Sierra Metals Reports Second Quarter 2022 Production Results

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Positive)
Tags
Rhea-AI Summary

Sierra Metals reports positive Q2 2022 production results, achieving a 12% increase in consolidated copper equivalent production to 17.8 million pounds compared to Q1 2022. Bolivar mine saw a 37% increase in daily throughput, while Yauricocha achieved an 11% improvement in copper equivalent production. However, Cusi mine experienced a 38% decline in silver equivalent production due to flooding. Overall, the company maintains operational stability amidst challenging market conditions.

Positive
  • 12% increase in consolidated copper equivalent production to 17.8 million pounds from Q1 2022.
  • 37% increase in average daily throughput at Bolivar to 2,930 tonnes per day.
  • Yauricocha mine showed an 11% increase in copper equivalent production over Q1 2022.
Negative
  • 38% decline in silver equivalent production at Cusi due to flooding.

(All metal prices reported in USD)

TORONTO--(BUSINESS WIRE)-- Sierra Metals Inc. (TSX: SMT) (BVL:SMT) (NYSE AMERICAN: SMTS) (“Sierra Metals” or “the Company”) announces second quarter 2022 production results.

Photo 1 Arial Photo of Bolivar Mine (Photo: Business Wire)

Photo 1 Arial Photo of Bolivar Mine (Photo: Business Wire)

Results are from Sierra Metals’ three underground mines in Latin America: The Yauricocha polymetallic mine in Peru, and the Bolivar copper and Cusi silver mines in Mexico.

Second Quarter 2022 Consolidated Production Highlights

  • Consolidated production guidance met with ongoing operational turnaround program at Bolivar
  • Consolidated copper equivalent production of 17.8 million pounds; a 12% increase from Q1 2022
  • Average daily throughput at Bolivar of 2,930 tonnes per day; a 37% increase from Q1 2022

Consolidated Q2 2022 results will be released on Thursday August 11th with a Shareholder Conference Call and Webcast to be held on Friday August 12th at 11:00 AM EDT

Luis Marchese, CEO of Sierra Metals, commented, “We continue to focus on the goals set forth when we announced our operational turnaround program, maintaining our strong commitment to health, safety, environment and the well-being of our stakeholders. In the current reduced commodities price and high inflation environment, we continue to monitor operations and production to determine any necessary modifications to our plans”

“Earlier this year, we provided a timeline for delivering initial improvements at our operations, which included a plan to ramp up production starting in Q2 of this year. Our turnaround program is starting to take effect with quarter-over-quarter improvements. At Yauricocha, we report quarter-over-quarter improvements to average daily tonnage and slightly higher grades for all metals except lead, with a 12% increase in copper equivalent production over Q1 2022. At Bolivar, when compared to Q1 2022, we report a 37% quarter-over-quarter improvement in average daily throughput during this quarter, along with slight increases to grades which resulted in a 62% increase in copper equivalent production over Q1 2022. At Cusi, an unexpected underground flooding event during the quarter resulted in a 38% decrease in quarter-over-quarter silver equivalent production.”

He concluded, “We are trending in the right direction with consolidated production improvements from our mines, having achieved production within our guidance for H1. Our disciplined approach to achieve stabilized mining operations continues, with our primary goal in mind – to achieve a full recovery at Bolivar. Infill drilling and exploration programs continue, in order to better define current resources and aim for new high grade ore bodies such as the Fortuna discovery at Yauricocha.”

Consolidated Production Results

Six months ended June 30,
Consolidated Production Q2 2022 Q1 2022 % Var. Q2 2021 % Var.

2022

2021

 
Tonnes processed

640,181

590,730

8%

787,534

-19%

1,230,911

1,561,955

Daily throughput

7,316

6,751

8%

9,000

-19%

7,034

8,925

 
 
Silver production (000 oz)

608

734

-17%

954

-36%

1,342

1,915

Copper production (000 lb)

8,334

6,324

32%

9,535

-13%

14,658

17,430

Lead production (000 lb)

3,333

4,216

-21%

7,960

-58%

7,549

16,964

Zinc production (000 lb)

10,426

10,492

-1%

21,133

-51%

20,918

45,256

Gold Production (oz)

2,622

1,923

36%

2,812

-7%

4,545

5,448

 
 
Copper equivalent pounds (000's)(1)

17,794

15,896

12%

24,786

-28%

33,670

50,157

 
(1) Copper equivalent pounds for Q2 2022 were calculated using the following realized prices: $22.65/oz Ag, $4.30/lb Cu, $1.79/lb Zn, $1.00/lb Pb, $1,872/oz Au. Copper equivalent pounds for Q2 2021 were calculated using the following realized prices: $26.80/oz Ag, $4.37/lb Cu, $1.34/lb Zn, $0.97/lb Pb, $1,818/oz Au. Copper equivalent pounds for 6M 2022 were calculated using the following realized prices: $23.30/oz Ag, $4.42/lb Cu, $1.74/lb Zn, $1.03/lb Pb, $1,873/oz Au. Copper equivalent pounds for 6M 2021 were calculated using the following realized prices: $26.62/oz Ag, $4.13/lb Cu, $1.29/lb Zn, $0.94/lb Pb, $1,798/oz Au.

Q2 2022 throughput from the Yauricocha Mine was 317,087 tonnes which is in line with throughput during Q1 2022. Higher grades in all metals with the exception of lead, resulted in an 11% increase to copper equivalent pounds produced. When compared to Q2 2021, throughput from the Yauricocha Mine was 4% lower when combined with lower grades, except for copper and gold, which resulted in a 21% decrease in copper equivalent pounds produced.

At the Bolivar Mine, throughput was 256,372 tonnes during Q2 2022 or 37% higher as compared to Q1 2022. Higher copper, silver and gold grades resulted in a 62% increase to copper equivalent pound production when compared to the previous quarter. When compared to Q2 2021, throughput at Bolivar was 33% lower and grades were lower for all metals except for gold, resulting in a 46% decrease in copper equivalent pounds produced.

At Cusi, throughput was 66,722 tonnes during Q2 2022 or 21% lower as compared to Q1 2022. Lower throughput and lower grades resulted in a 38% decrease in silver equivalent production. When comparing Q2 2022 to Q2 2021, silver equivalent production remained flat due to higher head grades for all metals, despite a 9% decrease in throughput.

Yauricocha Mine, Peru

The Yauricocha Mine processed 317,087 tonnes during Q2 2022, which was in line with throughput in Q1 2022. However, we note an improvement when compared to Q1 2022 copper equivalent pound production, with an 11% increase to 12.1 million pounds due to improved grades in all metals with the exception of lead.

When compared to Q2 2021, there was a 4% decrease from the 328,909 tonnes processed in the same quarter of 2021. Negative variances in the lead and zinc grades and positive variance in the copper grade resulted from mining in the Esperanza ore body. Despite a 39% increase in copper production, copper equivalent production was 21% lower than the Q2 2021 production, due to lower quantities of silver, zinc and lead produced.

A summary of production from the Yauricocha Mine for Q2 2022 is provided below:

Six months ended June 30,
Yauricocha Production Q2 2022 Q1 2022 % Var. Q2 2021 % Var.

2022

2021

 
Tonnes processed

317,087

315,250

1%

328,909

-4%

632,337

655,120

Daily throughput

3,624

3,603

1%

3,759

-4%

3,613

3,744

 
 
Silver grade (g/t)

44.65

39.40

13%

56.94

-22%

42.03

55.65

Copper grade

0.93%

0.79%

18%

0.70%

33%

0.86%

0.63%

Lead grade

0.58%

0.66%

-12%

1.20%

-52%

0.62%

1.27%

Zinc grade

1.88%

1.83%

3%

3.27%

-43%

1.86%

3.49%

Gold Grade (g/t)

0.54

0.52

4%

0.45

20%

0.53

0.44

 
Silver recovery

58.64%

63.99%

-8%

80.14%

-27%

61.30%

79.70%

Copper recovery

78.66%

77.22%

2%

72.67%

8%

77.90%

69.84%

Lead recovery

75.81%

82.50%

-8%

90.14%

-16%

78.28%

90.15%

Zinc recovery

79.21%

82.09%

-4%

89.23%

-11%

80.12%

89.82%

Gold Recovery

21.62%

20.06%

8%

21.99%

-2%

20.84%

20.91%

 
 
Silver production (000 oz)

267

256

4%

483

-45%

523

934

Copper production (000 lb)

5,127

4,279

20%

3,697

39%

9,406

6,379

Lead production (000 lb)

3,060

3,828

-20%

7,831

-61%

6,888

16,537

Zinc production (000 lb)

10,426

10,492

-1%

21,133

-51%

20,918

45,256

Gold Production (oz)

1,179

1,057

12%

1,043

13%

2,236

1,933

 
 
Copper equivalent pounds (000's)(1)

12,105

10,876

11%

15,308

-21%

22,969

31,142

 
 
(1) Copper equivalent pounds for Q2 2022 were calculated using the following realized prices: $22.65/oz Ag, $4.30/lb Cu, $1.79/lb Zn, $1.00/lb Pb, $1,872/oz Au. Copper equivalent pounds for Q2 2021 were calculated using the following realized prices: $26.80/oz Ag, $4.37/lb Cu, $1.34/lb Zn, $0.97/lb Pb, $1,818/oz Au. Copper equivalent pounds for 6M 2022 were calculated using the following realized prices: $23.30/oz Ag, $4.42/lb Cu, $1.74/lb Zn, $1.03/lb Pb, $1,873/oz Au. Copper equivalent pounds for 6M 2021 were calculated using the following realized prices: $26.62/oz Ag, $4.13/lb Cu, $1.29/lb Zn, $0.94/lb Pb, $1,798/oz Au.

Bolivar Mine, Mexico

The Bolivar mine processed 256,372 tonnes in Q2 2022, compared to 187,556 tonnes in Q1 2022, which was a 37% increase. Higher production as well as higher grades in all metals resulted in a 62% increase in copper equivalent pound production.

When comparing Q2 2022 to Q2 2021, tonnes were 33% lower and grades for copper and silver were 27% and 35% lower respectively, while gold was 14% higher. The change in grade profile is due to the depletion of Bolivar West and the new contribution of the Bolivar NorthWest orebody. When compared to Q2 2021, the decrease in throughput and grades resulted in a 46% decrease in copper equivalent pounds produced during Q2 2022.

While the operational turnaround effort continues at Bolivar, we expect higher plant throughput for the balance of the year, due to improved access to mineralized areas including higher contribution from the Bolivar Northwest zone.

A summary of production for the Bolivar Mine for Q2 2022 is provided below:

Six months ended June 30,
Bolivar Production Q2 2022 Q1 2022 % Var. Q2 2021 % Var.

Q2 2022

Q2 2021

 
Tonnes processed (t)

256,372

187,556

37%

385,331

-33%

443,928

756,939

Daily throughput

2,930

2,144

37%

4,404

-33%

2,537

4,325

 
 
Copper grade

0.63%

0.58%

9%

0.86%

-27%

0.61%

0.82%

Silver grade (g/t)

12.36

10.97

13%

19.06

-35%

11.77

19.31

Gold grade (g/t)

0.24

0.16

50%

0.21

14%

0.20

0.20

 
Copper recovery

90.61%

85.22%

6%

79.89%

13%

88.35%

82.25%

Silver recovery

80.99%

88.44%

-8%

85.74%

-6%

84.11%

85.13%

Gold recovery

65.93%

63.53%

4%

63.19%

4%

65.11%

66.95%

 
 
Copper production (000 lb)

3,207

2,045

57%

5,838

-45%

5,252

11,051

Silver production (000 oz)

83

58

43%

202

-59%

141

399

Gold production (oz)

1,283

592

117%

1,627

-21%

1,875

3,218

 
 
Copper equivalent pounds (000's)(1)

4,199

2,597

62%

7,754

-46%

6,788

15,024

 
 
(1) Copper equivalent pounds for Q2 2022 were calculated using the following realized prices: $22.65/oz Ag, $4.30/lb Cu, $1.79/lb Zn, $1.00/lb Pb, $1,872/oz Au. Copper equivalent pounds for Q2 2021 were calculated using the following realized prices: $26.80/oz Ag, $4.37/lb Cu, $1.34/lb Zn, $0.97/lb Pb, $1,818/oz Au. Copper equivalent pounds for 6M 2022 were calculated using the following realized prices: $23.30/oz Ag, $4.42/lb Cu, $1.74/lb Zn, $1.03/lb Pb, $1,873/oz Au. Copper equivalent pounds for 6M 2021 were calculated using the following realized prices: $26.62/oz Ag, $4.13/lb Cu, $1.29/lb Zn, $0.94/lb Pb, $1,798/oz Au.

Cusi Mine, Mexico

Operating at an average throughput of 763 tpd, Cusi processed 21% fewer tonnes of ore in Q2 2022 as compared to Q1 2022, mainly due to the unexpected underground flooding issues in the quarter. The decrease in grades and throughput at the Cusi Mine resulted in a 38% decrease in silver equivalent ounces.

When comparing Q2 2022 to Q2 2021, the mine processed 9% fewer tonnes of ore. Silver production decreased 4% to 0.3 million ounces, gold production increased 13% to 160 ounces and lead production increased 112% to 0.3 million pounds. Silver equivalent production of 283,000 ounces for the quarter was in line with Q2 2021.

A summary of production for the Cusi Mine for Q2 2022 is provided below:

Six months ended June 30,
Cusi Production Q2 2022 Q1 2022 % Var. Q2 2021 % Var. Q2 2022 Q2 2021 % Var.
 
Tonnes processed (t)

66,722

87,924

-24%

73,294

-9%

154,646

149,896

Daily throughput(2)

763

964

-21%

838

-9%

884

857

 
 
Silver grade (g/t)

146.34

173.96

-16%

138.94

5%

162.04

148.28

Gold grade (g/t)

0.17

0.19

-11%

0.16

6%

0.18

0.16

Lead grade

0.23%

0.26%

-12%

0.10%

130%

0.24%

0.16%

 
Silver recovery (flotation)

82.07%

85.37%

-4%

81.96%

0%

83.93%

81.39%

Gold recovery (lixiviation)

43.64%

49.94%

-13%

37.41%

17%

47.17%

38.51%

Lead recovery

80.78%

76.96%

5%

82.95%

-3%

77.86%

81.90%

 
 
Silver production (000 oz)

258

420

-39%

269

-4%

678

582

Gold production (oz)

160

274

-42%

142

13%

434

297

Lead production (000 lb)

273

388

-30%

129

112%

661

427

 
 
Silver equivalent ounces (000's)(1)

283

458

-38%

283

0%

742

617

 
(1) Silver equivalent ounces for Q2 2022 were calculated using the following realized prices: $22.65/oz Ag, $4.30/lb Cu, $1.79/lb Zn, $1.00/lb Pb, $1,872/oz Au. Silver equivalent ounces for Q2 2021 were calculated using the following realized prices: $26.80/oz Ag, $4.37/lb Cu, $1.34/lb Zn, $0.97/lb Pb, $1,818/oz Au. Silver equivalent ounces for 6M 2022 were calculated using the following realized prices: $23.30/oz Ag, $4.42/lb Cu, $1.74/lb Zn, $1.03/lb Pb, $1,873/oz Au. Silver equivalent ounces for 6M 2021 were calculated using the following realized prices: $26.62/oz Ag, $4.13/lb Cu, $1.29/lb Zn, $0.94/lb Pb, $1,798/oz Au.

Quality Control
Américo Zuzunaga, FAusIMM (Mining Engineer) and Vice President, Technical, is a Qualified Person under National Instrument 43-101 – Standards of Disclosure for Mineral Projects.

About Sierra Metals
Sierra Metals Inc. is a diversified Canadian mining company with Green Metal exposure including increasing copper production and base metal production with precious metals byproduct credits, focused on the production and development of its Yauricocha Mine in Peru, and Bolivar and Cusi Mines in Mexico. The Company is focused on increasing production volume and growing mineral resources. Sierra Metals has recently had several new key discoveries and still has many more exciting brownfield exploration opportunities at all three Mines in Peru and Mexico that are within close proximity to the existing mines. Additionally, the Company also has large land packages at all three mines with several prospective regional targets providing longer-term exploration upside and mineral resource growth potential.

The Company's Common Shares trade on the Bolsa de Valores de Lima and on the Toronto Stock Exchange under the symbol "SMT" and on the NYSE American Exchange under the symbol "SMTS".

For further information regarding Sierra Metals, please visit www.sierrametals.com.

Continue to Follow, Like and Watch our progress:

Web: www.sierrametals.com | Twitter: sierrametals | Facebook: SierraMetalsInc | LinkedIn: Sierra Metals Inc | Instagram: sierrametals

Forward-Looking Statements

This press release contains forward-looking information within the meaning of Canadian and United States securities legislation. Forward-looking information relates to future events or the anticipated performance of Sierra and reflect management's expectations or beliefs regarding such future events and anticipated performance based on an assumed set of economic conditions and courses of action. In certain cases, statements that contain forward-looking information can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", "believes" or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might", or "will be taken", "occur" or "be achieved" or the negative of these words or comparable terminology. By its very nature forward-looking information involves known and unknown risks, uncertainties and other factors that may cause actual performance of Sierra to be materially different from any anticipated performance expressed or implied by such forward-looking information.

Forward-looking information is subject to a variety of risks and uncertainties, which could cause actual events or results to differ from those reflected in the forward-looking information, including, without limitation, the risks described under the heading "Risk Factors" in the Company's annual information form dated March 16, 2022 for its fiscal year ended December 31, 2021 and other risks identified in the Company's filings with Canadian securities regulators and the United States Securities and Exchange Commission, which filings are available at www.sedar.com and www.sec.gov, respectively.

The risk factors referred to above are not an exhaustive list of the factors that may affect any of the Company's forward-looking information. Forward-looking information includes statements about the future and is inherently uncertain, and the Company's actual achievements or other future events or conditions may differ materially from those reflected in the forward-looking information due to a variety of risks, uncertainties and other factors. The Company's statements containing forward-looking information are based on the beliefs, expectations, and opinions of management on the date the statements are made, and the Company does not assume any obligation to update such forward-looking information if circumstances or management's beliefs, expectations or opinions should change, other than as required by applicable law. For the reasons set forth above, one should not place undue reliance on forward-looking information.

Investor Relations

Sierra Metals Inc.

Tel: +1 (416) 366-7777

Email: info@sierrametals.com

Luis Marchese

CEO

Sierra Metals Inc.

Tel: +1 (416) 366-7777

Source: Sierra Metals Inc.

FAQ

What were Sierra Metals' production results for Q2 2022?

Sierra Metals reported a 12% increase in consolidated copper equivalent production to 17.8 million pounds compared to Q1 2022.

How much did the Bolivar mine's throughput increase in Q2 2022?

The Bolivar mine's average daily throughput increased by 37% to 2,930 tonnes per day in Q2 2022.

What caused the decline in Cusi mine's production in Q2 2022?

The decline in silver equivalent production at the Cusi mine was caused by an unexpected underground flooding event.

When will Sierra Metals release its consolidated Q2 2022 results?

Sierra Metals will release its consolidated Q2 2022 results on August 11, 2022.

What is the stock symbol for Sierra Metals?

The stock symbol for Sierra Metals is SMTS.

SMTS

NYSE:SMTS

SMTS Rankings

SMTS Latest News

SMTS Stock Data

32.71M
117.91M
0.96%
40.63%
Link
Canada
Toronto