LUCA ACHIEVES TARGETED THROUGHPUT RATES AT CAMPO MORADO AND TAHUEHUTO MINES
Luca Mining Corp. (TSXV: LUCA) (OTCQX: LUCMF) has achieved significant operational milestones at its two mining operations. At the Campo Morado zinc/copper/gold mine, the company reached its targeted throughput of 2,000 tonnes per day (tpd), representing a 43% increase over the previous six months. In January 2025, the Campo Morado mill processed over 62,850 tonnes of ore, with plans to increase throughput to 2,400 tpd.
At the Tahuehueto gold/silver mine, commissioning is nearing completion with mill throughput stabilizing at 1,000 tpd. Despite a planned shutdown exceeding one week in January 2025, the mill processed over 24,700 tonnes of ore. The company is currently constructing a new warehouse to ensure sufficient parts and commodity supply redundancy for commercial production.
Luca Mining Corp. (TSXV: LUCA) (OTCQX: LUCMF) ha raggiunto traguardi operativi significativi nelle sue due operazioni minerarie. Presso la miniera di zinco/rame/oro Campo Morado, l'azienda ha raggiunto la capacità di lavorazione target di 2.000 tonnellate al giorno (tpd), con un incremento del 43% rispetto ai sei mesi precedenti. Nel gennaio 2025, l'impianto di Campo Morado ha trattato oltre 62.850 tonnellate di minerale, con piani per aumentare la capacità a 2.400 tpd.
Presso la miniera d'oro/argento Tahuehueto, il commissioning sta per concludersi con la stabilizzazione della capacità del mulino a 1.000 tpd. Nonostante una chiusura programmata di oltre una settimana a gennaio 2025, il mulino ha lavorato oltre 24.700 tonnellate di minerale. Attualmente, l'azienda sta costruendo un nuovo magazzino per garantire una sufficiente disponibilità di parti e materia prima per la produzione commerciale.
Luca Mining Corp. (TSXV: LUCA) (OTCQX: LUCMF) ha logrado hitos operativos significativos en sus dos operaciones mineras. En la mina de zinc/cobre/oro Campo Morado, la compañía alcanzó su capacidad de procesamiento objetivo de 2,000 toneladas por día (tpd), lo que representa un aumento del 43% respecto a los seis meses anteriores. En enero de 2025, la planta de Campo Morado procesó más de 62,850 toneladas de mineral, con planes para aumentar el rendimiento a 2,400 tpd.
En la mina de oro/plata Tahuehueto, la puesta en marcha está casi completa y la capacidad del molino se está estabilizando en 1,000 tpd. A pesar de un cierre programado que excede una semana en enero de 2025, el molino procesó más de 24,700 toneladas de mineral. Actualmente, la compañía está construyendo un nuevo almacén para garantizar un suministro suficiente de piezas y materias primas para la producción comercial.
루카 마이닝 주식회사 (TSXV: LUCA) (OTCQX: LUCMF)는 두 개의 광산 운영에서 중요한 운영 이정표를 달성했습니다. 캄포 모라도 아연/구리/금 광산에서 이 회사는 하루 처리량 목표인 2,000톤(tpd)에 도달했으며, 이는 지난 6개월 대비 43% 증가한 수치입니다. 2025년 1월, 캄포 모라도 제련소는 62,850톤 이상의 광석을 처리했으며, 향후 처리량을 2,400 tpd로 늘릴 계획입니다.
타후에후에토 금/은 광산에서는 커미셔닝이 완료에 가까워지며, 제련소의 처리량이 1,000 tpd로 안정화되고 있습니다. 2025년 1월에 일주일 이상 예정된 가동 중단이 있었음에도 불구하고, 제련소는 24,700톤 이상의 광석을 처리했습니다. 현재 회사는 상업 생산을 위한 충분한 부품 및 원자재 공급을 보장하기 위해 새로운 창고를 건설하고 있습니다.
Luca Mining Corp. (TSXV: LUCA) (OTCQX: LUCMF) a atteint des jalons opérationnels significatifs dans ses deux opérations minières. À la mine de zinc/cuivre/or Campo Morado, la société a atteint son objectif de traitement de 2 000 tonnes par jour (tpd), représentant une augmentation de 43 % par rapport aux six mois précédents. En janvier 2025, l'usine de Campo Morado a traité plus de 62 850 tonnes de minerai, avec des plans pour augmenter le débit à 2 400 tpd.
À la mine d'or/argent Tahuehueto, la mise en service touche à sa fin avec un débit de l'usine se stabilisant à 1 000 tpd. Malgré un arrêt programmé de plus d'une semaine en janvier 2025, l'usine a traité plus de 24 700 tonnes de minerai. Actuellement, la société construit un nouvel entrepôt pour garantir un approvisionnement suffisant en pièces et en matières premières pour la production commerciale.
Luca Mining Corp. (TSXV: LUCA) (OTCQX: LUCMF) hat bedeutende Betriebsmeilensteine in seinen beiden Bergbauoperationen erreicht. In der Campo Morado Zink/Kupfer/Goldmine erreichte das Unternehmen den angestrebten Durchsatz von 2.000 Tonnen pro Tag (tpd), was einem Anstieg von 43% gegenüber den letzten sechs Monaten entspricht. Im Januar 2025 verarbeitete die Campo Morado-Mühle über 62.850 Tonnen Erz und plant, den Durchsatz auf 2.400 tpd zu erhöhen.
In der Tahuehueto Gold/Silbermine steht die Inbetriebnahme kurz vor dem Abschluss, und der Mühlendurchsatz stabilisiert sich bei 1.000 tpd. Trotz einer geplanten Stilllegung von mehr als einer Woche im Januar 2025 verarbeitete die Mühle über 24.700 Tonnen Erz. Das Unternehmen baut derzeit ein neues Lagerhaus, um eine ausreichende Versorgung mit Ersatzteilen und Rohstoffen für die kommerzielle Produktion sicherzustellen.
- Campo Morado achieved 2,000 tpd target, representing 43% throughput increase
- Campo Morado processed 62,850 tonnes in January 2025
- Tahuehueto mill reached 1,000 tpd stability
- Tahuehueto processed 24,700 tonnes in January 2025 despite planned shutdown
- None.
The Company has achieved its targeted throughput rates at the
Tahuehueto
Commissioning of this new gold mine has been progressing extremely well and is nearing completion. Throughput at the Tahuehueto mill has started to stabilize at the 1,000 tpd level. In the month of January 2025, even with a planned shutdown of greater than one week (consisting of testing and commiserate adjustments), the mill processed over 24,700 tonnes of ore; an exciting milestone for Luca. In preparation for commercial production, the Company is working to ensure sufficient parts and commodity supply redundancy is in place for its operations through purchasing and stocking a new warehouse now under construction on site.
Dan Barnholden, CEO, commented, "I am very pleased to see that our careful planning is allowing us to meet these important throughput objectives. Steady and stable operations with back up contingencies are key to consistent results. I would like to congratulate our entire Luca team and affiliates on a job well done. We've been able to quickly increase production at both operations and we can clearly see a path forward for further increases ahead."
About Luca Mining Corp.
Luca Mining (TSX-V: LUCA, OTCQX: LUCMF, Frankfurt: Z68) is a diversified Canadian mining company with two
The
The Tahuehueto epithermal gold and silver mine is a new underground operation in Durango State. The Company is commissioning the Tahuehueto mill and expects to achieve commercial production in early 2025.
Qualified Person
The technical information contained in this news release has been reviewed and approved by Mr. Paul D. Gray, P.Geo., Vice-President Exploration at Luca Mining. Mr. Gray is a Qualified Person for the Company as defined by National Instrument 43-101.
On Behalf of the Board of Directors
(signed) "Dan Barnholden"
Dan Barnholden, Chief Executive Officer
For more information, please visit: www.lucamining.com
Cautionary Note Regarding Forward-Looking Statements
It should be noted that Luca declared commercial production at
Statements contained in this news release that are not historical facts are "forward-looking information" or "forward-looking statements" (collectively, "Forward-Looking Information") within the meaning of applicable Canadian securities laws. Forward Looking Information includes, but is not limited to, disclosure regarding the Financings, the anticipated timing of closing thereof and the expected use of proceeds therefrom; and other possible events, conditions or financial performance that are based on assumptions about future economic conditions and courses of action; the timing and costs of future activities on the Company's properties, such as production rates and increases; success of exploration, development and bulk sample processing activities, and timing for processing at its own mineral processing facility on the Tahuehueto project site. In certain cases, Forward-Looking Information can be identified using words and phrases such as "plans," "expects," "scheduled," "estimates," "forecasts," "intends," "anticipates" or variations of such words and phrases. In preparing the Forward-Looking Information in this news release, the Company has applied several material assumptions, including, but not limited to, that all requisite approvals in respect of the Financings will be received, and all conditions precedent to completion of the Financings will be satisfied, in a timely manner; the Company will be able to raise additional capital as necessary; the current exploration, development, environmental and other objectives concerning the Campo Morado Mine and the Tahuehueto Project can be achieved; the program to improve mining operations at
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
View original content to download multimedia:https://www.prnewswire.com/news-releases/luca-achieves-targeted-throughput-rates-at-campo-morado-and-tahuehuto-mines-302368318.html
SOURCE Luca Mining Corp.
FAQ
What throughput rate did LUCMF achieve at Campo Morado mine in February 2025?
How many tonnes did LUCMF process at Campo Morado in January 2025?
What is LUCMF's target throughput rate for Campo Morado in the coming months?