Oregon Set to Commence Writing Draft Permits for Paramount’s High Grade Grassy Mountain Gold Mine

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Paramount Gold Nevada Corp. (NYSE American: PZG) has announced a significant milestone in the permitting process for its Grassy Mountain gold mine project in Oregon. The Environmental Evaluation and Socioeconomic Analysis (EE) documents are now available for public review before the Project Coordinating Committee meeting on September 12, 2024. Final approval of the EE is expected in early October, allowing state agencies to begin drafting permits, which Paramount anticipates receiving in mid-2025.

The EE, completed by Stantec under DOGAMI's direction, confirms that the project is designed to surpass all viable alternatives and is expected to have positive economic impacts on local, state, and federal budgets. The analysis predicts minimal environmental impacts and minor, beneficial effects on environmental justice communities. Paramount expects to receive both Federal and State permits in late 2025, paving the way for construction to begin shortly after.

Paramount Gold Nevada Corp. (NYSE American: PZG) ha annunciato un traguardo significativo nel processo di autorizzazione per il suo progetto minerario d'oro di Grassy Mountain in Oregon. I documenti di Valutazione Ambientale e Analisi Socioeconomica (EE) sono ora disponibili per la revisione pubblica prima della riunione del Comitato di Coordinamento del Progetto, prevista per il 12 settembre 2024. L'approvazione finale dell'EE è attesa per inizio ottobre, permettendo alle agenzie statali di iniziare a redigere i permessi, che Paramount prevede di ricevere a metà del 2025.

L'EE, completata da Stantec sotto la direzione di DOGAMI, conferma che il progetto è progettato per superare tutte le alternative valide e si prevede avrà impatto economico positivo sui bilanci locali, statali e federali. L'analisi prevede impatti ambientali minimi e effetti minori ma benefici sulle comunità di giustizia ambientale. Paramount prevede di ricevere i permessi federali e statali a fine 2025, aprendo la strada all'inizio della costruzione subito dopo.

Paramount Gold Nevada Corp. (NYSE American: PZG) ha anunciado un hito significativo en el proceso de permisos para su proyecto de mina de oro en Grassy Mountain en Oregón. Los documentos de Evaluación Ambiental y Análisis Socioeconómico (EE) están ahora disponibles para revisión pública antes de la reunión del Comité Coordinador del Proyecto el 12 de septiembre de 2024. Se espera que la aprobación final de la EE se produzca a principios de octubre, lo que permitirá a las agencias estatales comenzar a redactar los permisos, que Paramount anticipa recibir a mediados de 2025.

La EE, completada por Stantec bajo la dirección de DOGAMI, confirma que el proyecto está diseñado para superar todas las alternativas viables y se espera que tenga impactos económicos positivos en los presupuestos locales, estatales y federales. El análisis prevé impactos ambientales mínimos y efectos menores pero beneficiosos en las comunidades de justicia ambiental. Paramount espera recibir tanto los permisos federales como estatales a finales de 2025, allanando el camino para que la construcción comience poco después.

파라마운트 골드 네바다 코퍼레이션(뉴욕 증권거래소: PZG)은 오리건의 그래시 마운틴 금광 프로젝트에 대한 허가 절차에서 중요한 이정표를 발표했습니다. 환경 평가 및 사회경제적 분석(EE) 문서가 2024년 9월 12일 프로젝트 조정 위원회 회의 전에 공개 검토를 위해 제공됩니다. EE의 최종 승인은 10월 초에 예상되며, 이를 통해 주 기관들은 허가서를 작성하기 시작할 수 있으며, 파라마운트는 2025년 중반에 이를 받을 것으로 기대하고 있습니다.

DOGAMI의 지시에 따라 Stantec에서 완료한 EE는 프로젝트가 모든 실행 가능한 대안을 초과하도록 설계되었으며, 긍정적인 경제적 영향을 지역, 주 및 연방 예산에 미칠 것으로 예상된다고 확인합니다. 분석 결과 환경적 영향이 최소화되며 환경 정의 공동체에 대한 미미하지만 유익한 효과가 있을 것으로 예상됩니다. 파라마운트는 2025년 말에 연방 및 주 허가를 받을 것으로 기대하며, 이를 통해 건설이 곧 시작될 수 있습니다.

Paramount Gold Nevada Corp. (NYSE American: PZG) a annoncé une étape importante dans le processus d'autorisation de son projet de mine d'or de Grassy Mountain dans l'Oregon. Les documents d'Évaluation Environnementale et d'Analyse Socioéconomique (EE) sont désormais disponibles pour examen public avant la réunion du Comité de Coordination du Projet le 12 septembre 2024. L'approbation finale de l'EE est attendue début octobre, permettant aux agences d'État de commencer à rédiger les permis, que Paramount prévoit de recevoir à la mi-2025.

L'EE, réalisée par Stantec sous la direction de DOGAMI, confirme que le projet est conçu pour surpasser toutes les alternatives viables et devrait avoir des impacts économiques positifs sur les budgets locaux, étatiques et fédéraux. L'analyse prédit des impacts environnementaux minimes et des effets mineurs mais bénéfiques sur les communautés de justice environnementale. Paramount s'attend à recevoir les permis fédéraux et étatiques fin 2025, ouvrant la voie à un début de construction peu après.

Paramount Gold Nevada Corp. (NYSE American: PZG) hat einen bedeutenden Meilenstein im Genehmigungsprozess für sein Goldminenprojekt Grassy Mountain in Oregon angekündigt. Die Dokumente zur Umweltbewertung und zur sozioökonomischen Analyse (EE) stehen jetzt zur öffentlichen Einsichtnahme vor der Sitzung des Projektkoordinationsteams am 12. September 2024 zur Verfügung. Die endgültige Genehmigung der EE wird Anfang Oktober erwartet, was den staatlichen Behörden ermöglicht, mit der Erstellung der Genehmigungen zu beginnen, die Paramount voraussichtlich Mitte 2025 erhalten wird.

Die EE, die von Stantec unter der Leitung von DOGAMI abgeschlossen wurde, bestätigt, dass das Projekt darauf ausgelegt ist, alle möglichen Alternativen zu übertreffen und voraussichtlich positive wirtschaftliche Auswirkungen auf lokale, staatliche und bundesstaatliche Haushalte haben wird. Die Analyse sagt minimale Umweltauswirkungen und geringfügige, aber positive Effekte auf Umweltgerechtigkeitsgemeinschaften voraus. Paramount erwartet, sowohl Bundes- als auch Landesgenehmigungen Ende 2025 zu erhalten, was den Weg für einen baldigen Baubeginn ebnen wird.

Positive
  • EE documents for Grassy Mountain project available for public review, indicating progress in the permitting process
  • Draft permits expected to be received in mid-2025
  • Project designed to surpass all viable alternatives according to EE analysis
  • Positive revenue impact predicted for local, state, and federal budgets
  • Minimal environmental impacts and beneficial effects on environmental justice communities anticipated
  • Federal and State permits expected in late 2025, allowing construction to commence shortly after
Negative
  • None.

Insights

The progress in Oregon's permitting process for Paramount's Grassy Mountain gold mine is a significant milestone. The Environmental Evaluation and Socioeconomic Analysis (EE) availability for public review signals advancement towards final approval. This step is important as it paves the way for drafting permits, expected by mid-2025.

The EE's positive findings, particularly regarding minimal environmental impact and net benefits to the local community, are encouraging for the project's viability. The anticipated positive revenue impact on local, state and federal budgets, coupled with minor impacts on public services, suggests a favorable economic outlook.

However, investors should note that the timeline for receiving both Federal and State permits by late 2025 is still subject to potential delays. The mining sector's sensitivity to regulatory processes means that any unforeseen issues during the public review or subsequent stages could affect the project's timeline and, consequently, Paramount's stock performance.

The Environmental Evaluation for Paramount's Grassy Mountain project represents a critical juncture in the permitting process. Oregon's stringent environmental standards, requiring the use of "best available, practicable and necessary technologies," set a high bar for project approval. The EE's conclusion that the project is designed to surpass all viable alternatives is a strong endorsement of Paramount's environmental commitment.

However, the public review period and upcoming Project Coordinating Committee meeting could still unveil concerns or opposition. The project's anticipated minor and beneficial impacts on environmental justice communities is particularly noteworthy, as this aspect often faces scrutiny in mining projects. Investors should monitor the public response closely, as it could influence the final approval process and potentially impact Paramount's timeline and costs.

The Grassy Mountain gold mine project presents a compelling economic opportunity for Malheur County and Eastern Oregon. The EE's findings of positive revenue impacts on local government budgets throughout the project's lifetime, coupled with beneficial effects on state and federal budgets, indicate strong fiscal potential. This could translate into improved public services and infrastructure in the region.

The project's minimal anticipated impact on public services suggests that the local infrastructure can accommodate the development without significant strain. However, investors should consider the long-term economic sustainability beyond the mine's operational life. While the immediate economic boost is clear, the report doesn't address post-mining economic plans, which could be important for the region's long-term prosperity and potentially affect Paramount's social license to operate.

WINNEMUCCA, Nev., Aug. 27, 2024 (GLOBE NEWSWIRE) -- Paramount Gold Nevada Corp. (NYSE American: PZG) (“Paramount” or the “Company”) is pleased to announce that the Environmental Evaluation and Socioeconomic Analysis (collectively, “EE” or “EE documents”) for the Grassy Mountain project have been made available for public review prior to the upcoming Project Coordinating Committee (“PCC”) meeting scheduled to be held on September 12, 2024.

Following the PCC meeting, final approval of the EE is expected at a state Technical Review Team meeting anticipated to be held in early October.

Based on Oregon permitting regulations, the EE ensures the use of the best available, practicable, and necessary technologies to minimize environmental impacts.

Paramount’s President, COO and Director, Mr. Glen Van Treek stated, “This is a critical milestone in the State permitting process that allows the lead agencies to start writing draft permits which we expect to receive in mid-2025. Further, the analysis has confirmed that the Grassy Mountain project is designed to surpass all viable alternatives.”

The EE documents were completed by Stantec, a global leader in engineering, architecture, mining and environmental consulting under the direction of DOGAMI with input from state permitting agencies.

Paramount CEO and Director, Ms. Rachel Goldman stated, “Paramount’s objective has been to develop Grassy Mountain as a net benefit to Malheur County, Eastern Oregon and all our stakeholders. The following summary reaffirms that we are on track to achieve that goal.”

” Revenues from the Project would be positive to the local government budgets over the lifetime of the Project. The proposed Project would also have positive tax impacts to the state and federal budgets. No significant impacts are anticipated on public safety, healthcare, education, and parks and recreation availability for Malheur County due to the proposed Project. Likewise, no significant impacts are anticipated on water, wastewater, solid waste, and power needs due to the proposed Project. Impacts to environmental justice communities (i.e., minority, low-income, tribal, and traditionally underrepresented communities) are anticipated to be minor and beneficial.1

Paramount expects to receive both Federal and State permits in late 2025 which will allow construction to commence shortly thereafter.

About Paramount Gold Nevada Corp.
Paramount Gold Nevada Corp. is a U.S. based precious metals exploration and development company. Paramount’s strategy is to create shareholder value through exploring and developing its mineral properties and to realize this value for its shareholders in three ways: by selling its assets to established producers; entering joint ventures with producers for construction and operation; or constructing and operating mines for its own account.

Paramount holds a 100% interest in three projects: Grassy Mountain; Sleeper and Bald Peak.

The Grassy Mountain Gold Project ("Grassy") consists of approximately 8,200 acres located on private and BLM land in Malheur County, Oregon. Grassy contains a gold-silver deposit (100% located on private land) for which results of a positive Feasibility Study have been released and key permitting milestones accomplished.

The Sleeper Gold Project is in Northern Nevada, the world’s premier mining jurisdiction. The Sleeper Gold Project, which includes the former producing Sleeper mine, totals 2,474 unpatented mining claims (approximately 44,917 acres).

The drill ready, Bald Peak Project in Nevada, consists of approximately 2,260 acres.

Safe Harbor for Forward-Looking Statements

This release and related documents may include "forward-looking statements" and “forward-looking information” (collectively, “forward-looking statements”) pursuant to applicable United States and Canadian securities laws. Paramount’s future expectations, beliefs, goals, plans or prospects constitute forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and other applicable securities laws. Words such as "believes," "plans," "anticipates," "expects," "estimates" and similar expressions are intended to identify forward-looking statements, although these words may not be present in all forward-looking statements. Forward-looking statements included in this news release include, without limitation, statements with respect to the use of proceeds from the Offerings. Forward-looking statements are based on the reasonable assumptions, estimates, analyses and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, but which may prove to be incorrect. Management believes that the assumptions and expectations reflected in such forward-looking statements are reasonable. Assumptions have been made regarding, among other things: the conclusions made in the feasibility study for the Grassy Mountain Gold Project (the “FS”); the quantity and grade of resources included in resource estimates; the accuracy and achievability of projections included in the FS; Paramount’s ability to carry on exploration and development activities, including construction; the timely receipt of required approvals and permits; the price of silver, gold and other metals; prices for key mining supplies, including labor costs and consumables, remaining consistent with current expectations; work meeting expectations and being consistent with estimates and plant, equipment and processes operating as anticipated. There are a number of important factors that could cause actual results or events to differ materially from those indicated by such forward-looking statements, including, but not limited to: uncertainties involving interpretation of drilling results; environmental matters; the ability to obtain required permitting; equipment breakdown or disruptions; additional financing requirements; the completion of a definitive feasibility study for the Grassy Mountain Gold Project; discrepancies between actual and estimated mineral reserves and mineral resources, between actual and estimated development and operating costs and between estimated and actual production; the global epidemics, pandemics, or other public health crises, including the novel coronavirus (COVID-19) global health pandemic, and the spread of other viruses or pathogens and the other factors described in Paramount’s disclosures as filed with the SEC and the Ontario, British Columbia and Alberta Securities Commissions.

Except as required by applicable law, Paramount disclaims any intention or obligation to update any forward-looking statements as a result of developments occurring after the date of this document.

Paramount Gold Nevada Corp.
Rachel Goldman, CEO and Director

Christos Theodossiou, Director of Corporate Communications
844.488.2233

Twitter: @ParamountNV

1Socioeconomics and Environmental Justice Report completed by Stantec – p7 (Executive Summary)


FAQ

When is the Project Coordinating Committee meeting for Paramount's Grassy Mountain project (PZG)?

The Project Coordinating Committee meeting for Paramount's Grassy Mountain project is scheduled for September 12, 2024.

What is the expected timeline for Paramount (PZG) to receive draft permits for the Grassy Mountain gold mine?

Paramount expects to receive draft permits for the Grassy Mountain gold mine in mid-2025.

When does Paramount Gold Nevada Corp. (PZG) anticipate receiving final Federal and State permits for Grassy Mountain?

Paramount Gold Nevada Corp. expects to receive both Federal and State permits for the Grassy Mountain project in late 2025.

What are the key findings of the Environmental Evaluation for Paramount's Grassy Mountain project (PZG)?

The Environmental Evaluation found that the Grassy Mountain project is designed to surpass all viable alternatives, with positive economic impacts and minimal environmental effects.

Paramount Gold Nevada Corp.

NYSE:PZG

PZG Rankings

PZG Latest News

PZG Stock Data

21.15M
44.69M
20.8%
9.41%
0.4%
Gold
Metal Mining
Link
United States of America
WINNEMUCCA