Binary Unit Commences Operations

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags
Rhea-AI Summary

Polaris Renewable Energy has successfully completed the construction and testing of a 10.4 MW geothermal power plant at the San Jacinto Geothermal Project in Nicaragua. Initial operations began on December 30, 2022, with full capacity achieved by December 31. Technical commercial operation is expected to be declared by local authorities this month. The company anticipates revenue from electricity delivered during the commissioning phase at a rate of $111.20 per MWh following a renegotiated power purchase agreement. This milestone reflects significant progress in Polaris’ project development efforts.

Positive
  • Successful completion of 10.4 MW geothermal plant at San Jacinto.
  • Initial operations commenced on December 30, 2022.
  • Full capacity achieved on December 31, 2022.
  • Revenue during commissioning phase at $111.20 per MWh.
Negative
  • None.

TORONTO, ON / ACCESSWIRE / January 3, 2023 / Polaris Renewable Energy Inc. (TSX:PIF) ("Polaris" or the "Company"), a Toronto-based company engaged in the operation, acquisition and development of renewable energy projects in Latin America, is pleased to announce that it has completed construction, testing and initial operation of a 10.4 MW (net) geothermal binary power plant (Organic Rankine Cycle) at the San Jacinto Geothermal Project in Telica, Leon, Republicof Nicaragua.

Initial start-up, tests and deliveries of energy commenced on December 30th, 2022. Full capacity was achieved on December 31st, 2022. Certain standard commissioning tests will continue to be performed over the course of the next two weeks with technical Commercial Operation expected to be declared by local authorities within the month. However, as anticipated, any deliveries of electricity during the commissioning phase will be paid at the rate in the current Power Purchase Agreement ("PPA") of $111.20 / Mwhr.

Marc Murnaghan, Polaris' CEO commented "The completion of the Binary unit within the anticipated timeframe is a very important milestone for the Company. The addition of a Binary unit to the San Jacinto project has always been contemplated since the commencement of the project more than a decade ago. It represents the culmination of efforts to renegotiate the PPA in 2020, execute a refinancing in 2021/22 and, most importantly, execute the project construction with our own staff in Nicaragua. To do this in what continues to be a challenging environment is noteworthy. We are confident that it will add significant value to the project for many years to come."

About Polaris Renewable Energy Inc.

Polaris Renewable Energy Inc. (formerly, Polaris Infrastructure Inc.) is a Canadian publicly traded company engaged in the acquisition, development, and operation of renewable energy projects in the Americas. We are a high-performing and financially sound contributor in the energy transition.

The Company's operations are in 5 Latin American countries and include a geothermal plant (~72 MW), 4 run-of-river hydroelectric plants (~33 MW), 1 solar (photovoltaic) project in operation (25 MW) and 2 solar projects with an expected total capacity of approximately 10 MW, currently under construction.

For more information, contact:

Investor Relations
Polaris Renewable Energy Inc.
Phone: +1 647-245-7199
Email: info@PolarisREI.com

SOURCE: Polaris Renewable Energy Inc.



View source version on accesswire.com:
https://www.accesswire.com/733771/Binary-Unit-Commences-Operations

FAQ

What recent milestone did Polaris Renewable Energy achieve?

Polaris Renewable Energy completed the construction and initial operation of a 10.4 MW geothermal power plant at the San Jacinto project.

When did the geothermal plant at San Jacinto begin operations?

Initial operations began on December 30, 2022.

What is the expected revenue rate during the commissioning phase of the San Jacinto project?

The expected revenue rate during the commissioning phase is $111.20 per MWh.

What capacity was achieved by the geothermal power plant on December 31, 2022?

The geothermal power plant achieved its full capacity of 10.4 MW on December 31, 2022.

POLARIS RENEWABLE ENERGY

OTC:RAMPF

RAMPF Rankings

RAMPF Latest News

RAMPF Stock Data

187.58M
20.41M
2.99%
21.58%
Utilities - Renewable
Utilities
Link
United States of America
Toronto