Sandfire Resources America announced the outcome of a legal challenge regarding its Mine Operating Permit. The Montana District Court ruled on April 8, 2022, in favor of the plaintiffs, stating the Montana DEQ violated the Montana Metal Mines Reclamation Act and Montana Environmental Policy Act. This ruling may impact the development timeline for Sandfire's Black Butte Copper Project. The company plans to evaluate the decision and strategize accordingly. Senior VP Jerry Zieg stated confidence in the project's regulatory compliance and safety standards.

Positive
  • Sandfire America has invested significantly in meeting Montana's stringent permitting requirements.
  • The project is recognized as one of the most comprehensive and safest mining plans in Montana.
Negative
  • The court ruling indicates potential regulatory setbacks, impacting the project timeline.
  • Uncertainty regarding the remedy could delay project advancement and investor confidence.

WHITE SULPHUR SPRINGS, Mont., April 11, 2022 (GLOBE NEWSWIRE) -- Sandfire Resources America Inc. (“Sandfire America” or the “Company”) announces results of the state District Court Legal Challenge related to its Mine Operating Permit.

On July 16, 2021, District Court Judge Bidegaray heard oral arguments for summary judgment from plaintiffs and defendants regarding a legal complaint filed on June 4, 2020 by the plaintiffs claiming to represent the environmental community. The suit was filed jointly against the Montana Department of Environmental Quality (MT DEQ) and Tintina Montana Inc. Additional intervenors in the suit supporting the MT DEQ and Tintina Montana Inc, include Meagher County, Broadwater County, and the Montana Department of Justice.

A decision on the case was issued on April 8, 2022 and received by the Company on April 11, 2022. The Order grants the plaintiffs' motion for summary judgment stating that the Montana DEQ violated the Montana Metal Mines Reclamation Act (MMRA) and Montana Environmental Policy Act (MEPA) in its analysis. A remedy will be decided after additional briefing, due to the court within 45 days. Upon receipt of the Judge’s remedy, the Company will have a clearer picture of the impact, if any, on the project development timeline.

The Company is reviewing the legal decision and will then make a plan on going forward after the information has been evaluated.

Sandfire America’s Senior Vice President Jerry Zieg shared, “We have gone above and beyond industry standards to satisfy Montana’s permitting requirements, which provide one of the toughest regulatory processes worldwide. The Montana DEQ has done comprehensive, diligent work in the environmental and technical analyses and the project continues to be cited as one of the most comprehensive and safest mining plans Montana has ever seen. This is an ongoing process and we continue to have confidence in our project.”

Contact Information:
Sandfire Resources America Inc.
Nancy Schlepp, VP of Communications
Mobile: 406-224-8180
Office: 406-547-3466
Email: nschlepp@sandfireamerica.com

Jerry Zieg, Vice President of Exploration for the Company, is a Qualified Person for the purposes of NI 43-101 and has also reviewed and approved the information of a scientific or technical nature contained in this news release.

Cautionary Note Regarding Forward-Looking Statements: Certain disclosures in this document constitute “forward looking information” within the meaning of Canadian securities legislation, including statements regarding the District Court Legal Challenge related to the Company’s Mine Operating Permit, permitting timelines and the Company’s plans for advancing the Black Butte Copper Project and expected outcomes. In making these forward-looking statements, the Company has applied certain factors and assumptions that the Company believes are reasonable, including that the Company will receive required regulatory approvals, that the Company will continue to be able to access sufficient funding to execute its plans, and that the results of exploration and development activities are consistent with management’s expectations. However, the forward-looking statements in this document are subject to numerous risks, uncertainties and other factors, including factors relating to the Company’s operation as a mineral exploration and development company and the Black Butte Copper Project, that may cause future results to differ materially from those expressed or implied in such forward-looking statements, including that results of exploration and development activities will not be consistent with management’s expectations, delays in obtaining or inability to obtain required government or other regulatory approvals or financing, failure of plant, equipment or processes to operate as anticipated, the risk of accidents, labor disputes, inclement or hazardous weather conditions, unusual or unexpected geological conditions, ground control problems, earthquakes, flooding and all of the other risks generally associated with the development of mining facilities. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Readers are cautioned not to place undue reliance on forward-looking statements. The Company does not intend, and expressly disclaims any intention or obligation to, update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

 


FAQ

What was the outcome of Sandfire Resources America's legal challenge?

The Montana District Court ruled in favor of the plaintiffs, indicating the Montana DEQ violated permitting laws.

How will the court ruling affect Sandfire Resources America's project timeline?

The ruling could potentially delay the development timeline for the Black Butte Copper Project.

What are the implications of the court's decision on Sandfire Resources America?

The company needs to evaluate the legal decision and its potential impact on project development.

When did the court rule on the legal challenge against Sandfire Resources America?

The court issued its ruling on April 8, 2022.

What is the Black Butte Copper Project?

It is a project by Sandfire Resources America focusing on copper mining in Montana.

SANDFIRE RES AMER INC

OTC:SRAFF

SRAFF Rankings

SRAFF Latest News

SRAFF Stock Data

226.23M
133.93M
86.91%
4.17%
Other Industrial Metals & Mining
Basic Materials
Link
United States of America
Vancouver