MAG Silver Reports Second Quarter Production From Juanicipio
MAG Silver Corp. reported strong Q2 production results from the Juanicipio Project, processing 154,069 tonnes of mineralized material. On a 100% basis, this resulted in 2,372,140 silver ounces and 5,609 gold ounces. MAG’s attributable share includes 1,043,742 silver ounces and 2,468 gold ounces. The company has improved cash reserves to $37M from $18M in Q1. Progress is being made on the power system tie-ins for the Juanicipio plant, with commissioning expected soon. The ramp-up to 85-90% capacity by year-end remains achievable.
- Q2 production yielded 2,372,140 silver ounces and 5,609 gold ounces.
- Cash balances increased to $37M from $18M in Q1.
- Strong progress on commissioning of the Juanicipio plant.
- Operational team well positioned to produce first concentrates in H2 2022.
- Mill commissioning timeline extended, awaiting power grid tie-in approval.
VANCOUVER, British Columbia, July 27, 2022 (GLOBE NEWSWIRE) -- MAG Silver Corp. (TSX / NYSE American: MAG) (“MAG” or the “Company”) is pleased to report second quarter (Q2) production of underground development and stope material from the Juanicipio Project (
Total Juanicipio production for the quarter, based on provisional estimates before offtake agreement adjustments, totaled 2,372,140 silver ounces and 5,609 gold ounces (MAG’s attributable
Mineralized material from Juanicipio continues to be processed through the nearby Saucito and Fresnillo beneficiation plants (
The revenue from current production, net of processing and treatment charges, is being used to offset initial project capital and sustaining capital cash requirements, reducing the need for capital contributions from Fresnillo and MAG. At the end of the quarter Juanicipio held cash balances of
Construction of the Juanicipio plant was delivered by Fresnillo on schedule during the fourth quarter of 2021. However, as previously disclosed, the mill commissioning timeline was extended until tie-in approval to the national power grid is obtained from the federal power authorities (see Press Release December 27, 2021). We are pleased to report good progress on the required power system shutdowns to enable the final tie-in of the Juanicipio sub-station to the national power grid, and commencement of electrical commissioning of the plant is expected to occur in the coming weeks.
“We are delighted with the progress reported by the Fresnillo team on the electricity shutdowns that pave the way for the final tie-in to the power grid. Commissioning of the new electrical system is expected over the next few weeks followed by the commissioning of the grinding mills. The rest of the process plant has been fully commissioned and awaits the energizing of the mills. Target ramp-up to 85
Qualified Person: Dr. Peter Megaw, Ph.D., C.P.G., has acted as the Qualified Person as defined in National Instrument 43-101 for this disclosure and supervised the preparation of the technical information in this release. Dr. Megaw has a Ph.D. in geology and more than 40 years of relevant experience focused on ore deposit exploration worldwide. He is a Certified Professional Geologist (CPG 10227) by the American Institute of Professional Geologists and an Arizona Registered Geologist (ARG 21613). Dr. Megaw is not independent as he is Chief Exploration Officer and a Shareholder of MAG.
About MAG Silver Corp. (www.magsilver.com)
MAG Silver Corp. is a Canadian development and exploration company focused on becoming a top-tier primary silver mining company by exploring and advancing high-grade, district scale, silver-dominant projects in the Americas. Its principal focus and asset is the Juanicipio Project (
Neither the Toronto Stock Exchange nor the NYSE American has reviewed or accepted responsibility for the accuracy or adequacy of this press release, which has been prepared by management.
This release includes certain statements that may be deemed to be “forward-looking statements” within the meaning of the US Private Securities Litigation Reform Act of 1995. All statements in this release, other than statements of historical facts are forward looking statements, including statements that address our expectations with respect to the timing and success of plant pre-commissioning and commissioning activities, processing rates of development materials, future mineral production, and events or developments. Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "plan", "continue", "estimate", "expect", "may", "will", "project", "predict", "potential", "targeting", "intend", "could", "might", "should", "believe" and similar expressions. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements. Although MAG believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include, but are not limited to, impacts (both direct and indirect) of COVID-19, timing of receipt of required permits, changes in applicable laws, changes in commodities prices, changes in mineral production performance, exploitation and exploration successes, continued availability of capital and financing, and general economic, market or business conditions, political risk, currency risk and capital cost inflation. In addition, forward-looking statements are subject to various risks, including that data is incomplete and considerable additional work will be required to complete further evaluation, including but not limited to drilling, engineering and socio-economic studies and investment. The reader is referred to the MAG Silver’s filings with the SEC and Canadian securities regulators for disclosure regarding these and other risk factors. There is no certainty that any forward-looking statement will come to pass, and investors should not place undue reliance upon forward-looking statements.
Please Note: Investors are urged to consider closely the disclosures in MAG's annual and quarterly reports and other public filings, accessible through the Internet at www.sedar.com and www.sec.gov.
LEI: 254900LGL904N7F3EL14
FAQ
What were MAG Silver's Q2 production results for 2022?
How much cash did MAG Silver have at the end of Q2 2022?
When is MAG Silver expected to commence electrical commissioning of the Juanicipio plant?
What percentage of the Juanicipio Project does MAG Silver own?