Electric Grid Enhancements Completed in the Mahoning Valley
FirstEnergy's subsidiary, American Transmission Systems, completed a $5 million upgrade to a 22-mile transmission line in Mahoning and Columbiana counties, Ohio. Approximately 250 new horizontal post insulators were installed, replacing crossarms and some poles. This project aims to enhance grid reliability and prevent outages for about 1,500 Ohio Edison customers. The work started in August 2022 and concluded in March 2024. This is part of the Energize365 program, which plans $26 billion in grid investments from 2024 to 2028 to enhance reliability and support future energy demands.
- Completed a $5 million project to enhance grid reliability.
- Installed approximately 250 new horizontal post insulators.
- Upgraded a 22-mile transmission line, replacing crossarms and some poles.
- Enhanced grid reliability for approximately 1,500 Ohio Edison customers.
- Part of the Energize365 program, aiming for $26 billion in grid investments from 2024 to 2028.
- Project started in August 2022 and concluded in March 2024, showing timely completion.
- No direct mention of immediate financial benefits or revenue impact.
- Potentially high investment with $26 billion planned for Energize365, could impact short-term financials.
Work will help prevent or minimize the impact of outages for 1,500 FirstEnergy customers
New horizontal post insulators were installed on the 69-kilovolt transmission line, which runs southwest from a substation in
Work to replace the insulators began in August 2022 and was completed in March. Several poles were also replaced as part of the
Carl Bridenbaugh, FirstEnergy's Vice President of Transmission: "This new, upgraded equipment will help prevent potential outages and ensure that our transmission system continues to serve customers safely and reliably in the future."
The project is part of Energize365, a multi-year grid evolution program focused on transmission and distribution investments that will deliver the power FirstEnergy's customers depend on today while also meeting the challenges of tomorrow. With planned investments of
FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in
View original content to download multimedia:https://www.prnewswire.com/news-releases/electric-grid-enhancements-completed-in-the-mahoning-valley-302150431.html
SOURCE FirstEnergy Corp.
FAQ
What recent upgrades did FirstEnergy complete in Mahoning Valley?
How will FirstEnergy's upgrade impact Ohio Edison customers in Mahoning Valley?
When did FirstEnergy complete the recent grid enhancements in Mahoning Valley?
What is FirstEnergy's Energize365 program?