Operator of MVP Enters Into Consent Agreement with PHMSA
- The Consent Agreement outlines actions to reassure the public of MVP's integrity and commitment to safe construction and operation
- Enhancements to coating, inspection, and cathodic protection processes
- Accelerated timeline for inline inspections and cathodic protection surveys
- No material impact on project cost or schedule
Providing Transparency to Reassure Public Confidence and Reinforce MVP Integrity
In accordance with the terms of the Agreement, Equitrans and Mountain Valley Pipeline, LLC (Mountain Valley) agree with PHMSA that transparently outlining the steps being taken by the MVP project team to responsibly complete construction is of critical importance and will reinforce public confidence in the safe operation of the pipeline. The terms of the Consent Agreement are not expected to have a material impact on the total project cost or schedule.
“The terms of this Consent Agreement are directly aligned with Equitrans’ core values, which include continually striving to go above and beyond regulatory compliance requirements,” said Diana Charletta, Equitrans’ president and chief operating officer. “Importantly, the Agreement outlines actions that are designed to reassure the public of MVP’s integrity and demonstrates our commitment to safe, responsible construction and in-service operations. Safety has been, and will remain, MVP’s top priority, and we are committed to meeting or exceeding all applicable regulations to ensure the safety of our communities, employees, contractors, and assets.”
Key Safety Highlights of the Consent Agreement Include:
-
Enhancing MVP’s existing coating, remediation, and inspection processes by:
- Authorizing KTA-Tator, Inc. (KTA), a well-established engineering firm with expertise in the evaluation of protective coatings for numerous applications, to serve as the independent, third-party party pipeline coating expert
- Accepting KTA’s endorsement of MVP’s pipeline coating procedures and authorizing MVP to continue implementing those procedures throughout the project’s remaining construction phase
- Authorizing KTA to continue conducting a comprehensive field audit of MVP’s pipeline coating activities, including the deployment of multiple inspectors to observe ongoing coating assessment and remediation and the performance of adhesion testing at each spread
- Accelerating MVP’s previously planned series of inline inspections to verify the integrity of the pipeline
- Accelerating the regulatory timeline for conducting comprehensive cathodic protection surveys
In accordance with the project's comprehensive pipeline integrity program, previously approved by federal and state agencies, the MVP project team has been proactive in its approach to pipeline safety and integrity. Mountain Valley will continue to work closely with PHMSA and other regulators to maintain its high standards of safety and environmental stewardship as the project enters its final construction phase.
About Mountain Valley Pipeline
The Mountain Valley Pipeline (MVP) is a proposed underground, interstate natural gas pipeline system that spans approximately 303 miles from northwestern
View source version on businesswire.com: https://www.businesswire.com/news/home/20231003118892/en/
Media inquiries:
Natalie Cox – VP, Communications and Corporate Affairs / ncox@equitransmidstream.com
Source: Equitrans Midstream Corporation