Ivanhoe Mines Issues Second Quarter 2023 Financial Results, and Review of Construction and Exploration Activities
Kamoa-Kakula Copper Complex sold 101,526 tonnes of payable copper in Q2 2023 and recognized record quarterly revenue of
Ivanhoe Mines recorded Adjusted EBITDA of
Ivanhoe Mines recorded a quarterly profit of
Kamoa-Kakula's quarterly cost of sales total
Ivanhoe Mines announces significant preliminary testwork for improving copper recoveries at Kamoa-Kakula
Platreef progressing well towards Q3 2024 start-up; over 2,000 metres underground development completed
Ivanhoe Mines welcomes the inclusion of copper on the 2023 U.S. Department of Energy Critical Minerals List
Johannesburg, South Africa--(Newsfile Corp. - August 3, 2023) - Ivanhoe Mines' (TSX: IVN) (OTCQX: IVPAF) President Marna Cloete and Chief Financial Officer David van Heerden are pleased to present the company's financial results for the three and six months ended June 30, 2023. Ivanhoe Mines is a leading Canadian mining company developing and operating its four principal mining and exploration projects in Southern Africa: expanding the operations of the world-class Kamoa-Kakula Copper Complex in the Democratic Republic of Congo (DRC); building the tier-one Platreef palladium, rhodium, nickel, platinum, copper and gold development in South Africa; restarting the historic, ultra-high-grade Kipushi zinc-copper-lead-germanium mine in the DRC; as well as exploring the expansive exploration licences of Ivanhoe's Western Foreland for copper discoveries adjacent to Kamoa-Kakula. All figures are in U.S. dollars unless otherwise stated.
Watch an August 2023 video highlighting Ivanhoe Mines' construction and exploration activities: https://vimeo.com/850838953/163436ff95
https://vimeo.com/850838953/163436ff95
FINANCIAL HIGHLIGHTS
- Ivanhoe Mines recorded a profit of
$87 million for Q2 2023, net of a$27 million non-cash loss on the$575 million convertible bond fair valuation, compared with a profit of$82 million for Q1 2023. The profit in the quarter includes Ivanhoe Mines' share of profit and finance income from the Kamoa-Kakula joint venture of$123 million .
- Kamoa-Kakula sold 101,526 tonnes of payable copper during Q2 2023, recognizing a record revenue of
$702 million , an operating profit of$394 million and a quarterly EBITDA of$457 million .
- Kamoa-Kakula's cost of sales per pound (lb.) of payable copper sold was
$1.24 /lb. for Q2 2023 compared with$1.25 /lb. and$1.15 /lb. in Q1 2023 and Q2 2022, respectively. Cash costs (C1) per pound of payable copper produced in Q2 2023 totaled$1.41 /lb., compared to$1.42 /lb. and$1.42 /lb. in Q1 2023 and Q2 2022, respectively.
- Ivanhoe Mines Adjusted EBITDA was
$172 million for Q2 2023, compared with$101 million for the same period in 2022, and$172 million for Q1 2023.
- Since entering Phase 1 commercial production on July 1, 2021, the Kamoa-Kakula joint venture has generated
$1.82 billion of net cash from operating activities, which has funded both the Phase 2 and Phase 3 expansions to date.
- Ivanhoe Mines has a strong balance sheet with cash and equivalents of
$393 million on hand as at June 30, 2023, and expects Kamoa-Kakula's Phase 1 and Phase 2 cash flow to be sufficient to fund the Phase 3 expansion capital cost requirements at current copper prices.
- On May 22, 2023, Kipushi Corporation entered into a financing facility with Rawbank SA, one of the largest financial institutions in the Democratic Republic of the Congo. Under the terms of the facility, Rawbank provided an
$80 million loan, to be drawn down in two tranches of$40 million each. The first tranche has been drawn and will be used to fund Kipushi's working capital requirements. The facility bears interest of8% per annum. - On April 27, 2023, Ivanhoe and joint-venture partner Gécamines, the DRC's state-owned mining company, announced an offtake term sheet for
100% of Kipushi's zinc concentrate, together with a$250 -million facility supported by Glencore International AG. The offtake and financing term sheet is subject to the execution of final, binding agreements, which are expected to be concluded in conjunction with the new Kipushi Corporation joint-venture agreement in the coming months.
- On June 15, 2023, Ivanhoe announced the replacement of an outstanding
$77.4 -million loan receivable from High Power Exploration (HPX) with an equity investment in I-Pulse, its parent company, joining leading mining company BHP Group Limited as an investor. The company intends to enter into a collaboration agreement with I-ROX, an I-Pulse subsidiary, to investigate and develop applications for pulsed-power technology in the mining sector.
OPERATIONAL HIGHLIGHTS
- Record quarterly production of 103,786 tonnes of copper in concentrate was achieved at Kamoa-Kakula for Q2 2023, compared with 93,603 tonnes in Q1 2023 and 87,314 tonnes in Q2 2022.
- Over the first six months of 2023, Kamoa-Kakula has produced a total of 197,389 tonnes of copper in concentrate, placing it well on track to deliver annual production guidance of between 390,000 - 430,000 tonnes of copper.
- Kamoa-Kakula's Phase 1 and 2 concentrators milled a record 2.2 million tonnes of ore during the second quarter at an average feed grade of
5.2% copper. This included high-grade, run-of-mine ore from the Kakula Mine, supplemented with ore from the surface stockpiles to achieve throughput higher than original design capacity.
- On July 2, 2023, Kamoa-Kakula achieved a record daily milling rate of 29,968 dry metric tonnes, which is equivalent to an annual milling rate of 10 million tonnes per annum (after accounting for availability). For July, Kamoa-Kakula produced 35,636 tonnes of copper in concentrate, just short of a record, and achieved recoveries of
88% .
- Kamoa-Kakula's Phase 3 mine and concentrator expansion, 500,000-tonne-per-annum on-site, direct-to-blister copper smelter and the refurbishment of Turbine #5 at the Inga II hydroelectric facility are advancing on schedule and are expected to be complete in late 2024. At current copper prices, it is expected that cashflow from Kamoa-Kakula's Phase 1 and 2 operations will be sufficient to fund the remaining 2023 and 2024 expansion capital cost requirements of approximately
$2.1 billion .
- On July 27, 2023, Ivanhoe announced significant preliminary test work for improving copper recoveries at Kamoa-Kakula. In 2022, Kamoa Copper's process engineering team, together with a number of internationally recognized external metallurgy specialists, initiated work to investigate ways to economically recover additional copper units from the tailings stream of the Phase 1 and 2 concentrators. Results to-date indicate a significant improvement in total recoveries can be achieved by liberating copper from the tailings stream, which would further increase production, revenues and cash flow.
- Ivanhoe continues its expansive copper exploration program on its Western Foreland licences that cover approximately 2,407 square kilometres adjacent to Kamoa-Kakula. The 2023 exploration program is budgeted at approximately
$19 million . A total of 37 holes and 10,853 metres were completed during Q2 2023, following the conclusion of the wet-season in May. A total of 15,736 metres of diamond core have been drilled in the first half of 2023.
- Ivanhoe is on schedule to publish a maiden Mineral Resource estimate for its Makoko and Kiala high-grade copper discoveries in the Western Foreland in Q3 2023.
- Ivanhoe is undertaking optimization work to identify value-accretive options for installing hoisting capacity to Platreef's Shaft 3, which was originally planned as a ventilation and secondary escape shaft. Shaft 3 is currently under construction and now is planned to be equipped for hoisting. Shaft 3 is currently being reamed to a diameter of 5.1 metres. Approximately, 340 metres of the total 950 metres have been reamed to date, with completion planned in Q4 2023. The additional hoisting capacity from Shaft 3 may be used to accelerate underground mining activities for Phase 2, in advance of the completion of Shaft 2, which is expected in 2027.
- Platreef underground development work is focused on lateral development towards the high-grade Flatreef orebody on the 750-metre, 850-metre and 950-metre levels. More than 2,000 metres of lateral development has been completed to date across all three levels, advancing at a rate of approximately 200 metres per month. Once the crusher and loading feeder installation on the 950-metre level is completed at the end of August, the rate of lateral underground development is expected to increase to approximately 300 metres per month throughout the remainder of the year.
- Drilling of the pilot drill hole for the reaming of the 10-metre-diameter Shaft 2, which commenced in February 2023, was completed during the quarter. Preparations are now underway to commence reaming of Shaft 2 to an initial diameter of 3.1 metres.
- At the Kipushi Mine, overall construction progress is approximately
50% complete and construction of the concentrator is on schedule for commissioning in Q3 2024. The concentrator includes dense media separation and a milling and flotation circuit. Kipushi is expected to produce more than 270,000 tonnes of zinc contained in concentrate over the first five years of production.
- Kipushi's underground development activity is ahead of schedule, with 2,147 metres of lateral development completed since September 2022. Stoping of ultra-high-grade Big Zinc orebody is expected to begin in January 2024. The year-to-date underground development rate averages approximately 250 metres per month. The underground development rate is expected to increase to approximately 450 metres per month by year-end.
Christelle Nday (centre left) and Micheline Kyenge (centre right), President and Vice President of Kamoa's Women In Mining, conducted a tour of Kamoa-Kakula for a group of Grade 10 students from the nearby Mutoshi Technical Institute. The students are pictured in front of a 21-tonne underground loader at the Kansoko Mine portals.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_003full.jpg
Conference call for investors on Thursday, August 3, 2023
Ivanhoe Mines will hold an investor conference call to discuss its 2023 second-quarter financial results at 3:30 p.m. London time / 10:30 a.m. Eastern time / 7:30 a.m. Pacific time on Thursday, August 3. The conference call will conclude with a question-and-answer (Q&A) session. Media are invited to attend on a listen-only basis.
To view the webcast please use the following link: https://edge.media-server.com/mmc/p/3envh996
Analysts are invited to join by phone for the Q&A using the following link: https://register.vevent.com/register/BI41a67c7e4bc743e7975234c0ae560d1a
An audio webcast recording of the conference call, together with supporting presentation slides, will be available on Ivanhoe Mines' website at www.ivanhoemines.com.
After issuance, the Financial Statements and Management's Discussion and Analysis will be available at www.ivanhoemines.com and www.sedarplus.ca.
Read Ivanhoe's Second Quarter 2023 Sustainability Update: https://ivanhoemines.com/site/assets/files/3775/sustainability-review-q2-2023.pdf
https://ivanhoemines.com/site/assets/files/3775/sustainability-review-q2-2023.pdf
Construction of the off-gas handling structure and the adjoining furnace building at Kamoa-Kakula's direct-to-blister copper smelter.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_ivanhoe1en.jpg
Principal projects and review of activities
1. Kamoa-Kakula Copper Complex
Democratic Republic of Congo
The Kamoa-Kakula Copper Complex is approximately 25 kilometres southwest of the town of Kolwezi and about 270 kilometres west of Lubumbashi in the DRC Copperbelt. Kamoa-Kakula's Phase 1 concentrator began producing copper in May 2021 and achieved commercial production on July 1, 2021. The Phase 2 concentrator, which doubled nameplate production capacity, was commissioned in April 2022. Kamoa-Kakula is independently ranked by international mining consultant Wood Mackenzie to become the world's third-largest copper mining operation in 2027, following the completion of the ongoing Phase 3 expansion. Kamoa-Kakula's employee workforce is currently
The Kamoa-Kakula Copper Complex is operated as the Kamoa Holding joint venture between Ivanhoe Mines and Zijin Mining. Ivanhoe sold a
Kamoa-Kakula summary of operating and financial data
Q2 2023 | Q1 2023 | Q4 2022 | Q3 2022 | Q2 2022 | ||||||||||||
Ore tonnes milled (000's tonnes) | 2,244 | 1,930 | 2,006 | 2,082 | 1,950 | |||||||||||
Copper ore grade processed (%) | ||||||||||||||||
Copper recovery (%) | ||||||||||||||||
Copper in concentrate produced (tonnes) | 103,786 | 93,603 | 92,761 | 97,820 | 87,314 | |||||||||||
Payable copper sold (tonnes) | 101,526 | 86,777 | 92,208 | 93,812 | 85,794 | |||||||||||
Cost of sales per pound ($ per lb.) | 1.24 | 1.25 | 1.08 | 1.05 | 1.15 | |||||||||||
Cash cost (C1) ($ per lb.) | 1.41 | 1.42 | 1.42 | 1.43 | 1.42 | |||||||||||
Realized copper price ($ per lb.) | 3.79 | 4.04 | 3.54 | 3.50 | 4.34 | |||||||||||
Sales revenue before remeasurement ($'000) | 729,924 | 659,529 | 619,997 | 570,504 | 699,381 | |||||||||||
Remeasurement of contract receivables ($'000) | (27,542 | ) | 29,594 | 53,473 | (110,031 | ) | (205,248 | ) | ||||||||
Sales revenue after remeasurement ($'000) | 702,382 | 689,123 | 673,470 | 460,473 | 494,133 | |||||||||||
EBITDA ($'000)(1) | 456,628 | 457,311 | 452,089 | 251,086 | 285,477 | |||||||||||
EBITDA margin (% of sales revenue) |
All figures in the above tables are on a
(1) Unrealized foreign exchange losses have been excluded from EBITDA in the current and prior periods presented, as the Company believes that including the unrealized foreign exchange gains and losses does not give a valuable indication of the mine's ability to generate liquidity by producing operating cash flow to fund its working capital needs, service debt obligations, fund capital expenditures and distribute cash to its shareholders.
C1 cash cost per pound of payable copper produced can be further broken down as follows:
Q2 2023 | Q1 2023 | Q4 2022 | Q3 2022 | Q2 2022 | |||||||
Mining | ($ per lb.) | 0.39 | 0.41 | 0.40 | 0.41 | 0.39 | |||||
Processing | ($ per lb.) | 0.19 | 0.19 | 0.16 | 0.12 | 0.14 | |||||
Logistics charges (delivered to China) | ($ per lb.) | 0.45 | 0.46 | 0.50 | 0.56 | 0.51 | |||||
Treatment, refining and smelter charges | ($ per lb.) | 0.25 | 0.23 | 0.23 | 0.21 | 0.21 | |||||
General and administrative expenditure | ($ per lb.) | 0.13 | 0.13 | 0.13 | 0.13 | 0.17 | |||||
C1 cash cost per pound of payable copper produced | ($ per lb.) | 1.41 | 1.42 | 1.42 | 1.43 | 1.42 |
C1 cash costs are prepared on a basis consistent with the industry standard definitions by Wood Mackenzie cost guidelines but are not measures recognized under IFRS. In calculating the C1 cash cost, the costs are measured on the same basis as the company's share of profit from the Kamoa Holding joint venture that is contained in the financial statements. C1 cash costs are used by management to evaluate operating performance and include all direct mining, processing, and general and administrative costs. Smelter charges and freight deductions on sales to the final port of destination, which are recognized as a component of sales revenues, are added to C1 cash cost to arrive at an approximate cost of delivered, finished metal. C1 cash costs exclude royalties and production taxes and non-routine charges as they are not direct production costs.
All figures are on a
(L-R) Guelord Ilunga, control room overseer; Derick Yav Tshang, control room overseer; Carine Ndala, control room overseer; Jean-Saint Kabange, plant metallurgist; Dan Mutamba, senior control room officer; and Chris Tshibanda, control room overseer, stand in the Kamoa-Kakula concentrator plant control room.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_006full.jpg
Kamoa-Kakula produced a record 103,786 tonnes of copper in Q2 2023, including a monthly record of 35,856 tonnes for May 2023
Kamoa-Kakula's Phase 1 and 2 concentrators are now regularly operating at the increased processing rate of 9.2 million tonnes per annum (Mtpa), following the completion of the debottlenecking program. The
The Kamoa-Kakula Phase 1 and Phase 2 concentrators continued to perform strongly in the second quarter, breaking several records including the quarterly production of 103,786 tonnes of copper in concentrate, a quarter-on-quarter increase of
Kamoa-Kakula's Phase 1 and 2 concentrators milled a record 2.2 million tonnes of ore during the second quarter at an average feed grade of
For July, Kamoa-Kakula's Phase 1 and 2 concentrators milled 0.6 million tonnes of ore at an average feed grade of
The record second-quarter production at Kamoa-Kakula was achieved despite maintenance shutdowns in June and intermittent grid instability.
Since late Q4 2022, Kamoa Copper has been working alongside DRC's state-owned power company, La Société Nationale d'Electricité (SNEL), to identify the causes of instability across the southern DRC's grid infrastructure to assist with delivering long-lasting solutions. Kamoa Copper has identified a series of upgrades and has outlined a project plan to deliver the improvements. Mobilization of resources is underway, with vendor selection and equipment procurement having commenced.
Concurrently, Kamoa Copper's engineering team are working towards insulating Kamoa-Kakula from future instability by expanding on-site backup generation capacity, as well as sourcing additional power imported from the Zambian grid.
Over the next 12-18 months, on-site backup-power generation capacity will increase via a phased roll-out. During the second quarter, 11 megawatts (MW) of new generator capacity was installed, bringing the total on-site backup-power generation capacity to approximately 48 MW. Delivery of a further 30 MW in backup generation capacity, sufficient to power Kamoa-Kakula's entire Phase 1 and 2 operations in the event of grid disruptions, will commence later this year and is expected to be operational by Q2 2024. Over 130 MW of further backup generation capacity has been ordered and is expected to be installed in 2024, in time for the completion of the Phase 3 concentrator and smelter that are currently under construction.
Discussions are advancing to secure up to 100 MW of additional power via the Zambian grid interconnector, with the initial phase expected to be ready in the third quarter.
Draw-down of surface ore stockpiles at Kakula continues as required. While the ongoing expansion of underground infrastructure at the Kakula mine takes place, ore will be drawn as required from the stockpile to maximize copper production.
Kamoa-Kakula's high- and medium-grade ore surface stockpiles totaled approximately 4.1 million tonnes at an estimated grade of
Jurie Human, civil supervisor, Kamoa Copper and Julias Mblambo, site foreman with DRC-based contractor Kongo River Construction, study schematics underground at the Kakula Mine.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_007full.jpg
Significant preliminary testwork for improving copper recoveries at Kamoa-Kakula
On July 27, 2023, Ivanhoe announced highly promising preliminary testwork to further improve copper recoveries at Kamoa-Kakula by liberating copper from the tailings stream by a conventional process of fine-grinding the material followed by flotation, thickening and filtration. Initial preliminary results indicate that with a feed grade of less than
In 2022, Kamoa Copper's process engineering team, together with a number of internationally recognized external metallurgy specialists, initiated work to investigate ways to economically recover additional copper units from the tailings stream of the Phase 1 and 2 concentrators. There are 13 workstreams underway, including the process described above, which is subject to further metallurgical testwork and engineering work, to advance the project to an investment decision.
For context, in 2022 the Kamoa-Kakula Copper Complex milled approximately 7.1 million tonnes of ore at an average feed grade of
Figure 1. Global average copper head grade since 2000, compared with the average copper grade of Kamoa-Kakula's tailings during 2022.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_008full.jpg
Source: BMO Research, Wood Mackenzie
Construction of the Phase 3 concentrator plant and associated infrastructure is advancing well
Kamoa-Kakula's ongoing Phase 3 expansion is expected to be commissioned in Q4 2024 and includes a new 5-Mtpa concentrator at Kamoa, which is approximately 10 kilometres north of the Phase 1 and 2 concentrators.
The process design of the Phase 3 concentrator is very similar to that of the Phase 1 and 2 concentrators, but
Following the commissioning of Phase 3, Kamoa-Kakula will have a total design processing capacity of 14.2 Mtpa. The completion of Phase 3 is expected to increase annualized copper production to an average of approximately 620,000 tonnes per year over the next ten years, which will position Kamoa Copper as the world's third-largest copper mining complex in 2027, and the largest copper mine on the African continent. See Figure 2.
Figure 2: World's projected top 10 copper mines in 2027, by key metrics.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_009full.jpg
Note: Kamoa-Kakula production and grade are based on the Kamoa-Kakula 2023 PFS. The 'Cu Head Grade' for the projects benchmarked by Wood Mackenzie reflects the average reserve grade.
Source: Wood Mackenzie, 2023 (based on public disclosure, the Kamoa-Kakula 2023 PFS has not been reviewed by Wood Mackenzie).
Kamoa-Kakula's Phase 3 expansion, consisting of two new underground mines known as Kamoa 1 and Kamoa 2 and a new, 5-Mtpa concentrator plant, is well on track for first production in the fourth quarter of 2024. Construction of the twin declines to the Kamoa 1 and Kamoa 2 underground mines and excavation to access the Phase 3 mining areas is advancing well. The Kamoa 1 and Kamoa 2 mines share a single box cut with a twin service-and-conveyor decline. Over 2,000 metres of linear advance across both declines have been completed to date and access to the Kamoa 2 Mine has been achieved, holing of the services decline is expected in October 2023. Underground mining activities are expected to commence at Kamoa 1 in late 2023 and Kamoa 2 in 2025, which will both involve the same mechanized drift-and-fill mining methods used at the Kakula Mine.
Civil works for Kamoa-Kakula's Phase 3 concentrator plant are nearing completion, with over 25,000 cubic metres of concrete poured to date.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_010full.jpg
Construction of the concentrate thickener base is progressing well at Kamoa-Kakula's Phase 3 concentrator site.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_011full.jpg
Representatives from DRC-based contractor Prospere stand with members of the Kamoa Copper team in front of the foundation for Kamoa-Kakula's Phase 3 ball mill circuit.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_012full.jpg
Phase 3 concentrator project is
Detailed Phase 3 engineering design and procurement activities are nearly complete, with fabrication activities now
Civil works are nearing completion, with over 25,000 cubic metres of the total 30,000 cubic metres of concrete poured to date. The steel, mechanical, piping and plate work (SMPP) contract was also awarded during the quarter. Delivery of structural steel commenced during the quarter. Over 5,000 tonnes of the required 7,400 tonnes of structural steel and plate work have shipped to site. Orders for approximately 50,000 metres of the total 73,000 metres of piping have also been placed.
The last lot of the 1,830-tonne primary and secondary ball mill equipment package has been shipped by CITIC Heavy Industries of Henan province, China, with the first containers delivered to the Port of Durban, South Africa. Installation of the first of the two ball mills has commenced at the Phase 3 concentrator site, with scaffolding work well advanced. The first lots of the cone crushers, flotation cells, vibrating screens, concentrate filters, cyclone cluster, compressor and pump mechanical equipment packages are expected to be delivered to site imminently. Furthermore, the apron feeder was recently lifted into position inside the Phase 3 run-of-mine stockpile tunnel.
Smelter project is
The Phase 3 expansion also includes the integration of Africa's largest direct-to-blister flash smelter, which will have a capacity of 500,000 tonnes of 99+%-pure blister copper anodes per annum. The on-site smelter is being built adjacent to the existing Phase 1 and Phase 2 concentrator plants. The smelter will incorporate leading-edge technology supplied by Metso Outotec of Espoo, Finland and will meet the world-leading International Finance Corporation's (IFC) emissions standards.
All major foundations for the equipment and buildings are complete. Most of the structural steel and equipment have been ordered and are now being manufactured. The first lots of structural steel and mechanical equipment have been delivered to site. Approximately 726 truckloads of steel and equipment out of an estimated total of 5,400 have been delivered. The main mechanical and electrical construction contractors have been appointed and mobilization is underway. Mechanical erection has started for the direct-to-blister flash furnace and electric slag-cleaning furnace and gas cleaning system. Approximately 2,000 construction workers are now working at the smelter site, and this is expected to peak at 3,000 in December 2023.
Kamoa-Kakula's Phase 3 expansion includes the refurbishment of Turbine #5 at the Inga II hydroelectric power station. The turbine will supply an additional 178 megawatts of clean hydroelectric power to the national grid, which is sufficient to meet the power requirements of the Phase 3 concentrator, the flash smelter, as well as provide spare capacity for future expansions. The
Civil construction of Kamoa-Kakula's Phase 3 direct-to-blister smelter furnace is progressing on schedule for completion in Q4 2024. It will be Africa's largest direct-to-blister flash smelter.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_013full.jpg
Foundations and civil construction for the Phase 3 smelter high-strength acid storage and dispatch also are advancing on schedule. All major foundations for the equipment and buildings are complete.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_014full.jpg
The smelter will have a processing capacity of approximately 1.2 Mtpa of dry concentrate feed and is designed to run on a blend of concentrate produced from the Kakula (Phase 1 and 2) and Kamoa (Phase 3 and future Phase 4) concentrators. Under the Kamoa-Kakula 2023 Integrated Development Plan, the smelter is projected to accommodate approximately
As a by-product, the smelter will also produce in the region of 650,000 to 800,000 tonnes per year of high-strength sulphuric acid. There is strong demand for sulphuric acid in the DRC, as it is used to recover copper from oxide ores via the SX-EW (solvent extraction and electrowinning) process. The DRC market consumed approximately 6 million tonnes of acid in 2022. The vast majority of the consumed high-strength sulphuric acid is imported by regional consumers in the form of sulphur and burned in domestic acid plants.
The on-site smelter will offer transformative financial benefits for the Kamoa-Kakula Copper Complex, most notable being a material reduction in logistics costs, and to a lesser extent reduced concentrate treatment charges and local taxes, as well as revenue from acid sales. Logistics costs accounted for
Kamoa-Kakula's Phase 3 expansion also includes the rehabilitation of Turbine #5 at the Inga II hydroelectric power station, which is progressing well. The replaced turbine will supply an additional 178 megawatts (MW) of clean hydroelectric power to the national grid and provide power for Phase 3. Study work is also progressing well to upgrade the transmission capacity of the existing grid infrastructure between the Inga II hydropower facility and the Kamoa site.
COPPER PRODUCTION AND CASH COST GUIDANCE FOR 2023
Kamoa-Kakula 2023 Guidance | |
Contained copper in concentrate (tonnes) | 390,000 to 430,000 |
Cash cost (C1) ($ per pound) | 1.40 to 1.50 |
2023 full-year cash cost (C1) and production guidance remain unchanged. The figures are on a
Production guidance is based on assumptions about the disruption of power supply, among other things. The Kamoa-Kakula joint venture produced a total of 333,497 tonnes of copper in concentrate for the year ending December 31, 2022, and 197,389 tonnes in the first half of 2023 including 103,786 tonnes of copper in concentrate in Q2 2023.
Cash costs (C1) per pound of payable copper amounted to
Cash cost (C1) guidance is based on assumptions including, among other things, prevailing logistics costs based on estimated regional trucking capacity, particularly as regional idled operations are expected to come online, as well as increased benchmark treatment and refining charges, and inflation in consumables and other inputs.
C1 cash cost is a non-GAAP measure used by management to evaluate operating performance and includes all direct mining, processing, stockpile rehandling charges, and general and administrative costs. Smelter charges and freight deductions on sales to the final port of destination (typically China), which are recognized as a component of sales revenues, are added to C1 cash cost to arrive at an approximate cost of delivered finished metal.
For historical comparatives, see the non-GAAP Financial Performance Measures section of this news release.
Chikuk Kawiz Lea, a member of Kamoa's CADET program, stands at the Phase 1 and Phase 2 concentrator site. The program trains members of local communities for high-skill jobs at Kamoa-Kakula.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_015full.jpg
Construction teams at Kamoa-Kakula's Phase 3 concentrator site prepare for a structural steel lift with a new 450-tonne crane.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_016full.jpg
2. Platreef Project
South Africa
The Platreef Project is owned by Ivanplats (Pty) Ltd (Ivanplats), which is
The Platreef Project hosts an underground deposit of thick, platinum-group metals, nickel, copper, and gold mineralization on the Northern Limb of the Bushveld Igneous Complex in Limpopo Province - approximately 280 kilometres northeast of Johannesburg and eight kilometres from the town of Mokopane in South Africa.
On the Northern Limb, platinum-group metals mineralization is primarily hosted within the Platreef, a mineralized sequence traced for more than 30 kilometres along the strike. Ivanhoe's Platreef Project, within the Platreef's southern sector, is comprised of two contiguous properties: Turfspruit and Macalacaskop. Turfspruit, the northernmost property, is contiguous with, and along strike from, Anglo Platinum's Mogalakwena group of mining operations and properties.
Since 2007, Ivanhoe has focused its exploration and development activities on defining and advancing the down-dip extension of its original discovery at Platreef, now known as the Flatreef Deposit, which is amenable to highly mechanized, underground mining methods. With Shaft 1, the initial access to the deposit, now in operation and hoisting development rock from underground, Ivanhoe is focusing on construction activities to bring Phase 1 of Platreef into production by Q3 2024.
Platreef development is currently funded by
The Shaft 2 headgear concrete structure (right) beside Shaft 1 (left) was completed early in the quarter to a height of approximately 79 metres. Shaft 2's overall height will be approximately 100 metres above ground, including the steel structure housing the main winders.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_017full.jpg
Surface construction activities and lateral underground mine development are progressing well
Underground development work has been focused on lateral development towards the high-grade Flatreef orebody on the 750-metre, 850-metre and 950-metre levels. More than 2,000 metres of lateral development has been completed to date across all three levels (750-metre, 850-metre and 950-metre levels), advancing at a rate of approximately 200 metres per month. Once the crusher and loading feeder installation on the 950-metre level is completed at the end of August, the rate of lateral underground development is expected to continue to increase to approximately 300 metres per month through the remainder of the year. From January 2024, the advancement rate is expected to increase to approximately 500 metres per month.
Platreef's Phase 1 concentrator is on schedule for first production in Q3 2024. All foundation concrete has been poured, with formwork and steel fixing of the walls and plinths commenced. The fabrication of the long-lead order mechanical equipment items is progressing as planned. Over
Foundation for Platreef's Phase 1 flotation cells is advancing well. Platreef's Phase 1 concentrator is on schedule for first production in Q3 2024, with all foundation concrete poured.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_018full.jpg
The 10-metre diameter Shaft 2 currently under construction will have a hoisting capacity of 8 Mtpa. Shaft 2 will be utilized in subsequent development phases and will be among the largest hoisting shafts in the world. The Shaft 2 headgear concrete structure was completed early in the quarter to a height of approximately 79 metres. Shaft 2's overall height will be approximately 100 metres above ground, including the steel structure housing the main winders. The Shaft 2 headgear internal structural steel construction is progressing well. The kibble and stage winder civil construction is nearing completion with the winder deliveries planned for December 2023. The kibble winder ropes were recently delivered.
Drilling of the pilot drill hole for the reaming of Shaft 2, which commenced in February 2023, has reached the shaft bottom. Preparations are now underway to commence reaming Shaft 2 to an initial diameter of 3.1 metres. Raise boring will commence from the 950-metre level once bottom access has been established.
Construction of Platreef's first 5-MW solar-power plant commenced in Q4 2022 with commissioning expected later this year. The solar power plant inverter and solar panels were recently delivered to site. The power generated by this plant will support development activities and operations, together with other renewable energy sources to be introduced over time.
Sina Kekana, surveyor assistant, working at the base of Platreef's Shaft 2, which is on schedule for completion in late 2027.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_019full.jpg
Optimization work is underway to potentially accelerate Platreef's Phase 2 expansion
Ivanhoe has initiated optimization work to identify value-accretive options for installing hoisting capacity in Shaft 3 (previously named Vent Shaft 1). Shaft 3, originally planned as a ventilation and secondary escape shaft, is currently under construction and is now planned to be equipped for hoisting, which will provide additional hoisting capacity to remove ore and waste from the underground mine. This has the benefit of de-risking the development and ramp-up of the Phase 1 mine and may be used to accelerate the ramp-up of underground mining activities for Phase 2, in advance of the completion of Shaft 2, which is expected in 2027.
Shaft 3 is currently being reamed to a diameter of 5.1 metres. Approximately 340 metres of 950 metres have been reamed to date, with planned completion in Q4 2023. The manufacturing of the auxiliary winder for the Shaft 3 headgear is well-advanced and on schedule. The civil contractor responsible for the foundations of the stage winder and equipping winder has been appointed and is mobilizing.
Long-term supply of bulk water for the Platreef Mine
The water requirement for the Phase 1 operation is projected to peak at approximately three million litres per day, which will then increase to nine million litres per day once the Phase 2 expansion is complete. In January 2022, Ivanplats signed new agreements for the rights to receive local, treated water to supply the bulk water needed for the phased development plan at Platreef. These agreements replace those originally signed in 2018.
Under the terms of a new offtake agreement, the Mogalakwena Local Municipality (MLM) has agreed to supply at least three million litres per day of treated effluent, up to a maximum of 10 million litres per day for 32 years, from the date of first production, sourced from the town of Mokopane's Masodi Wastewater Treatment Works, currently under construction.
Ivanplats also has signed a sponsorship agreement where Ivanplats has undertaken the commitment to complete the partially constructed Masodi Wastewater Treatment Works, which was halted in 2018. Since construction was restarted, work on the completion of the water treatment plant is progressing well towards completion in Q3 2023.
In addition, Ivanplats signed the Memorandum of Agreement to upgrade and refurbish the sewerage treatment infrastructure to increase the water offtake for future expansions.
3. Kipushi Project
Democratic Republic of Congo
The Kipushi zinc-copper-germanium-silver-lead mine in the DRC is adjacent to the town of Kipushi, approximately 30 kilometres southwest of Lubumbashi on the Central African Copperbelt. Kipushi is approximately 250 kilometres southeast of the Kamoa-Kakula Copper Complex and less than one kilometre from the Zambian border. Ivanhoe acquired its
The Kipushi 2022 Feasibility Study focuses on the mining of Kipushi's zinc-rich Big Zinc and Southern Zinc zones, with an estimated 11.8 million tonnes of Measured and Indicated Mineral Resources grading
On April 27, 2023, Ivanhoe Mines announced the signing of a tri-partite offtake and financing term sheet between Kipushi Corporation SA, Gécamines and Glencore International AG (Glencore) to return the historic Kipushi zinc-copper-lead-germanium mine to production.
The offtake is for
The
The offtake and financing term sheet is subject to the execution of final, binding agreements, which are expected to be concluded in conjunction with the new Kipushi joint-venture agreement.
In June 2023, Kipushi Corporation finalized an unsecured,
The new facility has an annual interest rate of
The remaining initial capital for the Kipushi Project is
As previously reported, Kipushi Holding and Gécamines signed a new agreement to return the ultra-high-grade Kipushi Mine to commercial production in Q1 2022, which sets out the commercial terms that will form the basis of a new Kipushi joint-venture agreement establishing a robust framework for the mutually beneficial operation of Kipushi for years to come and are subject to execution of definitive documentation. Once the agreement is concluded, it is anticipated that Ivanhoe Mines' ownership in the Kipushi Project will reduce to
Construction of the new 800,000-tonne-per-annum concentrator facility is well underway. The concentrator is expected to produce more than 270,000 tonnes of zinc over the first five years of production.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_020full.jpg
Over 69 years, Kipushi produced a total of 6.6 million tonnes of zinc and 4.0 million tonnes of copper from 60 million tonnes of ore grading
Since acquiring its interest in the Kipushi Mine in 2011, Ivanhoe's drilling campaigns have upgraded and expanded the mine's zinc-rich Measured and Indicated Mineral Resources to an estimated 11.78 million tonnes grading
Based on testwork conducted for the Kipushi 2022 Feasibility Study, concentrate assays for the Kipushi Mine include significant quantities of germanium and gallium.
Germanium is a strategic metal used today in electronic devices, flat-panel display screens, light-emitting diodes, night vision devices, optical fibre, optical lens systems, and solar power arrays.
Gallium is a strategic metal used today to manufacture compound semiconductor wafers used in integrated circuits, and optoelectronic devices such as laser diodes, light-emitting diodes, photodetectors, and solar cells.
Kipushi concentrator is on schedule for first production in Q3 2024, with the overall project approximately
Construction of the new 800,000-tonne-per-annum concentrator facility is well underway. The concentrator includes dense media separation (DMS) and a milling and flotation circuit and is expected to produce more than 270,000 tonnes of zinc contained in concentrate over the first five years of operations. Design recoveries are targeted at
With overall project progress at approximately
The ball mill, fabricated by CITIC Heavy Industries of Henan Province, China, has arrived at the port of Durban, South Africa, and is expected to be delivered to site within a month. The DMS plant fabricated by Bond Equipment in Gauteng, South Africa, has been completed and is being prepared to be trucked to site. The fabrication of the flotation cells by FL Smidth in Gauteng, South Africa, is also complete and will be delivered to site in the coming month.
Kipushi steel erection commenced in April 2023 with 1,342 tonnes of total 2,074 tonnes dispatched to site. With overall project progress at approximately
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_021full.jpg
The structural, mechanical, piping and plate work (SMPP) contractor has completed and handed over its first structure, which is the electrical substation building.
Underground development activity is ramping up, with 2,147 metres of lateral development completed since September 2022. Stoping of the ultra-high-grade Big Zinc orebody is expected to begin in January 2024.
In line with the 2022 Kipushi Feasibility Study, mining will focus on the zinc-rich Big Zinc and Southern Zinc zones, with an estimated 11.8 million tonnes of Measured and Indicated Mineral Resources grading
In the first quarter of 2023, the underground mining contractor was appointed, and the phased on-site mobilization of mining crews and equipment is well underway. The primary mining fleet is supplied by Epiroc of Stockholm, Sweden. Over half of the primary fleet and secondary support equipment has been mobilized, with the remainder expected to be delivered at the end of the third quarter.
The underground mining operation is fully mechanized, highly efficient and designed to enable a quick ramp-up to a steady state. At the end of the second quarter, three mining crews have been deployed underground. Each mining crew made up of five miners per shift, is equipped with a primary fleet consisting of an Epiroc 282 Twin Boomer, a ST 14 Scooptram (LHD) and two MT42 dump trucks.
Tinette Brümmer from Epoch Resources at the earthworks site for Kipushi's new tailings storage facility.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_022full.jpg
The first Simba long-hole drill rig for stoping (production mining) has also arrived on site and is being prepared to be lowered underground. Concurrent training of new underground miners is ongoing, targeting a full complement of four crews by the end of the third quarter.
Underground development is taking place to open multiple access levels to the Big Zinc orebody, from the top down. Perimeter, access and ventilation drives are under development at several locations between the 1,220-metre and 1,335-metre levels, while decline development continues to spiral down parallel to the plunging Big Zinc deposit. 1,526 metres of horizontal development have been completed year to date, approximately
The year-to-date underground development rate have averaged approximately 250 metres per month. Following the mobilization of the remaining underground equipment fleet and the fourth mining crew, the underground development rate is expected to increase to approximately 450 metres per month by year-end.
Underground development throughout the remainder of the year will increasingly be in ore, grading between 20
With underground development well ahead of schedule, stoping of the ultra-high-grade Big Zinc orebody has been accelerated to commence in January 2024. Stoping is the process of extracting the ore from an underground mine, leaving behind an open space known as a stope.
The mining method of the Big Zinc orebody will be transverse sublevel open stoping in a primary and secondary sequence. The void of the mined-out stopes will be filled with cemented aggregate to maximize the extraction of the ultra-high-grade ore.
The total mining height of long-hole stopes is 60 metres (comprising of an upper 30-metre-high stope and lower 30-metre-high stope), which will be separated by 15-metre-high sill pillars. The long-hole stopes will be mined with a bottom-up mining sequence, with the lower stope extracted first followed by the upper stope. The stopes will be extracted using a primary and secondary long-hole stoping sequence.
Kipushi's operations will be supplied with hydroelectric power from DRC's state-owned electricity company, SNEL. A study completed in 2020 by Wood Mackenzie ranked Kipushi at the 2nd percentile of the Scope 1 + 2 emissions curve. See Figure 3 below.
Figure 3. Global zinc mine site scope 1+2 greenhouse gas (GHG) emissions in equivalent kilograms of carbon dioxide per tonne of equivalent zinc produced (kg CO2-e / t Zn eq.). Scope 1+2 annual GHG emissions from the Kipushi mine are forecast to be 0.06 equivalent tonnes of carbon dioxide per tonne of zinc produced (tCO2e/t Zn).
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_ivanhoe2en.jpg
Source: Wood Mackenzie, 2020
Dedicated Kipushi commercial border crossing to unlock direct access to Zambia
Kipushi Mine is adjacent to the border town of Kipushi, approximately 30 kilometres southwest of Lubumbashi on the DRC Copperbelt. Kipushi is approximately 250 kilometres southeast of the Kamoa-Kakula Copper Complex and less than one kilometre from the Zambian border.
The commercial border crossings at Kasumbalesa and Sakania, also in Haut-Katanga province, handle most of the DRC Copperbelt's imports and exports. They are located 110 kilometres and 230 kilometres by road southeast of Kipushi, respectively. The Kasumbalesa border experienced significant congestion in 2022 and Ivanhoe Mines has been working with the provincial government of Haut-Katanga on a series of initiatives to de-bottleneck the exporting of mineral products from the DRC.
One such initiative is a new commercial DRC-Zambia road border crossing at the town of Kipushi. Earlier this year, a series of study options were presented and reviewed by the provincial government of Haut-Katanga and the national authorities in the DRC. An agreement has since been reached to go ahead with building the new border crossing at Kipushi.
The new commercial border infrastructure consists of three project areas: a new 11-kilometre, street-lit, sealed by-pass road looping around the southern edge of Kipushi town; a new one-stop border post on the southern edge of the Kipushi town on the DRC side of the border, consisting of a staging area and a new administration building; and a new one-stop border post also consisting of a staging area and new administration building on the Zambian side of the border.
The vendor appointment by the Haut-Katanga province for the 11-kilometre, by-pass road is expected to be made imminently, with the mobilization of construction contractors to be made in the coming month. Project award for the border infrastructure is expected to be made towards the end of 2023.
Concurrently, work is underway by the Zambian government to upgrade roads for commercial traffic on the Zambian side of the border, connecting the T5 highway to the new commercial Kipushi border (See Figure 4). Upgrades have already commenced on some sections of road, with further infrastructure upgrades and all-weather proofing planned to take place over the next 12 to 18 months.
A new commercial DRC-Zambia border crossing at Kipushi will not only benefit the Kipushi Mine but also Kamoa-Kakula as an additional route for exporting concentrate products. In addition, the border crossing will provide socio-economic benefits to the community of Kipushi and the city of Lubumbashi, the capital of Haut-Katanga province, which is approximately 30 kilometres away.
Figure 4. Map of the current and planned commercial DRC-Zambia border infrastructure.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_025full.jpg
Kipushi follows in Kamoa-Kakula's footsteps with a strong focus on local recruitment and progressive workforce training. There are currently more than 1,800 employees and contractors working at the Kipushi site, peaking at approximately 2,000 in the fourth quarter of 2023. Once operations have ramped up to steady-state, total on-site labour, including mining and support contractors, is expected to be approximately 1,200. Of the current 504 full-time employees at Kipushi, approximately
A training program is underway to ensure that skills and practical experience gained during Kamoa-Kakula's construction, commissioning and operations are shared with the leadership and operations staff at Kipushi. Staff from Ivanhoe Mines regularly visit Kipushi and contribute to building on-site capacity, coaching and training, sharing lessons learned and experience gained at Kamoa-Kakula, while key personnel from Kipushi visit Kamoa-Kakula to learn from practical experience. A comprehensive up-skilling training program is also under development for Kipushi and is expected to be rolled out later this month.
4. Western Foreland Exploration Project
Democratic Republic of Congo
Ivanhoe's DRC exploration group is targeting Kamoa-Kakula-style copper mineralization on its Western Foreland Exploration Project. The 17 licences in the Western Foreland cover a combined area of 2,407 square kilometres to the north, south and west of the Kamoa-Kakula Copper Complex. The exploration group is using models that successfully led to the discoveries of Kakula, Kakula West, and the Kamoa North Bonanza Zone on the Kamoa Copper SA mining licence. The group is composed of a mixture of the same exploration geologists responsible for the previous discoveries and others with experience in the greater Copperbelt.
The focus of exploration during Q2 2023 has been on diamond and air core drilling, with four contractor diamond core drill rigs, one Ivanhoe Landcruiser diamond core drill rig, and one Ivanhoe air core drill rig working by the end of the quarter. A total of 15,736 metres of diamond core have been drilled in the first half of 2023, with 10,853 metres for a total of 37 holes completed in Q2 2023. Air core drilling has completed 69 holes year-to-date for a total of 1,795 metres.
Two drill holes were started during the quarter between the Makoko and Kakula deposits on the Kakula-Monwezi trend to investigate the potential for mineralization at depth between the two identified deposits, and proximal to regional structures. One hole deviated from the planned orientation and has been put on hold. The second hole intersected a splay fault off the Nchana Fault which prevented the hole from reaching target depth. Further drilling in this area will be carried out as deflections off the two existing holes, with directional drilling tools to be mobilized to the DRC later in the year to ensure the lower contact of the Foreland shelf stratigraphy with basement lithologies is intersected.
A further four holes were completed down dip of Makoko West to determine the potential for extension of mineralization into deeper parts of the Western Foreland shelf. These holes drilled Nguba Group stratigraphy before intersecting the Kibaran basement. Follow-up drilling is planned along sections to enhance the 3D geological interpretation of the area.
Road and bridge access to more remote parts of the Sakanama prospect were upgraded or constructed during the quarter. A single hole was drilled on this prospect, intersecting Roan group sediments to a depth of 443 metres.
Figure 5. Map highlighting Ivanhoe Mines' current exploration target areas across the Western Foreland licences.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_026full.jpg
Air core drilling was recommended on the Lupemba prospect during the quarter, extending the 800- by 800-metre grid of holes through exotic Kalahari sand cover. Drilling was carried out using a single air core rig, with a second air core rig planned to start drilling early in Q3 following repairs. Rock-chip samples are collected from each hole below the Kalahari sands, which average between 5 and 30 metres thick. These samples will be analyzed for multi-element geochemistry to map lithology and identify copper anomalism under variable thickness Kalahari sand cover.
Collection of ground gravity began in the quarter along regional lines across the Western Foreland Shelf on a tight grid in the extended Makoko west area. The ground gravity will be used to identify thicker sequences of Nguba Group sediments, which are an indication of growth faults. Pre-Katangan growth faults are a key targeting tool for sediment-hosted copper mineralization as they generate sub-grabens with thicker siltstone host rock units and increased primary sedimentary pyrite. These faults are also thought to have played a key role in focusing mineralized fluid movement through the basal Roan sedimentary package.
An internal mineral resource model completed in early Q2 identified locations where additional infill diamond drilling is required in the Makoko resource. Fourteen holes were drilled in Q2 using the Ivanhoe Landcruiser rig for short holes (<150m) and two Titan drill rigs for deeper holes. The holes produced a total of 2,200 metres of core which will be added to the Makoko geological database.
The maiden inferred Mineral Resource Estimate for Makoko and Kiala is on course to be released in Q3 2023.
5. The Mokopane Feeder Exploration Project
South Africa
Three new
This anomaly is interpreted to represent a primary feeder zone to the Rustenburg Layered Suite of the Northern Limb of the Bushveld Complex. Significant thickening of the Rustenburg Layered Suite, particularly of the more-dense Lower Zone units, is necessary to explain the large gravity anomaly. The proximity of the inferred feeder to the regional-scale crustal faults (the Ysterberg-Planknek and the Zebediela faults), as well as the anomalously thick zones of platinum-group metals mineralization at the Platreef Deposit, lead Ivanhoe to believe there is significant potential for Ni-Cu-PGE mineralization associated with this gravity feature.
Detailed high-resolution fixed-wing airborne magnetic and Falcon airborne gravity gradiometer geophysical surveys are being carried out to map and model the subsurface petrophysical characteristics of the anomaly. The magnetic survey was completed during Q2 2023, with the gravity survey to be flown during Q3 2023 due to equipment breakdown delays. Deep diamond drilling is now planned to commence in Q4 2023 to test targets identified from the results of the two surveys.
Figure 6. Image of the Platreef and Mokopane Feeder licences overlaid on the gravity geophysics anomaly.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/175992_702af782a4c83bf6_027full.jpg
SELECTED QUARTERLY FINANCIAL INFORMATION
The following table summarizes selected financial information for the prior eight quarters. Ivanhoe had no operating revenue in any financial reporting period. All revenue from commercial production at Kamoa-Kakula is recognized within the Kamoa Holding joint venture. Ivanhoe did not declare or pay any dividend or distribution in any financial reporting period.
Three months ended | |||||||||||||
June 30, | March 31, | December 31, | September 30, | ||||||||||
2023 | 2023 | 2022 | 2022 | ||||||||||
$'000 | $'000 | $'000 | $'000 | ||||||||||
Share of profit from joint venture | 73,066 | 82,659 | 83,324 | 34,057 | |||||||||
Finance income | 61,956 | 57,826 | 58,477 | 46,720 | |||||||||
Deferred tax recovery (expense) | 1,965 | 926 | (3,839 | ) | 4,252 | ||||||||
Gain (loss) on fair valuation of financial asset | 488 | (1,595 | ) | (1,170 | ) | (2,873 | ) | ||||||
Loss on fair valuation of embedded derivative liability | (26,618 | ) | (30,900 | ) | (66,600 | ) | (27,700 | ) | |||||
General administrative expenditure | (10,474 | ) | (8,571 | ) | (11,870 | ) | (9,199 | ) | |||||
Share-based payments | (7,120 | ) | (7,702 | ) | (7,809 | ) | (7,381 | ) | |||||
Finance costs | (5,539 | ) | (10,465 | ) | (10,457 | ) | (10,223 | ) | |||||
Exploration and project evaluation expenditure | (4,375 | ) | (3,381 | ) | (3,887 | ) | (4,312 | ) | |||||
Profit (loss) attributable to: | |||||||||||||
Owners of the Company | 92,042 | 86,637 | 41,884 | 26,344 | |||||||||
Non-controlling interests | (4,859 | ) | (4,157 | ) | (4,705 | ) | (2,477 | ) | |||||
Total comprehensive income (loss) attributable to: | |||||||||||||
Owners of the Company | 86,588 | 74,154 | 53,078 | 4,588 | |||||||||
Non-controlling interest | (5,443 | ) | (5,420 | ) | (3,621 | ) | (4,678 | ) | |||||
Basic profit per share | 0.08 | 0.07 | 0.03 | 0.02 | |||||||||
Diluted profit per share | 0.07 | 0.07 | 0.03 | 0.02 | |||||||||
Three months ended | |||||||||||||
June 30, | March 31, | December 31, | September 30, | ||||||||||
2022 | 2022 | 2021 | 2021 | ||||||||||
$'000 | $'000 | $'000 | $'000 | ||||||||||
Gain (loss) on fair valuation of embedded derivative liability | 183,600 | (66,400 | ) | (88,500 | ) | 54,900 | |||||||
Deferred tax recovery (expense) | 114,184 | (1,347 | ) | 74,069 | (50 | ) | |||||||
Share of profit from joint venture | 49,690 | 87,109 | 78,391 | 41,404 | |||||||||
Finance income | 38,596 | 31,505 | 27,978 | 26,437 | |||||||||
Exploration and project evaluation expenditure | (13,470 | ) | (12,243 | ) | (15,800 | ) | (15,677 | ) | |||||
Finance costs | (10,013 | ) | (7,391 | ) | (10,539 | ) | (10,451 | ) | |||||
General administrative expenditure | (8,957 | ) | (6,238 | ) | (10,658 | ) | (6,731 | ) | |||||
Share-based payments | (4,637 | ) | (7,389 | ) | (7,490 | ) | (5,117 | ) | |||||
Profit (loss) attributable to: | |||||||||||||
Owners of the Company | 316,242 | 26,394 | 45,833 | 89,806 | |||||||||
Non-controlling interests | 35,278 | (4,854 | ) | 2,333 | (4,456 | ) | |||||||
Total comprehensive income (loss) attributable to: | |||||||||||||
Owners of the Company | 306,381 | 45,495 | 29,774 | 72,470 | |||||||||
Non-controlling interest | 34,495 | (2,858 | ) | 632 | (6,277 | ) | |||||||
Basic profit per share | 0.26 | 0.02 | 0.04 | 0.07 | |||||||||
Diluted profit per share | 0.11(1) | 0.02 | 0.04 | 0.03(1) |
(1) During the period, the Company identified that it had not considered the effect of the convertible notes in the diluted profit per share calculation since issuance of the notes in March 2021. As a result, the diluted profit per share disclosed during the three and six months ended June 30, 2022 was overstated. Refer to Ivanhoe Mines Ltd. condensed consolidated interim financial statements for the three and six months ended June 30, 2023 for additional information.
DISCUSSION OF RESULTS OF OPERATIONS
Review of the three months ended June 30, 2023 vs. June 30, 2022
The company recorded a profit for Q2 2023 of
The Kamoa-Kakula Copper Complex sold 101,526 tonnes of payable copper in Q2 2023, realizing revenue of
Three months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Company's share of profit from joint venture | 73,066 | 49,690 | ||||
Interest on loan to joint venture | 49,837 | 34,874 | ||||
122,903 | 84,564 |
The company's share of profit from the Kamoa Holding joint venture was
Three months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Revenue from contract receivables | 729,924 | 699,381 | ||||
Remeasurement of contract receivables | (27,542 | ) | (205,248 | ) | ||
Revenue | 702,382 | 494,133 | ||||
Cost of sales | (277,646 | ) | (217,112 | ) | ||
Gross profit | 424,736 | 277,021 | ||||
General and administrative costs | (27,794 | ) | (23,964 | ) | ||
Amortization of mineral property | (3,005 | ) | - | |||
Profit from operations | 393,937 | 253,057 | ||||
Finance costs | (90,701 | ) | (66,828 | ) | ||
Foreign exchange (loss) gain | (29,333 | ) | 863 | |||
Finance income and other | 5,193 | 2,449 | ||||
Profit before taxes | 279,096 | 189,541 | ||||
Current tax expense | (119,120 | ) | (4,726 | ) | ||
Deferred tax recovery (expense) | 30,278 | (57,389 | ) | |||
Profit after taxes | 190,254 | 127,426 | ||||
Non-controlling interest of Kamoa Holding | (42,645 | ) | (27,044 | ) | ||
Total comprehensive income for the period | 147,609 | 100,382 | ||||
Company's share of profit from joint venture ( | 73,066 | 49,690 |
The realized and provisional copper prices used for the remeasurement (mark-to-market) of contract receivables for the three months ended June 30, 2023, and for the same period in 2022, can be summarized as follows:
Three months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Realized during the period - open at the start of the period | ||||||
Opening forward price ($/lb.)(1) | 4.05 | 4.69 | ||||
Realized price ($/lb.)(1) | 3.79 | 4.34 | ||||
Payable copper tonnes sold | 37,092 | 50,608 | ||||
Remeasurement of contract receivables ($'000) | (21,356 | ) | (39,227 | ) | ||
Realized during the period - new copper sold in the current period | ||||||
Provisional price ($/lb.)(1) | 4.00 | - | ||||
Realized price ($/lb.)(1) | 3.80 | - | ||||
Payable copper tonnes sold | 30,792 | - | ||||
Remeasurement of contract receivables ($'000) | (13,006 | ) | - | |||
Open at the end of the period - open at the start of the period | ||||||
Opening forward price ($/lb.)(1) | - | 4.69 | ||||
Closing forward price ($/lb.)(1) | - | 3.80 | ||||
Payable copper tonnes sold | - | 39,797 | ||||
Remeasurement of contract receivables ($'000) | - | (78,391 | ) | |||
Open at the end of the period - new copper sold in current period | ||||||
Provisional price ($/lb.)(1) | 3.77 | 4.26 | ||||
Closing forward price ($/lb.)(1) | 3.81 | 3.79 | ||||
Payable copper tonnes sold | 69,935 | 85,794 | ||||
Remeasurement of contract receivables ($'000) | 6,820 | (87,630 | ) | |||
Total remeasurement of contract receivables ($'000) | (27,542 | ) | (205,248 | ) |
(1) Calculated on a weighted average basis
Of the
Ivanhoe's exploration and project evaluation expenditure amounted to
Finance income for Q2 2023 amounted to
The company recognized a loss on the fair valuation of the embedded derivative financial liability of
In Q2 2022, the company recognized the deferred tax asset relating to the Kipushi Project resulting in a deferred tax recovery (income) of
Review of the six months ended June 30, 2023, vs. June 30, 2022
The company recorded a profit of
The company recognized income in aggregate of
Six months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Company's share of profit from joint venture | 155,725 | 136,799 | ||||
Interest on loan to joint venture | 97,429 | 63,163 | ||||
Company's income recognized from joint venture | 253,154 | 199,962 |
The company's share of profit from the Kamoa Holding joint venture was
Six months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Revenue from contract receivables | 1,389,453 | 1,166,834 | ||||
Remeasurement of contract receivables | 2,052 | (153,106 | ) | |||
Revenue | 1,391,505 | 1,013,728 | ||||
Cost of sales | (517,223 | ) | (340,482 | ) | ||
Gross profit | 874,282 | 673,246 | ||||
General and administrative costs | (58,440) | (39,732) | ||||
Amortization of mineral property | (5,601 | ) | - | |||
Profit from operations | 810,241 | 633,514 | ||||
Finance costs | (179,374 | ) | (121,471 | ) | ||
Foreign exchange (loss) gain | (34,218 | ) | 4,536 | |||
Finance income and other | 10,188 | 4,280 | ||||
Profit before taxes | 606,837 | 520,859 | ||||
Current tax expense | (195,593 | ) | (9,941 | ) | ||
Deferred tax expense | (9,339 | ) | (162,218 | ) | ||
Profit after taxes | 401,905 | 348,700 | ||||
Non-controlling interest of Kamoa Holding | (87,308 | ) | (72,339 | ) | ||
Total comprehensive income for the period | 314,597 | 276,361 | ||||
Company's share of profit from joint venture ( | 155,725 | 136,799 |
The realized and provisional copper prices used for the remeasurement (mark-to-market) of contract receivables for the six months ended June 30, 2023, and for the same period in 2022, can be summarized as follows.
Six months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Realized during the period - open at the start of the period | ||||||
Opening forward price ($/lb.)(1) | 3.90 | 4.55 | ||||
Realized price ($/lb.)(1) | 3.95 | 4.43 | ||||
Payable copper tonnes sold | 88,271 | 103,673 | ||||
Remeasurement of contract receivables ($'000) | 11,269 | (28,171 | ) | |||
Realized during the period - new copper sold in the current period | ||||||
Provisional price ($/lb.)(1) | 4.05 | - | ||||
Realized price ($/lb.)(1) | 3.94 | - | ||||
Payable copper tonnes sold | 86,913 | - | ||||
Remeasurement of contract receivables ($'000) | (21,556 | ) | - | |||
Open at the end of the period - open at the start of the period | ||||||
Opening forward price ($/lb.)(1) | 3.79 | 4.55 | ||||
Closing forward price ($/lb.)(1) | 4.05 | 4.23 | ||||
Payable copper tonnes sold | 6,625 | 76,716 | ||||
Remeasurement of contract receivables ($'000) | 3,748 | (55,278 | ) | |||
Open at the end of the period - new copper sold in current period | ||||||
Provisional price ($/lb.)(1) | 3.84 | 4.36 | ||||
Closing forward price ($/lb.)(1) | 3.88 | 4.13 | ||||
Payable copper tonnes sold | 100,241 | 137,713 | ||||
Remeasurement of contract receivables ($'000) | 8,591 | (69,657 | ) | |||
Total remeasurement of contract receivables ($'000) | 2,052 | (153,106 | ) |
(1) Calculated on a weighted average basis
Of the
Exploration and project evaluation expenditure amounted to
Finance income amounted to
As explained in the accounting for the convertible notes section in Ivanhoe Mines' MD&A for the three and six months ended June 30, 2023, the company recognized a loss on fair valuation of the embedded derivative financial liability of
The total comprehensive income for the six months ended June 30, 2023, included an exchange loss on translation of foreign operations of
Financial position as at June 30, 2023 vs. December 31, 2022
The company's total assets increased by
The company's investment in the Kamoa Holding joint venture increased by
June 30, | December 31, | |||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Company's share of net assets in joint venture | 666,165 | 510,439 | ||||
Loan advanced to joint venture | 1,634,030 | 1,536,601 | ||||
Total investment in joint venture | 2,300,195 | 2,047,040 |
The company's share of net assets in the Kamoa Holding joint venture can be broken down as follows:
June 30, 2023 | December 31, 2022 | ||||||||||||
$'000 | $'000 | $'000 | $'000 | ||||||||||
Assets | |||||||||||||
Property, plant and equipment | 3,340,132 | 1,653,365 | 2,733,176 | 1,352,922 | |||||||||
Mineral property | 784,286 | 388,222 | 789,888 | 390,995 | |||||||||
Indirect taxes receivable | 335,736 | 166,189 | 279,385 | 138,296 | |||||||||
Cash and cash equivalents | 333,204 | 164,936 | 365,633 | 180,988 | |||||||||
Consumable stores | 314,843 | 155,847 | 257,434 | 127,430 | |||||||||
Other receivables | 297,050 | 147,040 | 212,221 | 105,049 | |||||||||
Long-term loan receivable | 263,096 | 130,233 | 252,523 | 124,999 | |||||||||
Non-current inventory | 231,960 | 114,820 | 246,424 | 121,980 | |||||||||
Trade receivables | 106,031 | 52,485 | 63,196 | 31,282 | |||||||||
Current inventory | 78,141 | 38,680 | 27,011 | 13,370 | |||||||||
Right-of-use asset | 46,554 | 23,044 | 11,549 | 5,717 | |||||||||
Prepaid expenses | 14,253 | 7,055 | 9,216 | 4,562 | |||||||||
Non-current deposits | 1,872 | 927 | 2,272 | 1,125 | |||||||||
Deferred tax asset | 626 | 310 | 710 | 351 | |||||||||
Liabilities | |||||||||||||
Shareholder loans | (3,300,152 | ) | (1,633,575 | ) | (3,103,381 | ) | (1,536,174 | ) | |||||
Trade and other payables | (345,098 | ) | (170,824 | ) | (309,710 | ) | (153,306 | ) | |||||
Deferred tax liability | (283,180 | ) | (140,174 | ) | (273,841 | ) | (135,551 | ) | |||||
Income taxes payable | (137,368 | ) | (67,997 | ) | (14,600 | ) | (7,227 | ) | |||||
Equipment finance facility | (113,490 | ) | (56,178 | ) | (102,890 | ) | (50,931 | ) | |||||
Rehabilitation provision | (84,413 | ) | (41,784 | ) | (45,231 | ) | (22,389 | ) | |||||
Other provisions | (58,833 | ) | (29,122 | ) | (26,675 | ) | (13,204 | ) | |||||
Provisional payment facility | (53,520 | ) | (26,492 | ) | (38,866 | ) | (19,239 | ) | |||||
Lease liability | (47,624 | ) | (23,574 | ) | (13,243 | ) | (6,555 | ) | |||||
Non-controlling interest | (378,319 | ) | (187,268 | ) | (291,012 | ) | (144,051 | ) | |||||
Net assets of the joint venture | 1,345,787 | 666,165 | 1,031,189 | 510,439 |
Before commencing commercial production in July 2021, the Kamoa Holding joint venture principally used loans advanced to it by its shareholders to advance the Kamoa-Kakula Copper Complex through investing in development costs and other property, plant and equipment. No additional shareholder loans were advanced in 2022 or 2023 with joint venture cashflow funding its operations and expansions. The joint venture had a healthy cash position as at June 30, 2023, with cash and cash equivalents of
The Kamoa-Kakula's Phase 1 and 2 operations are anticipated to generate significant operating cash flow to fund Phase 3 capital cost requirements at current copper prices and the joint venture is arranging short-term financing facilities should a shortfall occur due to a significant decrease in copper prices. Kamoa-Kakula has
The cash flows of the Kamoa Holding joint venture can be summarized as follows:
Three months ended | Six months ended | |||||||||||
June 30, | June 30, | |||||||||||
2023 | 2022 | 2023 | 2022 | |||||||||
$'000 | $'000 | $'000 | $'000 | |||||||||
Net cash generated from operating activities | 405,417 | 249,877 | 851,957 | 634,362 | ||||||||
Change in working capital items | (83,794 | ) | 116,320 | (256,913 | ) | (43,646 | ) | |||||
Net cash used in investing activities | (370,232 | ) | (143,751 | ) | (623,388 | ) | (250,767 | ) | ||||
Net cash (used in) generated from financing activities | (6,142 | ) | (895 | ) | (3,744 | ) | 1,133 | |||||
Effect of foreign exchange rates on cash | (1,669 | ) | (5,097 | ) | (341 | ) | (6,664 | ) | ||||
Net cash (outflow) inflow | (56,420 | ) | 216,454 | (32,429 | ) | 334,418 | ||||||
Cash and cash equivalents - beginning of the period | 389,624 | 139,995 | 365,633 | 22,031 | ||||||||
Cash and cash equivalents - end of the period | 333,204 | 356,449 | 333,204 | 356,449 |
The Kamoa Holding joint venture's net increase in property, plant and equipment from December 31, 2022, to June 30, 2023, amounted to
Six months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Kamoa Holding joint venture | ||||||
Expansion capital | 518,049 | 267,756 | ||||
Sustaining capital | 105,707 | 25,709 | ||||
Initial capital | - | 9,009 | ||||
623,756 | 302,474 | |||||
Depreciation capitalized | 18,197 | 5,340 | ||||
Total capital expenditure | 641,953 | 307,814 | ||||
Borrowing costs capitalized | 51,544 | 21,554 | ||||
Total additions to property, plant and equipment for Kamoa Holding | 693,497 | 329,368 | ||||
Less depreciation, disposals and foreign exchange translation | (86,541 | ) | (54,296 | ) | ||
Net increase in property, plant and equipment of Kamoa Holding | 606,956 | 275,072 |
Ivanhoe's cash and cash equivalents decreased by
The net increase in property, plant and equipment amounted to
The main components of the additions to property, plant and equipment - including capitalized development costs - at the Platreef and Kipushi projects for the six months ended June 30, 2023, and for the same period in 2022, are set out in the following tables:
Six months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Platreef Project | ||||||
Phase 1 construction | 55,912 | 17,959 | ||||
Phase 2 construction | 25,785 | 4,722 | ||||
Salaries and benefits | 6,478 | 6,706 | ||||
Administrative and other expenditure | 3,288 | 3,053 | ||||
Depreciation | 3,152 | 739 | ||||
Studies and contracting work | 2,181 | 2,079 | ||||
Site costs | 1,984 | 1,034 | ||||
Social and environmental | 883 | 556 | ||||
Total development costs | 99,663 | 36,848 | ||||
Other additions to property, plant and equipment | 6,233 | 2,093 | ||||
Total additions to property, plant and equipment for Platreef | 105,896 | 38,941 |
Six months ended | ||||||
June 30, | ||||||
2023 | 2022 | |||||
$'000 | $'000 | |||||
Kipushi Project | ||||||
Mine construction costs | 39,159 | - | ||||
Administration and overheads | 6,619 | 3,519 | ||||
Salaries and benefits | 7,832 | 5,725 | ||||
Other expenditure | 5,186 | 2,107 | ||||
Depreciation - development | 4,170 | - | ||||
Studies and contracting work | 3,569 | 1,698 | ||||
Electricity | 3,533 | 1,544 | ||||
Other additions to property, plant and equipment | 427 | 1,459 | ||||
Depreciation - exploration and project evaluation | - | 3,759 | ||||
Total project expenditure | 70,495 | 19,811 | ||||
Accounted for as follows: | ||||||
Additions to property, plant and equipment | 38,265 | 1,459 | ||||
Development costs capitalized to property, plant and equipment | 32,230 | - | ||||
Exploration and project evaluation expenditure in the loss from operating activities | - | 18,352 | ||||
Total project expenditure | 70,495 | 19,811 |
Costs incurred during 2023 at the Platreef and Kipushi projects are deemed necessary to bring the project to commercial production and are therefore capitalized as property, plant and equipment.
On June 30, 2023, the company entered into an exchange agreement with I-Pulse Inc. (I-Pulse), under which the company replaced the outstanding convertible loan balance owed to it by HPX Inc. with an equity investment in I-Pulse. The company extended a
The company's total liabilities increased by
On May 22, 2023, Kipushi Corporation SA (Kipushi), a subsidiary of the company and the operator of the Kipushi Project, entered into a loan agreement with Rawbank SA (Rawbank), a financial institution in the DRC. Under the terms of the loan agreement, Rawbank provided an
LIQUIDITY AND CAPITAL RESOURCES
The company had
The company's capital expenditure for 2023 and 2024 can be summarized as follows:
Capital Expenditure | H1 2023 Actuals | 2023 Guidance | 2024 Guidance | ||||||
($' million) | ($' million) | ($' million) | |||||||
Kamoa-Kakula | |||||||||
Phase 3 expansion | 407 | 1,400 - 1,800 | 1,100 - 700 | ||||||
Phase 2 and other expansion capital | 111 | 120 | - | ||||||
Sustaining capital | 106 | 180 | 80 | ||||||
624 | 1,700 - 2,100 | 1,180 - 780 | |||||||
Platreef | |||||||||
Phase 1 initial capital | 77 | 190 - 240 | 200 - 150 | ||||||
Phase 2 capital | 26 | 60 | 60 | ||||||
103 | 250 - 300 | 260 - 210 | |||||||
Kipushi | |||||||||
Initial capital | 66 | 200 - 250 | 180 - 130 |
All capital expenditure figures are presented on a
The ranges provided reflect uncertainty in the timing of Kamoa-Kakula Phase 3 expansion, Platreef Phase 2 capital and Kipushi cash flows between calendar years 2023 and 2024. The 2024 capital expenditure guidance for Platreef and Kipushi excludes sustaining capital required in 2024 post-initial production.
As documented in the Kamoa-Kakula 2023 Integrated Development Plan announced on January 30, 2023, the remaining capital cost for the total Phase 3 expansion was estimated at
Construction for Platreef's Phase 1 Mine is well underway, with the first production on track for Q3 2024. The planned Phase 2 capital expenditure at Platreef mainly represents the continuation of sinking Shaft 2 and the construction of the Shaft 2 headframe, as well as Shaft 3 construction and equipping, allowing optionality for possible acceleration in Phase 2, which is currently under review.
Construction of the Kipushi Mine is also underway, with the processing plant scheduled for completion by Q3 2024. Of the
On May 22, 2023, Kipushi entered into a loan agreement with Rawbank SA, a financial institution in the DRC. Under the terms of the loan agreement, Rawbank provided an
Exploration activities at the Western Foreland Exploration Project in the DRC and other targets will continue in 2023 with an initial budget of
On March 17, 2021, the company closed a private placement offering of
The company has a mortgage bond outstanding on its offices in London, United Kingdom, of £3.2 million (
In 2013, the company became a party to a loan payable to ITC Platinum Development Limited, which had a carrying value and contractual value of
The company has an implied commitment in terms of spending on work programs submitted to regulatory bodies to maintain the good standing of exploration and exploitation permits at its mineral properties. The following table sets forth the company's long-term obligations:
Contractual obligations as at June 30, 2023 | Payments Due By Period | ||||||||||||
Total | Less than 1 year | 1-3 years | 4-5 years | After 5 years | |||||||||
$'000 | $'000 | $'000 | $'000 | $'000 | |||||||||
Convertible notes | 577,993 | 2,993 | 575,000 | - | - | ||||||||
Debt | 81,429 | 40,027 | 4,072 | - | 37,330 | ||||||||
Lease commitments | 1,689 | 348 | 770 | 571 | - | ||||||||
Total contractual obligations | 661,111 | 43,368 | 575,770 | 4,643 | 37,330 |
Debt in the above table represents the mortgage bond owing to Citibank, the loan payable to ITC Platinum Development Limited and the loan from Rawbank, as described above.
The company is required to fund its Kamoa Holding joint venture in an amount equivalent to its proportionate shareholding interest.
NON-GAAP FINANCIAL PERFORMANCE MEASURES
Kamoa-Kakula's C1 cash costs and C1 cash costs per pound
C1 cash costs and C1 cash costs per pound are non-GAAP financial measures. These are disclosed to enable investors to better understand the performance of Kamoa-Kakula in comparison to other copper producers who present results on a similar basis.
C1 cash costs are prepared on a basis consistent with the industry standard definitions by Wood Mackenzie cost guidelines but are not measures recognized under IFRS. In calculating the C1 cash cost, the costs are measured on the same basis as the company's share of profit from the Kamoa Holding joint venture that is contained in the financial statements. C1 cash costs are used by management to evaluate operating performance and include all direct mining, processing, and general and administrative costs. Smelter charges and freight deductions on sales to the final port of destination, which are recognized as a component of sales revenues, are added to C1 cash cost to arrive at an approximate cost of finished metal. C1 cash costs and C1 cash costs per pound exclude royalties and production taxes and non-routine charges as they are not direct production costs.
Reconciliation of Kamoa-Kakula's cost of sales to C1 cash costs, including on a per pound basis:
Three months ended | Six months ended | |||||||||||
June 30, | June 30, | |||||||||||
2023 | 2022 | 2023 | 2022 | |||||||||
$'000 | $'000 | $'000 | $'000 | |||||||||
Cost of sales | 277,646 | 217,112 | 517,223 | 340,482 | ||||||||
Logistics, treatment and refining charges | 123,887 | 113,671 | 235,330 | 162,512 | ||||||||
General and administrative expenditure | 27,794 | 23,964 | 58,440 | 39,732 | ||||||||
Royalties and production taxes | (59,994 | ) | (55,651 | ) | (113,806 | ) | (84,227 | ) | ||||
Depreciation | (47,722 | ) | (32,457 | ) | (86,210 | ) | (47,693 | ) | ||||
Power rebate | (4,779 | ) | - | (9,272 | ) | - | ||||||
Movement in finished goods inventory | (774 | ) | 545 | (1,462 | ) | 548 | ||||||
General and administrative expenditure of other group entities | (4,321 | ) | (2,074 | ) | (4,645 | ) | (2,302 | ) | ||||
C1 cash costs | 311,737 | 265,110 | 595,598 | 409,052 | ||||||||
Cost of sales per pound of payable copper sold ($ per lb.) | 1.24 | 1.15 | 1.25 | 1.12 | ||||||||
C1 cash costs per pound of payable copper produced ($ per lb.) | 1.41 | 1.42 | 1.41 | 1.34 | ||||||||
Payable copper produced in concentrate (tonnes) | 100,413 | 84,476 | 190,974 | 138,271 |
Figures in the above table are for the Kamoa-Kakula joint venture on a
EBITDA, Adjusted EBITDA, EBITDA margin and normalized profit
EBITDA, Adjusted EBITDA, EBITDA margin and normalized profit are non-GAAP financial measures. Ivanhoe believes that Kamoa-Kakula's EBITDA is a valuable indicator of the mine's ability to generate liquidity by producing operating cash flow to fund its working capital needs, service debt obligations, fund capital expenditures and distribute cash to its shareholders. EBITDA and Adjusted EBITDA are also frequently used by investors and analysts for valuation purposes. Kamoa-Kakula's EBITDA and the EBITDA and Adjusted EBITDA for the company are intended to provide additional information to investors and analysts and do not have any standardized definition under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared per IFRS. EBITDA and Adjusted EBITDA excludes the impact of cash costs of financing activities and taxes, and the effects of changes in operating working capital balances, and therefore are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate EBITDA and Adjusted EBITDA differently.
The EBITDA margin is an indicator of Kamoa-Kakula's overall health and denotes its profitability, which is calculated by dividing EBITDA by revenue. The EBITDA margin is intended to provide additional information to investors and analysts, does not have any standardized definition under IFRS, and should not be considered in isolation, or as a substitute, for measures of performance prepared per IFRS.
Reconciliation of profit after tax to Kamoa-Kakula's EBITDA:
Three months ended | Six months ended | |||||||||||
June 30, | June 30, | |||||||||||
2023 | 2022 | 2023 | 2022 | |||||||||
$'000 | $'000 | $'000 | $'000 | |||||||||
Profit after taxes | 190,254 | 127,426 | 401,905 | 348,700 | ||||||||
Finance costs | 90,701 | 66,828 | 179,374 | 121,471 | ||||||||
Current and deferred tax expense | 88,842 | 62,115 | 204,932 | 172,159 | ||||||||
Depreciation | 50,727 | 32,457 | 91,811 | 47,693 | ||||||||
Unrealized foreign exchange loss (gain)(1) | 41,355 | (836 | ) | 46,244 | (6,011 | ) | ||||||
Finance income | (5,251 | ) | (2,513 | ) | (10,327 | ) | (4,319 | ) | ||||
EBITDA | 456,628 | 285,477 | 913,939 | 679,693 |
Figures in the above table are for the Kamoa-Kakula joint venture on a
(1) Unrealized foreign exchange losses (gains) have been excluded from EBITDA in the current and prior periods presented, as the company believes that including the unrealized foreign exchange gains and losses does not give a useful indication of Kamoa-Kakula's overall health and profitability.
Reconciliation of profit after tax to Ivanhoe's EBITDA and adjusted EBITDA:
Three months ended | Six months ended | |||||||||||
June 30, | June 30, | |||||||||||
2023 | 2022 | 2023 | 2022 | |||||||||
$'000 | $'000 | |||||||||||
Profit after taxes | 87,183 | 351,520 | 169,663 | 373,060 | ||||||||
Finance income | (61,956 | ) | (38,596 | ) | (119,782 | ) | (70,101 | ) | ||||
Current and deferred tax recovery | (1,769 | ) | (114,183 | ) | (2,650 | ) | (112,976 | ) | ||||
Finance costs | 5,539 | 10,013 | 16,004 | 17,404 | ||||||||
Unrealized foreign exchange loss(1) | 1,934 | 2,384 | 3,225 | 752 | ||||||||
Depreciation | 609 | 2,276 | 1,085 | 4,538 | ||||||||
EBITDA | 31,540 | 213,414 | 67,545 | 212,677 | ||||||||
Share of profit from joint venture net of tax | (73,066 | ) | (49,690 | ) | (155,725 | ) | (136,799 | ) | ||||
Company's share of EBITDA from Kamoa-Kakula joint venture(2) | 180,489 | 114,309 | 361,285 | 268,934 | ||||||||
Loss (gain) on fair valuation of embedded derivative liability | 26,618 | (183,600 | ) | 57,518 | (117,200 | ) | ||||||
Non-cash share-based payments | 6,589 | 6,457 | 13,127 | 12,710 | ||||||||
Adjusted EBITDA | 172,170 | 100,890 | 343,750 | 240,322 |
(1) Unrealized foreign exchange losses have been excluded from EBITDA in the current and prior periods presented, as the Company believes that including the unrealized foreign exchange gains and losses does not give a valuable indication of the company’s ability to generate liquidity and operating cash flow and distribute cash to its shareholders.
(2) The company's attributable share of EBITDA from the Kamoa-Kakula joint venture is calculated using the company's effective shareholding in Kamoa Copper SA (
This news release should be read in conjunction with Ivanhoe Mines' audited 2022 Financial Statements and Management's Discussion and Analysis report available at www.ivanhoemines.com and at www.sedarplus.ca.
Disclosure of technical information
Disclosures of a scientific or technical nature in this news release regarding the Kamoa-Kakula Copper Complex (other than stockpiles estimation), the Platreef Project and the Kipushi Project have been reviewed and approved by Steve Amos, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of National Instrument 43-101 (NI 43-101). Mr. Amos is not considered independent under NI 43-101 as he is the Executive Vice President, Projects, at Ivanhoe Mines. Mr. Amos has verified the technical data related to the foregoing disclosed in this news release.
Disclosures of a scientific or technical nature regarding the Kamoa-Kakula stockpiles in this news release have been reviewed and approved by George Gilchrist, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Gilchrist is not considered independent under NI 43- 101 as he is the Vice President, Resources, at Ivanhoe Mines. Mr. Gilchrist has verified the technical data regarding the Kamoa-Kakula stockpiles disclosed in this news release.
Disclosures of a scientific or technical nature regarding the Western Foreland Exploration Project in this news release have been reviewed and approved by Stephen Torr, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Torr is not considered independent under NI 43-101 as he is the Vice President, Geosciences, at Ivanhoe Mines. Mr. Torr has verified the technical data regarding the Western Foreland Exploration Project disclosed in this news release.
Ivanhoe has prepared an independent, NI 43-101-compliant technical report for the Kamoa-Kakula Project, the Platreef Project and the Kipushi Project, each of which is available on the company's website and under the company's SEDAR+ profile at www.sedarplus.ca:
- Kamoa-Kakula Integrated Development Plan 2023 Technical Report dated March 6, 2023, prepared by OreWin Pty Ltd.; China Nerin Engineering Co. Ltd.; DRA Global; Epoch Resources; Golder Associates Africa; Metso Outotec Oyj; Paterson and Cooke; SRK Consulting Ltd.; and The MSA Group.
- The Kipushi 2022 Feasibility Study dated February 14, 2022, prepared by OreWin Pty Ltd., MSA Group (Pty) Ltd., SRK Consulting (South Africa) (Pty) Ltd, and METC Engineering.
- The Platreef 2022 Feasibility Study dated February 28, 2022, prepared by OreWin Pty Ltd., Mine Technical Services, SRK Consulting Inc., DRA Projects (Pty) Ltd and Golder Associates Africa.
These technical reports include relevant information regarding the effective dates and the assumptions, parameters and methods of the mineral resource estimates on the Platreef Project, the Kipushi Project and the Kamoa-Kakula Copper Complex cited in this news release, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this news release in respect of the Platreef Project, Kipushi Project and Kamoa-Kakula Copper Complex.
Information contact
Follow Robert Friedland (@robert_ivanhoe) and Ivanhoe Mines (@IvanhoeMines_) on Twitter.
Investors
Vancouver: Matthew Keevil +1.604.558.1034
London: Tommy Horton +44 7866 913 207
Media
Tanya Todd +1.604.331.9834
Website www.ivanhoemines.com
Forward-looking statements
Certain statements in this news release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified using words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events, or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance and results and speak only as of the date of this news release.
Such statements include without limitation, the timing and results of: (i) statements that Kamoa-Kakula expects Phase 1 and Phase 2 cash flow to be sufficient to fund the Phase 3 expansion capital cost requirements at current copper prices; (ii) statements regarding highly promising preliminary testwork to further improve copper recoveries at Kamoa-Kakula, with results indicating that recoveries well over
As well, all of the results of the feasibility study for the Kakula copper mine, the Kamoa-Kakula 2023 IDP, the Platreef 2022 feasibility study, and the Kipushi 2022 feasibility study constitute forward-looking statements or information and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects.
Furthermore, concerning this specific forward-looking information concerning the operation and development of the Kamoa-Kakula Copper Complex, Platreef and Kipushi projects, and the exploration of the Western Foreland Exploration Project and the Mokopane Feeder Exploration Project, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper, nickel, zinc, platinum, palladium, rhodium and gold; (vi) the availability of equipment and facilities necessary to complete development and exploration; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xvi) changes in project scope or design; (xvii) recoveries, mining rates and grade; (xviii) political factors; (xviii) water inflow into the mine and its potential effect on mining operations, and (xix) the consistency and availability of electric power.
This news release also contains references to estimates of Mineral Resources and Mineral Reserves. The estimation of Mineral Resources is inherently uncertain and involves subjective judgments about many relevant factors. Estimates of Mineral Reserves provide more certainty but still involve similar subjective judgments. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and quality of available data and of the assumptions made and judgments used in engineering and geological interpretation (including estimated future production from the company's projects, the anticipated tonnages and grades that will be mined and the estimated level of recovery that will be realized), which may prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that ultimately may prove to be inaccurate. Mineral Resource or Mineral Reserve estimates may have to be re-estimated based on: (i) fluctuations in copper, nickel, zinc, platinum group elements (PGE), gold or other mineral prices; (ii) results of drilling; (iii) metallurgical testing and other studies; (iv) proposed mining operations, including dilution; (v) the evaluation of mine plans after the date of any estimates and/or changes in mine plans; (vi) the possible failure to receive required permits, approvals and licences; and (vii) changes in law or regulation.
Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether such results will be achieved. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed above and under the "Risk Factors" section in the company's MD&A for the three and six months ended June 30, 2023, and its Annual Information Form, and elsewhere in this news release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.
Although the forward-looking statements contained in this news release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.
The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors outlined in the "Risk Factors" section in the company's MD&A for the three and six months ended June 30, 2023, and its Annual Information Form.
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/175992