STOCK TITAN

Sandfire Resources America Inc. Announces Win at the Montana Supreme Court with Complete Reinstatement of the Mine Operating Permit

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags
Rhea-AI Summary
Sandfire Resources America Inc. announces a positive ruling by the Montana Supreme Court allowing the Black Butte Copper Project to proceed with construction of its underground copper mine. The Company won on all counts with a 5-2 decision, overturning a previous District Court ruling. The project has all necessary permits to move forward.
Positive
  • Positive ruling by the Montana Supreme Court for Sandfire America's Black Butte Copper Project.
  • Company granted summary judgment to proceed with construction of the underground copper mine.
  • Successful appeal overturning a District Court ruling invalidating the mining permit.
  • All permits in place for the Black Butte Copper Project to progress.
  • Stipulated agreements finalized for water rights through the MT DNRC.
  • Challenges to water rights permit ongoing but not affecting current project status.
Negative
  • None.

WHITE SULPHUR SPRINGS, Mont., Feb. 26, 2024 (GLOBE NEWSWIRE) -- Sandfire Resources America Inc. (“Sandfire America” or the “Company”) announces the positive ruling by the Montana Supreme Court which reversed a 2021 district court decision and instructed the District Judge to have the Montana Department of Environmental Quality (MT DEQ) to completely reinstate Tintina Montana Inc.’s Mine Operating Permit, of the Black Butte Copper Project.

The Montana Supreme Court granted the Company’s request for summary judgement allowing Black Butte Copper to move forward with construction of its highly engineered, underground copper mine. The Company won on all counts in the Montana Supreme Court decision with a 5-2 decision upholding the 2020 decision of the MT DEQ to allow copper mining at the Black Butte Copper Project, overturning a District Court ruling that had invalidated the mining permit.

The original suit was filed jointly against the Montana Department of Environmental Quality and Tintina Montana Inc. (“Tintina,” Sandfire America’s wholly owned subsidiary) on June 4th, 2020, and the Montana Supreme Court heard oral arguments on the case on June 21, 2023. Additional intervenors in the suit supporting the MT DEQ and Tintina, include Meagher County, Broadwater County, and the Montana Department of Justice.

Lincoln Greenidge, CEO of Sandfire America shared, “Today’s victory in the Montana Supreme Court is a validation of the thoughtful and deliberate efforts of the Sandfire America team to design a world-class, environmentally safe mining project from the beginning. The fact is, ours is the most reviewed and examined proposed project in the history of Montana mining. The Court record stands at over 90,000 pages of testimony, information, and analysis. We thank the justices for their ruling, and their ability to recognize the amount of effort and extensive work that has gone into this project. Now, we look forward to progressing the project in a safe, responsible, and sustainable manner.”

Senior VP, Jerry Zieg concluded stating, “Tintina’s permit has been diligently considered by the professional and hardworking staff at the MT DEQ. It is a fantastic, well-designed project with a plan centered around safety which is why we were successful today. Over a decade ago, we set out to design a state of the art, environmentally protective underground mining project, and this decision is proof we’ve been successful.”

Black Butte Copper now has all permits to proceed with the project. Stipulated agreements regarding water rights granted through the Montana Department of Natural Resources and Conservation (MT DNRC) for the project have been finalized with all water rights being issued and available. There is a challenge to the Montana Constitution’s definition of the “beneficial use of water” using Black Butte Copper’s water use permit to challenge this definition. This case does not currently affect the Company’s water rights package. The challenge, naming both the MT DNRC and Tintina Montana Inc., was appealed by objectors after their loss at District Court and will be heard by Montana Supreme Court on Friday, March 29, 2024.

Contact Information:
Sandfire Resources America Inc.
Nancy Schlepp, VP of Communications and Government Relations
Mobile: 406-224-8180
Office: 406-547-3466
Email: nschlepp@sandfireamerica.com

Jerry Zieg, Vice President of Exploration for the Company, is a Qualified Person for the purposes of NI 43-101 and has also reviewed and approved the information of a scientific or technical nature contained in this news release.

Cautionary Note Regarding Forward-Looking Statements: Certain disclosures in this document constitute “forward looking information” within the meaning of Canadian securities legislation, including statements related to the Company’s Mine Operating Permit, the Company’s water rights , permitting timelines and the Company’s plans for advancing the Black Butte Copper Project and expected outcomes. In making these forward-looking statements, the Company has applied certain factors and assumptions that the Company believes are reasonable, including that the Company will receive required regulatory approvals, that the Company will continue to be able to access sufficient funding to execute its plans, and that the results of exploration and development activities are consistent with management’s expectations. However, the forward-looking statements in this document are subject to numerous risks, uncertainties and other factors, including factors relating to the Company’s operation as a mineral exploration and development company and the Black Butte Copper Project, that may cause future results to differ materially from those expressed or implied in such forward-looking statements, including that results of exploration and development activities will not be consistent with management’s expectations, delays in obtaining or inability to obtain required government or other regulatory approvals or financing, failure of plant, equipment or processes to operate as anticipated, the risk of accidents, labor disputes, inclement or hazardous weather conditions, unusual or unexpected geological conditions, ground control problems, earthquakes, flooding and all of the other risks generally associated with the development of mining facilities. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Readers are cautioned not to place undue reliance on forward-looking statements. The Company does not intend, and expressly disclaims any intention or obligation to, update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.


FAQ

What recent ruling did the Montana Supreme Court make regarding Sandfire America's project?

The Montana Supreme Court granted a positive ruling allowing the Black Butte Copper Project to move forward with construction of its underground copper mine.

Who filed the original suit against the Montana Department of Environmental Quality and Tintina Montana Inc.?

The original suit was filed jointly by Sandfire America against the Montana Department of Environmental Quality and Tintina Montana Inc.

What permits does the Black Butte Copper Project now have?

The project has all necessary permits to proceed with its construction.

What challenges are ongoing regarding water rights for the project?

There is a challenge to the Montana Constitution's definition of the 'beneficial use of water' using the project's water use permit, but it does not currently affect the project's water rights package.

Who is the CEO of Sandfire America?

Lincoln Greenidge is the CEO of Sandfire America.

When will the challenge to the water rights permit be heard by the Montana Supreme Court?

The challenge will be heard by the Montana Supreme Court on Friday, March 29, 2024.

SANDFIRE RES AMER INC

OTC:SRAFF

SRAFF Rankings

SRAFF Latest News

SRAFF Stock Data

226.23M
133.93M
86.91%
4.17%
Other Industrial Metals & Mining
Basic Materials
Link
United States of America
Vancouver