Met-Ed Upgrading Electric System in York County, Pennsylvania
FirstEnergy Corp. (NYSE: FE) subsidiary Met-Ed is enhancing electric service reliability for rural customers in southern York County, Pennsylvania. The project involves upgrading a power line along New Park Road to a higher voltage as part of a $153 million Long Term Infrastructure Improvement Plan. This initiative spans five years to boost the electric grid's reliability, helping to prevent service disruptions especially during severe weather.
The current upgrade includes rebuilding a 2.5-mile section, replacing 38 poles, and installing new transformers. Scheduled for completion by late 2023, the project will allow much of the local network to operate at 13,200 volts. This will enhance local grid performance and ensure Met-Ed meets current and future electrical demands of approximately 587,000 customers in the region.
- Investment of $153 million to improve grid reliability.
- Upgrade to a higher voltage will enhance service during severe weather.
- Scheduled completion by end of 2023 for improved local grid performance.
- None.
Project designed to enhance service reliability for rural customers
The upgrades are part of Met-Ed's Long Term Infrastructure Improvement Plan, a
"We are rebuilding a 2.5-mile section of an existing power line to operate at a higher voltage," said
Crews are expected later this spring to replace 38 poles. They also plan to set an additional 27 new poles along the line to shorten the distance of wire between poles to reduce sagging and maintain necessary clearances. Crews will install more than 100 cross arms and 12 new transformers as they hang new wire.
A device enabled with supervisory control and data acquisition (SCADA) technology will be placed at a key spot on the line. SCADA conveys real-time information about voltage and electric current conditions to distribution system operators. Based on conditions, operators can control the device remotely to quickly isolate damage and transfer customer load to a different source, helping to keep the lights on for customers when problems such as vehicles damaging poles or tree-related outages occur.
The project will start at Met-Ed's distribution substation near the intersection of
Scheduled for completion by the end of 2023, the project will result in much of the local electric network operating at 13,200 volts – enabling Met-Ed to better meet the area's current and future electrical needs. Met-Ed will eliminate the distribution substation near
Met-Ed serves approximately 587,000 customers within 3,300 square miles of eastern and southeastern
FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its 10 electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in
Editor's Note: A photo of line workers replacing a utility pole and cross arms is available on Flickr.
View original content to download multimedia:https://www.prnewswire.com/news-releases/met-ed-upgrading-electric-system-in-york-county-pennsylvania-301800743.html
SOURCE
FAQ
What is the recent Met-Ed project in York County, Pennsylvania?
What is the budget for Met-Ed's infrastructure project?
When is the Met-Ed electric upgrade project expected to be completed?
How many customers does Met-Ed serve?