Newcore Gold Files Technical Report for the Updated Preliminary Economic Assessment for the Enchi Gold Project, Ghana
Newcore Gold Ltd. (NCAUF) has filed a technical report supporting an updated Preliminary Economic Assessment (PEA) for its Enchi Gold Project in Ghana, effective June 8, 2021. The PEA indicates a robust project with a pre-tax NPV of $333 million at a gold price of $1,650/oz, and strong IRR metrics. The project has an inferred resource of 70.4 million tonnes grading 0.62 g/t Au, containing 1.4 million ounces of gold. Additional exploration is ongoing to enhance resources, with significant potential indicated by recent drilling results.
- Pre-tax NPV of $333 million at $1,650/oz gold price.
- Strong IRR of 54% pre-tax and 42% after-tax.
- Initial capital costs are estimated at $97 million with a payback of 2.3 years.
- Average annual production of 104,171 ounces in years 2-5, totaling 983,296 ounces over 11 years.
- Significant exploration upside with 46,000 metres of drilling not included in resource estimates.
- PEA results are preliminary and rely on inferred resources, which are speculative.
- Mineral resources are not mineral reserves and lack demonstrated economic viability.
VANCOUVER, British Columbia, July 13, 2021 (GLOBE NEWSWIRE) -- Newcore Gold Ltd. ("Newcore" or the "Company") (TSX-V: NCAU, OTCQX: NCAUF) reports it has filed the technical report supporting the updated independent Preliminary Economic Assessment ("PEA") completed for the Company’s
The positive PEA, the results of which were announced on June 8, 2021, highlights the potential for a technically simple, open pit mine and heap leach operation utilizing contract mining. The PEA also reflects an updated, pit constrained, Inferred Mineral Resource of 70.4 million tonnes ("Mt") grading 0.62 grams per tonne gold ("g/t Au") containing 1.4 million ounces gold. Only 20,195 metres of drilling from the ongoing 66,000 metre drill program was included in the updated Mineral Resource Estimate.
PEA Highlights (All currencies are reported in U.S. dollars unless otherwise specified)
- Strong Project Economics with Low Capital Intensity
- At a gold price of
$1,650 /oz:$333 million pre-tax net present value discounted at5% ("NPV5% ") and a54% pre-tax internal rate of return ("IRR"),$212 million after-tax NPV5% , and a42% after-tax IRR. - At a gold price of
$1,850 /oz:$471 million pre-tax NPV5% and a69% pre-tax IRR,$302 million after-tax NPV5% , and a54% after-tax IRR. - Initial capital costs estimated at
$97 million , with a short after-tax payback of 2.3 years.
- At a gold price of
- Establishing the Potential for a Robust Project with Significant Growth Potential
- Average annual gold production in years two through five of 104,171 ounces gold;
983,296 ounces gold recovered over an 11-year life of mine ("LOM"). - LOM strip ratio of 2.1 to 1, mined grade of 0.57 g/t gold and recovery of
79% . - LOM operating costs (1) estimated at
$923 /oz of gold, cash costs (2) estimated at$1,043 /oz of gold, LOM all-in sustaining costs (AISC) (3) estimated at$1,066 /oz of gold.
- Average annual gold production in years two through five of 104,171 ounces gold;
- Updated Mineral Resource Estimate, Including an Initial Resource at Kwakyekrom
- The PEA includes an updated Inferred Mineral Resource Estimate of 70.4 Mt grading 0.62 g/t Au containing 1.4 million ounces gold.
- Incorporates 20,195 metres of drilling completed at Enchi in 2020 and early 2021.
- Additional Exploration Upside from Ongoing 66,000 Metre Drill Program at Enchi
- 46,000 metres of additional drilling was not included in the Mineral Resource Estimate.
- Exploration and drilling activities continue on the Enchi Gold Project, with drilling testing a series of highly prospective targets directed at extending the existing Mineral Resources along strike and down dip, further drilling of advanced gold targets across the 216 km2 property, and first pass testing of multi-kilometre scale gold anomalies.
- Recent drilling results not included in the PEA Mineral Resource Estimate have intersected wide zones of oxide gold mineralization as well as high-grade core structures including 5.40 g/t Au over 9.0 m, 5.78 g/t Au over 7.0 m, 6.25 g/t Au over 6.0 m, 3.31 g/t Au over 9.0 m, and 2.95 g/t Au over 9.0 m and remain open along strike and to depth.
Note: Base case parameters assume a gold price of | |
(1) | Operating costs consist of mining costs, processing costs, and on-site G&A. |
(2) | Cash costs consist of operating costs plus treatment and refining charges, and royalties. |
(3) | AISC consists of cash costs plus sustaining capital (excluding closure costs and salvage value). |
The PEA is preliminary in nature, includes Inferred mineral resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that PEA results will be realized. Mineral resources are not mineral reserves and do not have demonstrated economic viability.
Further detail regarding the updated PEA for the Project is summarized in the Company’s news release dated June 8, 2021, as well as in the technical report which is available on Newcore’s website at newcoregold.com and under the Company’s SEDAR profile at www.sedar.com.
Qualified Persons
The updated PEA for the Enchi Gold Project was completed by BBA. The compilation of the technical report was completed by Todd McCracken, P. Geo. (Mineral Resource and Financial Model), Bahareh Asi, P. Eng. (Mining), David Willock, P. Eng. (Infrastructure), Mathieu Belisle, P. Eng. (Processing), Joe Amanor, MAusIMM(CP) (Site Investigation). By virtue of their education, membership to a recognized professional association and relevant work experience, Todd McCracken, Bahareh Asi, David Willock, Mathieu Belisle, and Joe Amanor are independent Qualified Persons as this term is defined by NI 43-101.
Mr. Gregory Smith, P. Geo, Vice President of Exploration of Newcore, is a Qualified Person as defined by NI 43-101, and has reviewed and approved the technical data and information contained in this news release. Mr. Smith has verified the technical and scientific data disclosed herein and has conducted appropriate verification on the underlying data including confirmation of the drillhole data files against the original drillhole logs and assay certificates.
About Newcore Gold Ltd.
Newcore Gold is advancing its Enchi Gold project located in Ghana, Africa’s largest gold producer (1). The Project currently hosts an Inferred Mineral Resource of 1.4 million ounces of gold at 0.62 g/t (2). Newcore Gold offers investors a unique combination of top-tier leadership, who are aligned with shareholders through their
On Behalf of the Board of Directors of Newcore Gold Ltd.
Luke Alexander
President, CEO & Director
For further information, please contact:
Mal Karwowska | Vice President, Corporate Development and Investor Relations
+1 604 484 4399
info@newcoregold.com
www.newcoregold.com
(1) | Source: Production volumes for 2020 as sourced from the World Gold Council |
(2) | Notes for Inferred Mineral Resource Estimate: |
1. | CIM definition standards were followed for the resource estimate. |
2. | The 2021 resource models used ordinary kriging (OK) grade estimation within a three-dimensional block model with mineralized zones defined by wireframed solids and constrained by pits shell for Sewum, Boin and Nyam. Kwakyekrom used Inverse Distance squared (ID2). |
3. | A base cut-off grade of 0.2 g/t Au was used with a capping of gold grades varied by deposit and zone. |
4. | A US |
5. | Metallurgical recoveries have been applied to four individual deposits and in each case three material types (oxide, transition, and fresh rock) with average recoveries of |
6. | A density of 2.20 g/cm3 for oxide, 2.45 g/cm3 for transition, and 2.70 g/cm3 for fresh rock was applied. |
7. | Optimization pit slope angles varied based on the rock types. |
8. | Mineral Resources that are not mineral reserves do not have economic viability. Numbers may not add due to rounding. |
9. | These numbers are from the technical report titled "Preliminary Economic Assessment for the Enchi Gold Project, Enchi, Ghana", with an effective date of June 8, 2021, prepared by Todd McCracken, P. Geo. and Greg Smith, P. Geo. in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects and is available under Newcore’s SEDAR profile at www.sedar.com. |
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Cautionary Note Regarding Forward-Looking Statements
This news release includes statements that contain "forward-looking information" within the meaning of the applicable Canadian securities legislation ("forward-looking statements"). All statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that involves discussion with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often, but not always using phrases such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "believes" or variations (including negative variations) of such words and phrases, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved) are not statements of historical fact and may be forward-looking statements. In this news release, forward-looking statements relate, among other things, to: timing of completion of a technical report summarizing the results of the PEA; the development, operational and economic results of the PEA, including cash flows, capital expenditures, development costs, extraction rates, recovery rates, mining cost estimates; estimation of mineral resources; statements about the estimate of mineral resources; magnitude or quality of mineral deposits; anticipated advancement of the Enchi Gold Project mine plan; future operations; future exploration prospects; the completion and timing of future development studies; results of our ongoing drill campaign; anticipated advancement of mineral properties or programs; future exploration prospects; and the future growth potential of Enchi.
These forward-looking statements, and any assumptions upon which they are based, are made in good faith and reflect our current judgment regarding the direction of our business. The assumptions underlying the forward-looking statements are based on information currently available to Newcore. Although the forward-looking statements contained in this news release are based upon what management of Newcore believes, or believed at the time, to be reasonable assumptions, Newcore cannot assure its shareholders that actual results will be consistent with such forward-looking statements, as there may be other factors that cause results not to be as anticipated, estimated or intended. Forward-looking information also involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include, among others: risks related to interpretation of metallurgical characteristics of the mineralization, changes in project parameters as plans continue to be refined, future metal prices, availability of capital and financing on acceptable terms, uninsured risks, regulatory changes, delays or inability to receive required approvals, taxes, mining title, the speculative nature of the Company’s business; the Company’s formative stage of development; the Company’s financial position; possible variations in mineralization, grade or recovery rates; actual results of current exploration activities; fluctuations in general macroeconomic conditions; fluctuations in securities markets; fluctuations in spot and forward prices of gold and other commodities; fluctuations in currency markets (such as the Canadian dollar to United States dollar exchange rate); change in national and local government, legislation, taxation, controls, regulations and political or economic developments; risks and hazards associated with the business of mineral exploration, development and mining (including environmental hazards, unusual or unexpected geological formations); the presence of laws and regulations that may impose restrictions on mining; employee relations; relationships with and claims by local communities; the speculative nature of mineral exploration and development (including the risks of obtaining necessary licenses, permits and approvals from government authorities); and title to properties.
Forward-looking statements contained herein are made as of the date of this news release and the Company disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results, except as may be required by applicable securities laws. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking information.
Non-GAAP Measures
This news release includes certain terms or performance measures commonly used in the mining industry that are not defined under International Financial Reporting Standards ("IFRS"), including cash costs and AISC per ounce of gold. Non-GAAP measures do not have any standardized meaning prescribed under IFRS and, therefore, they may not be comparable to similar measures employed by other companies. We believe that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate our performance. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.
FAQ
What are the key findings of Newcore Gold's updated PEA for the Enchi Gold Project?
What is the inferred mineral resource estimate for the Enchi Gold Project by Newcore Gold?
How much gold is expected to be produced annually according to Newcore Gold's PEA?
What ongoing activities are being conducted at Newcore Gold's Enchi Gold Project?