Trigon Metals Commissions Replacement Dewatering Pump Ahead of Schedule: Water Level to Return to 327 Metres Within Weeks at Kombat Mine, Namibia
Trigon Metals Inc. (TSX-V: TM; OTCQB: PNTZF) has successfully replaced the failed dewatering pump at its Kombat mine in Namibia. The new pump body was installed on July 26, 2024, and began pumping water on July 27, 2024. As of July 29, the mine has been dewatered 25 meters from the shaft collar, down from 227 meters on July 18. The pump is currently dewatering at 2860 cubic meters per hour.
The company has implemented modifications to prevent future pump failures. Mining and processing have continued normally from underground operations above 120 meters. Trigon remains focused on production from the Asis West underground complex and maintains its previous guidance. The company also announced that Aidan Sullivan, VP of Investor Relations, will be stepping down effective August 1, 2024.
Trigon Metals Inc. (TSX-V: TM; OTCQB: PNTZF) ha sostituito con successo la pompa di drenaggio guasta nella sua miniera Kombat in Namibia. Il corpo della nuova pompa è stato installato il 26 luglio 2024 e ha iniziato a pompare acqua il 27 luglio 2024. Al 29 luglio, la miniera è stata drenata di 25 metri dal collare del pozzo, rispetto ai 227 metri del 18 luglio. La pompa attualmente sta drenando a 2860 metri cubi all'ora.
L'azienda ha implementato modifiche per prevenire futuri guasti della pompa. L'estrazione e la lavorazione sono continuate normalmente dalle operazioni sotterranee sopra i 120 metri. Trigon rimane concentrata sulla produzione dal complesso sotterraneo di Asis West e mantiene le precedenti indicazioni. La società ha anche annunciato che Aidan Sullivan, VP delle Relazioni con gli Investitori, si dimetterà a partire dal 1 agosto 2024.
Trigon Metals Inc. (TSX-V: TM; OTCQB: PNTZF) ha reemplazado con éxito la bomba de desagüe fallida en su mina Kombat en Namibia. El cuerpo de la nueva bomba fue instalado el 26 de julio de 2024 y comenzó a bombear agua el 27 de julio de 2024. Al 29 de julio, la mina ha sido desaguada 25 metros desde el collar del pozo, bajando desde los 227 metros del 18 de julio. La bomba actualmente está drenando a 2860 metros cúbicos por hora.
La compañía ha implementado modificaciones para prevenir fallos futuros de la bomba. La minería y el procesamiento han continuado normalmente desde las operaciones subterráneas por encima de los 120 metros. Trigon sigue enfocándose en la producción del complejo subterráneo de Asis West y mantiene su previsión anterior. La empresa también anunció que Aidan Sullivan, VP de Relaciones con Inversores, renunciará a partir del 1 de agosto de 2024.
Trigon Metals Inc. (TSX-V: TM; OTCQB: PNTZF)는 나미비아의 콤바트 광산에서 고장 난 배수 펌프를 성공적으로 교체했습니다. 새로운 펌프 몸체는 2024년 7월 26일에 설치되었고, 2024년 7월 27일부터 물을 펌핑하기 시작했습니다. 7월 29일 현재, 광산은 샤프트 콜라에서 25미터의 배수를 완료하였으며, 이는 7월 18일의 227미터에서 감소한 수치입니다. 펌프는 현재 시간당 2860 입방미터의 속도로 배수하고 있습니다.
회사는 향후 펌프 고장을 방지하기 위해 수정 작업을 시행하였습니다. 120미터 이상에서의 지하 작업에서 채굴 및 가공이 정상적으로 계속되고 있습니다. Trigon은 Asis West 지하 단지에서의 생산에 집중하고 있으며, 이전의 지침을 유지하고 있습니다. 또한 회사는 투자자 관계 담당 부사장인 Aidan Sullivan이 2024년 8월 1일부터 사임할 것이라고 발표했습니다.
Trigon Metals Inc. (TSX-V: TM; OTCQB: PNTZF) a réussi à remplacer la pompe de déshydratation défaillante dans sa mine de Kombat en Namibie. Le corps de la nouvelle pompe a été installé le 26 juillet 2024 et a commencé à pomper de l'eau le 27 juillet 2024. Au 29 juillet, la mine a été déshydratée de 25 mètres par rapport au col de puits, contre 227 mètres le 18 juillet. La pompe déshydrate actuellement à 2860 mètres cubes par heure.
L'entreprise a mis en œuvre des modifications pour éviter de futures pannes de la pompe. L'extraction et le traitement se sont poursuivis normalement à partir des opérations souterraines au-dessus de 120 mètres. Trigon reste concentré sur la production du complexe souterrain d'Asis West et maintient ses précédentes prévisions. L'entreprise a également annoncé qu'Aidan Sullivan, VP des Relations avec les Investisseurs, démissionnera à compter du 1er août 2024.
Trigon Metals Inc. (TSX-V: TM; OTCQB: PNTZF) hat erfolgreich die ausgefallene Entwässerungspumpe in seiner Kombat Mine in Namibia ersetzt. Der Körper der neuen Pumpe wurde am 26. Juli 2024 installiert und begann am 27. Juli 2024 mit dem Pumpen von Wasser. Am 29. Juli war die Mine 25 Meter vom Schachtkranz entwässert, gegenüber 227 Metern am 18. Juli. Die Pumpe entwässert derzeit mit 2860 Kubikmetern pro Stunde.
Das Unternehmen hat Modifikationen implementiert, um zukünftige Pumpenausfälle zu verhindern. Der Abbau und die Verarbeitung haben normal über den 120 Metern fortgesetzt. Trigon bleibt auf die Produktion aus dem unterirdischen Komplex Asis West fokussiert und hält an den vorhergehenden Prognosen fest. Das Unternehmen gab außerdem bekannt, dass Aidan Sullivan, VP für Investor Relations, zum 1. August 2024 zurücktreten wird.
- Successful replacement of failed dewatering pump ahead of schedule
- Rapid dewatering progress: 25 meters in less than two days
- Continued normal mining and processing operations during pump replacement
- Implemented modifications to prevent future pump failures
- Maintained previous production guidance despite temporary setback
- Temporary setback in underground pumping progress due to pump failure
- VP of Investor Relations stepping down, potentially affecting investor communications
The replacement pump body (known as the wet end) was installed on July 26, 2024 and started pumping water from the mine on July 27, 2024. The mine has been dewatered 25 metres from the shaft collar as at 7:00a.m. (GMT +2:00), down from the stabilized level of 227 metres reported on July 18, 2024.
The new pump body was ordered from Yantai Xinhai Industry & Trade Co., Ltd., and airfreighted from
The pump is functioning as designed and is currently dewatering at 2860 cubic metres per hour. Trigon has taken measures to ensure that the previous failure issue was addressed through the implementation of the modifications to the new pump body, such as the installation of deflector plates and enhanced meshing and guarding on suction inlets of the pump, which will prevent foreign objects entering the pump.
Rennie Morkel, COO of Trigon Metals, commented, “I’m proud of our team’s commitment and endurance during this period. The team banded together from the procurement and logistics, to the installation and recommissioning during this time. We expect to recover to our former levels quickly which is attested to by the water level reducing by 25m in less than two days. This reinforces what we have learned over the past ten months of dewatering, where we have seen quick gains after brief interruptions. Although the loss of the wet end caused a temporary setback to the operations, we have demonstrated resilience and the ability to absorb this setback, where we would have struggled 8 months ago. I thank everyone for their commitment and sacrifices over this period.”
Jed Richardson, CEO and Executive Chairman of Trigon Metals, commented, “The pump replacement was managed effectively by the team and our redundancy systems prevented a flood like the one in 2007. The team has done exceptionally well in returning dewatering activities to previous levels. Our next key milestone is the installation and commissioning of the 11 level permanent pumpstation which is one of four planned pump stations underground.”
Mining and processing have continued as normal from the underground operations throughout this period, with activities focused on mining above 120 metres from the shaft collar. The remaining original pump is being monitored continuously and does not show any sign of fatigue or potential failure.
The Company remains focused on underground production from the Asis West underground complex. The pumping setbacks are not expected to impact plans and projections previously outlined in the Company’s guidance (see press release issued June 13, 2024).
Qualified Person
The technical information presented in this press release has been reviewed and approved for disclosure by Fanie Müller, P.Eng, VP Operations of Trigon, who is a Qualified Person as defined by NI 43-101.
Aidan Sullivan Steps Down as VP Investor Relations
Trigon Metals announces that Aidan Sullivan, Vice President of Investor Relations, will be stepping down from his position, effective August 1, 2024. We extend our heartfelt gratitude to Mr. Sullivan for his contributions and enthusiastic dedication to the Company. His efforts have positively contributed to our investor relations, and we wish him continued success in his future endeavors.
Trigon Metals Inc.
Trigon is a publicly-traded Canadian exploration and development company with its core business focused on copper and silver holdings in mine-friendly African jurisdictions. Currently, the company has operations in
Cautionary Notes
This news release may contain forward-looking statements. These statements include statements regarding the Company’s mining operations, the dewatering of the Kombat Mine, the installation of the water pump and maintenance of equipment, the timing and results of mining activities the Company’s strategies and the Company’s abilities to execute such strategies, the Company’s expectations for the Kombat Project, and the Company’s future plans and objectives. These statements are based on current expectations and assumptions that are subject to risks and uncertainties. Actual results could differ materially because of factors discussed in the management discussion and analysis section of our interim and most recent annual financial statements or other reports and filings with the TSX Venture Exchange and applicable Canadian securities regulations. We do not assume any obligation to update any forward-looking statements, except as required by applicable laws.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
View source version on businesswire.com: https://www.businesswire.com/news/home/20240729947883/en/
For further information, contact Investor Relations:
+1 647 276 6002
IR@trigonmetals.com
Website: www.trigonmetals.com
Source: Trigon Metals Inc.
FAQ
What is the current dewatering rate at Trigon Metals' Kombat mine?
How much progress has been made in dewatering the Kombat mine since July 18, 2024?
Has the pump replacement affected Trigon Metals' (PNTZF) production guidance?