STOCK TITAN

Endeavour Silver provides a Q3 2024 construction progress update on Terronera; the surface construction progress has reached 77% completion

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Positive)
Tags

Endeavour Silver Corp. (NYSE: EXK; TSX: EDR) has provided a Q3 2024 construction progress update for its Terronera Project in Jalisco, Mexico. The project has reached 77% overall completion, with surface mill and infrastructure construction at 90%. Key highlights include:

- $258 million spent to date, with $270 million committed out of the $271 million budget
- Underground development totaling 5,544 metres
- Primary jaw crusher commissioned in August
- Tailing Storage Facility progressing with underdrain embankment fill and pipe installation
- Workforce increased to over 250 Endeavour employees and 800 contract workers

The project is on track to begin commissioning systems near the end of Q4 2024, with focus on installing tailing and concentrate filters, and completing grinding, flotation, and thickening systems.

Endeavour Silver Corp. (NYSE: EXK; TSX: EDR) ha fornito un aggiornamento sui progressi della costruzione per il Progetto Terronera a Jalisco, Messico, per il terzo trimestre del 2024. Il progetto ha raggiunto un completamento complessivo del 77%, con la costruzione del molino di superficie e delle infrastrutture al 90%. I punti salienti includono:

- 258 milioni di dollari spesi fino ad oggi, con 270 milioni di dollari impegnati su un budget di 271 milioni di dollari
- Sviluppo sotterraneo totale di 5.544 metri
- Frantoio a mascella primario messo in funzione ad agosto
- Progresso della Struttura di Stoccaggio delle Ceneri con riempimento del terreno di drenaggio e installazione di tubazioni
- Aumento della forza lavoro a oltre 250 dipendenti di Endeavour e 800 lavoratori interni

Il progetto è sulla buona strada per iniziare la messa in servizio dei sistemi verso la fine del quarto trimestre del 2024, concentrandosi sull'installazione di filtri per ceneri e concentri, e sul completamento dei sistemi di macinazione, flottazione e addensamento.

Endeavour Silver Corp. (NYSE: EXK; TSX: EDR) ha proporcionado una actualización sobre el progreso de la construcción para su Proyecto Terronera en Jalisco, México, para el tercer trimestre de 2024. El proyecto ha alcanzado un 77% de finalización general, con la construcción del molino de superficie y la infraestructura al 90%. Los aspectos destacados incluyen:

- 258 millones de dólares gastados hasta la fecha, con 270 millones de dólares comprometidos de un presupuesto de 271 millones de dólares
- Desarrollo subterráneo total de 5,544 metros
- Triturador de mandíbula principal puesto en marcha en agosto
- Progreso de la Instalación de Almacenamiento de Relaves con llenado de terraplén de drenaje y instalación de tuberías
- Fuerza laboral aumentada a más de 250 empleados de Endeavour y 800 trabajadores contratados

El proyecto está en camino de comenzar la puesta en marcha de los sistemas hacia finales del cuarto trimestre de 2024, con enfoque en la instalación de filtros de relaves y concentrados, y en completar los sistemas de molienda, flotación y espesamiento.

Endeavour Silver Corp. (NYSE: EXK; TSX: EDR)는 멕시코 할리스코에 있는 테로네라 프로젝트에 대한 2024년 3분기 건설 진행 상황 업데이트를 제공했습니다. 해당 프로젝트는 77% 전반적인 완료율을 기록했고, 표면 밀 및 인프라 건설이 90%에 달하고 있습니다. 주요 내용은 다음과 같습니다:

- 현재까지 2억 5,800만 달러가 지출되었으며, 2억 7,000만 달러2억 7,100만 달러 예산에서 약속되었습니다.
- 총 5,544 미터의 지하 개발 진행
- 8월에 주요 조 크러셔 가동 시작
- 배수 임시 시설에서 배수 embankment 채우기 및 파이프 설치가 진행 중
- 250명 이상의 Endeavour 직원800명의 계약직 근로자로 인력 증가

프로젝트는 2024년 4분기 말에 시스템 커미셔닝을 시작할 예정이며, 테일링 및 농축 필터 설치와 분쇄, 부유 및 농축 시스템 완료에 중점을 두고 있습니다.

Endeavour Silver Corp. (NYSE: EXK; TSX: EDR) a fourni une mise à jour sur les progrès de construction de son Projet Terronera à Jalisco, au Mexique, pour le troisième trimestre de 2024. Le projet a atteint un taux d'achèvement global de 77%, avec la construction de la centrale de surface et des infrastructures à 90%. Les points clés incluent :

- 258 millions de dollars dépensés jusqu'à présent, avec 270 millions de dollars engagés sur un budget de 271 millions de dollars
- Développement souterrain totalisant 5 544 mètres
- Concasseur à mâchoire primaire mis en service en août
- Avancement de la structure de stockage des stériles avec le remplissage des remblais de drainage et l'installation de tuyaux
- Effectif augmenté à plus de 250 employés d'Endeavour et 800 travailleurs sous contrat

Le projet est sur la bonne voie pour commencer la mise en service des systèmes vers la fin du quatrième trimestre 2024, en mettant l'accent sur l'installation de filtres à stériles et à concentrés, ainsi que sur l'achèvement des systèmes de broyage, de flottation et d'épaississement.

Endeavour Silver Corp. (NYSE: EXK; TSX: EDR) hat ein Update zum Fortschritt der Bauarbeiten für das Terronera-Projekt in Jalisco, Mexiko, für das 3. Quartal 2024 bereitgestellt. Das Projekt hat einen Gesamtfortschritt von 77% erreicht, wobei der Bau der Oberflächenmühle und der Infrastruktur bei 90% steht. Zu den wichtigsten Punkten gehören:

- Bisher ausgegebene 258 Millionen Dollar, mit 270 Millionen Dollar verpflichtet aus einem Budget von 271 Millionen Dollar
- Unterirdische Entwicklung mit insgesamt 5.544 Metern
- Primär-Jaw-Crusher im August in Betrieb genommen
- Fortschritt der Tailings-Speicheranlage mit Füllung der Entwässerungsaufschüttung und Rohrinstallation
- Arbeitskraft auf über 250 Endeavour-Mitarbeiter und 800 Vertragsarbeiter erhöht

Das Projekt ist auf Kurs, die Inbetriebnahme der Systeme gegen Ende des 4. Quartals 2024 zu beginnen, mit dem Fokus auf die Installation von Tailings- und Konzentratsfiltern sowie den Abschluss der Mahlen-, Flotations- und Dicklegungssysteme.

Positive
  • Overall project progress reached 77% completion
  • Surface mill and infrastructure construction at 90% completion
  • $258 million of $271 million budget spent, with $270 million committed
  • Underground development totaled 5,544 metres
  • Primary jaw crusher commissioned in August
  • Project on track to begin commissioning systems by end of Q4 2024
Negative
  • None.

Insights

The Terronera project update demonstrates significant progress, with overall completion at 77% and surface construction at 90%. Key milestones include:

  • Commissioning of the primary jaw crusher
  • Completion of the Coarse Ore Stockpile and Reclaim tunnel
  • Advanced progress on grinding, thickening and flotation systems
  • Underground development reaching 5,544 meters

With $258 million spent and $270 million committed out of a $271 million budget, the project appears well-managed financially. The target to begin commissioning systems by Q4 2024 seems achievable, potentially leading to production ramp-up in early 2025.

This progress is positive for Endeavour Silver, as Terronera is set to become their flagship asset. The project's completion could significantly boost the company's production profile and potentially improve its cost structure, which may positively impact future financial performance.

Endeavour Silver's update highlights strong commitment to environmental, social and governance (ESG) principles:

  • Prioritizing safety with mine rescue equipment and refuge stations
  • Robust community engagement through local initiatives
  • Focus on environmental education and tree donation programs

These efforts demonstrate a proactive approach to maintaining social license to operate, which is important for mining projects. The company's investment in local infrastructure, education and entrepreneurship could foster positive long-term relationships with communities.

From an ESG perspective, the tailing storage facility (TSF) progress is particularly noteworthy. Proper TSF management is critical for environmental protection and risk mitigation. The detailed update on TSF construction suggests transparency and attention to this important aspect.

Overall, Endeavour's approach aligns with increasing investor focus on ESG factors, potentially enhancing the company's attractiveness to ESG-conscious investors and reducing operational risks.

VANCOUVER, British Columbia, Oct. 21, 2024 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q3 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos. All dollar ($) references in this news release are in United States dollars.

The Terronera project made substantial progress during the third quarter as the Upper Plant Platform nears completion. Surface mill and infrastructure construction reached 90%, further preparing for advancement into operations. Focus continues on the Lower Platform, where concrete work is well underway, and the Tailing Storage Facility, with underdrain embankment fill and pipe installation advancing at a good pace.

“We’re in the final construction phase with the finish line in sight,” commented Don Gray, Chief Operating Officer. “The Upper Platform is nearly complete, and the primary jaw crusher was commissioned, with rock crushed in August. The major focus is the Lower Platform and Tailing Storage Facility. Our dedicated Terronera team continues to meet the challenges both for developing the mine and constructing the mill facilities to keep the project on track to begin commissioning systems near the end of Q4.”

Q3 2024 Construction and Development Highlights

As of September 30, 2024, site works and activities included:

  • Safety – Health and safety for operational readiness is underway. The mine rescue equipment arrived, and team members are being recruited and trained. Two refuge stations were installed.
  • Community Relations – Local community support continues to be a priority. In Q3, the Company supported a series of local initiatives and investments such as: a municipal cooperative agreement; inauguration of an early-childhood development center; scholarships for university students in Santiago de Pinos; municipal road maintenance; workshops for business entrepreneurship for local residents; environmental education program for primary schools; community tree donation; and summer community workshops for children and youth.
  • Progress – Overall project progress (mine development and surface construction) reached 77% completion, with more than $258 million1 of the project's budget spent to date. Project commitments total $270 million1,2, 99% of the $271 million capital budget.

  • Mine Development – During the third quarter, 1,051 metres were developed underground for a project total of 5,544 metres. Furthermore:

    • Underground explosive magazines were completed and the explosive use permit application was submitted for approval, which is anticipated in Q4 2024.

    • Terronera main sump and pump station excavation and support were completed.

    • Development was nearly complete for the test stope that will be used to verify stope design criteria including opening span widths, length and height as well as establishing longhole drilling, blasting and backfill procedures.

    • Development ore was stockpiled on surface.

    • Slashing of an existing portal commenced for access to mine the high-gold grade La Luz vein, which is anticipated to be reached in H1 2025.
  • Upper Plant Platform Site – Mill and surface infrastructure construction was 90% complete and continues to transition to operations.

    • Primary Crusher – Primary jaw crusher was commissioned with rock crushed in August, marking a major project milestone.

    • Coarse Ore Stockpile and Reclaim ("COS") Tunnel – Reached 100% completion and pre-commissioning tests commenced.

    • Grinding and Thickening – Piping, mechanical, electrical, and instrumentation are expected to be completed in October.

    • Flotation – Compressor pressure vessel and air dryer systems were installed with piping connections in progress. Flotation equipment, including blowers, instrument, and valve installations are ongoing and scheduled for Q4 completion.

    • Raw and Process Water Tanks – Steel rings are in place and welding was over 90% complete. Inlet, outlet and access port installations, final weld testing, sand blast/mechanical cleaning, and painting are scheduled for completion in Q4.

  • Lower Facilities Platform and Tailing Storage Facility (TSF) – Lower Platform area was nearly 30% complete. Focus has been on completing the last section of the tailing filter bearing wall prior to starting the filter support deck; the first structural steel columns and beams were erected for the Concentration Filter building and equipment mechanical structures.

    • Main Embankment TSF – Excavation for the main embankment key trench was 100% complete, the secondary key was at 40% complete, and underdrain piping placement has been completed.

    • Tailing Filtration Area – More than 75% of the floor slab and 100% of the filter bearing wall for the tailing filter building has been poured. The tailing filters, which are stored at the Puerto Vallarta warehouse, are schedule to be transported to site for Q4 2024 installation.

    • Concentrate Filter Area – More than 80% of the floor slab and 75% of the pipe rack and equipment foundations in the concentrate filter area has been poured, and tank foundations and equipment pedestals were nearly complete.
  • Auxiliary Buildings – Laboratory and Plant Maintenance buildings reached 40% of completion.

    • Laboratory Building – Majority of the sheathing and insulation have been installed and steel studs are in place. Sheetrock and compressor and dryer installations are in progress.

    • Plant Maintenance Building – Structural steel installation started in late September.
  • Procurement –The project team continues to expedite pending arrivals. Procurement was 99% complete.

  • Onsite Personnel – At the end of Q3, the workforce increased to over 250 Endeavour Silver employees and over 800 contract workers, with the total number expected to decrease in Q4 2024 as commissioning begins.

Next Steps and Planning

The Terronera Project is tracking to begin commissioning systems near the end of Q4.

For Q4 2024, the tailing filter area, which was turned over to the mechanical contractor in early October, will allow focus on installing at least one tailing filter along with the concentrate filter using an extended work schedule to allow initial systems commissioning anticipated near the end of Q4. Grinding, flotation, and thickening systems will be mechanically completed in late October, allowing testing and ramp-up of these circuits to begin in November and December.

Mine development in Portals 1, 2, and 4 declines will continue, with longhole stopes being developed and initial production planned for Q4; ore will continue to be stockpiled for mill ramp-up. At La Luz, the portal is being constructed, and the orebody ramp access will advance in Q4.

The critical path remains the TSF, tailing concentrate filters construction, and the advancing underground mine.

Visit www.terronera.com, our dedicated project website, to stay informed on the ongoing development at Terronera. Explore updates, learn about our commitment to environmental stewardship, and discover the positive impacts on local communities.

About Endeavour Silver: Endeavour is a mid-tier precious metals company committed to sustainable and responsible mining practices. With operations in Mexico and the development of the new cornerstone mine in Jalisco State, the Company aims to contribute positively to the mining industry and the communities in which it operates. In addition, Endeavour has a portfolio of exploration projects in Mexico, Chile, and the United States, which has helped it achieve its goal of becoming a premier senior silver producer. 

Contact Information

Allison Pettit, Director of Investor Relations
Tel: (604) 640 4804
Email: apettit@edrsilver.com
Website: www.edrsilver.com

Follow Endeavour Silver on Facebook, X, Instagram and LinkedIn

Cautionary Note Regarding Forward-Looking Statements

This news release contains "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within applicable Canadian securities legislation. Such forward-looking statements and information herein include but are not limited to statements regarding the development and financing of the Terronera Project, including capital cost estimates, the anticipated timing of the project construction and commissioning, Terronera's forecasted operations, costs and expenditures, and the timing and results of various related activities. The Company does not intend to and does not assume any obligation to update forward-looking statements or information other than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties, and other factors that may cause Endeavor's actual results, level of activity, production levels, performance, or achievements, and its operations to be materially different from those expressed or implied by such statements. Such factors include but are not limited changes in production and costs guidance; the ongoing effects of inflation and supply chain issues on mine economics; national and local governments, legislation, taxation, controls, regulations and political or economic developments in Canada, Chile, the USA and Mexico; financial risks due to precious metals prices; operating or technical difficulties in mineral exploration, development and mining activities; risks and hazards of mineral exploration, development and mining; the speculative nature of mineral exploration and development; risks in obtaining necessary licenses and permits; continued compliance with the project loan debt facility; the ongoing effects of inflation and supply chain issues on the Terronera Project economics; fluctuations in the prices of silver and gold, fluctuations in the currency markets (particularly the Mexican peso, Chilean peso, Canadian dollar and US dollar); and challenges to the Company's title to properties; as well as those factors described in the section "risk factors" contained in the Company's most recent form 40F/Annual Information Form filed with the SEC and Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to the continued operation of the Company's mining operations, no material adverse change in the market price of commodities forecasted Terronera mine economics as of 2024, mining operations will operate, and the mining products will be completed under management's expectations and achieve their stated production outcomes, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or information, other factors may cause results to be materially different from those anticipated, described, estimated, assessed, or intended. There can be no assurance that any forward-looking statements or information will be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.


1 Financial figures are based on a preliminary estimate. Final unaudited figures will be released with the Q3 2024 financial statements on November 5, 2024.
2 Project commitments include total project expenditures.


FAQ

What is the current completion percentage of Endeavour Silver's Terronera Project (EXK)?

As of Q3 2024, Endeavour Silver's Terronera Project (EXK) has reached 77% overall completion, with surface mill and infrastructure construction at 90%.

How much of the Terronera Project (EXK) budget has been spent and committed?

As of Q3 2024, $258 million of the $271 million budget has been spent, with $270 million committed for the Terronera Project (EXK).

When is the Terronera Project (EXK) expected to begin commissioning systems?

The Terronera Project (EXK) is on track to begin commissioning systems near the end of Q4 2024.

What major milestone was achieved in the Terronera Project (EXK) during Q3 2024?

A major milestone achieved in Q3 2024 was the commissioning of the primary jaw crusher, with rock crushed in August.

Endeavour Silver Corp.

NYSE:EXK

EXK Rankings

EXK Latest News

EXK Stock Data

957.44M
261.48M
0.16%
40.53%
5.34%
Other Precious Metals & Mining
Basic Materials
Link
United States of America
Vancouver