Soluna Holdings (NASDAQ: SLNH) has released its January 2025 operations update, highlighting progress across multiple projects. Project Dorothy 1A and 1B underwent a planned one-week outage for substation interconnection and network upgrades, now operating at full capacity. Project Dorothy 2 (48 MW) completed its substation interconnection, with initial energization expected in late February and Phase 1 commissioning in early April.

Project Sophie (25 MW) is operating at 65% capacity due to utility substation equipment failure, with repairs expected in March. Project Ada launched a new 128-GPU Atlas Cloud cluster on February 4th, with two new GPU contracts in final negotiations. The AI pipeline now exceeds 1,500 Nvidia H100 GPUs. Project Kati (166 MW) is finalizing design scope for its first 83 MW of Bitcoin Hosting, with supplier negotiations ongoing.

Soluna Holdings (NASDAQ: SLNH) ha rilasciato l'aggiornamento delle operazioni di gennaio 2025, evidenziando i progressi in diversi progetti. Progetto Dorothy 1A e 1B ha subito un'interruzione programmata di una settimana per l'interconnessione della sottostazione e gli aggiornamenti di rete, e ora opera a pieno regime. Progetto Dorothy 2 (48 MW) ha completato l'interconnessione della sottostazione, con la prima energizzazione prevista per la fine di febbraio e la messa in servizio della Fase 1 all'inizio di aprile.

Progetto Sophie (25 MW) funziona al 65% della capacità a causa di un guasto all'apparecchiatura della sottostazione, con riparazioni previste per marzo. Progetto Ada ha lanciato un nuovo cluster Atlas Cloud da 128 GPU il 4 febbraio, con due nuovi contratti GPU in fase di negoziazione finale. Il pipeline AI ora supera 1.500 GPU Nvidia H100. Progetto Kati (166 MW) sta finalizzando l’ambito di progettazione per i suoi primi 83 MW di hosting Bitcoin, con negoziazioni con i fornitori ancora in corso.

Soluna Holdings (NASDAQ: SLNH) ha publicado su actualización de operaciones de enero de 2025, destacando el progreso en múltiples proyectos. Proyecto Dorothy 1A y 1B experimentó una interrupción planificada de una semana para la interconexión de subestaciones y las mejoras de red, operando ahora a plena capacidad. Proyecto Dorothy 2 (48 MW) completó su interconexión de subestación, con la primera energización esperada para finales de febrero y la puesta en marcha de la Fase 1 a principios de abril.

Proyecto Sophie (25 MW) opera al 65% de su capacidad debido a la falla del equipo de subestación, con reparaciones esperadas en marzo. Proyecto Ada lanzó un nuevo clúster Atlas Cloud de 128 GPU el 4 de febrero, con dos nuevos contratos de GPU en negociación final. La línea de IA ahora supera las 1.500 GPU Nvidia H100. Proyecto Kati (166 MW) está finalizando el alcance de diseño para sus primeros 83 MW de alojamiento de Bitcoin, con negociaciones con proveedores en curso.

솔루나 홀딩스(NASDAQ: SLNH)가 2025년 1월 운영 업데이트를 발표했으며, 여러 프로젝트에서의 진행 상황을 강조했습니다. 프로젝트 도로시 1A 및 1B는 변전소 상호 연결 및 네트워크 업그레이드를 위해 계획된 1주일의 정전을 겪었고, 지금은 전량 가동하고 있습니다. 프로젝트 도로시 2 (48 MW)는 변전소 상호 연결을 완료하였으며, 초기 전력 공급은 2월 말에 예정되어 있고, 1단계 커미셔닝은 4월 초에 이루어질 것입니다.

프로젝트 소피 (25 MW)는 공공 변전소 장비 고장으로 인해 65%의 용량으로 운영되고 있으며, 3월에 수리가 예상됩니다. 프로젝트 아다는 2월 4일에 새로운 128-GPU 아틀라스 클라우드 클러스터를 출시했으며, 현재 두 개의 새로운 GPU 계약이 최종 협상 중입니다. AI 파이프라인은 현재 1,500개 이상의 Nvidia H100 GPU를 초과합니다. 프로젝트 카티 (166 MW)는 첫 83 MW의 비트코인 호스팅을 위한 설계 범위를 마무리하고 있으며, 공급업체 협상이 진행 중입니다.

Soluna Holdings (NASDAQ: SLNH) a publié sa mise à jour opérationnelle de janvier 2025, mettant en avant des progrès sur plusieurs projets. Projet Dorothy 1A et 1B a subi une interruption planifiée d'une semaine pour l'interconnexion des sous-stations et les améliorations du réseau, fonctionnant désormais à pleine capacité. Projet Dorothy 2 (48 MW) a achevé son interconnexion de sous-station, avec une première énergisation prévue pour fin février et la mise en service de la Phase 1 début avril.

Projet Sophie (25 MW) fonctionne à 65% de sa capacité en raison d'une défaillance de l'équipement de la sous-station, avec des réparations prévues en mars. Projet Ada a lancé un nouveau cluster Atlas Cloud de 128 GPU le 4 février, avec deux nouveaux contrats GPU en négociations finales. Le pipeline d'IA dépasse désormais 1 500 GPU Nvidia H100. Projet Kati (166 MW) finalise la portée de conception pour ses 83 MW initiaux d'hébergement Bitcoin, les négociations avec les fournisseurs étant en cours.

Soluna Holdings (NASDAQ: SLNH) hat das Betriebsupdate für Januar 2025 veröffentlicht und Fortschritte in mehreren Projekten hervorgehoben. Projekt Dorothy 1A und 1B hatten eine geplante einwöchige Unterbrechung für die Interkonnektion der Umspannstation und Netzwerk-Upgrades, und arbeiten jetzt mit voller Kapazität. Projekt Dorothy 2 (48 MW) hat die Interkonnektion der Umspannstation abgeschlossen, mit einer ersten Inbetriebnahme, die für Ende Februar und die Inbetriebnahme der Phase 1 Anfang April geplant ist.

Projekt Sophie (25 MW) arbeitet aufgrund eines Ausfalls von Umspannstationstechnik mit 65% seiner Kapazität, mit Reparaturen, die für März erwartet werden. Projekt Ada hat am 4. Februar einen neuen 128-GPU Atlas Cloud-Cluster gestartet, mit zwei neuen GPU-Verträgen in den letzten Verhandlungen. Die KI-Pipeline überschreitet nun 1.500 Nvidia H100 GPUs. Projekt Kati (166 MW) finalisiert den Entwurfsumfang für seine ersten 83 MW Bitcoin-Hosting, die Verhandlungen mit Lieferanten sind im Gange.

Positive
  • New 128-GPU Atlas Cloud cluster deployment
  • AI pipeline exceeding 1,500 Nvidia H100 GPUs
  • Dorothy 2 substation interconnection completed
  • Multiple customer expansions with Bit Digital and Bitmine Immersion Technologies
Negative
  • Project Sophie operating at 65% capacity due to equipment failure
  • One-week outage at Dorothy 1A and 1B facilities

Insights

This monthly update reveals several strategic developments that position Soluna for potential growth in both traditional cryptocurrency mining and emerging AI computing markets:

Infrastructure Expansion & Diversification

  • The successful substation interconnection at Dorothy 2 (48 MW) marks a significant milestone, with imminent energization potentially unlocking substantial hosting revenue streams by early April.
  • Project Ada's deployment of a new 128-GPU Atlas Cloud cluster, replacing a previous arrangement, demonstrates the company's agile pivot toward high-demand AI infrastructure. The pipeline exceeding 1,500 Nvidia H100 GPUs and increasing demand for H200s indicates strong market validation.
  • The effective S-1 registration for the SEPA agreement with Yorkville Advisors provides important financial flexibility for future growth initiatives.

Operational Resilience & Customer Expansion

  • Despite temporary setbacks at Project Sophie (operating at 65% capacity) and a planned outage at Dorothy 1A/1B, the company maintains strong customer relationships, evidenced by expansion requests from established clients like Bit Digital.
  • The deployment of next-generation S21 mining units at Project Dorothy signals continued investment in efficiency improvements.

Strategic Market Positioning

  • The development of Project Grace with multiple cooling technologies and Project Ada's AI focus represents a strategic diversification beyond traditional crypto mining, potentially reducing revenue volatility.
  • The extensive pipeline for H100 and H200 GPUs positions Soluna to capitalize on the growing demand for AI computing infrastructure, potentially leading to higher-margin revenue streams compared to traditional hosting services.

ALBANY, N.Y.--(BUSINESS WIRE)-- Soluna Holdings, Inc. (“SHI” or the “Company”), (NASDAQ: SLNH), a developer of green data centers for intensive computing applications including Bitcoin mining and AI, announced its January 2025 project site-level operations, developments, and updates.

The construction of Soluna's Project Dorothy 2 is underway.(Photo: Business Wire)

The construction of Soluna's Project Dorothy 2 is underway.(Photo: Business Wire)

The Company has provided the following Corporate and Site Updates.

Key Company Metrics:

The monthly metrics are now available here.

Corporate Highlights:

  • Upcoming Webinar - Water Tower Research will host CEO John Belizaire for a Fireside Chat on Monday, February 10th at 11:00 AM ET. They will discuss company updates, project milestones, and Soluna’s pipeline. Register here to watch.
  • New AMA - CFO John Tunsion recently answered shareholders’ frequently asked questions in another installment of our Ask Me Anything (AMA) series. Read it here.
  • New Podcast Episodes - CEO John Belizaire hosts interviews with Soluna’s team and industry experts in a new limited series focused on AI, sustainability, and Soluna Cloud. Listen to the latest episodes here.
  • S-1 Registration Statement for SEPA Effective - The registration statement filed in conjunction with our Yorkville Advisors Standby Equity Purchase Agreement (“SEPA”) went effective.

Key Project Updates:

Project Dorothy 1A (25 MW, Bitcoin Hosting) / Project Dorothy 1B (25 MW, Bitcoin Prop-Mining):

  • Dorothy 1A and 1B incurred a 1-week planned outage for the Dorothy 2 substation interconnection.
  • The planned outage was used to upgrade the core network switches which will increase network security and reliability.
  • Additionally, critical power infrastructure maintenance was performed.
  • Following the outage, both sites have returned to full operation and are benefiting from warmer temperatures in the region resulting in minimal curtailments.

Project Dorothy 2 (48 MW, Bitcoin Hosting):

  • The substation interconnection was successfully completed, potentially paving the way for the initial energization of the site.
  • Coordination is underway with key partners to finalize grid and wind farm telemetry data to complete the energization checklist for ERCOT operations.
  • We completed a hosting tender with Hyperscale miners who have an interest in contracting for hosting.
  • A late February initial energization date is expected. Phase 1 commissioning and deployments are expected to begin early April.
  • The latest photos of the construction progress can be found here.

Project Grace (2 MW at Dorothy 2, AI Cloud/Hosting):

  • Behind-the-meter (BTM) architecture is progressing well with three different cooling technologies identified that can meet BTM Requirements.

Project Ada (1 MW, AI Cloud with HPE):

  • A new 128-GPU Atlas Cloud cluster went live on February 4th replacing the previously announced deal.
  • 2 new contracts for GPUs are in the final stages of negotiation which, if entered into, would sell out the initial cluster with HPE.
  • The AI pipeline now exceeds 1,500 Nvidia H100 GPUs since the DeepSeek announcements. Inbound requests for H200s have also increased.

Project Sophie (25 MW, Bitcoin Hosting with Profit Share, AI Hosting):

  • The site is operating at 65% capacity due to an equipment failure within the utility substation during the recent cold snap last month.
  • Our hyperscale mining partners are satisfied with the rapid resolution of the outage.
  • The local utility has secured the parts that failed and is expected to complete the repair in March.

Project Kati (166 MW, Bitcoin Hosting and AI):

  • Negotiations are underway with suppliers on long-lead electrical infrastructure.
  • The design scope is being finalized for the first 83 MW of Bitcoin Hosting with an EPC bid process expected to be facilitated in late February.
  • We anticipate the next phase of the substation interconnection work will occur in April.

Customer Success:

  • We are in the process of deploying a 3rd expansion request with the customer Bit Digital.
  • Deploying the second batch of next-generation units (S21s) at Project Dorothy.
  • Completed deployment of 2nd expansion request with customer Bitmine Immersion Technologies.
  • Reviewing partner proposals for Dorothy 2 Bitcoin Hosting availability.

View Soluna’s recent AMA here.
View Soluna 2024 Earnings Power Presentation here.

Safe Harbor Statement

This announcement contains forward-looking statements. These statements are made under the "safe harbor" provisions of the U.S. Private Securities Litigation Reform Act of 1995. These forward-looking statements include all statements, other than statements of historical fact, regarding our current views and assumptions with respect to future events regarding our business and other statements that are predictive in nature. These forward-looking statements can be identified by terminology such as “will,” “expects,” “anticipates,” “future,” “intends,” “plans,” “believes,” “estimates,” “confident” and similar statements. Readers are cautioned that any forward-looking information provided by us or on our behalf is not a guarantee of future performance. Actual results may differ materially from those contained in these forward-looking statements as a result of various factors disclosed in our filings with the SEC, including the “Risk Factors” section of our Annual Report on Form 10-K filed with the SEC on April 1, 2024. All forward-looking statements speak only as of the date on which they are made, and we undertake no duty to update or revise any forward-looking statements, whether as a result of new information, future events, or otherwise, except to the extent required by law.

About Soluna Holdings, Inc (SLNH)

Soluna is on a mission to make renewable energy a global superpower using computing as a catalyst. The company designs, develops, and operates digital infrastructure that transforms surplus renewable energy into global computing resources. Soluna’s pioneering data centers are strategically co-located with wind, solar, or hydroelectric power plants to support high-performance computing applications including Bitcoin Mining, Generative AI, and other compute-intensive applications. Soluna’s proprietary software MaestroOS(™) helps energize a greener grid while delivering cost-effective and sustainable computing solutions, and superior returns. To learn more visit solunacomputing.com. Follow us on X (formerly Twitter) at @SolunaHoldings.

Sam Sova

Partner and CEO

SOVA

Sam@letsgosova.com

Source: Soluna Holdings, Inc.

FAQ

What caused Project Sophie's reduced capacity in January 2025 for SLNH?

Project Sophie is operating at 65% capacity due to an equipment failure within the utility substation during a cold snap, with repairs expected to be completed in March 2025.

When is Soluna's Project Dorothy 2 expected to begin operations?

Project Dorothy 2 is expected to have initial energization in late February 2025, with Phase 1 commissioning and deployments beginning in early April 2025.

How many Nvidia H100 GPUs are in Soluna's AI pipeline after the DeepSeek announcements?

Soluna's AI pipeline now exceeds 1,500 Nvidia H100 GPUs following the DeepSeek announcements.

What is the current status of SLNH's Project Kati development?

Project Kati (166 MW) is in negotiations with suppliers for electrical infrastructure and finalizing design scope for the first 83 MW of Bitcoin Hosting, with EPC bid process expected in late February.

What upgrades were completed during Dorothy 1A and 1B's planned outage?

During the planned outage, Soluna upgraded core network switches to increase network security and reliability, and performed critical power infrastructure maintenance.

SOLUNA HOLDINGS INC

NASDAQ:SLNH

SLNH Rankings

SLNH Latest News

SLNH Stock Data

15.38M
7.66M
27.24%
5.23%
2.86%
Capital Markets
Finance Services
Link
United States
ALBANY