Largo Reports First Quarter 2023 Operational and Sales Results; Installation of its 6.1 MWh Vanadium Flow Battery and Construction of its Ilmenite Plant Nears Completion
Largo Inc. (LGO) reported its Q1 2023 operational results, producing 2,111 tonnes of vanadium pentoxide (V2O5), a decrease from 2,442 tonnes in Q1 2022. Despite heavy rains impacting high-grade ore availability, sales rose 28% to 2,849 tonnes compared to 2,232 tonnes in Q1 2022. The company is on track with production guidance and is set to complete its ilmenite concentration plant by Q2 2023. Largo Clean Energy is advancing its 6.1 MWh vanadium redox flow battery installation for Enel Green Power in Spain. Furthermore, Largo has joined the Long Duration Energy Storage Council to support global decarbonization efforts. Production challenges stem from adverse weather, but demand for vanadium, especially in the aerospace sector, remains strong.
- Sales increased by 28% to 2,849 tonnes of V2O5 equivalent in Q1 2023.
- Production levels are within guidance despite challenges.
- The ilmenite concentration plant is on schedule for commissioning in Q2 2023.
- Strong market demand for vanadium, particularly driven by the aerospace sector.
- V2O5 production decreased from 2,442 tonnes in Q1 2022 to 2,111 tonnes in Q1 2023.
- Effective V2O5 grade mined fell to 0.81% from 1.27% the previous year due to heavy rains limiting ore availability.
Q1 2023 and Other Highlights
- Quarterly V2O5 production of 2,111 tonnes (4.6 million lbs1) in Q1 2023 vs. 2,442 tonnes produced in Q1 2022; In the upper range of Company’s quarterly production guidance of 1,900-2,200 tonnes for Q1 2023
-
Quarterly sales of 2,849 tonnes of V2O5 equivalent (inclusive of 245 tonnes of purchased material) in Q1 2023, a
28% increase over the 2,232 equivalent tonnes sold (inclusive of 79 tonnes of purchased material) in Q1 2022 and well above the Company’s quarterly guidance range of 2,300-2,500 tonnes for Q1 2023 -
Construction of the Company’s ilmenite concentration plant progressed as planned in Q1 2023; The Company expects to complete commissioning in Q2 2023 and initiate a gradual ramp up of ilmenite concentrate production in early Q3 2023 as a new by-product of its vanadium operations in
Brazil - Largo Clean Energy (“LCE”) continued with the installation of its 6.1-megawatt hour (“MWh”) vanadium redox flow battery (“VRFB”) for Enel Green Power España (“EGPE”) in Q1 2023 with a majority of the site equipment installed
-
In
April 2023 , Largo completed its registration to become a member of theLong Duration Energy Storage Council , a global non-profit working group to accelerate the decarbonisation of the world through the acceleration of long duration energy storage - LCE and Ansaldo Green Tech (“Ansaldo”) continue to explore business opportunities to address the identified needs in the European energy sector. Discussions between LCE and Ansaldo have progressed beyond the stage of a memorandum of understanding ("MOU") to the stage of final agreement negotiations. While the exclusivity period contained in the previously announced non-binding MOU has expired, both parties continue negotiations and an update will be provided at the appropriate time
Largo Reports First Quarter 2023 Operational and Sales Results; Installation of its 6.1 MWh Vanadium Flow Battery and Construction of its Ilmenite Plant Nears Completion (Photo: Business Wire)
Maracás Menchen Mine Operational and Sales Results
Q1 2023 |
Q1 2022 |
|||
|
|
|
||
Total Ore Mined (tonnes) |
341,967 |
303,652 |
||
Ore Grade Mined - Effective Grade (%)2 |
0.81 |
1.27 |
||
|
|
|
||
Concentrate Produced (tonnes) |
78,695 |
92,324 |
||
Grade of Concentrate (%) |
2.99 |
3.21 |
||
Global Recovery (%)3 |
83.0 |
77.5 |
||
|
|
|
||
V2O5 produced (Flake + Powder) (tonnes) |
2,111 |
2,442 |
||
V2O5 produced (equivalent pounds) 1 |
4,653,953 |
5,383,682 |
||
Total V2O5 equivalent sold (tonnes) |
2,849 |
2,232 |
||
Produced V2O5 equivalent sold (tonnes) |
2,604 |
2,153 |
||
Purchased V2O5 equivalent sold (tonnes) |
245 |
79 |
||
|
Q1 2023 Operational and Sales Overview
-
Heavy Rains and Low Massive Ore Availability Impacts Quarterly Production Results in Q1 2023: V2O5 production in January was 354 tonnes, with 843 tonnes produced in February and 914 tonnes produced in March, for a total of 2,111 tonnes produced. Production in Q1 2023 was largely impacted by low ore availability due in part to the heavy rains at the mine in
December 2022 . Consequently, the Company performed its planned kiln maintenance and refractory refurbishment inJanuary 2023 . In Q1 2023, global recoveries3 averaged83.0% , being7% higher than the77.5% averaged in Q1 2022 and11% higher than the74.7% achieved in Q4 2022. In Q1 2023, a transition of the Company’s mining contractor was completed and the Company mined 341,967 tonnes of ore with an effective V2O5 grade2 of0.81% compared to 303,652 tonnes with an effective V2O5 grade2 of1.27% in Q1 2022. The impact to ore grade mined was due in part to the effects of low massive ore availability due to the heavy rains as noted previously.
-
Strong Sales Results in Q1 2023 Supported by Strong Spot Market Demand – China Leading the Way with VRFBs: In Q1 2023, the Company sold 2,849 tonnes of V2O5 equivalent (inclusive of 245 tonnes of purchased material), representing an increase of
28% over the 2,232 tonnes (inclusive of 79 tonnes of purchased material) sold in Q1 2022. In Q1 2023, spot demand for vanadium remained strong, primarily due to higher-than-expected demand from the aerospace sector. AtVanitec's 12th Energy Storage Committee meeting inChengdu, China in March, several announcements were made regarding the Chinese VRFB sector, including demand forecasts for expected VRFB manufacturing capacity. The cumulative installed capacity of electrochemical energy storage inChina is expected to reach 100 gigawatts (“GW”) by 2030, with VRFBs expected to represent30% of this capacity or approximately 180 gigawatt hours (“GWh”) using an average duration of 6 hours. It is estimated that 180 GWh of vanadium electrolyte would require approximately 1.5 million tonnes of V2O5 or approximately 7.5x current global production levels.
-
Inaugural VCHARGE VRFB Installation in
Spain Nears Completion in Q1 2023: LCE continued to progress with the delivery of its VRFB system for EGPE during Q1 2023. All required hardware for the installation was delivered and LCE's field service team completed a significant portion of the system installation, including the alternating current ("AC") power systems, chiller system, LCE’s power containers and electrolyte storage containers. The Company expects hot commissioning of the VRFB system to be completed inJune 2023 , however provisional acceptance by EGPE is now expected in Q3 2023 due in part to delays associated with the finalization of certain agreements and the receipt of government documentation required for the provision of services by qualified technicians.
- Ramp Up of Ilmenite Concentrate Production Expected in Early Q3 2023: Following the anticipated completion of construction and commissioning of its ilmenite concentration plant in Q2 2023, the Company expects to begin producing ilmenite concentrate in early Q3 2023. The Company expects a gradual ramp up of ilmenite production in Q3 2023 with the expectation of building sufficient stockpiles of produced material for sale in early 2024. The Company continues to explore alternative debt financing or strategic association options with regard to developing its titanium dioxide ("TiO2") pigment plant. Currently, there are no capital expenditure obligations for this plant in 2023, and the Company will provide further updates as required.
About Largo
Largo has a long and successful history as one of the world’s preferred vanadium companies through the supply of its VPURETM and VPURE+TM products, which are sourced from one of the world's highest-grade vanadium deposits at the Company's Maracás
Largo’s common shares trade on the
Cautionary Statement Regarding Forward-looking Information:
This press release contains “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian and
The following are some of the assumptions upon which forward-looking information is based: that general business and economic conditions will not change in a material adverse manner; demand for, and stable or improving price of V2O5 and other vanadium commodities; receipt of regulatory and governmental approvals, permits and renewals in a timely manner; that the Company will not experience any material accident, labour dispute or failure of plant or equipment or other material disruption in the Company’s operations at the Maracás
Forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". All information contained in this news release, other than statements of current and historical fact, is forward looking information. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Largo or Largo Clean Energy to be materially different from those expressed or implied by such forward-looking statements, including but not limited to those risks described in the annual information form of Largo and in its public documents filed on www.sedar.com and available on www.sec.gov from time to time. Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made. Although management of Largo has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Largo does not undertake to update any forward-looking statements, except in accordance with applicable securities laws. Readers should also review the risks and uncertainties sections of Largo's annual and interim MD&As which also apply.
Trademarks are owned by
______________________________
1 Conversion of tonnes to pounds, 1 tonne = 2,204.62 pounds or lbs.
2 Effective grade represents the percentage of magnetic material mined multiplied by the percentage of V2O5 in the magnetic concentrate.
3 Global recovery is the product of crushing recovery, milling recovery, kiln recovery, leaching recovery and chemical plant recovery.
View source version on businesswire.com: https://www.businesswire.com/news/home/20230418006151/en/
For further information:
Investor Relations
Senior Manager, External Relations
+1.416.861.9778
aguthrie@largoinc.com
Source:
FAQ
What were the key production figures for Largo Inc. (LGO) in Q1 2023?
How much vanadium did Largo Inc. (LGO) sell in Q1 2023?
What impact did weather have on Largo Inc.'s (LGO) production in Q1 2023?
What are Largo Inc.'s (LGO) future plans regarding its ilmenite concentration plant?