Two Enlight Facilities Win Bids in the Israel Electricity Authority's Energy Storage Tender and the Company Expects to Construct Total Storage Capacity in the Range of 1,300 to 1,900 MWh
Enlight Renewable Energy (NASDAQ: ENLT) has won bids for two energy storage facilities in southern Israel through the Israel Electricity Authority's first availability tariff tender. The facilities, Neot Smadar and Ohad, have a combined grid connection capacity of 300 MW AC, enabling total storage capacity of 1,300 MWh, potentially expanding to 1,900 MWh in the deregulated market.
The projects, expected to be operational by 2028, will require construction costs between $210-250 million and are projected to generate annual revenues of $75-85 million with EBITDA of $37-42 million. These facilities represent 20% of the total capacity awarded in the tender, strengthening Enlight's position in Israel's storage market. The company currently has approximately 8 GWh of mature storage projects set for operation by 2027 and a development portfolio of about 25 GWh, with 6 GWh located in Israel.
Enlight Renewable Energy (NASDAQ: ENLT) ha vinto gare per due impianti di stoccaggio energetico nel sud di Israele attraverso il primo bando per la tariffa di disponibilità dell'Autorità Elettrica di Israele. Gli impianti, Neot Smadar e Ohad, hanno una capacità di connessione alla rete combinata di 300 MW AC, consentendo una capacità totale di stoccaggio di 1.300 MWh, con la possibilità di espandersi a 1.900 MWh nel mercato deregolarizzato.
I progetti, che dovrebbero essere operativi entro il 2028, richiederanno costi di costruzione compresi tra $210-250 milioni e si prevede genereranno ricavi annuali di $75-85 milioni con un EBITDA di $37-42 milioni. Questi impianti rappresentano il 20% della capacità totale assegnata nel bando, rafforzando la posizione di Enlight nel mercato dello stoccaggio in Israele. L'azienda attualmente ha circa 8 GWh di progetti di stoccaggio maturi previsti per il 2027 e un portafoglio di sviluppo di circa 25 GWh, di cui 6 GWh situati in Israele.
Enlight Renewable Energy (NASDAQ: ENLT) ha ganado licitaciones para dos instalaciones de almacenamiento de energía en el sur de Israel a través de la primera licitación de tarifa de disponibilidad de la Autoridad de Electricidad de Israel. Las instalaciones, Neot Smadar y Ohad, tienen una capacidad de conexión a la red combinada de 300 MW AC, lo que permite una capacidad total de almacenamiento de 1,300 MWh, con la posibilidad de expandirse a 1,900 MWh en el mercado desregulado.
Se espera que los proyectos estén operativos para 2028 y requerirán costos de construcción entre $210-250 millones, proyectándose que generen ingresos anuales de $75-85 millones con un EBITDA de $37-42 millones. Estas instalaciones representan el 20% de la capacidad total adjudicada en la licitación, fortaleciendo la posición de Enlight en el mercado de almacenamiento de Israel. La empresa actualmente tiene aproximadamente 8 GWh de proyectos de almacenamiento maduros programados para operar en 2027 y un portafolio de desarrollo de alrededor de 25 GWh, con 6 GWh ubicados en Israel.
Enlight Renewable Energy (NASDAQ: ENLT)는 이스라엘 남부에 두 개의 에너지 저장 시설에 대한 입찰에서 승리하였습니다. 이는 이스라엘 전기청의 첫 번째 가용성 요금 입찰을 통해 이루어진 것입니다. Neot Smadar와 Ohad 시설은 300 MW AC의 결합된 전력망 연결 용량을 가지고 있으며, 총 저장 용량은 1,300 MWh로, 규제되지 않은 시장에서는 1,900 MWh로 확장될 가능성이 있습니다.
2028년까지 운영될 것으로 예상되는 이 프로젝트들은 $210-250 백만의 건설 비용이 필요하며, 연간 수익은 $75-85 백만으로 예상되며 EBITDA는 $37-42 백만으로 예상됩니다. 이 시설들은 입찰에서 할당된 총 용량의 20%를 차지하여 이스라엘의 저장 시장에서 Enlight의 입지를 강화합니다. 현재 이 회사는 2027년까지 운영될 약 8 GWh의 성숙한 저장 프로젝트를 보유하고 있으며, 약 25 GWh의 개발 포트폴리오를 가지고 있고, 이 중 6 GWh는 이스라엘에 위치해 있습니다.
Enlight Renewable Energy (NASDAQ: ENLT) a remporté des appels d'offres pour deux installations de stockage d'énergie dans le sud d'Israël grâce à la première offre de tarif de disponibilité de l'Autorité Électrique d'Israël. Les installations, Neot Smadar et Ohad, ont une capacité de connexion au réseau combinée de 300 MW AC, permettant une capacité de stockage totale de 1.300 MWh, pouvant potentiellement s'étendre à 1.900 MWh sur le marché déréglementé.
Les projets, qui devraient être opérationnels d'ici 2028, nécessiteront des coûts de construction compris entre $210-250 millions et devraient générer des revenus annuels de 75 à 85 millions de dollars avec un EBITDA de 37 à 42 millions de dollars. Ces installations représentent 20 % de la capacité totale attribuée dans l'appel d'offres, renforçant la position d'Enlight sur le marché du stockage en Israël. L'entreprise dispose actuellement d'environ 8 GWh de projets de stockage matures prévus pour 2027 et d'un portefeuille de développement d'environ 25 GWh, dont 6 GWh situés en Israël.
Enlight Renewable Energy (NASDAQ: ENLT) hat Ausschreibungen für zwei Energiespeicheranlagen im Süden Israels gewonnen, und zwar im Rahmen der ersten Verfügbarkeitstarif-Ausschreibung der israelischen Elektrizitätsbehörde. Die Anlagen, Neot Smadar und Ohad, verfügen über eine kombinierte Netzanschlusskapazität von 300 MW AC, was eine Gesamtspeicherkapazität von 1.300 MWh ermöglicht, die im deregulierten Markt auf bis zu 1.900 MWh erweitert werden kann.
Die Projekte, die voraussichtlich bis 2028 in Betrieb genommen werden, erfordern Baukosten zwischen $210-250 Millionen und werden voraussichtlich jährliche Einnahmen von $75-85 Millionen mit einem EBITDA von $37-42 Millionen generieren. Diese Anlagen repräsentieren 20% der insgesamt im Ausschreibungsverfahren vergebenen Kapazität und stärken die Position von Enlight im israelischen Speichermarkt. Das Unternehmen hat derzeit etwa 8 GWh ausgereifter Speicherprojekte, die bis 2027 in Betrieb genommen werden sollen, sowie ein Entwicklungsportfolio von etwa 25 GWh, wobei sich 6 GWh in Israel befinden.
- Won 20% of total capacity in Israel's energy storage tender
- Projects expected to generate $75-85M annual revenue
- Projected annual EBITDA of $37-42M
- Potential to increase storage capacity from 1,300 MWh to 1,900 MWh
- Strong pipeline with 8 GWh of mature projects by 2027
- High construction costs of $210-250M required
- Long timeline to operation (2028)
- Five-year lock-in period before market rate transition
Insights
The successful bid for two energy storage facilities marks a strategic coup for Enlight, securing 20% of Israel's total tender capacity. The projects' financial profile is particularly compelling, with projected EBITDA margins of approximately 49-50%, indicating strong operational efficiency and attractive economics in the energy storage sector.
The tender structure provides a sophisticated dual-phase revenue model: an initial five-year period with guaranteed availability tariffs, followed by the flexibility to participate in the deregulated market. This hybrid approach offers both revenue stability and upside potential, while the option to expand storage capacity from 1,300 MWh to 1,900 MWh provides valuable operational flexibility.
The strategic value extends beyond immediate financial returns. These facilities will enhance Enlight's competitive moat in Israel's energy storage market, where the company uniquely spans both medium and high-voltage storage sectors. With 8 GWh of mature storage projects expected online by 2027 and a development pipeline of 25 GWh, Enlight is positioning itself as a dominant player in the region's energy transition.
The projects' location in southern Israel carries additional strategic significance, addressing grid stability needs in a region important for the country's energy security. The 2028 operational timeline aligns with Israel's renewable energy targets and positions Enlight to capitalize on the expected growth in demand for grid-scale storage solutions.
The Company continues to lead the energy storage sector in Israel, as part of the accelerated development of energy storage systems in Europe and the United States
TEL AVIV, Israel, Feb. 17, 2025 (GLOBE NEWSWIRE) -- Enlight Renewable Energy (“Enlight”, "the Company”, NASDAQ: ENLT, TASE: ENLT.TA), a leading renewable energy platform, announced today that two of the Company’s energy storage facilities have won bids in the Israel Electricity Authority's first availability tariff tender process. The two sites, Neot Smadar and Ohad, are located in the south of Israel and have a combined grid connection capacity of 300 MW AC.
According to the tender's terms, after supplying power at the availability tariff rate for five years, the Company may transition to selling electricity into the deregulated market as well as increase the facilities’ storage capacity. Securing a grid connection of 300 MW AC will allow Enlight to build projects with a total storage capacity of 1,300 MWh, potentially rising to 1,900 MWh following the transition into the deregulated market. According to the tender's terms, the projects are expected to reach commercial operation by 2028.
The combined construction cost of the two facilities is expected to range between
Enlight has approximately 8 GWh of Mature1 storage projects that are expected to enter into operations by 2027. In addition, the Company has a portfolio of energy storage assets in various stages of development totaling approximately 25 GWh, of which about 6 GWh are located in Israel. The two sites selected in the tender represent
Gilad Peled, CEO of Enlight MENA commented, "Enlight is proud to lead the energy storage revolution in Israel with a significant double win, representing
1 Mature projects are defined as currently operating, under construction, and pre-construction (with construction start within a 0-12 month timeframe).
About Enlight Renewable Energy
Founded in 2008, Enlight develops, finances, constructs, owns, and operates utility-scale renewable energy projects. Enlight operates across the three largest renewable segments today: solar, wind and energy storage. A global platform, Enlight operates in the United States, Israel and 10 European countries. Enlight has been traded on the Tel Aviv Stock Exchange since 2010 (TASE: ENLT) and completed its U.S. IPO (Nasdaq: ENLT) in 2023. Learn more at www.enlightenergy.co.il.
Contacts:
Yonah Weisz
Director IR
investors@enlightenergy.co.il
Erica Mannion or Mike Funari
Sapphire Investor Relations, LLC
+1 617 542 6180
investors@enlightenergy.co.il
Cautionary Note Regarding Forward-Looking Statements
This press release contains forward-looking statements within the meaning of the U.S. Private Securities Litigation Reform Act of 1995. We intend such forward-looking statements to be covered by the safe harbor provisions for forward-looking statements as contained in Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. All statements contained in this press release other than statements of historical fact, including, without limitation, statements regarding the Company’s expectations relating to the Project, the PPA and the related interconnection agreement and lease option, and the completion timeline for the Project, are forward-looking statements. The words “may,” “might,” “will,” “could,” “would,” “should,” “expect,” “plan,” “anticipate,” “intend,” “target,” “seek,” “believe,” “estimate,” “predict,” “potential,” “continue,” “contemplate,” “possible,” “forecasts,” “aims” or the negative of these terms and similar expressions are intended to identify forward-looking statements, though not all forward-looking statements use these words or expressions. These statements are neither promises nor guarantees, but involve known and unknown risks, uncertainties and other important factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements, including, but not limited to, the following: our ability to site suitable land for, and otherwise source, renewable energy projects and to successfully develop and convert them into Operational Projects; availability of, and access to, interconnection facilities and transmission systems; our ability to obtain and maintain governmental and other regulatory approvals and permits, including environmental approvals and permits; construction delays, operational delays and supply chain disruptions leading to increased cost of materials required for the construction of our projects, as well as cost overruns and delays related to disputes with contractors; our suppliers’ ability and willingness to perform both existing and future obligations; competition from traditional and renewable energy companies in developing renewable energy projects; potential slowed demand for renewable energy projects and our ability to enter into new offtake contracts on acceptable terms and prices as current offtake contracts expire; offtakers’ ability to terminate contracts or seek other remedies resulting from failure of our projects to meet development, operational or performance benchmarks; various technical and operational challenges leading to unplanned outages, reduced output, interconnection or termination issues; the dependence of our production and revenue on suitable meteorological and environmental conditions, and our ability to accurately predict such conditions; our ability to enforce warranties provided by our counterparties in the event that our projects do not perform as expected; government curtailment, energy price caps and other government actions that restrict or reduce the profitability of renewable energy production; electricity price volatility, unusual weather conditions (including the effects of climate change, could adversely affect wind and solar conditions), catastrophic weather-related or other damage to facilities, unscheduled generation outages, maintenance or repairs, unanticipated changes to availability due to higher demand, shortages, transportation problems or other developments, environmental incidents, or electric transmission system constraints and the possibility that we may not have adequate insurance to cover losses as a result of such hazards; our dependence on certain operational projects for a substantial portion of our cash flows; our ability to continue to grow our portfolio of projects through successful acquisitions; changes and advances in technology that impair or eliminate the competitive advantage of our projects or upsets the expectations underlying investments in our technologies; our ability to effectively anticipate and manage cost inflation, interest rate risk, currency exchange fluctuations and other macroeconomic conditions that impact our business; our ability to retain and attract key personnel; our ability to manage legal and regulatory compliance and litigation risk across our global corporate structure; our ability to protect our business from, and manage the impact of, cyber-attacks, disruptions and security incidents, as well as acts of terrorism or war; the potential impact of the current conflicts in Israel on our operations and financial condition and Company actions designed to mitigate such impact; changes to existing renewable energy industry policies and regulations that present technical, regulatory and economic barriers to renewable energy projects; the reduction, elimination or expiration of government incentives for, or regulations mandating the use of, renewable energy; our ability to effectively manage our supply chain and comply with applicable regulations with respect to international trade relations, tariffs, sanctions, export controls and anti-bribery and anti-corruption laws; our ability to effectively comply with Environmental Health and Safety and other laws and regulations and receive and maintain all necessary licenses, permits and authorizations; our performance of various obligations under the terms of our indebtedness (and the indebtedness of our subsidiaries that we guarantee) and our ability to continue to secure project financing on attractive terms for our projects; limitations on our management rights and operational flexibility due to our use of tax equity arrangements; potential claims and disagreements with partners, investors and other counterparties that could reduce our right to cash flows generated by our projects; our ability to comply with tax laws of various jurisdictions in which we currently operate as well as the tax laws in jurisdictions in which we intend to operate in the future; the unknown effect of the dual listing of our ordinary shares on the price of our ordinary shares; various risks related to our incorporation and location in Israel; the costs and requirements of being a public company, including the diversion of management’s attention with respect to such requirements; certain provisions in our Articles of Association and certain applicable regulations that may delay or prevent a change of control; and other risk factors set forth in the section titled “Risk factors” in our Annual Report on Form 20-F for the fiscal year ended December 31, 2023, filed with the Securities and Exchange Commission (the “SEC”) and our other documents filed with or furnished to the SEC.
These statements reflect management’s current expectations regarding future events and speak only as of the date of this press release. You should not put undue reliance on any forward-looking statements. Although we believe that the expectations reflected in the forward-looking statements are reasonable, we cannot guarantee that future results, levels of activity, performance and events and circumstances reflected in the forward-looking statements will be achieved or will occur. Except as may be required by applicable law, we undertake no obligation to update or revise publicly any forward-looking statements, whether as a result of new information, future events or otherwise, after the date on which the statements are made or to reflect the occurrence of unanticipated events.

FAQ
What is the expected revenue from ENLT's new Israeli storage facilities?
How much storage capacity will ENLT's new Israeli facilities provide?
When will ENLT's Neot Smadar and Ohad storage facilities be operational?
What is the construction cost for ENLT's new Israeli storage facilities?
What percentage of Israel's storage tender capacity did ENLT win?