Norfolk Southern announces East Palestine track excavation and remediation plan
Norfolk Southern Corporation (NYSE: NSC) is enhancing its remediation plan in East Palestine, Ohio, by excavating soil and replacing tracks in the derailment area, responding to community concerns. The initial rail line work begins immediately, followed by the second line. Over 4,800 cubic yards of soil and 1.7 million gallons of liquid have already been collected. The remediation will comply with environmental standards set by state and federal agencies, involving soil excavation and groundwater monitoring. Norfolk Southern aims to build community confidence through close coordination with local authorities.
- Enhancement of remediation plan in response to community feedback.
- Excavation of over 4,800 cubic yards of soil completed, showing commitment to environmental safety.
- Involvement of local, state, and federal agencies in remediation efforts.
- Track removal may disrupt services temporarily, impacting train schedules.
"Our original plan would have effectively and safely remediated the soil under our tracks. As I listened to community members over the past two weeks, they shared with me their concerns about that approach. I appreciate the direct feedback, and I am addressing it. In coordination with
All of
The work will begin immediately. Soil preparation will be followed by track removal along the first rail line, excavation of the soil, and then rebuilding the track. The same process will then follow with the second track. Trains will continue running at slower speeds on one track while the other is being excavated.
The site will be fully remediated in accordance with the company's long-term plan that is being developed with the
Remediation Overview
- Begin preparation for the removal and excavation of the first rail line.
- Install and begin sampling shallow groundwater monitoring wells near the site.
- Continue active soil sampling around the site.
- Continue evaluating sediment and sampling in Sulphur Run,
Leslie Run , andBull Creek . - Continue to excavate soil on the site.
- Continue surface water sampling, while monitoring and aerating the streams.
- Evaluate the stormwater infrastructure around the site.
- Continue the disposal of impacted water at an approved disposal facility.
- Begin shipping impacted soil to an approved disposal facility.
For more information on
About
Since 1827,
View original content to download multimedia:https://www.prnewswire.com/news-releases/norfolk-southern-announces-east-palestine-track-excavation-and-remediation-plan-301753864.html
SOURCE
FAQ
What is Norfolk Southern's remediation plan in East Palestine, Ohio?
When will Norfolk Southern begin work on the tracks in East Palestine?
How much soil has Norfolk Southern excavated in East Palestine?
What environmental measures is Norfolk Southern implementing in East Palestine?