STOCK TITAN

Generation Completes Optimization Work for the Marathon Project with Improved Mine Plan and Reduced Capex

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Generation Mining has completed optimization work on its Marathon Palladium-Copper Project, achieving significant improvements. The optimized mine plan delivers an additional 78,000 ounces of palladium, 34,000 ounces of platinum, and 2 million pounds of copper in the first three years, generating estimated additional payable revenues of $190 million. The initial capital estimate has been reduced by $89 million to $961 million, despite industry-wide inflationary pressures. The project now shows improved economics with a 26% after-tax IRR and 2.1-year after-tax payback period.

Generation Mining ha completato i lavori di ottimizzazione sul suo Progetto Marathon Palladio-Rame, ottenendo miglioramenti significativi. Il piano minerario ottimizzato prevede un ulteriore 78.000 once di palladio, 34.000 once di platino e 2 milioni di libbre di rame nei primi tre anni, generando ricavi ulteriori stimati di $190 milioni. La stima del capitale iniziale è stata ridotta di $89 milioni a $961 milioni, nonostante le pressioni inflazionistiche a livello industriale. Il progetto ora mostra un'economia migliorata con un 26% di rendimento interno (IRR) dopo le tasse e un periodo di recupero dopo le tasse di 2,1 anni.

Generation Mining ha completado trabajos de optimización en su Proyecto de Paladio-Cobre Marathon, logrando mejoras significativas. El plan de minería optimizado proporciona 78,000 onzas de paladio, 34,000 onzas de platino y 2 millones de libras de cobre en los primeros tres años, generando ingresos adicionales estimados de $190 millones. La estimación de capital inicial se ha reducido en $89 millones a $961 millones, a pesar de las presiones inflacionarias en la industria. El proyecto ahora muestra una economía mejorada con un 26% de TIR después de impuestos y un período de recuperación después de impuestos de 2.1 años.

Generation Mining는 마라톤 팔라듐-구리 프로젝트의 최적화 작업을 완료하고 상당한 개선을 달성했습니다. 최적화된 광산 계획은 첫 3년 동안 78,000온스의 팔라듐, 34,000온스의 백금, 200만 파운드의 구리를 추가로 제공하며, 추가 지급 가능한 수익을 $190백만으로 추정합니다. 초기 자본 추정치는 업계 전반의 인플레이션 압박에도 불구하고 $89백만 줄어든 $961백만으로 조정되었습니다. 이 프로젝트는 이제 26%의 세후 내부수익률 (IRR)세후 회수 기간 2.1년이라는 개선된 경제성을 보여줍니다.

Generation Mining a terminé des travaux d'optimisation sur son Projet de Palladium-Cuivre Marathon, réalisant des améliorations significatives. Le plan minier optimisé fournit 78 000 onces de palladium, 34 000 onces de platine et 2 millions de livres de cuivre au cours des trois premières années, générant des revenus supplémentaires estimés à 190 millions de dollars. L'estimation du capital initial a été réduite de 89 millions de dollars à 961 millions de dollars, malgré les pressions inflationnistes dans l'industrie. Le projet présente maintenant une économie améliorée avec un IRR après impôts de 26% et un délai de récupération après impôts de 2,1 ans.

Generation Mining hat die Optimierungsarbeiten an seinem Marathon Palladium-Kupfer-Projekt abgeschlossen und signifikante Verbesserungen erzielt. Der optimierte Bergbauplan liefert in den ersten drei Jahren zusätzlich 78.000 Unzen Palladium, 34.000 Unzen Platin und 2 Millionen Pfund Kupfer, was zu geschätzten zusätzlichen Einnahmen von $190 Millionen führt. Die anfängliche Kapitaleinschätzung wurde trotz inflationärer Tendenzen in der Branche um $89 Millionen auf $961 Millionen gesenkt. Das Projekt zeigt nun eine verbesserte Wirtschaftlichkeit mit einer 26% nach Steuern IRR und einer nach Steuern 2,1 Jahre Rückzahlungsdauer.

Positive
  • Additional $190M in payable revenues and cost savings in first 3 years
  • Initial capital cost reduced by $89M to $961M
  • 26.3% after-tax IRR with 2.1-year payback period
  • Increased metal production: +78k oz palladium, +31k oz platinum in first 3 years
  • Reduced strip ratio from 2.9 to 1.8 in early mining phase
Negative
  • Operating costs increased to $27.44/t milled from $27.04/t
  • Sustaining capital increased by $78M to $502M
  • Peak mining rate increased by 15 Mt/year requiring higher equipment capacity

Highlights:

  • Mine plan optimized with reduced strip ratio bringing additional 78k ounces of palladium, 34k ounces of Platinum and 2M lb of Copper in the first 3 years
  • Estimated $190M in additional payable revenues1 and operating cost benefits by the end of year 3 of operations
  • Initial Capital estimate reduced by $89M despite industry-wide inflationary cost pressures
  • Improved Project Economics with a 26% after-tax IRR and 2.1 year after-tax payback period1

TORONTO--(BUSINESS WIRE)-- Generation Mining Limited (TSX:GENM, OTCQB: GENMF) ("Gen Mining" or the "Company") is pleased to provide an update on the project optimization work (the “Optimization Work”) previously announced on June 6, 20242 on the Marathon Palladium-Copper Project (the “Marathon Project”) in Northwestern Ontario. The Optimization Work focused on two key aspects: (1) optimization of the mine plan to maximize metal production and defer waste stripping in the early years of operations in order to improve early cash flows and reduce the payback period (“Mine Plan Optimization”); and (2) review and optimization of the plant design and layout, including sizing of key equipment, plant footprint and foundations, in order to reduce the initial Project capital costs (“Initial Capital Optimization”).

Jamie Levy, President and CEO, commenting on the Optimization Work, remarks:

“The optimized mine plan is a notable improvement to the existing plan, with $190 million in additional payable metal revenues1 and savings from a reduced strip ratio during the initial 3-years of mine operations.

The other meaningful improvement to the project is the optimized plant design and ancillary changes recommended by Ausenco, which represent a net savings in total project capital costs of over $89 million, after taking into account the impact of inflation on certain construction materials and equipment, and other design change escalations since the end of 2022.

This optimization work by Ausenco and our team represents a meaningful improvement to the financeability, constructability and economics of our project following several years of significant inflation in many input costs, and validates the continued robustness of the Marathon Project.”

The Mine Plan Optimization was carried out by the Company and the Initial Capital Optimization was performed by the Company in collaboration with Ausenco Engineering Canada ULC (“Ausenco”). All amounts are reported in Canadian dollars unless otherwise noted herein.

Mine Plan Optimization

The Company evaluated alternative pit sequencing options that exploit the benefit of the ore body’s proximity to surface. The results of this work demonstrated the viability of focussing on a higher grade, lower strip ratio for the initial phase of mining operations. This results in the deferral of approximately 36 million tonnes of waste stripping during the first three years of operations while increasing the amount of recovered and payable metals during this period.

Highlights of the Mine Plan Optimization are as follows:

 

Units

Optimization
Work

Technical
Report3

Variance

LOM Throughput

 

Peak Process Plant Throughput

tpd

27,700

27,700

Nil

Mt/year

10.1

10.1

Nil

Peak Mining Rate

tpd

157,000

115,000

42,000

Mt/year

57

42

+15

Production Data (to end of Y3 of Operations, Incl. Pre-Production)

 

Total Mined

Mt

97

132

(35)

Total Waste Mined

Mt

62

98

(36)

Total Ore Mined

Mt

35

34

+1

Strip Ratio

waste:ore

1.8

2.9

(1.1)

Payable Metal (to end of Y3 of Operations, Incl. Pre-Production)

 

Palladium

k oz

669

591

+78

Copper

M lbs

139

137

+2

Platinum

k oz

143

112

+31

Gold

k oz

43

36

+7

Silver

k oz

512

477

+35

The deferral of 36 million tonnes of waste material and increasing payable metal production up to the end of the third year of operations, including the pre-production period, is estimated to result in $190 million in additional revenues and cost savings during this period.

As a result of this new sequencing the peak mining tonnage will increase to 57 Mtpa. The costs associated with this stripping are included in the life of mine operating costs, capital costs and project economics, discussed below.

Initial Capital Optimization

The Company engaged Ausenco to perform a review of the Marathon Project’s capital and operating costs, with a primary focus on the Processing Plant and ancillary infrastructure. This work benefitted from Ausenco’s extensive experience in plant design and construction of copper concentrators, most recently at Capstone Copper’s Mantoverde Mine in Chile, as well as their recent experience working in Northern Ontario at Alamos Gold’s Magino Mine. The goal of the work was to improve the designs for Project constructability and to decrease initial capital costs as compared to the estimates disclosed in the Technical Report.

The optimization work included changes to the plant layout and footprint, adjustment of equipment selections to ensure key equipment is ‘fit for purpose’, and review of the foundation and structural designs to take advantage of favourable site geotechnical conditions and minimal overburden across the site.

Total initial capex is now expected to be $961 million4 (“Initial Capital”), or a reduction of $89 million from the amounts previously estimated in the Technical Report, and reflects updated costing for inflation since the effective date of the Technical Report. The key changes from the Optimization Work are summarized below:

Capital Costs

Impact $M(a)

Explanation of Cost and Variance

Equipment and Building Layout

(71)

Reduced plant pad footprint (-22%)
Reduced plant volume (-20%)
Reduced concrete (-46%)
Reduced Structural Steel (-30%)
Improved Electrical layout and e-rooms

Equipment Sizing

(29)

Reduced mill sizing (SAG, Ball, Regrind)
Reduced electrical redundancy

Equipment Deferrals

(35)

Pebble crusher and tailings thickener deferred to sustaining capital

Reduced tailings thickener size

Market Escalation Impacts

+50

Inflation in construction labour rates
Inflation in mechanical parts costs

Earthworks and Site Infrastructure

+6

Escalation on Earthworks
Offset by optimization of site infrastructure

Mobile Equipment Leases(b)

+4

Escalation on mobile equipment costs

Project Indirects

(14)

Re-estimation of EPCM and some reallocation to direct costs

Total

(89)

Overall reduction as compared to Technical Report

Notes:

(a) (negative) numbers represent a reduction from the Technical Report values.

(b) Includes additional leasing deposits and payments during the construction and pre-production phase only.

As part of the initial capital cost review, the processing plant costs were estimated at a Class 3 AACE standard. In addition, the mining fleet was retendered to obtain current market pricing and the earthworks scope was partially retendered and adjusted for inflation.

Operating Costs

The Project operating costs have been updated and are reflected in the below table.

Unit Operating Costs (Average LOM)

 

Units

Optimization
Work

Technical
Report

Mining

$/t mined

3.43

3.25

$/t milled

12.32

11.45

Processing

$/t milled

8.27

8.70

G&A

$/t milled

2.53

2.67

Transport & Refining Charges

$/t milled

4.22

4.13

Royalty

$/t milled

0.10

0.09

Total Unit Operating Cost

$/t milled

27.44

27.04

Project operating costs per tonne of ore milled have increased primarily as a result of changes in mining costs, with an offset from reduced processing costs. Mining costs have been impacted by escalation in equipment maintenance parts (per manufacturer’s guidance), updated fuel pricing, mining operating labour rates, and adjustment to truck cycle times under the optimized mining plan. Processing costs have been updated to reflect consumable pricing and labour cost estimates. Consumption rates for consumables are largely unchanged.

Capital Costs

The initial capital costs for construction and ramp-up, together with expected sustaining capital and closure costs, are presented in the table below:

Capital Area

Units

Optimization
Work

Technical
Report

Variance

Mining Equipment for Construction(a)

$M

61

57(b)

4

Processing Plant

$M

280

345

(65)

Infrastructure

$M

86

72

14

TSF, Water Management and Earthworks

$M

80

95

(15)

EPCM, General and Owners Cost

$M

210

228

(18)

Preproduction, Startup, Commissioning

$M

153

157

(4)

Contingency

$M

92

97

(5)

Initial Capital

$M

961

1,050(b)

(89)

Preproduction revenue(c)

$M

(173)

(156)

(17)

Total

$M

788

894

(106)

Sustaining Capital

$M

502

424

78

Closure and Reclamation Costs

$M

72

72

Nil

Notes:

(a) Mining Equipment acquired for Construction is presented as the cost of equipment deposits and lease payments during the construction and pre-production period. The remainder of the equipment leasing costs are incurred during operations and are included in the financial analysis.

(b) The Technical Report presented the capital costs for mining and surface equipment as $117M, the initial capital sub-total as $1,112M, and a $58M Equipment Financing adjustment. For consistency of presentation, the net cost of leased mining equipment during the construction and pre-production period, including working capital adjustments, is presented above.

(c) See Economic Analysis, below, for additional information on the different metal price assumptions used in the Optimization Work and the Technical Report.

Economic Analysis

In order to quantify and assess the value of the Optimization Work to the economics of the Marathon Project, the Company completed an economic analysis using the following key assumptions:

Key Assumptions(a)

Units

Optimization
Work

Technical
Report

Palladium Price

US$/oz

1,525

1,800

Copper Price

US$/lb

4.00

3.70

Platinum Price

US$/oz

950

1,000

Gold Price

US$/oz

2,000

1,800

Silver Price

US$/oz

24.00

22.50

Foreign Exchange

$:US$

1.35

1.35

Diesel Price

$/litre

1.10

1.17

Electricity

$/kWhr

0.07

0.07

Note:

(a) Metal price assumptions are based on the adjusted 3-year historical trailing averages as of November 1, 2024 for each of the metals. The 3-year averages are as follows: Palladium - US$1,523/oz, Copper at U$4.02/lb, Platinum at US$964/oz, Gold at US$1,995/oz and Silver at US$24.02/oz.

The economic analysis of the Optimization Work is based on the same economic model used for the economic analysis in the Technical Report. The model inputs principally consist of metal production volumes and metal prices, unit operating costs, capital costs, sustaining capital expenditures, treatment charges (“TCs”) and refining charges (“RCs”), royalty terms, closure and reclamation costs, and taxation rates. The economic analysis of the Optimization Work also includes the impact of the sale of gold and platinum metal under the Precious Metal Purchase Agreement with Wheaton Precious Metals Corp. (“PMPA”), excluding any delay ounces. Although current market TCs and RCs are lower, the TCs and RCs in the economic analysis are unchanged from the Technical Report. The economic analysis does not consider any potential economic benefits which the Marathon Project may qualify for under any government incentive programs for critical mineral production.

The following table presents the key outputs of the economic analysis for the Optimization Work, as compared to the economic analysis contained in the Technical Report, and the economic analysis contained in the technical report adjusted for the metal price assumptions used in the Optimization Work.

Financial Evaluation(a)

Units

Optimization
Work

Technical
Report
(using Optimization
Metal Prices)

Technical
Report

Pre-Tax Cash Flow (undiscounted)

$M

2,877

2,859

3,387

Pre-Tax NPV6%

$M

1,555

1,464

1,798

Pre-Tax IRR

%

32.8

22.2

31.9

Pre-Tax Payback

years

1.9

2.5

2

After-Tax Cash Flow (undiscounted)

$M

1,923

1,929

2,285

After-Tax NPV6%

$M

998

935

1,164

After-Tax IRR

%

26.3

22.2

25.8

After-Tax Payback

years

2.1

2.9

2.3

Note:

(a) The economic analysis was carried out in real terms (i.e., without inflation factors) in Q4 2024 Canadian dollars, assuming no project construction financing but inclusive of mining equipment leasing.

Project Cash Flows

The table below highlights the estimated cumulative cash flows to the end of year 3 which result from the Mine Plan Optimization, the Initial Capital Optimization, and the Optimization Work on sustaining capital and operating cost estimates. This analysis is presented in comparison to the same analysis performed for (a) the Technical Report, and (b) the Technical Report using the same metal prices as the Optimization Work.

Cash flows from the project’s start to the end of year 3 of operations are approximately $247 million greater than the Technical Report cash flows and $129 million greater by the end of year 5 at the same metal prices. These cumulative cash flows include the initial capital cost used to construct the project, including the impact of the PMPA, and therefore the positive cash flow results support the short payback period.

Financial Evaluation

Units

Optimization
Work

Technical
Report
(adjusted for Optimization
Metal Prices)

Technical
Report

Cumulative After-Tax Cash Flow to End of Y3

$M

232

(15.3)

91

Cumulative After-Tax Cash Flow to End of Y5

$M

470

341

523

Sensitivities

The Project has significant leverage to palladium and copper prices. The after-tax valuation sensitivities for the key metrics are shown below.

Palladium Price US$/oz

1,000

1,250

1,500

1,525

1,750

2,000

NPV6% ($M)

394

682

969

998

1,257

1,543

Payback (yrs)

4.5

2.5

2.1

2.1

1.9

1.5

IRR (%)

14.8%

20.5%

25.8%

26.3%

30.7%

35.2%

Copper Price US$/lb

3.00

3.50

4.00

4.50

5.00

NPV6% ($M)

726

863

998

1,135

1,270

Payback (yrs)

2.4

2.2

2.1

2.0

1.9

IRR (%)

21.7%

24.1%

26.3%

28.5%

30.5%

After-Tax NPV 6%
Results

Palladium Price Sensitivity (US$/oz)

1,000

1,250

1,500

1,525

1,750

2,000

Copper
Price
Sensitivity
(US$/lb)

3

112

410

697

726

984

1,274

3.5

255

546

834

863

1,122

1,408

4

394

682

969

998

1,257

1,543

4.5

531

819

1,106

1,135

1,393

1,678

5

666

954

1,242

1,270

1,528

1,812

After-Tax Results

OPEX Sensitivity

+30%

+15%

0%

-15%

-30%

NPV 6% ($M)

620

810

998

1,188

1,376

Payback (yrs)

2.4

2.2

2.1

1.9

1.9

IRR (%)

19.9%

23.2%

26.3%

29.2%

31.9%

After-Tax Results

CAPEX Sensitivity

+30%

+15%

0%

-15%

-30%

NPV 6% ($M)

779

889

998

1,109

1,218

Payback (yrs)

3.0

2.4

2.1

1.5

1.2

IRR (%)

18.2%

21.7%

26.3%

32.8%

42.8%

Further Opportunities and Next Steps

As part of the Optimization Work, Ausenco identified approximately $75 million of further optimization opportunities that require additional analysis. The opportunities relate to additional layout optimizations, adjustments that would require additional processing and metallurgical testwork, and market re-tendering. Additional work will be required to validate some of the concepts and to determine if these opportunities can be realized.

The Company anticipates integrating the Optimization work into the Project designs and will continue to investigate additional construction efficiencies and opportunities, including working with contractors to incorporate new earthworks details and cost estimates.

The Optimized Mine Plan discussed herein does not result in any material change to mineral resource and reserve estimates. Future work will determine if any of the 2024 drilling (see July 31, 2024 press release)5 will be incorporated into an updated mineral resource estimate.

The Company is continuing to finalize the provincial construction permits and pursue project financing opportunities in order to bring the Marathon Project into production.

Footnotes:

1 See “Economic Analysis” in this release for additional information on the metal price assumptions used in the Optimization Work and the Technical Report.

2 See https://genmining.com/news/2024/generation-mining-continues-with-project-optimizat-8979/.

3 All references herein to the “Technical Report” refer to the Company’s NI 43-101 technical report for the Marathon Project entitled, “Amended Feasibility Study Update Marathon Palladium & Copper Project Ontario, Canada” dated May 31, 2024 with an effective date of December 31, 2022.

4 Initial capital is the total project capital, inclusive of 10% deposits and lease payments for mobile equipment during the construction and pre-production phase. The balance of this mobile equipment cost is amortized during the operations phase.

5 See https://genmining.com/news/2024/generation-mining-receives-key-approval-from-the-f-9207/.

Qualified Person

The scientific and technical content of this news release was reviewed, verified, and approved by Drew Anwyll, P.Eng., M.Eng, Chief Operating Officer of the Company, and a Qualified Person as defined by Canadian Securities Administrators’ National Instrument 43-101 - Standards of Disclosure for Mineral Projects.

Forward-Looking Information

This news release contains certain forward-looking information and forward-looking statements, as defined in applicable securities laws (collectively referred to herein as "forward-looking statements"). Forward-looking statements reflect current expectations or beliefs regarding future events or the Company’s future performance. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts", "projects”, “predicts”, “intends”, “anticipates”, “targets” or “believes”, or variations of, or the negatives of, such words and phrases or state that certain actions, events or results “may”, “could”, “would”, “should”, “might” or “will” be taken, occur or be achieved, including statements relating to mine planning and pit designs; the timing and amount of estimated future revenues, the timing and volume of payable mineral production, the payback period, and financial returns from the Marathon Project.

Although the Company believes that the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the statements. There are certain factors that could cause actual results to differ materially from those in the forward-looking information. These include the timing for a construction decision; the progress of development at the Marathon Project, including progress of project expenditures and contracting processes, the Company’s plans and expectations with respect to liquidity management, continued availability of capital and financing, the future prices of palladium, copper and other commodities, permitting timelines, exchange rates and currency fluctuations, increases in costs, requirements for additional capital, and the Company’s decisions with respect to capital allocation, and the impact of COVID-19, inflation, global supply chain disruptions, global conflicts, including the wars in Ukraine and Israel, the project schedule for the Marathon Project, key inputs, staffing and contractors, continued availability of capital and financing, uncertainties involved in interpreting geological data and the accuracy of mineral reserve and resource estimates, environmental compliance and changes in environmental legislation and regulation, the Company’s relationships with Indigenous communities, results from planned exploration and drilling activities, local access conditions for drilling, and general economic, market or business conditions, as well as those risk factors set out in the Company’s annual information form for the year ended December 31, 2023, and in the continuous disclosure documents filed by the Company on SEDAR+ at www.sedarplus.ca.

Readers are cautioned that the foregoing list of factors is not exhaustive of the factors that may affect forward-looking statements. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements in this news release speak only as of the date of this news release or as of the date or dates specified in such statements. The Company disclaims any intention or obligation to update or revise any forward- looking information, whether as a result of new information, future events or otherwise, other than as required by law. For more information on the Company, investors are encouraged to review the Company’s public filings on SEDAR+ at www.sedarplus.ca.

For further information please contact:



Jamie Levy

President and Chief Executive Officer

(416) 640-2934 (O)

(416) 567-2440 (M)

jlevy@genmining.com

Source: Generation Mining Limited

FAQ

What is the new initial capital cost for Generation Mining's Marathon Project after optimization?

After optimization, the initial capital cost for the Marathon Project (GENMF) has been reduced by $89 million to $961 million, despite industry-wide inflationary pressures.

How much additional revenue will Generation Mining's optimization work generate in the first 3 years?

The optimization work is expected to generate $190 million in additional payable revenues and cost savings during the first three years of operations.

What is the new after-tax IRR for Generation Mining's Marathon Project?

The Marathon Project now shows an improved after-tax Internal Rate of Return (IRR) of 26.3% with a 2.1-year payback period.

How much additional metal production will Generation Mining's optimization achieve in first 3 years?

The optimization will add 78,000 ounces of palladium, 34,000 ounces of platinum, and 2 million pounds of copper in the first three years of production.

GENERATION MINING LTD

OTC:GENMF

GENMF Rankings

GENMF Latest News

GENMF Stock Data

28.01M
187.54M
20.36%
8.69%
Other Industrial Metals & Mining
Basic Materials
Link
United States of America
Toronto