LEADING EDGE MATERIALS' NORRA KARR HREE PROJECT MOVES FORWARD
Leading Edge Materials (LEMIF) has provided an update on its 100% owned Norra Kärr Heavy Rare Earth Elements (HREE) Project. The company is advancing its Rapid Development Plan (RDP) with a phased approach, focusing on quick initial production of nepheline syenite and HREE concentrate stockpiling.
The project aligns with the European Commission's recently published Joint White Paper for European Defence Readiness 2023, which emphasizes the strategic importance of critical raw materials. The company could proceed directly to a Feasibility Study for the quarrying operation, with environmental workstreams running parallel.
Ongoing testwork is evaluating nepheline syenite and aegirine market opportunities. The PEA2021 financial model will be updated in Q2 2025, with potential upside in nepheline syenite pricing from US$12-65 to US$100-500 per tonne in higher-value markets. A decision on Strategic Project status under the Critical Raw Materials Act is pending, following the company's August 2024 application and recent submission for a 25-year mining lease.
Leading Edge Materials (LEMIF) ha fornito un aggiornamento sul suo progetto Norra Kärr Heavy Rare Earth Elements (HREE), di cui detiene il 100%. L'azienda sta avanzando con il suo Piano di Sviluppo Rapido (RDP) seguendo un approccio graduale, concentrandosi sulla rapida produzione iniziale di nefelina sienite e sull'accumulo di concentrato di HREE.
Il progetto è in linea con il recente Documento Bianco Congiunto pubblicato dalla Commissione Europea per la Prontezza alla Difesa Europea 2023, che sottolinea l'importanza strategica delle materie prime critiche. L'azienda potrebbe procedere direttamente a uno Studio di Fattibilità per l'operazione di estrazione, con i lavori ambientali che si svolgono in parallelo.
I test in corso stanno valutando le opportunità di mercato per la nefelina sienite e l'egirina. Il modello finanziario PEA2021 sarà aggiornato nel secondo trimestre del 2025, con un potenziale aumento del prezzo della nefelina sienite da 12-65 USD a 100-500 USD per tonnellata nei mercati di maggior valore. Una decisione sullo stato di Progetto Strategico ai sensi della Legge sulle Materie Prime Critiche è in attesa, a seguito della domanda dell'azienda di agosto 2024 e della recente presentazione per una concessione mineraria di 25 anni.
Leading Edge Materials (LEMIF) ha proporcionado una actualización sobre su proyecto Norra Kärr Heavy Rare Earth Elements (HREE), del cual posee el 100%. La empresa está avanzando con su Plan de Desarrollo Rápido (RDP) con un enfoque por fases, centrándose en la producción inicial rápida de nefelina sienita y el acopio de concentrado de HREE.
El proyecto se alinea con el reciente Documento Blanco Conjunto publicado por la Comisión Europea para la Preparación de Defensa Europea 2023, que enfatiza la importancia estratégica de las materias primas críticas. La empresa podría proceder directamente a un Estudio de Viabilidad para la operación de extracción, con trabajos ambientales que se desarrollan en paralelo.
Los trabajos de prueba en curso están evaluando las oportunidades de mercado para la nefelina sienita y la egirina. El modelo financiero PEA2021 se actualizará en el segundo trimestre de 2025, con un potencial aumento en el precio de la nefelina sienita de 12-65 USD a 100-500 USD por tonelada en mercados de mayor valor. Una decisión sobre el estado de Proyecto Estratégico bajo la Ley de Materias Primas Críticas está pendiente, tras la solicitud de la empresa en agosto de 2024 y la reciente presentación para un contrato de minería de 25 años.
Leading Edge Materials (LEMIF)는 100% 소유한 Norra Kärr 중희토류 원소(HREE) 프로젝트에 대한 업데이트를 제공했습니다. 이 회사는 단계적 접근 방식을 통해 신속한 초기 생산과 HREE 농축물 비축에 집중하며 신속 개발 계획(RDP)을 진행하고 있습니다.
이 프로젝트는 최근 유럽연합 집행위원회가 발표한 2023 유럽 방위 준비를 위한 공동 백서와 일치하며, 이는 중요한 원자재의 전략적 중요성을 강조합니다. 이 회사는 채굴 작업에 대한 타당성 조사로 직접 진행할 수 있으며, 환경 작업이 병행하여 진행됩니다.
현재 진행 중인 테스트 작업은 네펠린 시엔나이트와 에기린의 시장 기회를 평가하고 있습니다. PEA2021 재무 모델은 2025년 2분기에 업데이트될 예정이며, 네펠린 시엔나이트 가격이 12-65 USD에서 100-500 USD로 상승할 가능성이 있습니다. 2024년 8월 회사의 신청 및 최근 25년 광산 임대 계약 제출 후, 중요한 원자재 법에 따른 전략적 프로젝트 상태에 대한 결정이 보류 중입니다.
Leading Edge Materials (LEMIF) a fourni une mise à jour sur son projet Norra Kärr Heavy Rare Earth Elements (HREE), dont il détient 100%. L'entreprise avance son Plan de Développement Rapide (RDP) avec une approche par étapes, en se concentrant sur la production initiale rapide de néphéline syénite et le stockage de concentré de HREE.
Le projet s'aligne sur le récent Document Blanc Conjoint publié par la Commission Européenne pour la Préparation à la Défense Européenne 2023, qui souligne l'importance stratégique des matières premières critiques. L'entreprise pourrait passer directement à une Étude de Faisabilité pour l'opération d'extraction, les travaux environnementaux se déroulant en parallèle.
Les travaux de test en cours évaluent les opportunités de marché pour la néphéline syénite et l'égirine. Le modèle financier PEA2021 sera mis à jour au deuxième trimestre 2025, avec un potentiel de hausse du prix de la néphéline syénite de 12-65 USD à 100-500 USD par tonne sur des marchés de plus grande valeur. Une décision sur le statut de Projet Stratégique en vertu de la Loi sur les Matières Premières Critiques est en attente, suite à la demande de l'entreprise d'août 2024 et à la récente soumission pour un bail minier de 25 ans.
Leading Edge Materials (LEMIF) hat ein Update zu seinem 100% im Besitz befindlichen Norra Kärr Heavy Rare Earth Elements (HREE) Projekt bereitgestellt. Das Unternehmen verfolgt seinen Rapid Development Plan (RDP) mit einem phasenweisen Ansatz und konzentriert sich auf die schnelle anfängliche Produktion von Nephelinsyenit und die Lagerung von HREE-Konzentrat.
Das Projekt steht im Einklang mit dem kürzlich veröffentlichten gemeinsamen Weißbuch der Europäischen Kommission zur europäischen Verteidigungsbereitschaft 2023, das die strategische Bedeutung kritischer Rohstoffe betont. Das Unternehmen könnte direkt zu einer Machbarkeitsstudie für den Abbau übergehen, während die Umweltarbeiten parallel laufen.
Aktuelle Testarbeiten bewerten die Marktchancen für Nephelinsyenit und Ägirine. Das Finanzmodell PEA2021 wird im 2. Quartal 2025 aktualisiert, mit einem möglichen Anstieg des Nephelinsyenitpreises von 12-65 USD auf 100-500 USD pro Tonne in wertvolleren Märkten. Eine Entscheidung über den Status des strategischen Projekts gemäß dem Gesetz über kritische Rohstoffe steht aus, nachdem das Unternehmen im August 2024 einen Antrag gestellt und kürzlich einen Antrag auf eine 25-jährige Bergbaulizenz eingereicht hat.
- Project aligns with EU's strategic priorities for critical raw materials security
- Potential significant revenue upside from nepheline syenite pricing (US$100-500/tonne vs. previous US$12-65/tonne)
- Application submitted for 25-year mining lease
- Phased development approach reduces risk and environmental impact
- Project still awaiting Strategic Project status decision
- Current nepheline syenite contribution to 11% of total revenue
- Additional product qualification needed for higher-value markets
LEADING EDGE MATERIALS’ NORRA KÄRR HREE PROJECT MOVES FORWARD
Vancouver, March 23, 2025 – Leading Edge Materials Corp. (“Leading Edge Materials” or the “Company”) (TSXV: LEM) (Nasdaq First North: LEMSE) (OTCQB: LEMIF) provides an update for the
- The Company continues to advance its Rapid Development Plan (“RDP”) for extraction at Norra Kärr, aiming to achieve the shortest possible timeframe to production of heavy rare earth element concentrate and nepheline syenite. A phased development approach is under consideration—starting small and quickly—to enable early access to the deposit, initial production and sales of nepheline syenite, cash flow generation, and stockpiling of HREE concentrate for later processing and sales. This approach minimizes both risk and environmental impact.
- On March 19, the European Commission (“EC”) published its Joint White Paper for European Defence Readiness 2023, highlighting the increasing geopolitical competition over critical raw materials (“CRMs”). The document states: “The EU’s strategic competitors are heavily investing… [in] security of supply of critical raw materials, fundamental for our economic and industrial production, defence capabilities, and competitiveness. They are increasingly a cause for competition and conflicts and part of power politics, as excessive dependencies can be exploited.” It also underscores the need for the EU and its member states to build strategic reserves of raw materials. The Rapid Development Plan for Norra Kärr aligns closely with this mission and the Company could progress directly to a Feasibility Study for the quarrying operation, and undertake environmental and other workstreams in parallel, to expedite the timeline to production and thereby contribute to the EU’s 2030 objectives for CRMs security of supply.
- Testwork is underway on nepheline syenite and aegirine to assess their mineralogy, chemical composition, and leachate chemistry. The results will help evaluate market opportunities for these potential products, including demand and pricing scenarios.
- The Preliminary Economic Assessment (“PEA2021”) financial model will be updated in Q2 2025, incorporating revised price assumptions for nepheline syenite and a full review of all other modelling inputs. In the PEA2021, three nepheline syenite markets were selected, those requiring the least amount of additional processing and product qualification, with pricing ranging from US
$12 -65 per tonne. These assumptions were conservative, and the Company is now investigating higher value markets such as functional filler products with comparable prices at the time of US$100 -500 per tonne. In the PEA2021, nepheline syenite contributed11% of the total revenue and there is the potential for significant upside in pricing and revenue contribution to the overall project economics. - A decision on the Company’s application for Strategic Project status under the Critical Raw Materials Act (CRMA) is expected soon. Since submitting the application in August 2024, the Company has made tangible progress with Norra Kärr, including the significant milestone of submitting a new application for an Exploitation Concession (Bearbetningskoncession)—a 25-year mining lease—and continues to explore creative pathways to early and sustainable production.
Kurt Budge, Chief Executive Officer, writes:
“Stockpiling rare earth elements has become a recurring theme in Europe, and now the EC’s White Paper underscores the urgency of building strategic reserves of raw materials.
Norra Kärr is already a stockpile of rare earth elements—right in the ground. But with nepheline syenite as a commercial product to finance a quarrying operation, we have a pathway to providing access to these critical raw materials at a time when they are most needed.
The wait for the EU’s decision on Strategic Project status has been long. While being selected would be an advantage, the reality is undeniable: geopolitical tensions and fragile global trade flows make Norra Kärr essential to Sweden and Europe’s supply of heavy rare earth elements.
Whatever the EU’s decision, Norra Kärr isn’t just an exciting project—it’s a strategically vital one. And with Europe’s urgent demand for HREEs, fast-tracking development is no longer an option—it’s an imperative.”
On behalf of the Board of Directors,
Leading Edge Materials Corp.
Kurt Budge, CEO
For further information, please contact the Company at:
1.778-373-6727
info@leadingedgematerials.com
www.leadingedgematerials.com
About Leading Edge Materials
Leading Edge Materials is a Canadian public company focused on developing a portfolio of critical raw material projects located in the European Union. Critical raw materials are determined as such by the European Union based on their economic importance and supply risk. They are directly linked to high growth technologies such as lithium-ion batteries and permanent magnets for electric motors and wind power that underpin the sustainability transition of society. The portfolio of projects includes the
Additional Information
The information was submitted for publication through the agency of the contact person set out above, on March 23, 2025, at 11:30 PM Vancouver time.
Leading Edge Materials is listed on the TSXV under the symbol “LEM”, OTCQB under the symbol “LEMIF” and Nasdaq First North Stockholm under the symbol “LEMSE”. Mangold Fondkommission AB is the Company’s Certified Adviser on Nasdaq First North and may be contacted via email CA@mangold.se or by phone +46 (0) 8 5030 1550.
Reader Advisory
This news release may contain statements which constitute “forward-looking information”, including statements regarding the plans, intentions, beliefs and current expectations of the Company, its directors, or its officers with respect to the future business activities of the Company. The words “may”, “would”, “could”, “will”, “intend”, “plan”, “anticipate”, “believe”, “estimate”, “expect” and similar expressions, as they relate to the Company, or its management, are intended to identify such forward-looking statements. Investors are cautioned that any such forward-looking statements are not guarantees of future business activities and involve risks and uncertainties, and that the Company’s future business activities may differ materially from those in the forward-looking statements as a result of various factors, including, but not limited to, fluctuations in market prices, changes in the Company’s intended use of proceeds from the Private Placement, successes of the operations of the Company, continued availability of capital and financing and general economic, market or business conditions. There can be no assurances that such information will prove accurate and, therefore, readers are advised to rely on their own evaluation of such uncertainties. The Company does not assume any obligation to update any forward-looking information except as required under the applicable securities laws.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accept responsibility for the adequacy or accuracy of this news release.
Attachment