STOCK TITAN

New Transformer Installed and Energized in Downtown Bradford Substation

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags

FirstEnergy's Pennsylvania Electric Company (Penelec) has installed and energized a new transformer at a Bradford substation, enhancing service reliability for over 1,000 customers, including the University of Pittsburgh's Bradford campus. The 40,000-pound transformer replaced a faulty unit and features forced-air cooling fans for increased capacity. This installation is part of Energize365, a multi-year grid evolution program with planned investments of $26 billion between 2024-2028. Additionally, Penelec completed a forestry project in the Bradford area, removing approximately 1,400 hazardous trees and utilizing helicopter-mounted saws for efficient tree trimming along power lines.

La Pennsylvania Electric Company (Penelec) di FirstEnergy ha installato e attivato un nuovo trasformatore in una sottostazione a Bradford, migliorando l'affidabilità del servizio per oltre 1.000 clienti, incluso il campus dell'Università di Pittsburgh a Bradford. Il trasformatore da 40.000 libbre ha sostituito un'unità difettosa e dispone di ventilatori a circuito forzato per aumentare la capacità. Questa installazione fa parte di Energize365, un programma di evoluzione della rete pluriennale con investimenti previsti di 26 miliardi di dollari tra il 2024 e il 2028. Inoltre, Penelec ha completato un progetto di silvicoltura nell'area di Bradford, rimuovendo circa 1.400 alberi pericolosi e utilizzando seghe montate su elicotteri per un'efficiente potatura degli alberi lungo le linee elettriche.

La Pennsylvania Electric Company (Penelec) de FirstEnergy ha instalado y energizado un nuevo transformador en una subestación en Bradford, mejorando la fiabilidad del servicio para más de 1,000 clientes, incluyendo el campus de la Universidad de Pittsburgh en Bradford. El transformador de 40,000 libras reemplazó una unidad defectuosa y cuenta con ventiladores de enfriamiento por aire forzado para aumentar la capacidad. Esta instalación es parte de Energize365, un programa de evolución de la red a varios años con inversiones planificadas de 26 mil millones de dólares entre 2024 y 2028. Además, Penelec completó un proyecto forestal en el área de Bradford, eliminando aproximadamente 1,400 árboles peligrosos y utilizando sierras montadas en helicópteros para un recorte eficiente de árboles a lo largo de las líneas eléctricas.

퍼스트 에너지의 펜실베이니아 일렉트릭 컴퍼니(Penelec)가 브래드포드 변전소에 새로운 변압기를 설치하고 전력을 공급하여 1,000명 이상의 고객, 특히 피츠버그 대학교 브래드포드 캠퍼스의 서비스 신뢰성을 향상시켰습니다. 40,000파운드의 변압기는 고장난 장치를 대체하였으며, 용량을 늘리기 위해 강제 공기 냉각 팬을 갖추고 있습니다. 이번 설치는 2024년부터 2028년까지 260억 달러의 투자가 계획된 Energize365라는 다년간의 그리드 진화 프로그램의 일환입니다. 또한, Penelec는 브래드포드 지역에서 약 1,400그루의 위험한 나무를 제거하고 전선 주변의 나무를 효율적으로 다듬기 위해 헬리콥터 장착 톱을 사용하여 임업 프로젝트를 완료했습니다.

La Pennsylvania Electric Company (Penelec) de FirstEnergy a installé et mis en service un nouveau transformateur dans une sous-station à Bradford, améliorant la fiabilité du service pour plus de 1 000 clients, y compris le campus de l'Université de Pittsburgh à Bradford. Le transformateur de 40 000 livres a remplacé une unité défectueuse et dispose de ventilateurs de refroidissement à air forcé pour augmenter la capacité. Cette installation fait partie de Energize365, un programme d'évolution du réseau sur plusieurs années avec des investissements prévus de 26 milliards de dollars entre 2024 et 2028. De plus, Penelec a achevé un projet forestier dans la région de Bradford, en éliminant environ 1 400 arbres dangereux et en utilisant des scies montées sur hélicoptères pour un élagage efficace des arbres le long des lignes électriques.

Die Pennsylvania Electric Company (Penelec) von FirstEnergy hat einen neuen Transformator in einer Umspannanlage in Bradford installiert und in Betrieb genommen, um die Servicezuverlässigkeit für über 1.000 Kunden, einschließlich des Campus der University of Pittsburgh in Bradford, zu verbessern. Der 40.000 Pfund schwere Transformator ersetzte eine defekte Einheit und verfügt über Zwangsluftkühler zur Erhöhung der Kapazität. Diese Installation ist Teil von Energize365, einem mehrjährigen Programm zur Weiterentwicklung des Stromnetzes mit geplanten Investitionen von 26 Milliarden Dollar zwischen 2024 und 2028. Darüber hinaus hat Penelec ein Forstprojekt in der Umgebung von Bradford abgeschlossen, bei dem etwa 1.400 gefährliche Bäume entfernt und Hubschrauber-geführte Sägen für eine effiziente Baumpflege entlang der Stromleitungen eingesetzt wurden.

Positive
  • Installation of new transformer enhances service reliability for over 1,000 customers
  • Part of $26 billion Energize365 grid evolution program (2024-2028)
  • New transformer offers increased capacity with forced-air cooling system
  • Completion of significant forestry project improving service reliability
Negative
  • Previous transformer failure required temporary mobile substation solution

Insights

This transformer upgrade represents a meaningful infrastructure enhancement for FirstEnergy's grid reliability. The new unit's forced-air cooling system provides increased capacity over the previous natural-air model, directly benefiting 1,000+ customers including critical facilities like the University of Pittsburgh's Bradford campus and local industrial operations.

The investment aligns with FirstEnergy's ambitious Energize365 program, which has allocated $26 billion for grid modernization between 2024-2028. This systematic approach to infrastructure upgrades, combined with proactive maintenance like the recent forestry project removing 1,400 hazardous trees, demonstrates a comprehensive strategy to improve service reliability and prepare for increased electrification demands.

While this specific project's cost isn't disclosed, it represents the type of critical infrastructure investment needed to maintain grid stability and support future growth. The successful implementation and two-month operational track record indicates positive execution of FirstEnergy's capital deployment strategy.

New Penelec equipment to enhance electric service reliability for more than 1,000 customers

ERIE, Pa., Oct. 24, 2024 /PRNewswire/ -- FirstEnergy Pennsylvania Electric Company (FE PA), a FirstEnergy Corp. (NYSE: FE) subsidiary doing business as Penelec in northwestern Pennsylvania, recently energized a new transformer at a substation in Bradford to enhance electric service reliability for more than 1,000 customers in Bradford and Bradford Township, including the University of Pittsburgh's Bradford campus.

The substation's previous transformer experienced an issue last fall and could not be repaired. A mobile substation provided temporary service to customers until a new transformer could be located, transported and installed to help ensure long-term grid stability.

John Hawkins, FirstEnergy President, Pennsylvania: "Resolving this critical issue was a top priority so we could provide our customers – including industrial facilities and the local Pitt campus – with reliable electric service. We engineered a solution, identified a spare transformer capable of handling the electrical load and installed the unit. I am pleased to report the new transformer has been in service for more than two months and operating as designed."

The new transformer measures 7-feet by-4-feet, stands 11 feet tall and weighs nearly 40,000 pounds. A large crane hoisted the unit over the substation fence and onto a concrete foundation. Electricians installed new electric cables in the substation to power the transformer's forced-air cooling fans, which provide more capacity than the former transformer that relied on natural air circulation to cool. Access into the substation was also enhanced to prevent utility trucks from blocking the street when using the front gate.

With the new transformer in place and operating properly, the mobile substation has been disconnected and is ready for deployment to where it is needed next.

Photos of a crane removing the old transformer from the Bradford West Substation near the University of Pittsburgh's Bradford campus and the aerial saw are available for download on Flickr.

The work is part of Energize365, a multi-year grid evolution program focused on transmission and distribution investments that will deliver the power FirstEnergy's customers depend on today while also meeting the challenges of tomorrow. With planned investments of $26 billion between 2024 and 2028, the program will create a smarter, more secure grid that will meet and exceed reliability targets and accommodate electric vehicles, the electrification of homes and businesses and clean energy sources.

Earlier this year, Penelec completed a significant forestry project to improve electric service reliability for customers in the Bradford area, some of whom had experienced outages caused by off-right-of-way trees during several powerful winter windstorms. About 40 tree-trimming contractors worked for two months along three power lines to take down roughly 1,400 dead, diseased or leaning trees that posed a danger to poles and wires.

As part of that effort, contractor Aerial Solutions used a helicopter saw to trim trees along a 13-mile power line running through rugged, heavily wooded terrain from a substation in Lewis Run which supplies much of the Bradford region with electricity. The aerial saw looks like a large chainsaw suspended from a helicopter and is the ideal tool to cleanly remove limbs and branches along power line corridors that are inaccessible for bucket trucks or in environmentally sensitive areas. This fast, safe and efficient method of trimming covers more area in a day than ground crews might complete in a week.      

Penelec serves approximately 597,000 customers within 17,600 square miles of northern and central Pennsylvania and western New York. Follow Penelec on X @Penelec and on Facebook at facebook.com/PenelecElectric.

FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving more than six million customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate approximately 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Visit FirstEnergy online at firstenergycorp.com and follow FirstEnergy on X @FirstEnergyCorp.

 

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/new-transformer-installed-and-energized-in-downtown-bradford-substation-302286106.html

SOURCE FirstEnergy Corp.

FAQ

What is the cost of FirstEnergy's (FE) Energize365 program investment between 2024-2028?

FirstEnergy (FE) plans to invest $26 billion in the Energize365 program between 2024 and 2028.

How many customers will benefit from FirstEnergy's (FE) new Bradford substation transformer?

The new transformer will enhance electric service reliability for more than 1,000 customers in Bradford and Bradford Township, including the University of Pittsburgh's Bradford campus.

How many trees did Penelec (FE) remove in their recent Bradford area forestry project?

Penelec removed approximately 1,400 dead, diseased, or leaning trees that posed a danger to poles and wires in the Bradford area.

FirstEnergy Corp.

NYSE:FE

FE Rankings

FE Latest News

FE Stock Data

24.28B
575.60M
0.12%
89.57%
1.79%
Utilities - Regulated Electric
Electric Services
Link
United States of America
AKRON