Skeena Gold & Silver Draws US$45 Million of Funding Under Gold Stream Arrangement; Provides Progress Update on Eskay Creek
Skeena Resources (TSX/NYSE:SKE) has received US$45 million as the second tranche of its US$200 million gold stream arrangement for the Eskay Creek Gold-Silver Project. This funding follows receipt of Bulk Technical Sample permits in December 2024. Three remaining tranches of US$50 million each will be available until March 2026, subject to conditions.
The company maintains a buyback option to reduce the stream percentage by 66.67% within 12 months of project completion by repaying the deposit plus 18% IRR. During the 2024 season (June-November), early works activities included technical sample area clearing, pilot haul road development, infrastructure pad advancement, and civil earthworks for the Volcano Creek substation.
Engineering and procurement are progressing on budget with major mill equipment contracted, including structural steel, SAG/ball mills, flotation cells, and electrical components. The project remains on track for production in 2027.
Skeena Resources (TSX/NYSE:SKE) ha ricevuto 45 milioni di dollari come seconda tranche del suo accordo di streaming d'oro da 200 milioni di dollari per il progetto Eskay Creek Gold-Silver. Questo finanziamento segue il ricevimento dei permessi per campioni tecnici bulk a dicembre 2024. Tre tranche residue di 50 milioni di dollari ciascuna saranno disponibili fino a marzo 2026, soggette a condizioni.
L'azienda mantiene un'opzione di riacquisto per ridurre la percentuale di streaming del 66,67% entro 12 mesi dal completamento del progetto, rimborsando il deposito più un IRR del 18%. Durante la stagione 2024 (giugno-novembre), le attività preliminari hanno incluso la bonifica dell'area dei campioni tecnici, lo sviluppo della strada di trasporto pilota, il progresso della piattaforma infrastrutturale e i lavori civili per la sottostazione di Volcano Creek.
Ingegneria e approvvigionamento stanno procedendo secondo il budget con attrezzature principali per il mulino già contrattate, inclusi acciaio strutturale, mulini SAG/a sfere, celle di flottazione e componenti elettrici. Il progetto rimane in carreggiata per la produzione nel 2027.
Skeena Resources (TSX/NYSE:SKE) ha recibido 45 millones de dólares como la segunda tranche de su acuerdo de streaming de oro de 200 millones de dólares para el proyecto Eskay Creek Gold-Silver. Este financiamiento sigue a la obtención de los permisos para muestras técnicas bulk en diciembre de 2024. Tres tranches restantes de 50 millones de dólares cada una estarán disponibles hasta marzo de 2026, sujeto a condiciones.
La compañía mantiene una opción de recompra para reducir el porcentaje de streaming en un 66,67% dentro de los 12 meses posteriores a la finalización del proyecto, reembolsando el depósito más un IRR del 18%. Durante la temporada 2024 (junio-noviembre), las actividades preliminares incluyeron la limpieza del área de muestras técnicas, el desarrollo de la carretera de transporte piloto, el avance de la plataforma de infraestructura y los trabajos civiles para la subestación de Volcano Creek.
La ingeniería y la adquisición están progresando dentro del presupuesto con el equipo principal del molino contratado, incluidos acero estructural, molinos SAG/balas, celdas de flotación y componentes eléctricos. El proyecto sigue en camino para la producción en 2027.
스키나 리소스 (TSX/NYSE:SKE)는 에스카이 크릭 금-은 프로젝트를 위한 2억 달러 금 거래 계약의 두 번째 분할금으로 4,500만 달러를 받았습니다. 이 자금은 2024년 12월 대량 기술 샘플 허가를 받은 후에 확보된 것입니다. 5천만 달러의 남은 세 분할금은 2026년 3월까지 조건에 따라 이용 가능합니다.
회사는 프로젝트 완료 후 12개월 이내에 보증금을 재상환하고 18%의 내부수익률(IRR)을 더함으로써 스트림 비율을 66.67% 줄일 수 있는 매입 옵션을 유지합니다. 2024 시즌(6월-11월) 동안 조기 작업 활동에는 기술 샘플 지역 정리, 파일럿 운송 도로 개발, 인프라 패드 진행 및 화산 크릭 변전소를 위한 토목 작업이 포함되었습니다.
엔지니어링과 조달은 예산에 맞춰 진행 중이며, 계약된 주요 밀 장비에는 구조 강철, SAG/볼 밀, 부유 셀 및 전기 구성 요소가 포함됩니다. 프로젝트는 2027년 생산 목표에 맞춰 순항하고 있습니다.
Skeena Resources (TSX/NYSE:SKE) a reçu 45 millions USD comme deuxième tranche de son accord de flux d'or de 200 millions USD pour le projet Eskay Creek Gold-Silver. Ce financement fait suite à l'obtention des permis d'échantillons techniques en vrac en décembre 2024. Trois tranches restantes de 50 millions USD chacune seront disponibles jusqu'en mars 2026, sous réserve de conditions.
L'entreprise maintient une option de rachat afin de réduire le pourcentage de flux de 66,67 % dans les 12 mois suivant l'achèvement du projet en remboursant le dépôt plus un retour sur investissement interne (IRR) de 18 %. Au cours de la saison 2024 (juin-novembre), les activités précoces comprenaient le déblaiement de la zone d'échantillonnage technique, le développement de la route de transport pilote, l'avancement de la plateforme d'infrastructure et les travaux de génie civil pour le poste de transformation de Volcano Creek.
L'ingénierie et l'approvisionnement avancent dans le respect du budget, avec des équipements majeurs de moulin contractés, y compris de l'acier de structure, des moulins SAG/billes, des cellules de flottation et des composants électriques. Le projet reste sur la bonne voie pour une production en 2027.
Skeena Resources (TSX/NYSE:SKE) hat 45 Millionen US-Dollar als zweite Tranche seiner 200 Millionen US-Dollar Goldstream-Vereinbarung für das Eskay Creek Gold-Silber-Projekt erhalten. Diese Finanzierung folgt auf den Erhalt der Genehmigungen für Bulk-Technische Proben im Dezember 2024. Drei verbleibende Tranchen von jeweils 50 Millionen US-Dollar werden bis März 2026 verfügbar sein, vorbehaltlich von Bedingungen.
Das Unternehmen hat eine Rückkaufoption beibehalten, um den Streaming-Prozentsatz innerhalb von 12 Monaten nach Projektabschluss um 66,67 % zu reduzieren, indem der Vorschuss plus 18 % IRR zurückgezahlt wird. In der Saison 2024 (Juni-November) umfassten frühe Arbeitsaktivitäten die Räumung des technischen Probenbereichs, die Entwicklung der Pilottransportroute, den Fortschritt der Infrastrukturplattform und Erdarbeiten für die Umspannstation Volcano Creek.
Die Ingenieur- und Beschaffungsmaßnahmen liegen im Budget, und die wichtigsten Mühlenkomponenten sind bereits vertraglich gebunden, darunter Strukturstahl, SAG/Kugelmühlen, Flotationseinheiten und elektrische Komponenten. Das Projekt ist weiterhin auf Kurs für die Produktion im Jahr 2027.
- Secured US$45 million in funding with additional US$150 million available through 2026
- Obtained key permits for early works activities
- Major mill equipment and long lead-time items successfully contracted
- Project remains on schedule for 2027 production target
- Maintains flexibility with 66.67% stream buyback option
- Significant future capital requirements with three US$50 million tranches pending
- Stream arrangement includes 18% IRR cost for buyback option
Insights
The
The procurement progress of major mill equipment and securing of long-lead items significantly de-risks the project's execution timeline. The company's ability to meet the conditions for the stream funding indicates strong project advancement and regulatory compliance. With
The early works progress in 2024 demonstrates efficient operational execution, particularly in site preparation and infrastructure development. Key accomplishments include:
- Technical sample area preparation enabling scaled-up equipment deployment in 2025
- Strategic advancement of two pilot haul roads
- Infrastructure pad development using in-house capabilities
- Initiation of Volcano Creek substation works for hydroelectric power integration
VANCOUVER, BC / ACCESSWIRE / January 6, 2025 / Skeena Resources Limited (TSX:SKE)(NYSE:SKE) ("Skeena Gold & Silver", "Skeena" or the "Company") collected US
Randy Reichert, President & Chief Executive Officer of Skeena, commented: "The current tranche of the gold stream financing will enable Skeena to continue advancing the Project, with further drawdowns anticipated throughout 2025. We are encouraged by the supportive and constructive dialogue with the Province of British Columbia, which has helped facilitate early works activities in 2024. As a result, we are progressing with our pre-development plans and proactively de-risking the Project to stay on track for production in 2027."
US
Skeena Gold & Silver has collected the second tranche of US
Skeena is entitled to a buyback provision to reduce the stream percentage by
2024 Early Works Review
In June 2024, Skeena Gold & Silver received approval for an amendment to the Mines Act permit M-197 from the Province of British Columbia, which allowed for early works activities at Eskay Creek. The approval of this permit was the first step required to facilitate the commencement of a Technical Sample Quarry and land clearing work to begin.
During the 2024 season from June to November, activities included:
Access to the technical sample area and clearing of the area was completed in the summer using smaller equipment. This preparation will enable the use of larger, more efficient equipment in the summer of 2025, to facilitate further advancements in the development of the technical sample quarry. Two Pilot haul roads were advanced: one connecting to the Tom Mackay Tailings Storage Facility and the other providing access to the infrastructure pad area.
Advancement of the infrastructure pad area, with bulk earthworks efficiently self-performed by the skilled project development team on-site.
Commencement of civil earthworks for the Volcano Creek substation (237kV tie-in) to interconnect with Coast Mountain Hydro to supply future hydro-sourced electricity to the project.
Concurrent with project activities onsite, engineering and procurement is progressing well and on budget with the estimates outlined in the 2023 Definitive Feasibility Study. Most of the major mill equipment has been contracted including the building structural steel and installation, SAG/ball mills, tertiary/regrind mills, jaw crusher, flotation cells, concentrate thickener, concentrate dryer, and transformers and the circuit breakers. Long lead-time items such as electrical components have also been secured. Other critical contracts continue to advance including the selection of a mobile mining fleet supplier.
About Skeena
Skeena is a leading precious metals developer that is focused on advancing the Eskay Creek Gold-Silver Project - a past producing mine located in the renowned Golden Triangle in British Columbia, Canada. Eskay Creek will be one of the highest-grade and lowest cost open-pit precious metals mines in the world, with substantial silver by-product production that surpasses many primary silver mines. Skeena is committed to sustainable mining practices and maximizing the potential of its mineral resources. In partnership with the Tahltan Nation, Skeena strives to foster positive relationships with Indigenous communities while delivering long-term value and sustainable growth for its stakeholders.
On behalf of the Board of Directors of Skeena Gold & Silver,
Walter Coles | Randy Reichert |
Contact Information
Investor Inquiries: info@skeenaresources.com
Office Phone: +1 604 684 8725
Company Website: www.skeenagoldsilver.com
Qualified Persons
In accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects, Paul Geddes, P.Geo., Senior Vice President, Exploration & Resource Development, is the Qualified Person for the Company and has prepared, validated, and approved the technical and scientific statements and information contained or incorporated by reference in the news release. The Company strictly adheres to CIM Best Practices Guidelines in conducting, documenting, and reporting the exploration activities on its projects.
Cautionary note regarding forward-looking statements
Certain statements and information contained or incorporated by reference in this news release constitute "forward-looking information" and "forward-looking statements" within the meaning of applicable Canadian and United States securities legislation (collectively, "forward-looking statements"). These statements relate to future events or our future performance. The use of words such as "anticipates", "believes", "proposes", "contemplates", "generates", "targets", "is projected", "is planned", "considers", "estimates", "expects", "is expected", "potential" and similar expressions, or statements that certain actions, events or results "may", "might", "will", "could", or "would" be taken, achieved, or occur, may identify forward-looking statements. All statements other than statements of historical fact are forward-looking statements. Specific forward-looking statements contained herein include, but are not limited to, statements regarding the progress of development at Eskay, including the construction budget, schedule and required funding in respect thereof; the timing for and the Company's progress towards commencement of commercial production; the Company's capital structure; the Company's ability to buy back the gold stream in the future; amounts drawn and the timing of and completion of conditions precedent in respect of the Senior Secured Loan, gold stream agreement, additional equity investment and the cost over-run facility, the availability of the Senior Secured Loan as a source of future liquidity; and the results of the Definitive Feasibility Study, processing capacity of the mine, anticipated mine life, probable reserves, estimated project capital and operating costs, sustaining costs, results of test work and studies, planned environmental assessments, the future price of metals, metal concentrate, and future exploration and development. Such forward-looking statements are based on material factors and/or assumptions which include, but are not limited to, the estimation of mineral resources and reserves, the realization of resource and reserve estimates, metal prices, taxation, the estimation, timing and amount of future exploration and development, capital and operating costs, the availability of financing, the receipt of regulatory approvals, environmental risks, title disputes and the assumptions set forth herein and in the Company's MD&A for the year ended December 31, 2023, its most recently filed interim MD&A, and the Company's Annual Information Form ("AIF") dated March 28, 2024. Such forward-looking statements represent the Company's management expectations, estimates and projections regarding future events or circumstances on the date the statements are made, and are necessarily based on several estimates and assumptions that, while considered reasonable by the Company as of the date hereof, are not guarantees of future performance. Actual events and results may differ materially from those described herein, and are subject to significant operational, business, economic, and regulatory risks and uncertainties. The risks and uncertainties that may affect the forward-looking statements in this news release include, among others: the inherent risks involved in exploration and development of mineral properties, including permitting and other government approvals; changes in economic conditions, including changes in the price of gold and other key variables; changes in mine plans and other factors, including accidents, equipment breakdown, bad weather and other project execution delays, many of which are beyond the control of the Company; environmental risks and unanticipated reclamation expenses; and other risk factors identified in the Company's MD&A for the year ended December 31, 2023, its most recently filed interim MD&A, the AIF dated March 28, 2024, the Company's short form base shelf prospectus dated January 31, 2023, and in the Company's other periodic filings with securities and regulatory authorities in Canada and the United States that are available on SEDAR+ at www.sedarplus.ca or on EDGAR at www.sec.gov.
Readers should not place undue reliance on such forward-looking statements. Any forward-looking statement speaks only as of the date on which it is made and the Company does not undertake any obligations to update and/or revise any forward-looking statements except as required by applicable securities laws.
SOURCE: Skeena Resources Limited
View the original press release on accesswire.com
FAQ
How much funding did Skeena Resources (SKE) receive in its latest gold stream tranche?
When is Skeena's Eskay Creek project expected to begin production?
What are the terms of SKE's gold stream buyback option?
How much additional funding is available to Skeena (SKE) through the gold stream arrangement?