EP 98 Operational Update: Tamboran Commence Shenandoah South Pilot Project drilling program
Tamboran Resources (NYSE: TBN, ASX: TBN) has commenced its Shenandoah South (SS) Pilot Project drilling program in EP 98. The company has spudded the SS-2H well, targeting the Middle Velkerri B Shale at a depth of approximately 9,910 feet. This will be followed by the SS-3H well, both designed with a 10,000-foot horizontal section and up to 60 stimulation stages each.
The drilling program utilizes Helmerich & Payne's super-spec FlexRig® Flex 3 rig and Liberty Energy's modern frac fleet, recently mobilized from the US. Initial flow test results are expected in Q1 2025, with production from the SS Pilot Project anticipated to commence in H1 2026, subject to approvals. This campaign represents the largest single campaign in the Beetaloo Basin to date.
Tamboran Resources (NYSE: TBN, ASX: TBN) ha avviato il programma di perforazione del suo Progetto Pilota Shenandoah South (SS) nell'EP 98. L'azienda ha iniziato la perforazione del pozzo SS-2H, mirando allo Shale Middle Velkerri B a una profondità di circa 9.910 piedi. Seguirà il pozzo SS-3H, entrambi progettati con una sezione orizzontale di 10.000 piedi e fino a 60 fasi di stimolazione ciascuno.
Il programma di perforazione utilizza il FlexRig® Flex 3 super-specifico di Helmerich & Payne e la moderna flotta di fracking di Liberty Energy, recentemente mobilitata dagli Stati Uniti. I risultati iniziali dei test di flusso sono attesi nel Q1 2025, con la produzione del Progetto Pilota SS prevista per iniziare nel H1 2026, soggetta ad approvazioni. Questa campagna rappresenta la più grande campagna singola nel Bacino Beetaloo finora.
Tamboran Resources (NYSE: TBN, ASX: TBN) ha comenzado su programa de perforación del Proyecto Piloto Shenandoah South (SS) en el EP 98. La compañía ha comenzado a perforar el pozo SS-2H, con el objetivo del Shale Middle Velkerri B a una profundidad de aproximadamente 9,910 pies. Esto será seguido por el pozo SS-3H, ambos diseñados con una sección horizontal de 10,000 pies y hasta 60 etapas de estimulación cada uno.
El programa de perforación utiliza la plataforma FlexRig® Flex 3 super-específica de Helmerich & Payne y la moderna flota de fracturación de Liberty Energy, recientemente movilizada desde EE.UU. Se esperan los resultados iniciales de las pruebas de flujo en el primer trimestre de 2025, con la producción del Proyecto Piloto SS prevista para comenzar en la primera mitad de 2026, sujeto a aprobaciones. Esta campaña representa la mayor campaña única en la Cuenca Beetaloo hasta la fecha.
탐보란 자원 (NYSE: TBN, ASX: TBN)이 EP 98에서 신안도남부(SS) 파일럿 프로젝트의 시추 프로그램을 시작했습니다. 회사는 약 9,910피트 깊이에서 미들 벨케리 B 셰일을 목표로 하는 SS-2H 우물의 시추를 시작했습니다. 그 후 SS-3H 우물이 이어지며, 두 우물 모두 10,000피트의 수평 섹션과 각각 최대 60개의 자극 단계를 설계했습니다.
시추 프로그램은 헬메리치 & 페인의 슈퍼 스펙 FlexRig® Flex 3 리그와 최근 미국에서 배치된 리버티 에너지의 최신 프랙 선대를 이용합니다. 초기 유속 테스트 결과는 2025년 1분기에 예상되며, SS 파일럿 프로젝트의 생산은 2026년 1분기에 시작될 것으로 예상되고, 승인 여부에 따라 달라질 수 있습니다. 이번 캠페인은 지금까지 비탈루 분지에서의 가장 큰 단일 캠페인을 나타냅니다.
Tamboran Resources (NYSE: TBN, ASX: TBN) a lancé son programme de forage pour le Projet Pilote Shenandoah South (SS) dans l'EP 98. La société a commencé le forage du puits SS-2H, visant le schiste Middle Velkerri B à une profondeur d'environ 9 910 pieds. Cela sera suivi par le puits SS-3H, tous deux conçus avec une section horizontale de 10 000 pieds et jusqu'à 60 étapes de stimulation chacune.
Le programme de forage utilise le FlexRig® Flex 3 super-spécifique de Helmerich & Payne et la flotte moderne de fracturation de Liberty Energy, récemment mobilisée depuis les États-Unis. Les premiers résultats des tests de flux sont attendus au premier trimestre 2025, avec une production du Projet Pilote SS prévue pour débuter au premier semestre 2026, sous réserve d'approbation. Cette campagne représente la plus grande campagne unique dans le Bassin de Beetaloo à ce jour.
Tamboran Resources (NYSE: TBN, ASX: TBN) hat mit seinem Shenandoah South (SS) Pilotprojekt- Bohrprogramm im EP 98 begonnen. Das Unternehmen hat den SS-2H-Brunnen abgeteuft, der auf das Middle Velkerri B Shale in einer Tiefe von etwa 9.910 Fuß abzielt. Darauf folgt der SS-3H-Brunnen, beide mit einem horizontalen Abschnitt von 10.000 Fuß und bis zu 60 Stimulationsepochen entworfen.
Das Bohrprogramm nutzt den Super-Spec FlexRig® Flex 3-Rigg von Helmerich & Payne und die moderne Frac-Flotte von Liberty Energy, die kürzlich aus den USA mobilisiert wurden. Erste Fließtestergebnisse werden im 1. Quartal 2025 erwartet, während die Produktion des SS-Pilotprojekts voraussichtlich im ersten Halbjahr 2026 beginnen wird, vorbehaltlich der Genehmigungen. Diese Kampagne stellt die größte Einzelkampagne im Beetaloo-Becken bis heute dar.
- Commencement of the largest single drilling campaign in the Beetaloo Basin
- Utilization of advanced drilling and fracking equipment from strategic partners
- Planned 40 MMcf/d SS Pilot Project with production expected in H1 2026
- Potential for increased efficiency and optimized gas flows with new Liberty frac fleet
- Initial flow test results not expected until Q1 2025
- Production commencement subject to stakeholder and regulatory approvals
Insights
Tamboran's commencement of the Shenandoah South Pilot Project drilling program marks a significant milestone in the Beetaloo Basin's development. The planned 10,000-foot horizontal sections for both SS-2H and SS-3H wells represent the longest lateral wells in the basin to date, potentially enhancing productivity and economics.
The introduction of Liberty Energy's modern frac fleet is a game-changer. This advanced equipment could substantially increase the number of completed stages per day and optimize gas flows, potentially leading to improved well performance and reduced costs. However, investors should note that initial flow test results aren't expected until Q1 2025, with production commencing in H1 2026, indicating a long lead time before potential revenue generation.
Tamboran's strategic partnerships with Helmerich & Payne and Liberty Energy, both major shareholders, provide a competitive edge in the Beetaloo Basin. These collaborations ensure access to advanced drilling and stimulation equipment, potentially leading to operational efficiencies and cost savings.
The company's 77.5% interest in EP 98/117 and 95% interest in the Shenandoah South-2 DSUs indicate significant upside potential if the project proves successful. However, investors should be aware of the substantial capital expenditure required for this extensive drilling program and the long timeline to production. The project's success is important for Tamboran's future cash flows and valuation, but it also carries considerable exploration and development risks.
Highlights
-
Tamboran Resources Corporation has commenced its Shenandoah South (SS) Pilot Project drilling program with the spudding of the Shenandoah South 2 (SS-2H) well in EP 98. The SS-2H well is being drilled off a new pad located approximately 3 miles north of the Shenandoah South 1H (SS-1H) well and within the Tamboran-operated SS Pilot Project area (
47.5% working interest). - Following the drilling of the SS-2H well, Tamboran will immediately drill the Shenandoah South 3H (SS-3H) well off the same pad ahead of the stimulation program.
- The SS-2H and SS-3H wells will be drilled with the Helmerich & Payne (NYSE: HP) super-spec FlexRig® Flex 3 rig and will target the Middle Velkerri B Shale at a depth of approximately 9,910 feet (3,020 metres). Each well is expected to be drilled in 30 days.
-
Both the SS-2H and SS-3H wells are designed to include a 10,000-foot (3,000-metre) horizontal section and will each be stimulated with up to 60 stages utilizing the Liberty Energy (NYSE: LBRT) modern frac fleet which has recently been mobilized from the US to
Australia . The increased efficiency and performance of the Liberty frac fleet is expected to result in a material increase in the number of completed stages per day and optimized gas flows. - Initial flow test results from each well are expected in Q1 2025. Once flow testing is complete, both wells will be suspended as future producers to supply Tamboran’s proposed 40 million cubic feet per day (MMcf/d) SS Pilot Project. Production from the SS Pilot Project is expected to commence in H1 2026, subject to final stakeholder and regulatory approvals.
- The two well program will be the largest single campaign in the Beetaloo Basin to date.
Tamboran Resources Corporation Managing Director and CEO, Joel Riddle, said:
“We are excited to commence our 2024 Beetaloo Basin drilling program, which includes the longest horizontal wells drilled in the Beetaloo Basin to date. With up to 120 stimulation stages to be completed across the two wells, this will be the largest single campaign in the basin to date.
“With the new Liberty stimulation equipment being mobilized from the US to
“It is our strategic partnerships with our largest shareholders, H&P and Liberty, which have dedicated equipment in Tamboran’s Beetaloo Basin operations, that put us in a commanding position to derisking significant, long duration gas reserves in the Beetaloo Basin.”
EP 98/117 interests
Company |
Interest |
Tamboran (B2) Pty Limited1 |
|
Falcon Oil and Gas Australia Limited (Falcon) |
|
Total |
|
Shenandoah South-2 Drilling Spacing Units (DSUs) – 51,200-acres2
Company |
Interest |
Tamboran (B2) Pty Limited1 |
|
Falcon Oil and Gas Australia Limited (Falcon) |
|
Total |
|
1Tamboran (B2) is a
2Subject to the completion of the SS-2H and SS-3H wells on the Shenandoah South pad 2.
This announcement was approved and authorized for release by Joel Riddle, the Managing Director and Chief Executive Officer of Tamboran Resources Corporation.
About Tamboran Resources Corporation
Tamboran Resources Corporation, (“Tamboran” or the “Company”), through its subsidiaries, is the largest acreage holder and operator with approximately 1.9 million net prospective acres in the Beetaloo Sub-basin within the Greater McArthur Basin in the
Tamboran’s key assets include a
Disclaimer
Tamboran makes no representation, assurance or guarantee as to the accuracy or likelihood of fulfilment of any forward-looking statement or any outcomes expressed or implied in any forward-looking statement. The forward-looking statements in this report reflect expectations held at the date of this document. Except as required by applicable law or the ASX Listing Rules, Tamboran disclaims any obligation or undertaking to publicly update any forward-looking statements, or discussion of future financial prospects, whether as a result of new information or of future events.
The information contained in this announcement does not take into account the investment objectives, financial situation or particular needs of any recipient and is not financial product advice. Before making an investment decision, recipients of this announcement should consider their own needs and situation and, if necessary, seek independent professional advice. To the maximum extent permitted by law, Tamboran and its officers, employees, agents and advisers give no warranty, representation or guarantee as to the accuracy, completeness or reliability of the information contained in this presentation. Further, none of Tamboran nor its officers, employees, agents or advisers accept, to the extent permitted by law, responsibility for any loss, claim, damages, costs or expenses arising out of, or in connection with, the information contained in this announcement.
Note on Forward-Looking Statements
This press release contains “forward-looking” statements related to the Company within the meaning of Section 21E of the Securities Exchange Act of 1934, as amended (the “Exchange Act”) and Section 27A of the Securities Act of 1933, as amended. Forward-looking statements reflect the Company’s current expectations and projections about future events at the time, and thus involve uncertainty and risk. The words “believe,” “expect,” “anticipate,” “will,” “could,” “would,” “should,” “may,” “plan,” “estimate,” “intend,” “predict,” “potential,” “continue,” and the negatives of these words and other similar expressions generally identify forward-looking statements.
It is possible that the Company’s future financial performance may differ from expectations due to a variety of factors, including but not limited to: 1) our early stage of development with no material revenue expected until 2026 and our limited operating history; 2) the substantial additional capital required for our business plan, which we may be unable to raise on acceptable terms; 3) our strategy to deliver natural gas to the Australian East Coast and select Asian markets being contingent upon constructing additional pipeline capacity, which may not be secured; 4) the absence of proved reserves and the risk that our drilling may not yield natural gas in commercial quantities or quality; 5) the speculative nature of drilling activities, which involve significant costs and may not result in discoveries or additions to our future production or reserves; 6) the challenges associated with importing
It is not possible to foresee or identify all such factors. Any forward-looking statements in this document are based on certain assumptions and analyses made by the Company in light of its experience and perception of historical trends, current conditions, expected future developments, and other factors it believes are appropriate in the circumstances. Forward-looking statements are not a guarantee of future performance and actual results or developments may differ materially from expectations. While the Company continually reviews trends and uncertainties affecting the Company’s results of operations and financial condition, the Company does not assume any obligation to update or supplement any particular forward-looking statements contained in this document.
View source version on businesswire.com: https://www.businesswire.com/news/home/20240829390482/en/
Investor enquiries:
Chris Morbey, Vice President – Corporate Development and Investor Relations
+61 2 8330 6626
Investors@tamboran.com
Media enquiries:
+61 2 8330 6626
Media@tamboran.com
Source: Tamboran Resources Corporation
FAQ
What is the target depth for the SS-2H and SS-3H wells in Tamboran's (TBN) Shenandoah South Pilot Project?
How long are the horizontal sections planned for Tamboran's (TBN) SS-2H and SS-3H wells?
When does Tamboran Resources (TBN) expect to have initial flow test results from the SS-2H and SS-3H wells?