and
Cautionary Note to United States Investors
This news release has been prepared in accordance with the requirements of the securities laws in effect in
View original content to download multimedia:https://www.prnewswire.com/news-releases/trilogy-metals-announces-positive-study-results-for-the-bornite-copper-project-located-in-alaska-usa-302351132.html
SOURCE Trilogy Metals Inc.
FAQ
What is the expected copper production from TMQ's Bornite Project?
What is the after-tax NPV and IRR for TMQ's Bornite Project?
How much initial capital is required for TMQ's Bornite Project?
What is the copper recovery rate expected at TMQ's Bornite Project?