Sierra Madre Declares Industrial Production at the Guitarra Mine Processing Plant

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Very Positive)
Tags

Sierra Madre Gold and Silver has announced the commencement of industrial production at its Guitarra mine processing plant in Mexico. The plant has operated at 86% of milling capacity (516 wet metric tonnes daily) for two months, surpassing the 80% engineering standard required for industrial production declaration.

Production highlights include: October - 13,208 wet tonnes processed, yielding 296.84 dry tonnes of concentrate (21,186 oz silver, 295.3 oz gold); November - 13,064 wet tonnes processed, yielding 317.7 dry tonnes of concentrate (22,917 oz silver, 363.3 oz gold). The company sold 17 truckloads totaling 546.2 dry tonnes of concentrate across both months.

The mine currently operates 11 stopes, including three new vein discoveries outside the 2023 NI 43-101 resource estimation. The company aims to achieve full commercial underground production by December 31, 2024.

Sierra Madre Gold and Silver ha annunciato l'inizio della produzione industriale presso il suo impianto di processamento della miniera Guitarra in Messico. L'impianto ha funzionato all'86% della capacità di macinazione (516 tonnellate metriche umide al giorno) per due mesi, superando il 80% dello standard ingegneristico richiesto per la dichiarazione di produzione industriale.

I punti salienti della produzione includono: ottobre - 13.208 tonnellate umide processate, con un rendimento di 296,84 tonnellate secche di concentrato (21.186 once d'argento, 295,3 once d'oro); novembre - 13.064 tonnellate umide processate, con un rendimento di 317,7 tonnellate secche di concentrato (22.917 once d'argento, 363,3 once d'oro). La società ha venduto 17 carichi di camion per un totale di 546,2 tonnellate secche di concentrato in entrambi i mesi.

La miniera attualmente opera 11 stope, comprese tre nuove scoperte di vene al di fuori della stima delle risorse NI 43-101 del 2023. L'azienda mira a raggiungere una produzione sotterranea commerciale totale entro il 31 dicembre 2024.

Sierra Madre Gold and Silver ha anunciado el inicio de la producción industrial en su planta de procesamiento de la mina Guitarra en México. La planta ha operado al 86% de su capacidad de molienda (516 toneladas métricas húmedas diarias) durante dos meses, superando el 80% del estándar de ingeniería requerido para declarar producción industrial.

Los aspectos destacados de la producción incluyen: octubre - 13,208 toneladas húmedas procesadas, que resultaron en 296.84 toneladas secas de concentrado (21,186 oz de plata, 295.3 oz de oro); noviembre - 13,064 toneladas húmedas procesadas, que resultaron en 317.7 toneladas secas de concentrado (22,917 oz de plata, 363.3 oz de oro). La empresa vendió 17 cargamentos sumando 546.2 toneladas secas de concentrado en ambos meses.

Actualmente, la mina opera 11 stope, incluyendo tres nuevos descubrimientos de venas fuera de la estimación de recursos NI 43-101 de 2023. La empresa tiene como objetivo alcanzar la producción comercial subterránea completa para el 31 de diciembre de 2024.

시에라 마드레 골드 앤 실버가 멕시코의 귀타라 광산 가공 공장에서 산업 생산을 시작한다고 발표했습니다. 이 공장은 두 달 동안 가공 능력의 86% (일일 516 습식 톤)로 운영되었으며, 산업 생산 선언에 필요한 엔지니어링 기준인 80%를 초과했습니다.

생산 하이라이트는 다음과 같습니다: 10월 - 13,208 습식 톤 가공, 296.84 건조 톤의 농축물 생산 (21,186 온스의 은, 295.3 온스의 금); 11월 - 13,064 습식 톤 가공, 317.7 건조 톤의 농축물 생산 (22,917 온스의 은, 363.3 온스의 금). 회사는 두 달 동안 총 546.2 건조 톤의 농축물에 대해 17대의 트럭을 판매했습니다.

이 광산은 현재 11개의 스톱을 운영 중이며, 2023 NI 43-101 자원 추정치 외부에 있는 3개의 새로운 광맥 발견이 포함됩니다. 회사는 2024년 12월 31일까지 완전 상업적 지하 생산을 달성하는 것을 목표로 하고 있습니다.

Sierra Madre Gold and Silver a annoncé le début de sa production industrielle dans son usine de traitement de la mine Guitarra au Mexique. L'usine a fonctionné à 86 % de sa capacité de broyage (516 tonnes métriques humides par jour) pendant deux mois, dépassant le standard d'ingénierie de 80 % requis pour la déclaration de production industrielle.

Les faits saillants de la production incluent : octobre - 13 208 tonnes humides traitées, donnant 296,84 tonnes sèches de concentré (21 186 oz d'argent, 295,3 oz d'or) ; novembre - 13 064 tonnes humides traitées, donnant 317,7 tonnes sèches de concentré (22 917 oz d'argent, 363,3 oz d'or). L'entreprise a vendu 17 chargements de camions totalisant 546,2 tonnes sèches de concentré sur les deux mois.

La mine exploite actuellement 11 zones, y compris trois nouvelles découvertes de veines en dehors de l'estimation des ressources NI 43-101 de 2023. L'entreprise vise à atteindre une production souterraine commerciale complète d'ici le 31 décembre 2024.

Sierra Madre Gold and Silver hat den Beginn der industriellen Produktion in seiner Verarbeitungsanlage der Guitarra-Mine in Mexiko angekündigt. Die Anlage hat zwei Monate lang mit 86 % der Mahllkapazität (516 nassen metrischen Tonnen täglich) betrieben, was die erforderlichen 80 % des Ingenieurstandards für die Erklärung der industriellen Produktion übertrifft.

Die Produktionshöhepunkte beinhalten: Oktober - 13.208 nasse Tonnen verarbeitet, wobei 296,84 trockene Tonnen Konzentrat gewonnen wurden (21.186 Unzen Silber, 295,3 Unzen Gold); November - 13.064 nasse Tonnen verarbeitet, mit 317,7 trockenen Tonnen Konzentrat (22.917 Unzen Silber, 363,3 Unzen Gold). Das Unternehmen verkaufte in beiden Monaten insgesamt 17 Lkw-Ladungen mit insgesamt 546,2 trockenen Tonnen Konzentrat.

Die Mine betreibt derzeit 11 Stollen, einschließlich drei neuer Venenentdeckungen außerhalb der Ressourcenschätzung nach NI 43-101 von 2023. Das Unternehmen strebt an, bis zum 31. Dezember 2024 eine vollumfängliche kommerzielle Untertageproduktion zu erreichen.

Positive
  • Achieved industrial production over 6 months ahead of original guidance
  • Operating at 86% of milling capacity, exceeding 80% engineering standard
  • Successfully produced and sold 546.2 dry tonnes of concentrate in Oct-Nov
  • Discovered three new veins outside the 2023 resource estimation
  • 20 out of 27 working faces are in economically interesting vein material
Negative
  • None.

Vancouver, British Columbia--(Newsfile Corp. - December 10, 2024) - Sierra Madre Gold and Silver Ltd. (TSXV: SM) (OTCQX: SMDRF) ("Sierra Madre" or the "Company") is pleased to announce that industrial production has begun at the Guitarra mine processing plant in Estado de Mexico, Mexico. The plant has been operating at 86% of the milling circuit nameplate capacity, or 516 wet metric tonnes per day, for the last two (2) months, exceeding the engineering standard of 80% for 30 days necessary to declare industrial commercial production.

Production statistics for the last two months:

  • October: 13,208 wet tonnes of economically interesting vein material processed, producing 296.84 dry tonnes of concentrate, containing 21,186 ounces of silver and 295.3 ounces of gold.
  • November: 13,064 wet tonnes processed, producing 317.7 dry tonnes of concentrate, containing 22,917 ounces of silver and 363.3 ounces of gold.

Alexander Langer, Sierra Madre CEO and President states, "Since acquiring La Guitarra in the spring of 2023 the Company has been focused on executing its goal of restarting production. We are pleased to have reached industrial production at the processing plant, on budget and over 6 months before original guidance. Moving Sierra Madre from an exploration and development company to achieving processing plant industrial production at Guitarra, is a major milestone. I wish to thank everyone involved for their hard work and dedication."

In October and November combined, 17 truckloads, containing a total of 546.2 dry tonnes of concentrate were sold.

During November, the Guitarra mine had 11 stopes in production; three (3) of which are on new vein discoveries outside of the 2023 NI 43-101 resource estimation. Nine (9) production drives also produced economically interesting vein material for mill feed and seven (7) development drives in waste rock were also active. In all, the Company had 27 working faces, of which 20 were in economically interesting vein material. We continue to work towards our established underground mining targets and the achievement of full commercial production from the underground by December 31, 2024.

Sierra Madre also announces that, pursuant to its Stock Option Plan, it has granted stock options to 2 new employees of La Guitarra Compania Minera, S.A. DE C.V., to purchase an aggregate of 300,000 common shares of the Company at the price of $0.50 per share for a period of 5 years from the grant date. The options will vest 1/3 immediately as of the date of grant; 1/3 six months after the date of the grant; and 1/3 twelve months after the date of the grant. This stock option grant is subject to acceptance by the TSX Venture Exchange.

Qualified Person

Mr. Gregory Smith, P. Geo, Director of Sierra Madre, is a Qualified Person as defined by NI 43-101, and has reviewed and approved the technical data and information contained in this news release. Mr. Smith has verified the technical and scientific data disclosed herein.

About Sierra Madre

Sierra Madre Gold and Silver Ltd. (TSXV: SM) (OTCQX: SMDRF) is a precious metals development and exploration company focused on evaluating the potential of restarting the Guitarra mine in the Temascaltepec mining district, Mexico, and the exploration and development of its Tepic property in Nayarit, Mexico. The Guitarra mine is a permitted, past-producing underground mine, which includes a 500 t/d processing facility that operated until mid-2018.

The +2,600 ha Tepic Project hosts low-sulphidation epithermal gold and silver mineralization with an existing historic resource.

Sierra Madre's management team has played key roles in managing the exploration and development of more than 22Moz gold and 600Moz silver in combined mineral reserves and mineral resources. Sierra Madre's team of professionals has collectively raised over $1 billion for mining companies.

On behalf of the board of directors of Sierra Madre Gold and Silver Ltd.,

"Alexander Langer"
Alexander Langer
President, Chief Executive Officer and Director
1-604-765-1604

Contact:
investor@sierramadregoldandsilver.com

Cautionary Note Regarding Production Decisions

The Company's decision to place the mine into commercial production, expand a mine, make other production related decisions, or otherwise carry out mining and processing operations, is largely based on internal non-public Company data and reports from previous operations and the results of test mining and processing. The Company is not basing any production decisions on NI 43-101 compliant reserve estimates, preliminary economic assessments or feasibility studies and, as a result, there is greater risk and uncertainty as to future economic results from the Guitarra Mine Complex, including increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit, and a higher technical risk of failure than would be the case if a feasibility study were completed and relied upon to make a production.

Cautionary Note Regarding Forward-Looking Information

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

This press release contains "forward-looking information" and "forward-looking statements" within the meaning of applicable securities legislation. The forward-looking statements herein are made as of the date of this press release only, and the Company does not assume any obligation to update or revise them to reflect new information, estimates or opinions, future events or results or otherwise, except as required by applicable law. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budgets", "scheduled", "estimates", "forecasts", "predicts", "projects", "intends", "targets", "aims", "anticipates" or "believes" or variations (including negative variations) of such words and phrases or may be identified by statements to the effect that certain actions "may", "could", "should", "would", "might" or "will" be taken, occur or be achieved. Forward-looking statements include, without limitation, statements regarding discussions of future plans, including the expected timing of concentrate shipments; the Company increasing production; the Company receiving revenues on a weekly basis and such revenues allowing the Company to comfortably expand to commercial production without further capital needs; and the Company's plan to return the Guitarra mine to full commercial production and the expected timing and production levels thereof.

The forward-looking statements involve numerous risks and uncertainties, and actual results might differ materially from results suggested in any forward-looking statements. These risks and uncertainties include, among other things, that predicted production levels will be achieved and that existing production levels will be maintained.

In making the forward-looking statements in this news release, the Company has applied certain material assumptions, including without limitation, that the Company will be able to execute its future plans as intended, that predicted production levels will be achieved and that existing production levels will be maintained.

Although management of the Company has attempted identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements and forward-looking information. Readers are cautioned that reliance on such information may not be appropriate for other purposes.

SOURCE: Sierra Madre Gold and Silver Ltd.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/233152

FAQ

What is Sierra Madre's (SMDRF) current production capacity at the Guitarra mine?

The Guitarra mine processing plant is operating at 86% of milling circuit nameplate capacity, processing 516 wet metric tonnes per day.

How much silver and gold did Sierra Madre (SMDRF) produce in November 2023?

In November, Sierra Madre produced 22,917 ounces of silver and 363.3 ounces of gold from 13,064 wet tonnes of processed material.

When does Sierra Madre (SMDRF) expect to achieve full commercial production at Guitarra?

Sierra Madre aims to achieve full commercial production from the underground operations by December 31, 2024.

How many new vein discoveries has Sierra Madre (SMDRF) made at the Guitarra mine?

Sierra Madre has discovered three new veins outside of the 2023 NI 43-101 resource estimation.

SIERRA MADRE GOLD SILVER

OTC:SMDRF

SMDRF Rankings

SMDRF Latest News

SMDRF Stock Data

51.57M
66.19M
52.56%
4.36%
Other Precious Metals & Mining
Basic Materials
Link
United States of America
Vancouver