Arras Minerals Corp. (TSXV:ARK)(OTCQB:ARRKF) has provided an update on its exploration activities in NE Kazakhstan. Key highlights include:

  • Completion of a 3,547 line-kilometer Heli-TEM survey at the Bozshakol project
  • Ongoing KGK drill program at Aktasty and Maisor licenses (Bozshakol project)
  • 80% completion of Ground IP Survey at the Elemes project, with core drilling underway
  • Completion of KGK drill program at the Tay project

The company is progressing well across its project portfolio, with drilling activities at Elemes and Bozshakol aimed at identifying priority targets for future campaigns. At Tay, initial results show zones of chalcopyrite mineralization, with assay results expected in October.

Arras Minerals Corp. (TSXV:ARK)(OTCQB:ARRKF) ha fornito un aggiornamento sulle sue attività di esplorazione nel NE del Kazakistan. I punti salienti includono:

  • Completamento di un'indagine Heli-TEM di 3.547 chilometri lineari presso il progetto Bozshakol
  • Programma di perforazione KGK in corso presso le licenze di Aktasty e Maisor (progetto Bozshakol)
  • 80% di completamento dell'indagine Ground IP presso il progetto Elemes, con perforazioni in corso
  • Completamento del programma di perforazione KGK presso il progetto Tay

La società sta progredendo bene nel suo portafoglio progetti, con attività di perforazione a Elemes e Bozshakol volte a identificare obiettivi prioritari per future campagne. A Tay, i risultati iniziali mostrano zone di mineralizzazione da calcopirite, con risultati di analisi attesi per ottobre.

Arras Minerals Corp. (TSXV:ARK)(OTCQB:ARRKF) ha proporcionado una actualización sobre sus actividades de exploración en el NE de Kazajistán. Los aspectos más destacados incluyen:

  • Finalización de un estudio Heli-TEM de 3.547 kilómetros lineales en el proyecto Bozshakol
  • Programa de perforación KGK en curso en las licencias de Aktasty y Maisor (proyecto Bozshakol)
  • 80% de finalización del estudio Ground IP en el proyecto Elemes, con perforaciones en marcha
  • Finalización del programa de perforación KGK en el proyecto Tay

La empresa está avanzando bien en su cartera de proyectos, con actividades de perforación en Elemes y Bozshakol destinadas a identificar objetivos prioritarios para futuras campañas. En Tay, los resultados iniciales muestran zonas de mineralización de calcopirita, con resultados de ensayos esperados para octubre.

Arras Minerals Corp. (TSXV:ARK)(OTCQB:ARRKF)는 카자흐스탄 동북부 지역에서 진행 중인 탐사 활동에 대한 업데이트를 제공했습니다. 주요 내용은 다음과 같습니다:

  • Bozshakol 프로젝트에서 3,547km의 Heli-TEM 조사가 완료되었습니다.
  • Aktasty 및 Maisor 라이센스(Bozshakol 프로젝트)에서 KGK 드릴 프로그램이 진행되고 있습니다.
  • Elemes 프로젝트에서 지상 IP 조사 진행률이 80%이며, 코어 드릴링이 진행 중입니다.
  • Tay 프로젝트에서 KGK 드릴 프로그램이 완료되었습니다.

회사는 Elemes와 Bozshakol 프로젝트에서 향후 캠페인을 위한 우선 순위 목표를 식별하기 위해 잘 진행되고 있습니다. Tay에서는 초기 결과가 칼코프라이트 광물화 영역을 보여주며, 분석 결과는 10월에 예상됩니다.

Arras Minerals Corp. (TSXV:ARK)(OTCQB:ARRKF) a fourni une mise à jour sur ses activités d'exploration dans le nord-est du Kazakhstan. Les points clés incluent :

  • Achèvement d'une enquête Heli-TEM de 3 547 kilomètres linéaires dans le projet Bozshakol
  • Programme de forage KGK en cours dans les licences d'Aktasty et de Maisor (projet Bozshakol)
  • Complétion à 80 % de l'enquête Ground IP dans le projet Elemes, avec des forages en cours
  • Achèvement du programme de forage KGK dans le projet Tay

La société progresse bien dans son portefeuille de projets, avec des activités de forage à Elemes et Bozshakol visant à identifier des cibles prioritaires pour de futures campagnes. À Tay, les premiers résultats montrent des zones de minéralisation chalcopyrite, les résultats d'analyse étant attendus en octobre.

Arras Minerals Corp. (TSXV:ARK)(OTCQB:ARRKF) hat ein Update zu seinen Explorationsaktivitäten im Nordosten Kasachstans bereitgestellt. Die wichtigsten Highlights umfassen:

  • Abschluss einer 3.547 Kilometer langen Heli-TEM-Untersuchung im Bozshakol-Projekt
  • Laufendes KGK-Bohrprogramm im Aktasty- und Maisor-Lizenzgebiet (Bozshakol-Projekt)
  • 80% abgeschlossen bei der Boden-IP-Untersuchung im Elemes-Projekt, mit laufenden Kernausbohrungen
  • Abschluss des KGK-Bohrprogramms im Tay-Projekt

Das Unternehmen macht gute Fortschritte in seinem Projektportfolio, mit Bohraktivitäten in Elemes und Bozshakol, die darauf abzielen, vorrangige Ziele für zukünftige Kampagnen zu identifizieren. Bei Tay zeigen erste Ergebnisse Zonen mit Chalcopyritmineralisierung; die Analyseergebnisse werden im Oktober erwartet.

Positive
  • Completion of 3,547 line-kilometer Heli-TEM survey at Bozshakol project
  • 80% completion of Ground IP Survey at Elemes project, with core drilling underway
  • Identification of high-priority targets at Elemes project
  • Ongoing 17,000-meter KGK drill program at Bozshakol project
  • Visual results from Tay project showing zones of chalcopyrite mineralization
Negative
  • Tay project drilling results showed less intensive alteration and sulfides than expected

VANCOUVER, BC / ACCESSWIRE / September 4, 2024 / Arras Minerals Corp. (TSXV:ARK)(OTCQB:ARRKF) ("Arras" or "the Company") is pleased to provide an update on its exploration activities underway across the project portfolio in NE Kazakhstan.

Highlights

  • 3,547 line-kilometer Heli-TEM survey over the entire 1397 square-kilometer Bozshakol project mineral tenement package announced July 22, 2024 has now been completed

  • KGK Drill program underway at Aktasty and Maisor licenses (Bozshakol project) targeting high-priority areas to test bedrock under 10-40 m of unconsolidated cover

  • Ground IP Survey at Elemes project is now 80% completed, high priority targets identified, core drill program now underway at Berezski East and Berezski Central targets

  • KGK Drill program at Tay project completed

Figure 1. Map of Arras projects in Pavlodar, Kazakhstan

Bozshakol Project:

The Bozshakol Project (Package "A" in Figure 1) is located 56km to the northwest of the town of Ekibastuz and surrounds and covers the potential continuation of mineralization of KAZ Minerals' Bozshakol copper- mine.

The Heli-Tem survey announced on July 22 nd has now been completed. Analysis of data is underway. A 17,000-meter KGK drill program has commenced at the Aktasty and Maisor licenses to test the bedrock at targets identified through geophysics and soil sampling completed to date, and to better understand the subsurface geology that lays below 10-40 m of quaternary cover. This program, along with the Heli-Tem survey is expected to inform on priority drill targets for 2025.

Elemes Project:

The Ground IP Survey at the Elemes project which commenced in July is approximately 80% complete and expected to be finished in September. The survey over the Berezski East and Berezski Central target areas has been completed and drill targets for these areas prioritized. A core drill is now underway at these areas with drilling at the Elemes Project expected to continue across a number of priority targets into November with 5000m planned for this Phase I program. Initial assays are expected in November.

Figure 2. Berezski Target at Elemes Project showing soil geochemistry and exploration targets.

Tay Project:

A 5,424m KGK drilling program has been completed at the Tay Project. This program targeted the Soviet-era IP anomaly that formed the basis to acquire the license earlier this year. The 135 KGK holes successfully tested the top of bedrock across the anomaly returning predominantly basalts and schists.

Following completion of the KGK program, a single line of Ground IP survey was undertaken which confirmed the location of the Soviet IP anomaly with inversion analysis indicating an anomaly at approximately 140m below surface. Given the KGK drill is not able to reach that depth, a single core hole was drilled to test the heart of the anomaly and was drilled to 400 m. Visual results from the hole indicate several zones of chalcopyrite mineralization along fractures within basalts and gabbros. Priority intervals have been dispatched to the assay lab with results expected in October.

Tim Barry, CEO commented, "We are very pleased with how the programs are progressing so far this summer with activity across virtually the entire license package. The Ground IP survey at Elemes has progressed well and we are excited to have a drill turning there now as we begin to test the first batch of new priority targets at this exciting project. Additionally, all the work taking place at the Bozshakol group is advancing this project area to prioritize drill targets and follow-up areas ahead of an expected busy drilling campaign in 2025. At Tay, while we are awaiting assay results, we were surprised to not see more intensive alteration and sulfides in the drill core given how well the IP anomaly was confirmed with our own Ground IP survey. Once assays are received, we will review and decide on next steps at Tay."

Qualified Person: The scientific and technical disclosure for this news release has been prepared under supervision of and approved by Matthew Booth, Vice President of Exploration, of Arras Minerals Corp., a Qualified Person for the purposes of NI 43-101. Mr. Booth has over 19 years of mineral exploration experience and is a Qualified Person member of the American Institute of Professional Geologists (CPG 12044).

On behalf of the Board of Directors

"Tim Barry"

Tim Barry, MAusIMM CP(Geo)
Chief Executive Officer and Director

INVESTOR RELATIONS:

+1 604 687 5800
info@arrasminerals.com

Further information can be found on:

About Arras Minerals Corp.

Arras is a Canadian exploration and development company advancing a portfolio of copper and gold assets in northeastern Kazakhstan, including the Option Agreement on the Beskauga copper and gold project. The Company has established the third-largest license package in the country prospective for copper and gold (behind Rio Tinto and Fortescue). In December 2023, the Company entered into a strategic alliance with Teck Resources ("Teck") in which Teck will sole fund a US$5 million generative exploration program over a portion of the Arras license package in 2024-2025 focusing on critical minerals. The Company's shares are listed on the TSX-V under the trading symbol "ARK" and on the OTCQB under the trading symbol "ARRKF".

Cautionary Note to U.S. Investors concerning estimates of Measured, Indicated, and Inferred Resources: This press release uses the terms "measured resources", "indicated resources", and "inferred resources" which are defined in, and required to be disclosed by, NI 43-101. The Company advises U.S. investors that these terms are not recognized by the SEC. The estimation of measured, indicated and inferred resources involves greater uncertainty as to their existence and economic feasibility than the estimation of proven and probable reserves. U.S. investors are cautioned not to assume that measured and indicated mineral resources will be converted into reserves. The estimation of inferred resources involves far greater uncertainty as to their existence and economic viability than the estimation of other categories of resources. U.S. investors are cautioned not to assume that estimates of inferred mineral resources exist, are economically minable, or will be upgraded into measured or indicated mineral resources. Under Canadian securities laws, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies.

Disclosure of "contained ounces" in a resource is permitted disclosure under Canadian regulations, however the SEC normally only permits issuers to report mineralization that does not constitute "reserves" by SEC standards as in place tonnage and grade without reference to unit measures. Accordingly, the information contained in this press release may not be comparable to similar information made public by U.S. companies that are not subject NI 43-101.

Cautionary note regarding forward-looking statements: This news release contains forward-looking statements regarding future events and Arras' future results that are subject to the safe harbors created under the U.S. Private Securities Litigation Reform Act of 1995, the Securities Act of 1933, as amended, and the Exchange Act, and applicable Canadian securities laws. Forward-looking statements include, among others, statements regarding plans and expectations of the exploration program Arras is in the process of undertaking, including the expansion of the Mineral Resource, and other aspects of the Mineral Resource estimates for the Beskauga project. These statements are based on current expectations, estimates, forecasts, and projections about Arras' exploration projects, the industry in which Arras operates and the beliefs and assumptions of Arras' management. Words such as "expects," "anticipates," "targets," "goals," "projects," "intends," "plans," "believes," "seeks," "estimates," "continues," "may," variations of such words, and similar expressions and references to futureperiods, are intended to identify such forward-looking statements. Forward-looking statements are subject to a number of assumptions, risks and uncertainties, many of which are beyond management's control, including undertaking further exploration activities, the results of such exploration activities and that such results support continued exploration activities, unexpected variations in ore grade, types and metallurgy, volatility and level of commodity prices, the availability of sufficient future financing, and other matters discussed under the caption "Risk Factors" in the Management Discussion and Analysis filed on the Company's profile on SEDAR on February 28, 2024 and in the Company's Annual Report on Form 20-F for the fiscal year ended October 31, 2023 filed with the U.S. Securities and Exchange Commission filed on February 28, 2024 available on www.sec.gov. Readers are cautioned that forward-looking statements are not guarantees of future performance and that actual results or developments may differ materially from those expressed or implied in the forward-looking statements. Any forward-looking statement made by the Company in this release is based only on information currently available and speaks only as of the date on which it is made. The Company undertakes no obligation to publicly update any forward-looking statement, whether written or oral, that may be made from time to time, whether as a result of new information, future developments, or otherwise.

SOURCE: Arras Minerals Corp.



View the original press release on accesswire.com

FAQ

What is the status of Arras Minerals' Heli-TEM survey at the Bozshakol project?

The 3,547 line-kilometer Heli-TEM survey over the entire 1397 square-kilometer Bozshakol project mineral tenement package has been completed, and data analysis is currently underway.

What drilling activities are currently taking place at Arras Minerals' Elemes project?

Core drilling is currently underway at the Berezski East and Berezski Central target areas of the Elemes project, with 5000m planned for the Phase I program. Initial assays are expected in November.

What were the results of Arras Minerals' KGK drilling program at the Tay project?

The 5,424m KGK drilling program at the Tay project has been completed, with 135 holes testing the top of bedrock across a Soviet-era IP anomaly. A single core hole drilled to 400m showed several zones of chalcopyrite mineralization along fractures within basalts and gabbros.

When does Arras Minerals (TSXV:ARK) expect to receive assay results from the Tay project?

Arras Minerals expects to receive assay results from priority intervals of the Tay project core hole in October 2024.

SILVER BULL RESOURCES NEW

OTC:SVBL

SVBL Rankings

SVBL Latest News

SVBL Stock Data

4.26M
42.28M
9.51%
0.41%
Other Industrial Metals & Mining
Basic Materials
Link
United States of America
Vancouver