enCore Energy Continues to Expand Uranium Production at the Alta Mesa Plant

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

enCore Energy reports significant progress in uranium production expansion at its Alta Mesa Plant in South Texas. The company is approaching flow capacity at the first of three ion exchange (IX) circuits, each with 2,500 gallons per minute capacity. Since June 2024 startup, Wellfield 7 has expanded from 27 injection and 34 recovery wells to 46 injection and 52 recovery wells, achieving a 2,100 gpm flow rate. The facility's total capacity of 7,500 gpm equals 1.5 million pounds of yellowcake annually when fully operational. The second IX circuit is planned for Q1/25, with the third circuit expected by end of 2025.

enCore Energy riporta significativi progressi nell'espansione della produzione di uranio presso il suo impianto di Alta Mesa nel sud del Texas. L'azienda sta raggiungendo la capacità di flusso nel primo dei tre circuiti di scambio ionico (IX), ciascuno con una capacità di 2.500 galloni al minuto. Dall'avvio nel giugno 2024, il Wellfield 7 è passato da 27 pozzi di iniezione e 34 pozzi di recupero a 46 pozzi di iniezione e 52 pozzi di recupero, raggiungendo una portata di 2.100 gpm. La capacità totale dell'impianto di 7.500 gpm corrisponde a 1,5 milioni di sterline di yellowcake all'anno quando sarà completamente operativo. Il secondo circuito IX è pianificato per il primo trimestre del 2025, mentre il terzo circuito è previsto entro la fine del 2025.

enCore Energy informa sobre avances significativos en la expansión de la producción de uranio en su Planta Alta Mesa en el sur de Texas. La compañía está acercándose a la capacidad de flujo en el primero de tres circuitos de intercambio iónico (IX), cada uno con una capacidad de 2,500 galones por minuto. Desde el inicio en junio de 2024, el Wellfield 7 ha crecido de 27 pozos de inyección y 34 pozos de recuperación a 46 pozos de inyección y 52 pozos de recuperación, logrando una tasa de flujo de 2,100 gpm. La capacidad total de la instalación de 7,500 gpm equivale a 1.5 millones de libras de yellowcake anualmente cuando esté completamente operativo. El segundo circuito IX está planeado para el primer trimestre de 2025, con el tercer circuito esperado para finales de 2025.

enCore Energy는 텍사스 남부의 Alta Mesa 플랜트에서 우라늄 생산 확대에 대한 중대한 진행 상황을 보고했습니다. 이 회사는 각각 분당 2,500갤론 용량을 갖춘 세 개의 이온교환(IX) 회로 중 첫 번째 회로에서 유량 용량에 접근하고 있습니다. 2024년 6월 가동 이후, Wellfield 7은 27개의 주입 정점과 34개의 회수 정점에서 46개의 주입 정점과 52개의 회수 정점으로 확대되어 2,100 gpm의 유량을 달성했습니다. 시설의 총 용량인 7,500 gpm은 완전히 가동될 때 연간 150만 파운드의 옐로우케이크에 해당합니다. 두 번째 IX 회로는 2025년 1분기로 예정되어 있으며, 세 번째 회로는 2025년 말까지 예상됩니다.

enCore Energy fait état de progrès significatifs dans l'expansion de la production d'uranium à son usine d'Alta Mesa dans le sud du Texas. L'entreprise s'approche de la capacité d'écoulement du premier de trois circuits d'échange d'ions (IX), chacun ayant une capacité de 2 500 gallons par minute. Depuis le démarrage en juin 2024, le Wellfield 7 est passé de 27 puits d'injection et 34 puits de récupération à 46 puits d'injection et 52 puits de récupération, atteignant un taux de flux de 2 100 gpm. La capacité totale de l'installation de 7 500 gpm équivaut à 1,5 million de livres de yellowcake par an lorsqu'elle est pleinement opérationnelle. Le deuxième circuit IX est prévu pour le premier trimestre 2025, tandis que le troisième circuit est attendu d'ici la fin de 2025.

enCore Energy berichtet über bedeutende Fortschritte bei der Erweiterung der Uranproduktion in seiner Alta Mesa-Anlage im Süden von Texas. Das Unternehmen nähert sich der Durchflusskapazität des ersten von drei Ionenaustauschschaltungen (IX), die jeweils eine Kapazität von 2.500 Gallonen pro Minute haben. Seit dem Start im Juni 2024 hat sich Wellfield 7 von 27 Injektions- und 34 Rückgewinnungsbohrungen auf 46 Injektions- und 52 Rückgewinnungsbohrungen erweitert, mit einer Durchflussrate von 2.100 gpm. Die Gesamtkapazität der Anlage von 7.500 gpm entspricht bei vollständigem Betrieb 1,5 Millionen Pfund Yellowcake pro Jahr. Der zweite IX-Kreis ist für das erste Quartal 2025 geplant, der dritte Kreis wird bis Ende 2025 erwartet.

Positive
  • Expansion of Wellfield 7 from 27/34 to 46/52 injection/recovery wells
  • Current flow rate achievement of 2,100 gpm, near first IX circuit capacity
  • Total facility capacity of 1.5 million pounds of yellowcake annually
  • Historical production of 5 million lbs U3O8 between 2005-2013
  • Substantial resource base with 3.41M lbs measured & indicated and 16.79M lbs inferred
Negative
  • Full production capacity won't be reached until end of 2025
  • Operating at partial capacity with only one of three IX circuits currently active

Insights

The expansion at Alta Mesa represents a significant operational milestone in uranium production capacity. The plant's ramp-up to 2,100 gpm on the first IX circuit (out of 2,500 gpm capacity) demonstrates strong execution. The planned expansion to three IX circuits with a total capacity of 7,500 gpm could enable 1.5 million pounds of annual uranium production when fully operational.

The wellfield expansion from 27 injection/34 recovery wells to 46 injection/52 recovery wells shows robust operational scaling. With uranium spot prices near $106/lb, reaching full production capacity could generate substantial revenue. The phased approach to expansion, with the second and third IX circuits coming online through 2025, provides a measured path to full capacity while managing operational risks.

The project's resource base is substantial with 3.41 million pounds of Measured & Indicated resources and 16.79 million pounds of Inferred resources. The average grades of 0.109% U3O8 for M&I and 0.120% U3O8 for Inferred are favorable for ISR mining. The large private land position of 200,000+ acres provides significant exploration upside potential. The proven production history of 5 million pounds between 2005-2013 validates the technical viability of the operation.

NASDAQ:EU
TSXV:EU
www.encoreuranium.com 

DALLAS, Oct. 24, 2024 /PRNewswire/ - enCore Energy Corp. (NASDAQ: EU) (TSXV: EU) (the "Company" or "enCore"), a uranium producer and America's Clean Energy Company™, today provided an update on the production ramp up at its South Texas Alta Mesa In-Situ Recovery ("ISR") Uranium Central Processing Plant ("Alta Mesa CPP") and Wellfield. The Company has achieved an important milestone in the expansion of production and is now nearing flow capacity at the first of Alta Mesa CPP's three ion exchange circuits ("IX circuits"). The three IX circuits can provide dissolved uranium in groundwater to the Alta Mesa CPP from multiple wellfields simultaneously.

Significant operational highlights include:

  • The three IX circuits each have 2,500 gallons per minute ("gpm") capacity. The first IX circuit was commissioned in June 2024, with the second IX circuit planned to commence operation in Q1/25 and the third IX circuit planned to be online by year end of 2025. Ion exchange is a filtration system which removes liquid uranium from groundwater before it is dried and processed into U3O8 ("yellowcake" or "uranium") at the CPP;
  • The Alta Mesa CPP's three IX circuits have a total flow rate of 7,500 gpm, equaling an annual recovery capacity of 1.5 million pounds of yellowcake when operating at full capacity;
  • Since the June 2024 start-up of the Alta Mesa CPP, enCore has expanded Wellfield 7 from 27 injection and 34 recovery wells to 46 injection and 52 recovery wells while bringing the flow rate up to 2,100 gpm. Wellfield 7 is projected to provide the initial feed to all three IX circuits;
  • The next ramp up currently underway, with an estimated completion date of November 2024, will further expand the number of injection and production wells at Wellfield 7 and is expected to increase flow rates to the capacity of the first IX circuit.

enCore Energy's Alta Mesa Plant (CNW Group/enCore Energy Corp.)

Paul Goranson, the Company's Chief Executive Officer said, "We have been very pleased with the results from the first phase at Alta Mesa and production from the initial startup. As we expand Wellfield 7, we expect continued success which will build up flow rates to support all three of the IX circuits at the Alta Mesa CPP.  We continue to work towards reaching full capacity through 2025 with plans to be fully operational at all three of our IX circuits."

enCore Energy CPP Process (IX Circuits operate within Resin Reloading) (CNW Group/enCore Energy Corp.)

Alta Mesa In-Situ Recovery ("ISR") Uranium Central Processing Plant ("CPP") & Wellfield ("Alta Mesa")

The Alta Mesa CPP and Wellfield hosts a fully licensed and constructed ISR uranium plant, located on 200,000+ acres of private land in the state of Texas. Alta Mesa is enCore's second producing location and operates under a 70/30 joint venture between enCore Energy Corp. and Boss Energy Limited (ASX:BOE; OTCQX:BQSSF) with enCore Energy as the managing operator.

Total operating capacity at the Alta Mesa CPP is currently 1.5 million lbs. U3O8 ("uranium") per year with an additional drying and packaging capacity of more than 0.5 million lbs. U3O8. The Alta Mesa CPP historically produced nearly 5 million lbs. U3O8 between 2005 and 2013, when full production was curtailed as a result of low uranium prices. 

Alta Mesa CPP and Wellfield highlights:

  • Alta Mesa CPP's operations are located on 200,000 acres of private land, with 100% of minerals privately owned, and in a supportive jurisdiction with primary regulatory authority residing with the State of Texas.
  • The Alta Mesa CPP utilizes well-known ISR technology to extract uranium in a non-invasive process using natural groundwater and oxygen, coupled with a proven ion exchange process, to recover the uranium.

Alta Mesa & Mesteña Grande Mineral
Resource Summary (0.30 GT cutoff)1,2

    Tons    

Avg. Grade

(% U3O8)

    Pounds    

Total Measured Mineral Resource1

54,000

0.152

164,000

Alta Mesa Indicated Mineral Resource

1,397,000

0.106

2,959,000

Mesteña Grande Indicated Mineral Resource

119,000

0.120

287,000

Total Measured & Indicated Resources

1,570,000

0.109

3,410,000

Alta Mesa Inferred Mineral Resource

1,263,000

0.126

3,192,000

Mesteña Grande Inferred Mineral Resource

5,733,000

0.119

13,601,000

Total Inferred Resources

6,996,000

0.120

16,793,000

1,2 Represents that portion of the in-place mineral resource that are estimated to be recoverable within existing wellfields. Wellfield recovery factors have not been applied to indicated and inferred mineral resources. As reported in the NI-43-101 Technical Report Summary for the Alta Mesa Uranium Project, Brooks and Jim Hogg Counties, Texas, USA completed by Doug Beahm, PE, PG, of BRS Engineering. (Effective January 19, 2023).


John M. Seeley, Ph.D., P.G., C.P.G., enCore's Manager of Geology and Exploration, and a Qualified Person under NI 43-101, has reviewed and approved the technical disclosure in this news release on behalf of the Company.

About enCore Energy Corp.

enCore Energy Corp., America's Clean Energy Company™, is committed to providing clean, reliable, and affordable fuel for nuclear energy as the only United States uranium producer with multiple production facilities in operation. The enCore team is led by industry experts with extensive knowledge and experience in all aspects of In-Situ Recovery ("ISR") uranium operations and the nuclear fuel cycle. enCore solely utilizes ISR for uranium extraction, a well-known and proven technology co-developed by the leaders at enCore Energy.

Following upon enCore's demonstrated production success in South Texas, future projects in the production pipeline include the Dewey-Burdock project in South Dakota and the Gas Hills project in Wyoming. The Company holds other assets including significant New Mexico resources, non-core assets and proprietary databases. enCore is committed to working with local communities and indigenous governments to create positive impact from corporate developments.

Cautionary Note Regarding Forward Looking Statements: 

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Certain information contained in this news release, including: any information relating to the Company being a leading uranium company, statements regarding future or potential production, and any other statements regarding future expectations, beliefs, goals or prospects; may constitute "forward-looking information" and "forward-looking statements" within the meaning of applicable Canadian and United States securities laws and regulations (collectively, "forward-looking statements"). All statements in this news release that are not statements of historical fact (including statements containing the words "expects", "is expected", "does not expect", "plans", "anticipates", "does not anticipate", "believes", "intends", "estimates", "projects", "potential", "scheduled", "forecast", "budget" and similar expressions or variations (including negative variations) of such words and phrases, or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken) should be considered forward-looking statements. All such forward-looking statements are subject to important risk factors and uncertainties, many of which are beyond the company's ability to control or predict. Forward-looking statements necessarily involve known and unknown risks, including, without limitation, risks associated with general economic conditions; adverse industry events; future legislative and regulatory developments; the ability of enCore to implement its business strategies; including achieving expected levels of production at Rosita and Alta Mesa in the planned time frame or at all; and other risks. A number of important factors could cause actual results or events to differ materially from those indicated or implied by such forward-looking statements, including without limitation exploration and development risks, changes in commodity prices, access to skilled mining personnel, the results of exploration and development activities; production risks; uninsured risks; regulatory risks; defects in title; the availability of materials and equipment, timeliness of government approvals and unanticipated environmental impacts on operations; litigation risks; risks posed by the economic and political environments in which the Company operates and intends to operate; increased competition; assumptions regarding market trends and the expected demand and desires for the Company's products and proposed products; reliance on industry equipment manufacturers, suppliers and others; the failure to adequately protect intellectual property; the failure to adequately manage future growth; adverse market conditions, the failure to satisfy ongoing regulatory requirements and factors relating to forward looking statements listed above which include risks as disclosed in the Company's annual information form filings. Should one or more of these risks materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual results may vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected. The Company assumes no obligation to update the information in this communication, except as required by law. Additional information identifying risks and uncertainties is contained in filings by the Company with the various securities commissions which are available online at www.sec.gov and www.sedar.com. Forward-looking statements are provided for the purpose of providing information about the current expectations, beliefs and plans of management. Such statements may not be appropriate for other purposes and readers should not place undue reliance on these forward-looking statements, that speak only as of the date hereof, as there can be no assurance that the plans, intentions or expectations upon which they are based will occur. Such information, although considered reasonable by management at the time of preparation, may prove to be incorrect and actual results may differ materially from those anticipated. Forward-looking statements contained in this news release are expressly qualified by this cautionary statement.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/encore-energy-continues-to-expand-uranium-production-at-the-alta-mesa-plant-302285741.html

SOURCE enCore Energy Corp.

FAQ

What is the current production capacity at enCore Energy's Alta Mesa Plant (EU)?

The Alta Mesa Plant currently has a total operating capacity of 1.5 million lbs U3O8 per year when operating at full capacity with all three IX circuits running at 7,500 gpm total flow rate.

When will enCore Energy (EU) complete the Alta Mesa Plant expansion?

enCore Energy plans to complete the Alta Mesa Plant expansion by the end of 2025, with the second IX circuit starting in Q1/25 and the third circuit by year-end 2025.

What is the current flow rate at enCore Energy's Alta Mesa Wellfield 7 (EU)?

As of October 2024, Wellfield 7 is operating at a flow rate of 2,100 gpm, with plans to increase to the first IX circuit's full capacity of 2,500 gpm by November 2024.

enCore Energy Corp.

NASDAQ:EU

EU Rankings

EU Latest News

EU Stock Data

607.01M
180.79M
2.12%
44.62%
4.22%
Uranium
Energy
Link
United States of America
Corpus Christi