Maritime Initiates Re-Commissioning Program at the Pine Cove Mill
Maritime Resources Corp. (TSXV: MAE) (OTC Pink: MRTMF) has initiated refurbishment work at its Pine Cove mill in Newfoundland and Labrador. The company acquired the Point Rousse Project in 2023, including the Pine Cove gold processing plant and tailings storage facility. Key highlights include:
- Appointment of Dwight Goudie as Pine Cove Mill Manager
- Ongoing excavation and stockpiling of mineralized material
- Commencement of mechanical and electrical inspections
- Sourcing of reagents and recruitment of key personnel
- Discharge of 2 million cubic metres of water from the tailings storage facility
The company aims to process mineralized stockpile inventory, providing cash flow for the development of its Hammerdown Gold Project. Maritime has identified approximately 85,000-115,000 tonnes of stockpiled and tailings material grading about 1.1 grams per tonne gold, potentially containing 3,000 to 4,000 ounces of gold.
Maritime Resources Corp. (TSXV: MAE) (OTC Pink: MRTMF) ha avviato lavori di ristrutturazione presso il suo impianto di Pine Cove in Newfoundland e Labrador. L'azienda ha acquisito il Progetto Point Rousse nel 2023, che include l'impianto di lavorazione dell'oro di Pine Cove e la struttura di stoccaggio dei fanghi. I punti salienti includono:
- Nomina di Dwight Goudie come Manager dell'Impianto di Pine Cove
- Escavazione e accumulo di materiale mineralizzato in corso
- Inizio delle ispezioni meccaniche ed elettriche
- Ricerca di reagenti e reclutamento di personale chiave
- Scarico di 2 milioni di metri cubi d'acqua dalla struttura di stoccaggio dei fanghi
L'azienda mira a lavorare l'inventario di stoccaggio mineralizzato, fornendo flusso di cassa per lo sviluppo del suo Progetto Oro Hammerdown. Maritime ha identificato circa 85.000-115.000 tonnellate di materiale stoccato e di fanghi con un contenuto d'oro di circa 1,1 grammi per tonnellata, che potrebbe contenere da 3.000 a 4.000 once d'oro.
Maritime Resources Corp. (TSXV: MAE) (OTC Pink: MRTMF) ha iniciado trabajos de renovación en su planta de Pine Cove en Newfoundland y Labrador. La compañía adquirió el Proyecto Point Rousse en 2023, que incluye la planta de procesamiento de oro de Pine Cove y la instalación de almacenamiento de relaves. Los aspectos destacados incluyen:
- Nombramiento de Dwight Goudie como Gerente de la Planta de Pine Cove
- Excavación y acopio de material mineralizado en curso
- Inicio de inspecciones mecánicas y eléctricas
- Obtención de reactivos y contratación de personal clave
- Descarga de 2 millones de metros cúbicos de agua desde la instalación de almacenamiento de relaves
La empresa tiene como objetivo procesar el inventario de acopio mineralizado, proporcionando flujo de efectivo para el desarrollo de su Proyecto de Oro Hammerdown. Maritime ha identificado aproximadamente 85.000-115.000 toneladas de material acumulado y relaves con un contenido promedio de 1,1 gramos por tonelada de oro, que potencialmente contiene entre 3.000 y 4.000 onzas de oro.
Maritime Resources Corp. (TSXV: MAE) (OTC Pink: MRTMF)는 뉴펀들랜드와 래브라도에 있는 Pine Cove 공장에서 개보수 작업을 시작했습니다. 회사는 2023년에 Pine Cove 금 가공 플랜트와 제련 슬러지 저장 시설을 포함한 Point Rousse 프로젝트를 인수했습니다. 주요 하이라이트는 다음과 같습니다:
- Dwight Goudie를 Pine Cove 공장 관리자로 임명
- 광물화된 자원의 굴착 및 축적 진행 중
- 기계 및 전기 검사 시작
- 시약 조달 및 주요 인력 채용
- 슬러지 저장 시설에서 200만 입방 미터의 물 방출
회사는 광물화된 재고를 처리하여 Hammerdown 금 프로젝트 개발을 위한 현금 흐름을 제공하는 것을 목표로 하고 있습니다. Maritime은 약 85,000-115,000톤의 축적 및 슬러지로 이루어진 물질의 평균 함량이 톤당 약 1.1그램의 금으로, 잠재적으로 3,000에서 4,000온스의 금을 포함하고 있음을 확인했습니다.
Maritime Resources Corp. (TSXV: MAE) (OTC Pink: MRTMF) a entamé des travaux de rénovation à son usine de Pine Cove à Terre-Neuve-et-Labrador. La société a acquis le projet Point Rousse en 2023, y compris l'usine de traitement de l'or de Pine Cove et l'installation de stockage des résidus. Les points clés incluent :
- Nommer Dwight Goudie en tant que responsable de l'usine de Pine Cove
- Excavation et stockage de matériel minéralisé en cours
- Début des inspections mécaniques et électriques
- Recherche de réactifs et recrutement de personnel clé
- Décharge de 2 millions de mètres cubes d'eau de l'installation de stockage des résidus
La société vise à traiter l'inventaire de stock de matériel minéralisé, fournissant un flux de trésorerie pour le développement de son projet d'or Hammerdown. Maritime a identifié environ 85 000 à 115 000 tonnes de matériel de stockage et de résidus avec un grade d'environ 1,1 gramme d'or par tonne, contenant potentiellement entre 3 000 et 4 000 onces d'or.
Maritime Resources Corp. (TSXV: MAE) (OTC Pink: MRTMF) hat die Renovierungsarbeiten an seiner Pine Cove-Mühle in Neufundland und Labrador begonnen. Das Unternehmen hat 2023 das Point Rousse-Projekt erworben, einschließlich der Pine Cove-Goldverarbeitungsanlage und der Abraumlagerstätte. Zu den wichtigsten Punkten gehören:
- Ernennung von Dwight Goudie zum Mühlenleiter von Pine Cove
- Laufende Ausgrabungen und Lagerung von mineralisiertem Material
- Beginn der mechanischen und elektrischen Inspektionen
- Beschaffung von Reagenzien und Rekrutierung von Schlüsselpersonal
- Ableitung von 2 Millionen Kubikmetern Wasser aus der Abraumlagerstätte
Das Unternehmen plant, das mineralisierte Lagerinventar zu verarbeiten, um einen Cashflow für die Entwicklung seines Hammerdown-Goldprojekts zu gewährleisten. Maritime hat ungefähr 85.000-115.000 Tonnen gelagertes und Abraum-material mit einem Gehalt von etwa 1,1 Gramm Gold pro Tonne identifiziert, das potenziell 3.000 bis 4.000 Unzen Gold enthalten könnte.
- Initiation of refurbishment work at Pine Cove mill to restart operations
- Appointment of experienced industry veteran Dwight Goudie as Mill Manager
- Identification of 85,000-115,000 tonnes of stockpiled material with potential 3,000-4,000 ounces of contained gold
- Successful dewatering of tailings storage facility, reducing water level by 14m since acquisition
- Partnership with Shoreline Aggregates for cost-effective site operations and reclamation work
- Uncertainty whether stockpiled and tailings material will be delineated as a mineral resource
- Additional capital expenditure required for mill recommissioning and equipment upgrades
Toronto, Ontario--(Newsfile Corp. - October 9, 2024) - Maritime Resources Corp. (TSXV: MAE) (OTC Pink: MRTMF) ("Maritime" or the "Company") is pleased to announce that refurbishment work has begun at the Company's Pine Cove mill ("Pine Cove") in the Baie Verte mining district of Newfoundland and Labrador. Maritime acquired the Point Rousse Project in 2023, including the Pine Cove gold processing plant and large capacity in-pit tailings storage facility. The plant operated until the first quarter of 2023 and has been on a care and maintenance program since then.
Highlights:
Appointment of industry veteran Dwight Goudie as Pine Cove Mill Manager
Excavation and stockpiling of mineralized material is ongoing ahead of processing operations restart
Mechanical and electrical inspections, minor repairs have commenced
Sourcing of reagents and consumables, recruitment of key personnel is underway
2 million cubic metres of water discharged from the tailings storage facility year to date
Garett Macdonald, President and CEO comments, "With the closing of the
Pine Cove Mill
A comprehensive program of equipment upgrades and inspections are now underway throughout the processing plant, focusing on all electrical and mechanical systems to ensure a safe start up. Maritime's care and maintenance team is working with industry consultants and local contractors to complete the work at the plant over the next two months. Maritime has begun sourcing the necessary reagents and minor equipment to support processing operations later this year. Recruitment of key personnel is also underway.
Figure 1: Pine Cove Site View
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4548/226082_bc09a4e79423ba88_001full.jpg
Mill Manager Appointment
Maritime is pleased to announce the appointment of Dwight Goudie as Mill Manager for the Company. Mr. Goudie is a resident of the Baie Verte mining district and has over 40 years of combined mill maintenance, plant construction and mineral processing experience, from western Canada's Tumbler Ridge region, and in more recent years operating process plants for FireFly Metals Ltd (previously Rambler Metals and Mining Limited).
Mineralized Stockpiles
Mineralized material from around the process plant and mill yard is being stockpiled near the facility while completing additional sampling of the area. Gold bearing material from tailings storage facility #2 (TSF2) has been excavated and hauled to the stockpile yard. Maritime has identified approximately 85,000-115,000 tonnes of stockpiled and tailings material grading approximately 1.1 grams per tonne gold for approximately 3,000 to 4,000 ounces of contained gold (June 6, 2024 News Release). The potential quantity and grade are conceptual in nature and there has been insufficient exploration to define a mineral resource. It is uncertain whether further exploration would result in the stockpiled and tailings material being delineated as a mineral resource. Tonnages were estimated from surveyed volumes of the stockpile and tailings areas applying bulk density factors of 2.0 tonnes per cubic metre ("t/m3") for compacted stockpile material and 1.5 t/m3 for screened fines material. Grades were estimated from assay results of the 677 samples that were collected and were in line with the grades processed by previous operators.
Figure 2. Stockpiling Mineralized Material
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4548/226082_bc09a4e79423ba88_002full.jpg
Tailings Storage Facility
Maritime continues to prepare the Pine Cove Pit tailings impoundment area for future tailings disposal. Dewatering activities have been ongoing throughout the year with approximately 2 million cubic metres of environmentally compliant water discharge year to date. This has resulted in a water level reduction of over 14 m since acquiring the asset in August 2023, positioning the operation well for future tailings and water management.
The first tailings storage facility supporting former operations at Pine Cove, TSF1, contains inert tailings and is located adjacent to the site office complex. Maritime is currently working with Shoreline Aggregates Inc. "Shoreline" to schedule the beginning of reclamation work of this area in the fourth quarter of 2024. "As we continue to strengthen our partnership with Shoreline at Pine Cove, both parties continue to realize the mutual benefits of operating on one site. Having a company with heavy equipment and a skilled workforce operating at our site means that we are able to find creative and cost effective arrangements to execute work such as this," added Perry Blanchard, Vice President of Environment and Sustainability.
TSF2, also used for inert tailings storage during past operations, is being repurposed in support of Shoreline's wash plant operations. Under the direction of the facility's Engineer of Record, Knight Piesold, TSF2 will be used for recycling of wash plant water and capture and removal of fines during Shoreline's aggregate production. Construction work is near completion and the facility will be ready for Shoreline's operations in 2025. Fines containing gold which are captured in this facility will be recovered and processed in the Pine Cove mill.
Figure 3. Pine Cove Tailings Facility
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4548/226082_bc09a4e79423ba88_003full.jpg
Qualified Person
The technical content of this news release has been reviewed and approved by Mr. Stacy Freudigmann, P.Eng. F.AusIMM. of Canenco Consulting Corp., an independent consultant for process engineering and metallurgy, who is a "Qualified Person" as defined in National Instrument 43-101 - Standards of Disclosure for Mineral Projects.
About Maritime Resources Corp.
Maritime (TSXV: MAE) (OTC Pink: MRTMF) is a gold exploration and development company focused on advancing the Hammerdown Gold Project in the Baie Verte District of Newfoundland and Labrador, a top tier global mining jurisdiction. Maritime holds a
On Behalf of the Board:
Garett Macdonald, MBA, P.Eng.
President and CEO
Phone: (416) 365-5321
info@maritimegold.com
www.maritimeresourcescorp.com
Twitter
Facebook
LinkedIn
YouTube
Caution Regarding Forward Looking Statements:
Certain of the statements made and information contained herein is "forward-looking information" within the meaning of National Instrument 51-102 - Continuous Disclosure Obligations. Forward-looking statements are often identified by terms such as "will", "may", "should", "anticipate", "expects", "intends", "indicates" "plans" and similar expressions. Forward-looking statements include, but are not limited to, statements concerning the Hammerdown mineralization, its' metallurgical response, precious metal extraction based on the ongoing metallurgical testwork, the Project's strong environmental attributes, new opportunities to generate cash flows and add value for shareholders, estimating contained gold in and generating cash flow from mineralized stockpiles and tailings material at the Point Rousse project, estimated all-in sustaining costs, estimated project capital costs, first production being achieved at the Project, provision of additional employment and business opportunities in the region, and ability of the Company to engage with local service providers, amongst other things, which involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking information. All forward-looking statements and forward-looking information are based on reasonable assumptions that have been made by the Company in good faith as at the date of such information. Such assumptions include, without limitation, the price of and anticipated costs of recovery of, base metal concentrates, gold and silver, the presence of and continuity of such minerals at modeled grades and values, the capacities of various machinery and equipment, the use of ore sorting technology will produce positive results, the availability of personnel, machinery and equipment at estimated prices, mineral recovery rates, and others. Forward-looking information is subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking information, including, without limitation, the ability of the Company to continue to be able to access the capital markets for the funding necessary to acquire, maintain and advance exploration properties or business opportunities; global financial conditions, including competition within the industry to acquire properties of merit or new business opportunities, and competition from other companies possessing greater technical and financial resources; difficulties in advancing towards a development decision and executing exploration programs on the Company's proposed schedules and within its cost estimates, whether due to weather conditions, availability or interruption of power supply, mechanical equipment performance problems, natural disasters or pandemics in the areas where it operates; increasingly stringent environmental regulations and other permitting restrictions or maintaining title or other factors related to exploring of its properties, such as the availability of essential supplies and services; factors beyond the capacity of the Company to anticipate and control, such as the marketability of mineral products produced from the Company's properties; uncertainty as to whether the acquisition of assets and new mineral property interests will be completed in the manner currently contemplated by the parties; uncertainty as to whether mineral resources will ever be converted into mineral reserves once economic considerations are applied; uncertainty as to whether inferred mineral resources will be converted to the measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied; government regulations relating to health, safety and the environment, and the scale and scope of royalties and taxes on production; and the availability of experienced contractors and professional staff to perform work in a competitive environment and the resulting adverse impact on costs and performance and other risks and uncertainties, including those described in each MD&A of financial condition and results of operations. In addition, forward-looking information is based on various assumptions including, without limitation, assumptions associated with exploration results and costs and the availability of materials and skilled labour. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Accordingly, readers are advised not to place undue reliance on forward-looking information. Except as required under applicable securities legislation, Maritime undertakes no obligation to publicly update or revise forward-looking information, whether as a result of new information, future events or otherwise.
Neither the TSX Venture Exchange ("TSX-V") nor its Regulation Services Provider (as that term is defined in the policies of the TSX-V) accepts responsibility for the adequacy or accuracy of this release.
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/226082
FAQ
What is Maritime Resources Corp's plan for the Pine Cove mill?
How much mineralized material has Maritime Resources Corp identified at Pine Cove?
Who has been appointed as the new Mill Manager for Maritime Resources Corp's Pine Cove operation?