Lumina Gold Announces Key Power Approvals for the Cangrejos Project
Lumina Gold (LMGDF) has secured important power infrastructure approvals for its Cangrejos gold-copper project. On January 15, 2025, CELEC approved the definitive feasibility level designs for connecting to Ecuador's national grid, including two dedicated transformers at La Avanzada substation and a 20-kilometer 138 kV transmission line to the Project.
The Feasibility Study, led by Ausenco Engineering Canada ULC, is 92% complete and on track for Q2 2025 completion. Key completed components include updated mineral resource estimates, mine planning, process facility design, infrastructure engineering, metals marketing study, vendor quotes, and major equipment selection. The team is now finalizing capital and operating cost estimates.
The Environmental Impact Study (EIS) is progressing as planned, with submission to Ecuador's government expected in mid-2025. The company aims to receive its Environmental License for construction and operation by early 2026.
Lumina Gold (LMGDF) ha ottenuto importanti approvazioni per le infrastrutture elettriche relative al suo progetto oro-rame Cangrejos. Il 15 gennaio 2025, CELEC ha approvato i progetti definitivi di fattibilità per la connessione alla rete nazionale dell'Ecuador, inclusi due trasformatori dedicati presso la sottostazione di La Avanzada e una linea di trasmissione di 20 chilometri a 138 kV verso il progetto.
Lo Studio di Fattibilità, guidato da Ausenco Engineering Canada ULC, è completato al 92% e dovrebbe essere terminato nel secondo trimestre del 2025. Tra i componenti completati ci sono le stime aggiornate delle risorse minerarie, la pianificazione mineraria, il design delle strutture di processo, l'ingegnerizzazione delle infrastrutture, lo studio di marketing dei metalli, i preventivi dei fornitori e la selezione delle attrezzature principali. Il team sta ora finalizzando le stime dei costi di capitale e operativi.
Lo Studio di Impatto Ambientale (EIS) sta progredendo come previsto, con la presentazione al governo dell'Ecuador attesa per la metà del 2025. L'azienda punta a ricevere la sua Licenza Ambientale per la costruzione e l'operazione entro inizio 2026.
Lumina Gold (LMGDF) ha obtenido importantes aprobaciones de infraestructura eléctrica para su proyecto de oro-cobre Cangrejos. El 15 de enero de 2025, CELEC aprobó los diseños definitivos de viabilidad para conectar con la red nacional de Ecuador, incluidos dos transformadores dedicados en la subestación La Avanzada y una línea de transmisión de 20 kilómetros a 138 kV hacia el proyecto.
El Estudio de Viabilidad, liderado por Ausenco Engineering Canada ULC, está completado en un 92% y se prevé que termine en el segundo trimestre de 2025. Los componentes completados incluyen estimaciones actualizadas de recursos minerales, planificación minera, diseño de la instalación de procesamiento, ingeniería de infraestructura, estudio de marketing de metales, cotizaciones de proveedores y selección de equipos principales. El equipo está finalizando ahora las estimaciones de costos de capital y operativos.
El Estudio de Impacto Ambiental (EIS) avanza según lo previsto, con la presentación al gobierno de Ecuador esperada para mediados de 2025. La empresa aspira a recibir su Licencia Ambiental para la construcción y operación a principios de 2026.
루미나 골드 (LMGDF)는 카그레호스 금-구리 프로젝트와 관련하여 중요한 전력 인프라 승인을 확보했습니다. 2025년 1월 15일, CELEC는 에콰도르 국가 전력망에 연결하기 위한 최종 타당성 설계를 승인했으며, 여기에는 라 아반사다 변전소에 두 개의 전용 변압기와 프로젝트까지의 20킬로미터 138kV 송전선이 포함됩니다.
타당성 조사는 Ausenco Engineering Canada ULC가 주도하며 92% 완료되었고 2025년 2분기 완료 예정입니다. 완료된 주요 구성 요소에는 업데이트된 광물 자원 추정치, 광산 계획, 처리 시설 설계, 인프라 공학, 금속 마케팅 연구, 공급업체 견적 및 주요 장비 선택이 포함됩니다. 팀은 이제 자본 및 운영 비용 추정을 마무리하고 있습니다.
환경 영향 연구 (EIS)는 계획대로 진행 중이며, 2025년 중반에 에콰도르 정부에 제출될 예정입니다. 회사는 2026년 초까지 건설 및 운영을 위한 환경 면허를 받는 것을 목표로 하고 있습니다.
Lumina Gold (LMGDF) a obtenu d'importantes approbations pour les infrastructures électriques de son projet d'or et de cuivre Cangrejos. Le 15 janvier 2025, CELEC a approuvé les conceptions définitives de faisabilité pour se connecter au réseau national équatorien, y compris deux transformateurs dédiés à la sous-station de La Avanzada et une ligne de transmission de 20 kilomètres à 138 kV vers le projet.
Le Étude de Faisabilité, dirigé par Ausenco Engineering Canada ULC, est achevé à 92 % et sur la bonne voie pour une finalisation au deuxième trimestre 2025. Les principales composantes finalisées comprennent des estimations actualisées des ressources minérales, la planification minière, le design de l'installation de traitement, l'ingénierie des infrastructures, l'étude de marketing des métaux, les devis des fournisseurs et la sélection des équipements majeurs. L'équipe finalise actuellement les estimations des coûts d'investissement et d'exploitation.
Le Étude d'Impact Environnemental (EIS) progresse comme prévu, avec une soumission au gouvernement équatorien prévue pour la mi-2025. L'entreprise vise à obtenir sa Licence Environnementale pour la construction et l'exploitation d'ici début 2026.
Lumina Gold (LMGDF) hat wichtige Genehmigungen für die Strominfrastruktur seines Cangrejos-Gold-Kupfer-Projekts erhalten. Am 15. Januar 2025 genehmigte CELEC die endgültigen Machbarkeitsentwürfe für den Anschluss an das nationale Stromnetz von Ecuador, einschließlich zweier spezieller Transformatoren in der Umspannstation La Avanzada und einer 20 Kilometer langen 138-kV-Übertragungsleitung zum Projekt.
Die Machbarkeitsstudie, die von Ausenco Engineering Canada ULC geleitet wird, ist zu 92 % abgeschlossen und auf Kurs für die Fertigstellung im 2. Quartal 2025. Zu den abgeschlossenen Hauptkomponenten gehören aktualisierte Schätzungen der Mineralressourcen, Bergbauplanung, Entwurf der Verarbeitungseinrichtung, Infrastrukturengineering, Metallmarketingstudie, Angebote von Anbietern und die Auswahl wichtiger Geräte. Das Team finalisiert derzeit die Kostenschätzungen für Kapital und Betrieb.
Die Umweltverträglichkeitsprüfung (EIS) schreitet planmäßig voran, und die Einreichung bei der Regierung von Ecuador wird für Mitte 2025 erwartet. Das Unternehmen strebt an, bis Anfang 2026 eine Umweltgenehmigung für Bau und Betrieb zu erhalten.
- Secured power infrastructure approvals for grid connection
- Feasibility Study 92% complete and on schedule
- Reserved area for transmission infrastructure at La Avanzada substation
- None.
Other Project Updates
Ausenco Engineering Canada ULC, the lead engineering contractor for the feasibility study for the Project (the "Feasibility Study"), has completed
- An updated mineral resource estimate, mine plan and schedule;
- Process flowsheet and facility design based on metallurgical testwork;
- Project infrastructure siting, engineering and design;
- Metals marketing study;
- Receipt of vendor quotes; and
- Selection of major project equipment.
The Project team is now focused on developing final capital and operating cost estimates to support the study's economic model.
Work for the Environmental Impact Study ("EIS") is progressing on schedule. This work will allow for the submission of the EIS to the Government of
About Lumina Gold
Lumina Gold Corp. (TSXV: LUM) is a
Follow us on: Twitter, Linkedin or Facebook.
Further details are available on the Company's website at https://luminagold.com/. To receive future news releases please sign up at https://luminagold.com/contact.
LUMINA GOLD CORP.
Signed: "Marshall Koval"
Marshall Koval, President & CEO, Director
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.
Cautionary Note Regarding Forward-Looking Information
Certain statements and information herein, including all statements that are not historical facts, contain forward-looking statements and forward-looking information within the meaning of applicable securities laws. Such forward-looking statements or information include but are not limited to statements or information with respect to: completion and anticipated timing of the Feasibility Study; connecting the Project to the National Grid and the designs for connection; the future energy demand of the Project; completing substation and power line construction; the commitment from CELEC to reserve the necessary area required to build the transmission infrastructure; completion and anticipated timing of the EIS submission; and receiving the Environmental License for the construction and operation of the Project by early 2026. Often, but not always, forward-looking statements or information can be identified by the use of words such as "will" or "projected" or variations of those words or statements that certain actions, events or results "will", "could", "are proposed to", "are planned to", "are expected to" or "are anticipated to" be taken, occur or be achieved.
With respect to forward-looking statements and information contained herein, the Company has made numerous assumptions including among other things, assumptions about general business and economic conditions, the prices of gold and copper, anticipated costs and expenditures, availability of power, the timely receipt of necessary approvals and licenses, the ability to meet current and future obligations, the Company's ability to comply with environmental laws, no unplanned delays or interruptions, the parameters of the transmission infrastructure, and expected
Although management of the Company believes that the assumptions made and the expectations represented by such statements or information are reasonable, there can be no assurance that a forward-looking statement or information herein will prove to be accurate. Forward-looking statements and information by their nature are based on assumptions and involve known and unknown risks, uncertainties and other factors which may cause the Company's actual results, performance or achievements, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. These factors include, but are not limited to: risks associated with the business of the Company; business and economic conditions in the mining industry generally; the supply and demand for labour and other project inputs; changes in commodity prices; changes in interest and currency exchange rates; risks relating to inaccurate geological and engineering assumptions (including with respect to the tonnage, grade and recoverability of reserves and resources); risks relating to unanticipated operational difficulties (including failure of equipment or processes to operate in accordance with specifications or expectations, cost escalation, unavailability of materials and equipment, government action or delays in the receipt of government approvals, industrial disturbances or other job action, and unanticipated events related to health, safety and environmental matters); risks relating to adverse weather conditions; political risk and social unrest; changes in general economic conditions or conditions in the financial markets; and other risk factors as detailed from time to time in the Company's continuous disclosure documents filed with Canadian securities administrators. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws.
View original content to download multimedia:https://www.prnewswire.com/news-releases/lumina-gold-announces-key-power-approvals-for-the-cangrejos-project-302362528.html
SOURCE Lumina Gold Corp.
FAQ
When will Lumina Gold (LMGDF) complete the Feasibility Study for Cangrejos project?
What power infrastructure approvals did LMGDF receive for Cangrejos project?
When does Lumina Gold expect to receive the Environmental License for Cangrejos?
What is the current completion status of LMGDF's Cangrejos Feasibility Study?