STOCK TITAN

Taseko Mines Provides Construction Update for Florence Copper

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Taseko Mines (TGB) has provided an update on the construction progress of its Florence Copper project. Key highlights include:

  • Project is approaching 40% completion as of September 30, 2024
  • First copper production anticipated in Q4 2025
  • Approximately 300,000 project hours worked with no reportable injuries or environmental incidents
  • 280 construction personnel currently on site
  • Earthworks and site preparation ~75% complete
  • Concrete foundations ~50% complete
  • 34 out of 90 production wells completed
  • 75 out of 170 permanent operating staff positions filled

The company expects total costs to be within 10-15% of the original US$232 million estimate. Taseko has also applied for a tax credit of up to US$110 million through the U.S. Department of Energy's 48C Program, with a decision expected in January 2025.

Taseko Mines (TGB) ha fornito un aggiornamento sui progressi nella costruzione del suo progetto Florence Copper. I punti salienti includono:

  • Il progetto è in procinto di raggiungere il 40% di completamento entro il 30 settembre 2024
  • La prima produzione di rame è prevista nel quarto trimestre del 2025
  • Circa 300.000 ore di lavoro del progetto senza infortuni o incidenti ambientali riportabili
  • 280 personale di costruzione attualmente in sito
  • I lavori di scavo e la preparazione del sito sono circa al 75% di completamento
  • Le fondamenta in cemento sono circa al 50% di completamento
  • 34 dei 90 pozzi di produzione completati
  • 75 delle 170 posizioni permanenti del personale operativo sono state occupate

L'azienda prevede che i costi totali siano entro il 10-15% della stima originale di 232 milioni di dollari USA. Taseko ha anche richiesto un credito d'imposta fino a 110 milioni di dollari USA attraverso il Programma 48C del Dipartimento dell'Energia degli Stati Uniti, con una decisione prevista per gennaio 2025.

Taseko Mines (TGB) ha proporcionado una actualización sobre el progreso de la construcción de su proyecto Florence Copper. Los puntos destacados incluyen:

  • El proyecto está casi al 40% de completarse al 30 de septiembre de 2024
  • Se anticipa que la primera producción de cobre será en el cuarto trimestre de 2025
  • Aproximadamente 300,000 horas de trabajo del proyecto sin lesiones o incidentes ambientales reportables
  • 280 personas de construcción actualmente en el sitio
  • Los trabajos de movimiento de tierra y la preparación del sitio están aproximadamente al 75% de completarse
  • Las fundaciones de concreto están aproximadamente al 50% de completarse
  • 34 de los 90 pozos de producción completados
  • 75 de las 170 posiciones de personal operativo permanente ocupadas

La empresa espera que los costos totales se mantengan dentro del 10-15% de la estimación original de 232 millones de dólares estadounidenses. Taseko también ha solicitado un crédito fiscal de hasta 110 millones de dólares estadounidenses a través del Programa 48C del Departamento de Energía de EE.UU., con una decisión esperada para enero de 2025.

Taseko Mines (TGB)는 Florence Copper 프로젝트의 건설 진행 상황에 대한 업데이트를 제공했습니다. 주요 하이라이트는 다음과 같습니다:

  • 프로젝트는 2024년 9월 30일 기준으로 40% 완공에 가까워지고 있습니다
  • 첫 번째 구리 생산이 2025년 4분기에 예상됩니다
  • 30만 프로젝트 근무 시간 동안 보고된 부상이나 환경 사고가 없습니다
  • 280명의 건설 인원이 현재 현장에 있습니다
  • 토공사 및 현장 준비가 약 75% 완료되었습니다
  • 콘크리트 기초가 약 50% 완료되었습니다
  • 90개 생산 우물 중 34개 완료
  • 170개의 상주 운영 직원 중 75개 자리가 채워졌습니다

회사는 총 비용이 원래 2억 3200만 달러 추정치의 10-15% 이내일 것으로 예상하고 있습니다. Taseko는 또한 미국 에너지부의 48C 프로그램을 통해 최대 1억 1000만 달러의 세액 공제를 신청했으며, 결정은 2025년 1월에 예상됩니다.

Taseko Mines (TGB) a fourni une mise à jour sur l'avancement de la construction de son projet Florence Copper. Les principaux points à retenir sont :

  • Le projet est en voie d'atteindre 40% d'achèvement au 30 septembre 2024
  • La première production de cuivre est prévue pour le quatrième trimestre 2025
  • Environ 300 000 heures de travail sur le projet sans blessures ni incidents environnementaux signalés
  • 280 personnes de construction actuellement sur place
  • Les travaux de terrassement et de préparation du site sont environ à 75% d'achèvement
  • Les fondations en béton sont environ à 50% d'achèvement
  • 34 des 90 puits de production achevés
  • 75 des 170 postes permanents du personnel opérationnel sont pourvus

L'entreprise s'attend à ce que les coûts totaux soient dans une fourchette de 10 à 15 % par rapport à l'estimation initiale de 232 millions de dollars américains. Taseko a également demandé un crédit d'impôt pouvant aller jusqu'à 110 millions de dollars américains via le programme 48C du département américain de l'Énergie, avec une décision attendue en janvier 2025.

Taseko Mines (TGB) hat ein Update zum Baufortschritt seines Florence Copper-Projekts bereitgestellt. Zu den wesentlichen Punkten gehören:

  • Das Projekt ist zum 30. September 2024 nahezu 40% abgeschlossen
  • Die erste Kupferproduktion wird im vierten Quartal 2025 erwartet
  • Etwa 300.000 Projektstunden gearbeitet ohne meldbare Verletzungen oder Umweltvorfälle
  • 280 Bauarbeiter sind derzeit vor Ort
  • Die Erdarbeiten und die Standortvorbereitung sind ca. 75% abgeschlossen
  • Die Betonfundamente sind ca. 50% abgeschlossen
  • 34 von 90 Produktionsbrunnen sind fertiggestellt
  • 75 von 170 Stellen im ständigen Betriebspersonal sind besetzt

Das Unternehmen erwartet, dass die Gesamtkosten innerhalb von 10-15% der ursprünglichen Schätzung von 232 Millionen US-Dollar liegen. Taseko hat auch einen Steueranreiz von bis zu 110 Millionen US-Dollar über das 48C-Programm des US-Energieministeriums beantragt, mit einer Entscheidung, die im Januar 2025 erwartet wird.

Positive
  • Project is on schedule with 40% completion
  • No reportable injuries or environmental incidents
  • First copper production anticipated in Q4 2025
  • 75% of total construction costs committed
  • Applied for US$110 million tax credit through DOE's 48C Program
Negative
  • Total costs expected to be 10-15% higher than original US$232 million estimate

Insights

This construction update for Taseko's Florence Copper project is positive for investors. Key points:

  • Project is ~40% complete and on schedule for first copper production in Q4 2025
  • No reportable injuries or environmental incidents after 300,000 project hours
  • 75% of construction costs committed, expected to be within 10-15% of $232 million estimate
  • Applied for up to $110 million tax credit from DOE 48C Program

The on-time, on-budget progress is encouraging. If approved, the potential $110 million tax credit would significantly offset costs. Florence Copper's low GHG intensity positioning is also noteworthy as ESG factors gain importance. Overall, this update suggests the transformative project remains on track to boost Taseko's production and financials starting late 2025.

From a technical perspective, this update is encouraging. Key observations:

  • Wellfield drilling progressing well with 34 of 90 production wells completed
  • Critical infrastructure like powerlines (65% complete) and water management systems underway
  • Transition from earthworks/concrete to equipment installation phase
  • Hiring of operational staff (44% complete) indicates good preparation for production

The absence of reportable incidents is particularly positive, suggesting strong safety protocols. The project's advancement to structural steel and equipment installation phases marks important milestones. The completion of over a third of production wells provides confidence in the project's ability to meet its production timeline. Overall, the technical aspects of the project appear to be progressing smoothly, supporting the projected Q4 2025 production start.

VANCOUVER, British Columbia, Oct. 21, 2024 (GLOBE NEWSWIRE) -- Taseko Mines Limited (TSX: TKO; NYSE MKT: TGB; LSE: TKO) ("Taseko" or the "Company") is pleased to provide a progress update for construction activities at its Florence Copper project.

To date, approximately 300,000 project hours have been worked and there have been no reportable injuries or environmental incidents. There are currently 280 construction personnel at site. All activities are advancing on schedule and as of September 30, 2024, the project is approaching 40% complete. First copper production is still anticipated in the fourth quarter 2025.

Since construction commenced earlier this year, the bulk of activities have been focused on earthworks, concrete, and wellfield drilling. Installation of structural steel, tanks, and process equipment is now underway.

Summary of key activities and status as of September 30, 2024:

  • Earthworks and site preparation for the plant area and commercial wellfield – ~75% complete
  • Concrete foundations for SX/EW plant and associated infrastructure – ~50% complete
  • Pre-assembly and installation of structural steel for the solvent extraction plant commenced in August
  • Installation of process equipment commenced in September
  • Powerline installation – ~65% complete
  • Wellfield drilling – a total of 34 production wells completed to date, out of a total of 90 to be drilled during the construction phase
  • Point of compliance well drilling – 9 wells completed to date, out of a total of 18
  • Construction of process and surface water runoff ponds
  • Hiring permanent operating staff – 75 of 170 total positions and all but one key management position has been filled

Stuart McDonald, President & CEO of Taseko, commented, “We are pleased with progress through the first nine months of construction. With approximately 75% of total construction costs now committed, we expect total costs to be within 10-15% of the original US$232 million* estimate. The project remains on track for first copper production in late 2025, which will be a transformative event for our Company.”

“In addition, we have applied to the U.S. Department of Energy’s Qualifying Advanced Energy Project Credit (48C) Program. Florence Copper, which is set to become North America’s lowest GHG-intensity primary copper producer, qualifies as a critical materials project. After submitting a concept paper in June, we received encouragement to proceed with the full application. We have now filed the application seeking a tax credit of up to US $110 million, and we expect to hear whether Florence qualifies for the credit, or not, in January 2025,” concluded Mr. McDonald.

The Company recently hosted a Florence Copper site tour and the associated presentation can be found on our website at https://tasekomines.com/investors/documents-and-reports/corporate-presentations/. Additionally, updated construction photos can be found on our website at https://tasekomines.com/properties/florence-copper/#construction-updates.

*Based on the Florence Copper 43-101 Technical Report dated March 15, 2023, with costing basis Q3 2022.

For further information on Taseko, see the Company’s website at www.tasekomines.com or contact:

Investor enquiries Brian Bergot, Vice President, Investor Relations – 778-373-4554

Stuart McDonald
President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

Caution Regarding Forward-Looking Information

This document contains “forward-looking statements” that were based on Taseko’s expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook”, “anticipate”, “project”, “target”, “believe”, “estimate”, “expect”, “intend”, “should” and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

  • uncertainties about the future market price of copper and the other metals that we produce or may seek to produce;
  • changes in general economic conditions, the financial markets, inflation and interest rates and in the demand and market price for our input costs, such as diesel fuel, reagents, steel, concrete, electricity and other forms of energy, mining equipment, and fluctuations in exchange rates, particularly with respect to the value of the U.S. dollar and Canadian dollar, and the continued availability of capital and financing;
  • uncertainties resulting from the war in Ukraine, and the accompanying international response including economic sanctions levied against Russia, which has disrupted the global economy, created increased volatility in commodity markets (including oil and gas prices), and disrupted international trade and financial markets, all of which have an ongoing and uncertain effect on global economics, supply chains, availability of materials and equipment and execution timelines for project development;
  • uncertainties about the continuing impact of the novel coronavirus (“COVID-19”) and the response of local, provincial, state, federal and international governments to the ongoing threat of COVID-19, on our operations (including our suppliers, customers, supply chains, employees and contractors) and economic conditions generally including rising inflation levels and in particular with respect to the demand for copper and other metals we produce;
  • inherent risks associated with mining operations, including our current mining operations at Gibraltar, and their potential impact on our ability to achieve our production estimates;
  • uncertainties as to our ability to control our operating costs, including inflationary cost pressures at Gibraltar without impacting our planned copper production;
  • the risk of inadequate insurance or inability to obtain insurance to cover material mining or operational risks;
  • uncertainties related to the feasibility study for Florence copper project (the “Florence Copper Project” or “Florence Copper”) that provides estimates of expected or anticipated capital and operating costs, expenditures and economic returns from this mining project, including the impact of inflation on the estimated costs related to the construction of the Florence Copper Project and our other development projects;
  • the risk that the results from our operations of the Florence Copper production test facility (“PTF”) and ongoing engineering work including updated capital and operating costs will negatively impact our estimates for current projected economics for commercial operations at Florence Copper;
  • uncertainties related to the accuracy of our estimates of Mineral Reserves (as defined below), Mineral Resources (as defined below), production rates and timing of production, future production and future cash and total costs of production and milling;
  • the risk that we may not be able to expand or replace reserves as our existing mineral reserves are mined;
  • the availability of, and uncertainties relating to the development of, additional financing and infrastructure necessary for the advancement of our development projects, including with respect to our ability to obtain any remaining construction financing potentially needed to move forward with commercial operations at Florence Copper;
  • our ability to comply with the extensive governmental regulation to which our business is subject;
  • uncertainties related to our ability to obtain necessary title, licenses and permits for our development projects and project delays due to third party opposition;
  • our ability to deploy strategic capital and award key contracts to assist with protecting the Florence Copper project execution plan, mitigating inflation risk and the potential impact of supply chain disruptions on our construction schedule and ensuring a smooth transition into construction;
  • uncertainties related to First Nations claims and consultation issues;
  • our reliance on rail transportation and port terminals for shipping our copper concentrate production from Gibraltar;
  • uncertainties related to unexpected judicial or regulatory proceedings;
  • changes in, and the effects of, the laws, regulations and government policies affecting our exploration and development activities and mining operations and mine closure and bonding requirements;
  • our dependence solely on our 87.5% interest in Gibraltar (as defined below) for revenues and operating cashflows;
  • our ability to collect payments from customers, extend existing concentrate off-take agreements or enter into new agreements;
  • environmental issues and liabilities associated with mining including processing and stock piling ore;
  • labour strikes, work stoppages, or other interruptions to, or difficulties in, the employment of labour in markets in which we operate our mine, industrial accidents, equipment failure or other events or occurrences, including third party interference that interrupt the production of minerals in our mine;
  • environmental hazards and risks associated with climate change, including the potential for damage to infrastructure and stoppages of operations due to forest fires, flooding, drought, or other natural events in the vicinity of our operations;
  • litigation risks and the inherent uncertainty of litigation, including litigation to which Florence Copper could be subject to;
  • our actual costs of reclamation and mine closure may exceed our current estimates of these liabilities;
  • our ability to meet the financial reclamation security requirements for the Gibraltar mine and Florence Project;
  • the capital intensive nature of our business both to sustain current mining operations and to develop any new projects, including Florence Copper;
  • our reliance upon key management and operating personnel;
  • the competitive environment in which we operate;
  • the effects of forward selling instruments to protect against fluctuations in copper prices, foreign exchange, interest rates or input costs such as fuel;
  • the risk of changes in accounting policies and methods we use to report our financial condition, including uncertainties associated with critical accounting assumptions and estimates; and Management Discussion and Analysis (“MD&A”), quarterly reports and material change reports filed with and furnished to securities regulators, and those risks which are discussed under the heading “Risk Factors”.

For further information on Taseko, investors should review the Company’s annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedarplus.ca, including the “Risk Factors” included in our Annual Information Form.

A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/0d8251a6-4f68-466e-9071-b6de8b08ac19


FAQ

What is the current completion percentage of Taseko's Florence Copper project as of September 30, 2024?

The Florence Copper project is approaching 40% completion as of September 30, 2024.

When is the expected first copper production date for Taseko's Florence Copper project (TGB)?

First copper production for Taseko's Florence Copper project (TGB) is anticipated in the fourth quarter of 2025.

How many construction personnel are currently working on Taseko's Florence Copper project?

There are currently 280 construction personnel working on site at Taseko's Florence Copper project.

What is the status of wellfield drilling at Taseko's Florence Copper project?

As of September 30, 2024, 34 out of 90 planned production wells have been completed during the construction phase at Taseko's Florence Copper project.

How much tax credit has Taseko Mines (TGB) applied for through the U.S. Department of Energy's 48C Program?

Taseko Mines (TGB) has applied for a tax credit of up to US$110 million through the U.S. Department of Energy's Qualifying Advanced Energy Project Credit (48C) Program.

Taseko Mines Limited

NYSE:TGB

TGB Rankings

TGB Latest News

TGB Stock Data

605.86M
296.13M
2.55%
30.74%
3.33%
Copper
Basic Materials
Link
United States of America
Vancouver