Cheniere Announces Substantial Completion of Train 1 at the Corpus Christi Stage 3 Project
Cheniere Energy (NYSE: LNG) has achieved Substantial Completion of Train 1 at the Corpus Christi Stage 3 Liquefaction Project (CCL Stage 3) on March 16, 2025, ahead of schedule and on budget. Bechtel Energy has transferred control of Train 1 to Cheniere, enabling LNG sales to be reflected in Cheniere's financial statements.
The project's key milestones include: Full notice to proceed issued in June 2022, first LNG production in December 2024, and first cargo loaded in February 2025. As of January 31, 2025, the overall project completion stands at 78.3%, with engineering at 97.6%, procurement at 97.2%, subcontract work at 88.8%, and construction at 45.5% complete.
CCL Stage 3 comprises seven midscale trains with an expected total production capacity of over 10 million tonnes per annum (mtpa) of LNG. Upon completion of all seven trains, the Corpus Christi facility's total production capacity will exceed 25 mtpa of LNG.
Cheniere Energy (NYSE: LNG) ha raggiunto il Completamento Sostanziale del Treno 1 presso il Corpus Christi Stage 3 Liquefaction Project (CCL Stage 3) il 16 marzo 2025, con un anticipo rispetto ai tempi previsti e rispettando il budget. Bechtel Energy ha trasferito il controllo del Treno 1 a Cheniere, consentendo che le vendite di LNG siano riflesse nei bilanci finanziari di Cheniere.
I principali traguardi del progetto includono: l'emissione della notifica completa per procedere a giugno 2022, la prima produzione di LNG a dicembre 2024 e il primo carico caricato a febbraio 2025. Al 31 gennaio 2025, il completamento complessivo del progetto è al 78,3%, con ingegneria al 97,6%, approvvigionamento al 97,2%, lavoro di subappalto all'88,8% e costruzione al 45,5% completata.
Il CCL Stage 3 comprende sette treni di media scala con una capacità totale di produzione attesa di oltre 10 milioni di tonnellate all'anno (mtpa) di LNG. Una volta completati tutti e sette i treni, la capacità totale di produzione dell'impianto di Corpus Christi supererà le 25 mtpa di LNG.
Cheniere Energy (NYSE: LNG) ha logrado la Finalización Sustancial del Tren 1 en el Proyecto de Licuefacción Corpus Christi Etapa 3 (CCL Etapa 3) el 16 de marzo de 2025, antes de lo previsto y dentro del presupuesto. Bechtel Energy ha transferido el control del Tren 1 a Cheniere, permitiendo que las ventas de LNG se reflejen en los estados financieros de Cheniere.
Los hitos clave del proyecto incluyen: la notificación completa para proceder emitida en junio de 2022, la primera producción de LNG en diciembre de 2024 y la primera carga cargada en febrero de 2025. A partir del 31 de enero de 2025, la finalización general del proyecto se sitúa en 78.3%, con ingeniería al 97.6%, adquisiciones al 97.2%, trabajo de subcontratación al 88.8% y construcción al 45.5% completada.
El CCL Etapa 3 comprende siete trenes de mediana escala con una capacidad total de producción esperada de más de 10 millones de toneladas por año (mtpa) de LNG. Una vez que se completen los siete trenes, la capacidad total de producción de la instalación de Corpus Christi superará las 25 mtpa de LNG.
Cheniere Energy (NYSE: LNG)는 2025년 3월 16일에 코퍼스 크리스티 3단계 액화 프로젝트 (CCL 3단계)의 트레인 1의 실질적인 완료를 달성하였으며, 예정보다 앞서 진행되고 예산 내에서 완료되었습니다. Bechtel Energy는 트레인 1의 제어를 Cheniere에 이관하여 LNG 판매가 Cheniere의 재무제표에 반영될 수 있도록 하였습니다.
프로젝트의 주요 이정표는 다음과 같습니다: 2022년 6월에 발행된 전체 진행 통지, 2024년 12월의 첫 LNG 생산, 2025년 2월의 첫 화물 적재. 2025년 1월 31일 기준으로 전체 프로젝트 완료율은 78.3%이며, 엔지니어링이 97.6%, 조달이 97.2%, 하도급 작업이 88.8%, 건설이 45.5% 완료되었습니다.
CCL 3단계는 연간 1000만 톤 (mtpa) 이상의 LNG 생산 능력을 가진 7개의 중형 트레인으로 구성되어 있습니다. 모든 7개의 트레인이 완료되면 코퍼스 크리스티 시설의 전체 생산 능력은 25 mtpa를 초과하게 됩니다.
Cheniere Energy (NYSE: LNG) a atteint l'achèvement substantiel du Train 1 du Projet de liquéfaction de Corpus Christi Étape 3 (CCL Étape 3) le 16 mars 2025, en avance sur le calendrier et dans le respect du budget. Bechtel Energy a transféré le contrôle du Train 1 à Cheniere, permettant ainsi que les ventes de LNG soient reflétées dans les états financiers de Cheniere.
Les principales étapes du projet comprennent : l'avis complet de démarrage délivré en juin 2022, la première production de LNG en décembre 2024 et le premier chargement effectué en février 2025. Au 31 janvier 2025, l'achèvement global du projet est de 78,3%, avec l'ingénierie à 97,6%, l'approvisionnement à 97,2%, le travail de sous-traitance à 88,8% et la construction à 45,5% achevée.
Le CCL Étape 3 comprend sept trains de taille intermédiaire avec une capacité de production totale attendue de plus de 10 millions de tonnes par an (mtpa) de LNG. Une fois les sept trains achevés, la capacité de production totale de l'installation de Corpus Christi dépassera 25 mtpa de LNG.
Cheniere Energy (NYSE: LNG) hat am 16. März 2025 den wesentlichen Abschluss von Train 1 im Corpus Christi Stage 3 Liquefaction Project (CCL Stage 3) erreicht, und zwar vor dem Zeitplan und im Budgetrahmen. Bechtel Energy hat die Kontrolle über Train 1 an Cheniere übertragen, was es ermöglicht, dass LNG-Verkäufe in den Finanzberichten von Cheniere ausgewiesen werden.
Die wichtigsten Meilensteine des Projekts umfassen: die vollständige Genehmigung zur Fortsetzung, die im Juni 2022 erteilt wurde, die erste LNG-Produktion im Dezember 2024 und die erste Beladung im Februar 2025. Stand 31. Januar 2025 liegt der Gesamtfortschritt des Projekts bei 78,3%, wobei die Ingenieurleistungen bei 97,6%, die Beschaffung bei 97,2%, die Subunternehmerarbeiten bei 88,8% und die Bauarbeiten bei 45,5% abgeschlossen sind.
CCL Stage 3 umfasst sieben mittlere Züge mit einer erwarteten Gesamtproduktionskapazität von über 10 Millionen Tonnen pro Jahr (mtpa) LNG. Nach Abschluss aller sieben Züge wird die Gesamtproduktionskapazität der Anlage in Corpus Christi 25 mtpa LNG überschreiten.
- Train 1 completed ahead of schedule and on budget
- Project execution showing strong progress with 78.3% overall completion
- LNG sales from Train 1 to be immediately reflected in financial statements
- Additional 10 mtpa production capacity to be added through Stage 3 expansion
- Construction phase still only 45.5% complete
Insights
Cheniere Energy's announcement of substantial completion of Train 1 at the Corpus Christi Stage 3 Project marks a significant operational achievement with immediate financial implications. This milestone was reached ahead of schedule and on budget - a remarkable accomplishment in the capital-intensive LNG industry where delays and cost overruns are common.
With this completion, financial results from LNG sales from Train 1 will now flow directly to Cheniere's bottom line, creating an immediate new revenue stream that will positively impact upcoming quarterly results. This represents the first of seven midscale trains in the Stage 3 expansion, which collectively will add over 10 million tonnes per annum (mtpa) of LNG production capacity.
The overall project execution demonstrates exceptional operational discipline, with the project at 78.3% completion as of January 31, 2025. The accelerated timeline - from notice to proceed in June 2022 to first cargo in February 2025 - validates Cheniere's brownfield expansion model, which offers significant cost and timing advantages over greenfield developments.
This Train 1 completion derisks the remaining construction process and strengthens Cheniere's competitive position in the global LNG market at a time of strong worldwide demand. When all seven trains achieve substantial completion, Cheniere's Corpus Christi facility will reach a total production capacity exceeding 25 mtpa, solidifying its position as a premier global LNG supplier with expanded cash flow generation capabilities.
“The substantial completion of the first train of CCL Stage 3 - ahead of schedule and on budget - marks another important milestone for Cheniere and further builds upon the track record of excellence in execution consistently delivered by the Cheniere and Bechtel teams,” said Jack Fusco, Cheniere’s President and Chief Executive Officer. “We remain focused on safely and efficiently bringing the remaining CCL Stage 3 trains online ahead of schedule, providing much-needed new LNG supply to the global market, and creating long-term value for our stakeholders by growing the
Full notice to proceed on CCL Stage 3 was issued to Bechtel by Cheniere in June 2022, with first LNG production from Train 1 achieved in December 2024 and the first cargo loaded in February 2025. CCL Stage 3 consists of seven midscale trains, with an expected total production capacity of over 10 million tonnes per annum (“mtpa”) of LNG. As of January 31, 2025, overall project completion for CCL Stage 3 was
About Cheniere
Cheniere Energy, Inc. is the leading producer and exporter of LNG in
For additional information, please refer to the Cheniere website at www.cheniere.com and Annual Report on Form 10-K for the year ended December 31, 2024, filed with the Securities and Exchange Commission.
Forward-Looking Statements
This press release contains certain statements that may include “forward-looking statements” within the meanings of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. All statements, other than statements of historical or present facts or conditions, included herein are “forward-looking statements.” Included among “forward-looking statements” are, among other things, (i) statements regarding Cheniere’s financial and operational guidance, business strategy, plans and objectives, including the development, construction and operation of liquefaction facilities, (ii) statements regarding regulatory authorization and approval expectations, (iii) statements expressing beliefs and expectations regarding the development of Cheniere’s LNG terminal and pipeline businesses, including liquefaction facilities, (iv) statements regarding the business operations and prospects of third-parties, (v) statements regarding potential financing arrangements, (vi) statements regarding future discussions and entry into contracts, (vii) statements relating to Cheniere’s capital deployment, including intent, ability, extent, and timing of capital expenditures, debt repayment, dividends, share repurchases and execution on the capital allocation plan, and (viii) statements relating to our goals, commitments and strategies in relation to environmental matters. Although Cheniere believes that the expectations reflected in these forward-looking statements are reasonable, they do involve assumptions, risks and uncertainties, and these expectations may prove to be incorrect. Cheniere’s actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in Cheniere’s periodic reports that are filed with and available from the Securities and Exchange Commission. You should not place undue reliance on these forward-looking statements, which speak only as of the date of this press release. Other than as required under the securities laws, Cheniere does not assume a duty to update these forward-looking statements.
View source version on businesswire.com: https://www.businesswire.com/news/home/20250316960570/en/
Cheniere Energy, Inc.
Investors
Randy Bhatia
713-375-5479
Frances Smith
713-375-5753
Media Relations
Randy Bhatia
713-375-5479
Bernardo Fallas
713-375-5593
Source: Cheniere Energy, Inc.