Largo Reports Fourth Quarter and Full Year 2022 Operational and Sales Results; Provides 2023 Guidance
Largo reported Q4 and FY 2022 operational results, achieving 10,436 tonnes of vanadium pentoxide (V2O5) production, slightly up from 10,319 tonnes in 2021. Q4 2022 production was 2,004 tonnes, stable compared to Q4 2021. Sales totaled 11,091 tonnes in 2022, down 3% year-over-year. The company faced operational challenges due to contractor transitions and heavy rainfall, leading to a 36% increase in rain-related downtime. Resulting Q1 2023 production guidance is 1,900 – 2,200 tonnes. Strong vanadium demand was noted in the aerospace sector, with prices rising to $10.08 per lb as of January 2023. Largo secured additional debt facilities for $45 million to support operations and capital projects.
- Strong demand for vanadium in the aerospace sector and VRFB deployments.
- Increased average V2O5 prices, reaching $10.08 per lb in January 2023, up from $9.44.
- Secured $45 million in debt facilities to support working capital and capital projects.
- Operational challenges due to contractor transitions resulted in 16 days of downtime.
- Q4 2022 V2O5 production was impacted by heavy rainfall, affecting output.
- Sales declined 3% in 2022 compared to 2021.
All amounts expressed are in
Q4 and FY 2022 Highlights
- Quarterly V2O5 production of 2,004 tonnes (4.4 million lbs1) in Q4 2022 vs. 2,003 tonnes in Q4 2021; Annual V2O5 production of 10,436 tonnes (23.0 million lbs1) in 2022 vs. 10,319 tonnes in 2021
-
Quarterly global V2O5 recovery of
74.7% in Q4 2022 vs.76.0% in Q4 2021; Annual global V2O5 recovery of79.1% in 2022 vs.79.7% in 2021 -
V2O5 production in Q4 2022 was largely impacted by a lower quantity of mined material available due in part to the Company's mining contractor transition in
September 2022 ; As a result, the low availability of mined material stockpiles was insufficient to effectively mitigate the impacts of corrective maintenance inNovember 2022 and heavy rain inDecember 2022 at MaracásMenchen Mine - Quarterly sales of 2,774 tonnes of V2O5 equivalent (inclusive of 118 tonnes of purchased material) in Q4 2022 vs. 2,899 tonnes in Q4 2021; Annual V2O5 equivalent sales of 11,091 (inclusive of 1,057 tonnes of purchased material) tonnes in 2022 vs. 11,393 tonnes in 2021 and within sales guidance of 11,000 – 12,000 tonnes
-
In Q4 2022, vanadium demand remained steady in the steel and chemical sectors, while the aerospace and vanadium redox flow battery ("VRFB") sectors saw considerable growth; In Europe, average V2O5 prices increased approximately
18% to per lb at the end of the quarter, and have risen to$9.44 as of$10.08 January 20, 2023 -
Largo Clean Energy (“LCE”) and Ansaldo Green Tech (“Ansaldo”) continued their negotiations to form a joint venture for the manufacture and commercial deployment of vanadium redox flow batteries (“VRFB”) in the European, African and
Middle East power generation markets; The exclusivity agreement between LCE and Ansaldo in accordance with the previously announced non-binding MOU has been extended toMarch 31, 2023 to allow for the completion of ongoing negotiations -
The Company progressed with the construction of its ilmenite concentration plant at its Maracás
Menchen Mine in Q4 2022; Received all required flotation structures and is finalizing the building of its desliming, flotation, filtration, warehouse and pipe rack structures; Commissioning to be completed in Q2 2023 -
The Company received 'Company of the Year in the Mineral Sector' for its work in Social Governance from
Brasil Mineral magazine and ‘Company of the Year’ fromCompanhia Baiana de Pesquisa Mineral (“CBPM”); These recognitions are the result of the Company’s dedication to executing on our on going Environment, Social and Governance (“ESG”) initiatives with the goal of progressing sustainable development at Largo
Largo Reports Fourth Quarter and Full Year 2022 Operational and Sales Results; Provides 2023 Guidance (Photo: Business Wire)
He continued: “In the coming year, we expect to meet our planned objectives to fully realize the value of our tier one vanadium company, including annual guidance for 2023, the completion of our ilmenite concentration plant, and the delivery of our inaugural VRFB for Enel in the second quarter of 2023.” He concluded: “While our negotiation with Ansaldo continues, LCE’s senior management continue to maintain their efforts on core development and system improvements required to support the current and future needs of the long duration energy storage sector. We are pleased to see a strengthening in vanadium demand, driven by strong high purity aerospace inquiries and new VRFB deployments, which has led to price increases in recent months.”
Maracás Menchen Mine Operational and Sales Results
Q4 2022 |
Q4 2021 |
2022 |
2021 |
|||||
|
|
|
|
|
||||
Total Ore Mined (tonnes) |
326,552 |
277,783 |
1,359,927 |
1,248,967 |
||||
Ore Grade Mined - Effective Grade (%)2 |
0.96 |
1.00 |
1.11 |
1.12 |
||||
|
|
|
|
|
||||
Concentrate Produced (tonnes) |
90,797 |
86,129 |
406,951 |
398,847 |
||||
Grade of Concentrate (%) |
2.94 |
3.13 |
3.18 |
3.23 |
||||
Global Recovery (%)3 |
74.7 |
76.0 |
79.1 |
79.7 |
||||
|
|
|
|
|
||||
V2O5 produced (Flake + Powder) (tonnes) |
2,004 |
2,003 |
10,436 |
10,319 |
||||
V2O5 produced (equivalent pounds) 1 |
4,420,263 |
4,415,854 |
23,007,414 |
22,749,473 |
||||
Total V2O5 equivalent sold (tonnes) |
2,774 |
2,899 |
11,091 |
11,393 |
||||
Produced V2O5 equivalent sold (tonnes) |
2,656 |
2,843 |
10,034 |
10,864 |
||||
Purchased V2O5 equivalent sold (tonnes) |
118 |
56 |
1,057 |
529 |
||||
|
|
|
|
|
Q4, FY 2022 and Other Highlights
-
Quarterly Operational Results Impacted by a Mining Contractor Change, Mine Sequencing and Heavy Rainfall: In Q4 2022, V2O5 production from the Maracás
Menchen Mine of 2,004 tonnes was in line with the 2,003 tonnes produced in Q4 2021. As a result of the Company's mining contractor transition and corrective maintenance at the leaching and deammoniator areas, 804 tonnes of V2O5 were produced inOctober 2022 . Production of 605 tonnes inNovember 2022 was affected by changes in mining sequence and 596 tonnes inDecember 2022 was affected by heavy rains at the Company's operations. Annual V2O5 production was 10,436 tonnes in 2022, being largely in line with the 10,319 tonnes produced in 2021. Lower annual production was due to preventative and corrective maintenance at Company’s plant facility in Maracás in Q1 2022, a planned kiln and cooler refractory refurbishment in Q3 2022 and heavy rainfall in December. In Q4 2022, global recoveries3 averaged74.7% as compared to the76.0% averaged in Q4 2021. The Company achieved an annual average global V2O5 recovery3 rate of79.1% in 2022. The Company mined 1,359,927 tonnes of ore with an effective V2O5 grade2 of1.11% in 2022 compared to 1,248,967 tonnes with an effective V2O5 grade2 of1.12% in 2021. The impact on the Company’s global recovery3 and mined ore in 2022 is primarily due to the reasons mentioned above. -
Rainfall Impact and Mitigation Efforts – Impacts to
January 2023 Production and Sales Expected: Despite rain-related mitigation efforts implemented at the end of 2021, the Company’s MaracásMenchen Mine experienced approximately36% more rainfall inDecember 2022 compared toDecember 2021 , and more than76% more rainfall on a single day during the same comparative month. This resulted in approximately 16 days of operational downtime inDecember 2022 andJanuary 2023 , during which time the Company performed preventative maintenance measure such as kiln refractory and electrostatic precipitator (“ESP”) repairs, previously planned forFebruary 2023 . In 2021, the Company constructed a diversion channel surrounding theCampbell Pit and upgraded its pumping system capacity to mitigate rainwater accumulation inside the pit. InDecember 2022 , the diversion channel successfully mitigated rain from entering the pit downstream, however, unexpected levels of heavy rainfall caused significant rainfall accumulation inside the pit. The Company plans to further upgrade its pumping system capacity and expects to build additional mined material stockpiles in 2023 to mitigate impacts to mining operations going forward. As a result of these rain-related impacts inDecember 2022 andJanuary 2023 , the Company expects Q1 2023 production and sales ranges of 1,900 – 2,200 tonnes and 2,300 – 2,500 tonnes, respectively. -
Annual Sales Results Within Guidance – Vanadium Prices Reflect Increase in Demand: In Q4 2022, V2O5 equivalent sales were 2,774 tonnes (inclusive of 118 tonnes of purchased material), representing a
4% decrease over Q4 2021. Total V2O5 equivalent sales were 11,091 tonnes (inclusive of 1,057 tonnes of purchased material) in 2022, representing a3% decrease over 2021. Lower sales in Q4 were impacted by the effects of lower production. Stronger vanadium prices exiting the quarter reflected an increase in demand from the high purity aerospace sector and continued growth in VRFB deployments, particularly inChina . The average benchmark price per lb of V2O5 inEurope was exiting the quarter, representing an increase of approximately$9.44 20% from the lows of 2022. As ofJanuary 20, 2023 , the benchmark price per lb of V2O5 inEurope was .$10.08 -
Inaugural VRFB Deployment Progress: During Q4 2022, LCE continued to make additional progress on the delivery of the Enel Green Power España (“EGPE”) contract. Substantially all of the hardware is either in transit or ready for installation at the deployment site in
Spain . The remaining items to be shipped are six of the twelve electrolyte storage containers, which will be shipped inFebruary 2023 and installed inMarch 2023 . Additionally, the Company expects the installation and interconnection of the AC and DC power systems to be completed in Q1 2023. The hot commissioning of the VRFB system as well as provisional acceptance, which requires the completion of as-build drawings, manuals, final punch-list items, and operational testing by EGPE is expected to be completed in Q2 2023. -
New Debt Facilities Secured in
Brazil : InDecember 2022 , the Company secured an additional debt facility of with a bank in$20.0 million Brazil . The facility is for three years, with a 360-day grace period and equal principal repayments due every six months until maturity following the grace period. In addition to a fee of0.7% , accrued interest at a rate of8.20% p.a. is to be paid every six months until maturity. InJanuary 2023 , the Company secured two additional debt facilities with banks inBrazil . The first facility of is for two years, with a 180-day grace period and equal principal repayments due every three months until maturity following the grace period. In addition, accrued interest at a rate of$15.0 million 6.85% p.a. is to be paid every three months. The second facility of is for three years, with a 360-day grace period and equal principal repayments due every six months until maturity following the grace period. In addition to a fee of$10.0 million 0.7% , accrued interest at a rate of8.36% p.a. is to be paid every six months. A portion of theDecember 2022 debt facility was used inDecember 2022 to repay the Company's existing debt facility secured in$15.0 million April 2022 and due for repayment inApril 2023 , with the remaining debt facilities primarily being used to address working capital pressures caused by ongoing capex projects in the first six months of 2023.
2023 Production, Sales and Cost Guidance
Tables summarizing the Company’s 2023 production, sales and cost guidance is provided below. It is expected that the Company will incur higher cash operating costs excluding royalties4 in the first half of 2023 as a result of lower sales in H1 2023, a result of previously noted rain-related operational impacts in Q4 2022 and Q1 2023. In H1 2023, the Company anticipates cash operating costs excluding royalties4 to be above the average cost guidance provided for 2023 with H2 2023 being closer to the lower end.
Tonnes V2O5 |
Q1 |
Q2 |
Q3 |
Q4 |
2023 |
||||||||||
|
Low |
High |
Low |
High |
Low |
High |
Low |
High |
Low |
High |
|||||
Productioni |
1,900 |
2,200 |
3,000 |
3,200 |
3,050 |
3,300 |
3,050 |
3,300 |
11,000 |
12,000 |
|||||
Sales |
2,300 |
2,500 |
2,300 |
2,500 |
2,850 |
3,150 |
2,850 |
3,150 |
10,300 |
11,300 |
|||||
i. The annual 2023 sales guidance does not include purchased material. |
Cash Operating Cost Excluding Royalties ($/lb sold)4 |
|
|
Vanadium Distribution Costs |
|
|
Corporate and |
|
|
Largo Clean Energy General and Administrative Expenses |
|
2023 Capital Expenditures Guidance
In 2023, the Company plans to invest approximately
Sustaining Capital Expenditures |
|
|
Capitalized Stripping Capital Expenditures |
|
|
Ilmenite Concentration Plant Capital Expenditures |
|
|
Dry Magnetic Separator Capital Expenditure |
|
|
Carry-Over Capital Expenditures |
|
Management has made the decision to postpone the Company's existing plans to further develop its titanium dioxide ("TiO2") pigment plant until additional funds are made available, either internally or externally. At this time, the Company is exploring alternative debt financing or strategic association options with advisors and will provide an update as things progress.
About Largo
Largo has a long and successful history as one of the world’s preferred vanadium companies through the supply of its VPURE™ and VPURE+™ products, which are sourced from one of the world's highest-grade vanadium deposits at the Company's Maracás
Largo’s common shares trade on the
Cautionary Statement Regarding Forward-looking Information:
This press release contains “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian and
The following are some of the assumptions upon which forward-looking information is based: that general business and economic conditions will not change in a material adverse manner; demand for, and stable or improving price of V2O5 and other vanadium commodities; receipt of regulatory and governmental approvals, permits and renewals in a timely manner; that the Company will not experience any material accident, labour dispute or failure of plant or equipment or other material disruption in the Company’s operations at the Maracás
Forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". All information contained in this news release, other than statements of current and historical fact, is forward looking information. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Largo or Largo Clean Energy to be materially different from those expressed or implied by such forward-looking statements, including but not limited to those risks described in the annual information form of Largo and in its public documents filed on www.sedar.com and available on www.sec.gov from time to time. Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made. Although management of Largo has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Largo does not undertake to update any forward-looking statements, except in accordance with applicable securities laws. Readers should also review the risks and uncertainties sections of Largo's annual and interim MD&As which also apply.
Trademarks are owned by
Future Oriented Financial Information:
Any financial outlook or future oriented financial information contained in this press release, as such term is defined by applicable securities laws, has been approved by management of Largo as of the date hereof and is provided for the purpose of providing information about management's current expectations and plans relating to the Company's 2023 guidance. Readers are cautioned that any such future oriented financial information contained herein should not be used for purposes other than those for which it is disclosed herein. The Company and its management believe that the prospective financial information as to the Company's anticipated 2023 guidance has been prepared on a reasonable basis, reflecting management's best estimates and judgments. However, because this information is highly subjective, it should not be relied on as necessarily indicative of future results.
Non-GAAP5 Measures
The Company uses certain non-GAAP financial performance measures in this press release, which are described in the following section.
Cash Operating Costs
The Company’s press release refers to cash operating costs per pound, a non-GAAP performance measure, in order to provide investors with information about a key measure used by management to monitor performance. This information is used to assess how well the Maracás
___________________________
1 Conversion of tonnes to pounds, 1 tonne = 2,204.62 pounds or lbs.
2 Effective grade represents the percentage of magnetic material mined multiplied by the percentage of V2O5 in the magnetic concentrate.
3 Global recovery is the product of crushing recovery, milling recovery, kiln recovery, leaching recovery and chemical plant recovery.
4 Cash operating costs excluding royalties per pound reported are on a non-GAAP basis. Refer to the “Non-GAAP Measures” section of this press release.
5 GAAP – Generally Accepted Accounting Principles
View source version on businesswire.com: https://www.businesswire.com/news/home/20230124005475/en/
Investor Relations
Senior Manager, External Relations
+1.416.861.9778
aguthrie@largoinc.com
Source:
FAQ
What were Largo's Q4 2022 production results for V2O5?
How much vanadium did Largo sell in FY 2022?
What is Largo's production guidance for Q1 2023?
What is the current price of V2O5 according to Largo's press release?