Eldorado Provides 2023 Production and Cost Guidance and Outlines Five-Year Growth Profile; Achieving Approximately 700K Ounces of Gold Production in 2027
Eldorado Gold Corporation announced its 2023 production and cost guidance, projecting gold production between 475,000 to 515,000 ounces. Average cash operating costs are expected to be $760 to $860 per ounce sold. The company anticipates total growth capital expenditures of $394 to $437 million, primarily for the Skouries project. Eldorado also highlighted a five-year outlook, predicting a 55% increase in gold production by 2027, with first production from Skouries anticipated in the second half of 2025. The guidance reflects challenges such as inflationary pressures affecting operational costs.
- Projected gold production growth of 55% from 2022 to 2027.
- First production from Skouries expected by H2 2025, adding significant copper production.
- Strong commitment to exploration and resource development across key jurisdictions.
- Slight decrease in 2023 production guidance due to production plan modifications.
- Higher operating costs driven by inflationary pressures on key consumables and labor.
VANCOUVER, British Columbia, Feb. 23, 2023 (GLOBE NEWSWIRE) -- Eldorado Gold Corporation (“Eldorado” or the “Company”) provides detailed 2023 production and cost guidance and five-year production outlook. All financial figures stated within this release are in U.S. dollars unless otherwise stated.
2023 Guidance Highlights
- Gold production of 475,000 to 515,000 ounces.
- Average Cash operating costs(1) of
$760 t o$860 per ounce sold. - Average Total operating costs(1) of
$860 t o$960 per ounce sold. - Average All-in sustaining costs(1) (“AISC”) of
$1,190 t o$1,290 per ounce sold. - Total Growth Capital(1) of
$394 t o$437 million , including$240 t o$260 million towards the advancement of the Skouries project. - Total Sustaining Capital(1) of
$114 t o$139 million . - Exploration expenditures of
$28 t o$31 million , focused on resource conversion drilling at Lamaque and Efemcukuru and resource growth and discovery in Quebec, Turkiye and Greece. An additional$7 t o$10 million of non-sustaining exploration expenditures is included in growth capital.
(1) These financial measures are non-IFRS financial measures. Certain additional disclosures for non-IFRS financial measures and ratios have been incorporated by reference, and additional detail can be found at the end of this press release and in the section 'Non-IFRS and Other Financial Measures and Ratios’ of Eldorado’s December 31, 2021 MD&A.
Five-Year Outlook
- Skouries incorporated into the five-year production guidance, with first production expected in the second half of 2025.
- Gold production of 675,000 to 735,000 ounces by 2027, resulting in growth of
55% over the five-year period, from 2022 production and a compound annual growth rate of over9% . - Continued strong commitment to exploration to unlock the outstanding potential of the Company’s brownfields property portfolio and identifying and developing new opportunities in Eldorado’s focus jurisdictions.
- Addition of critical mineral production, primarily copper, is not currently reflected in the five-year outlook.
“Eldorado is committed to growing a safe, sustainable and high-quality gold business, creating value today and for the future,” said George Burns, Eldorado’s President and Chief Executive Officer. “2022 proved to be a pivotal year for Eldorado. As we look forward to 2023 and beyond, we have taken a disciplined approach to business planning and capital allocation focused on investments that will generate strong returns and cash flow from our portfolio of long-life assets.”
“The addition of Skouries to our five-year production outlook provides significant near-term growth and positions the Company to deliver strong operational and financial performance. Additionally, Skouries is expected to produce on average 67 million pounds of copper per year, contributing to the supply chain of critical minerals in a socially and environmentally responsible way, and reducing our overall cash cost profile with the addition of material by-product credits,” added Burns.
The Company’s 2023 consolidated gold production is forecast to be between 475,000 to 515,000 ounces at an average cash operating cost(1) of
Similar to 2022, quarter-to-quarter gold production in 2023 is expected to fluctuate during the year, with higher production expected in the second half, accounting for the full commissioning of the agglomeration drum at Kisladag expected in the first half and reflecting some seasonality impacts at our operating sites.
(1) Cash operating costs per ounce sold and AISC per ounce sold are non-IFRS financial measures. Certain additional disclosures for non-IFRS financial measures and ratios have been incorporated by reference, and additional detail can be found at the end of this press release and in the section ‘Non-IFRS and Other Financial Measures and Ratios' of Eldorado’s December 31, 2021, MD&A.
Five-Year Gold Production Outlook
Production (oz) | 2023E | 2024E | 2025E(1) | 2026E | 2027E |
Kisladag | 160,000 -170,000 | 195,000 -205,000 | 180,000 - 190,000 | 150,000 - 160,000 | 165,000 - 175,000 |
Lamaque | 170,000 - 180,000 | 180,000 - 190,000 | 175,000 - 185,000 | 180,000 - 200,000 | 180,000 - 200,000 |
Efemcukuru | 80,000 - 90,000 | 75,000 - 85,000 | 75,000 - 85,000 | 75,000 - 85,000 | 60,000 - 70,000 |
Olympias | 60,000 - 75,000 | 65,000 - 75,000 | 75,000 - 85,000 | 80,000 - 90,000 | 75,000 - 85,000 |
Skouries | - | - | 80,000 - 90,000(2) | 145,000 - 155,000 | 195,000 - 205,000 |
Total(3) | 475,000 - 515,000 | 515,000 - 555,000 | 585,000 - 635,000 | 630,000 - 690,000 | 675,000 - 735,000 |
(1) Includes expected pre-commercial production from Skouries.
(2) First production at Skouries is expected in H2 2025, followed by a ramp-up and commercial production by the end of 2025.
(3) Figures may not down add due to rounding.
2023 Cost(1) and Capital Expenditure Guidance
2023E | 2023E | |||
Consolidated Costs | Corporate ($ millions) | |||
Cash Operating Cost – C1 ($/oz sold) | 760 – 860 | General and Administrative | 35 – 38 | |
Total Cash Cost – C2 ($/oz sold) | 860 – 960 | Exploration & Evaluation(2,3) | 28 – 31 | |
AISC ($/oz sold) | 1,190 – 1,290 | Depreciation | 265 – 275 | |
Kisladag | Growth Capital ($ millions) | |||
Cash Operating Cost – C1 ($/oz sold) | 750 – 850 | Kisladag | 110 – 120 | |
Total Cash Cost – C2 ($/oz sold) | 850 – 950 | Lamaque | 37 – 42 | |
Sustaining Capex ($ millions) | 14 – 19 | Efemcukuru | 4 – 8 | |
Olympias | 3 – 7 | |||
Lamaque | Skouries | 240 – 260 | ||
Cash Operating Cost – C1 ($/oz sold) | 670 – 770 | |||
Total Cash Cost – C2 ($/oz sold) | 700 – 800 | |||
Sustaining Capex ($ millions) | 60 – 70 | |||
Efemcukuru | ||||
Cash Operating Cost – C1 ($/oz sold) | 790 – 890 | |||
Total Cash Cost – C2 ($/oz sold) | 920 – 1,020 | |||
Sustaining Capex ($ millions) | 10 – 15 | |||
Olympias | ||||
Cash Operating Cost – C1 ($/oz sold) | 980 – 1,080 | |||
Total Cash Cost – C2 ($/oz sold) | 1,130 – 1,230 | |||
Sustaining Capex ($ millions) | 30 – 35 |
(1) These financial measures are non-IFRS financial measures. Certain additional disclosures for non-IFRS financial measures and ratios have been incorporated by reference and additional detail can be found at the end of this press release and in the section ‘Non-IFRS and Other Financial Measures and Ratios’ of Eldorado’s December 31, 2021 MD&A.
(2)
(3) Assumes the expected sale of Certej in H1 2023.
TURKIYE
At Kisladag and Efemcukuru, labour costs increased in 2023 related to commitments under our collective bargaining agreement which included an annual adjustment to labour rates in line with the annual consumer inflation rate. To support our workforce with the rising costs of food and electricity, approximately half of the adjustment was provided in mid-2022 with the remaining provided in January 2023. Labour costs are denominated in local currency and as the weakening of the Turkish Lira against the U.S. dollar has slowed in recent months, cost increases are not being offset by currency movements at present.
Kisladag
In 2023, Kisladag is expected to mine and place on leach approximately 12.5 to 13.0 million tonnes of ore at an average gold grade of 0.70 to 0.75 grams per tonne. With the commissioning of the enhanced metallurgical process circuit, including the High-Pressure Grinding Roll, additional conveyors, and the agglomeration drum, average recoveries in 2023 are expected to increase. In addition to increased mining and processing costs as a result of higher throughput and lower grades, cash operating costs per ounce in 2023 also reflect increases in labour rates, utility costs, and consumable costs relative to 2022.
Planned 2023 sustaining capital of
Efemcukuru
In 2023, Efemcukuru is expected to mine and process approximately 530,000 to 550,000 tonnes of ore at an average gold grade of 5.50 to 6.00 grams per tonne. Cash operating costs per ounce in 2023 reflect increases in labour rates, utility costs, and consumable costs. Planned sustaining capital expenditures for 2023 of
CANADA
Lamaque
In 2023, Lamaque is expected to mine and process approximately 860,000 to 870,000 tonnes of ore at an average gold grade of 6.25 to 6.75 grams per tonne. Cash operating costs per ounce of
Sustaining capital expenditures for 2023 are expected to be approximately
Expensed exploration programs in 2023 will focus on early-stage targets at Sigma-Lamaque, continued exploration drilling on the Bourlamaque property, and other early-stage targets.
GREECE
Olympias
In 2023, Olympias is expected to mine approximately 460,000 to 490,000 tonnes of ore at an average grade of 7.50 to 8.50 grams per tonne of gold, 140 to 150 grams per tonne of silver, 4.0 to
Planned 2023 sustaining capital expenditures of
Skouries
Project spending at Skouries in 2023 is expected to be focused on finalizing detailed engineering, which is
As discussed in further detail in the news release dated December 15, 2022, Eldorado remains confident in the three-year construction and commissioning schedule and capital cost estimate, with first production expected in the second half of 2025, commercial production at the end of 2025, and the first full year of production in 2026. Capital spending during this period is expected to be relatively balanced, albeit higher in 2024 and 2023, as the first half of 2023 includes the mobilization period.
Additionally, based on the “Technical Report, Skouries Project, Greece” prepared for Eldorado with an effective date of January 22, 2022, annual copper production over the life of mine at Skouries is expected to be approximately 67 million pounds per year, which is not currently incorporated in the Company’s five-year outlook.
Perama Hill
Spending at Perama Hill during the year is forecast to be less than
2023 Commodity and Currency Price Assumptions
Gold ($/oz) | |
Silver ($/oz) | |
Lead ($/mt) | |
Zinc ($/mt) | |
USD : CDN | 1 : 1.30 |
EURO : USD | 1 : 0.92 |
USD: TRY | 1 : 21.0 |
Qualified Person
Except as otherwise noted, Simon Hille, FAusIMM, Senior Vice President, Technical Services & Operations, is the Qualified Person under NI 43-101 responsible for preparing and supervising the preparation of the scientific or technical information contained in this press release and verifying the technical data disclosed in this document relating to our operating mines and development projects. Jessy Thelland, géo (OGQ No. 758), a member in good standing of the Ordre des Géologues du Québec, is the qualified person as defined in NI 43-101 responsible for, and has verified and approved, the scientific and technical disclosure contained in this press release for the Quebec projects.
About Eldorado Gold
Eldorado is a gold and base metals producer with mining, development and exploration operations in Turkiye, Canada and Greece. The Company has a highly skilled and dedicated workforce, safe and responsible operations, a portfolio of high-quality assets, and long-term partnerships with local communities. Eldorado's common shares trade on the Toronto Stock Exchange (TSX: ELD) and the New York Stock Exchange (NYSE: EGO).
Contacts
Investor Relations
Lisa Wilkinson, VP, Investor Relations
604.757 2237 or 1.888.353.8166
lisa.wilkinson@eldoradogold.com
Media
Louise McMahon, Director Communications & Public Affairs
604.616 2296 or 1.888.353.8166
louise.mcmahon@eldoradogold.com
Non-IFRS and Other Financial Measures and Ratios
Certain non-IFRS financial measures and ratios are included in this press release, including cash operating costs and cash operating costs per ounce sold, total cash costs and total cash costs per ounce sold, all-in sustaining costs ("AISC") and AISC per ounce sold, sustaining and growth capital.
Please see the December 31, 2021 MD&A for explanations and discussion of these non-IFRS and other financial measures and ratios. The Company believes that these measures and ratios, in addition to conventional measures and ratios prepared in accordance with International Financial Reporting Standards (“IFRS”), provide investors an improved ability to evaluate the underlying performance of the Company. The non-IFRS and other financial measures and ratios are intended to provide additional information and should not be considered in isolation or as a substitute for measures or ratios of performance prepared in accordance with IFRS. These measures and ratios do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers. Certain additional disclosures for these and other financial measures and ratios have been incorporated by reference and can be found in the section 'Non-IFRS and Other Financial Measures and Ratios' in the December 31, 2021 MD&A available on SEDAR at www.sedar.com and on the Company's website under the 'Investors' section.
The most directly comparable IFRS financial measures and results from the year ended December 31, 2021 are below.
Non-IFRS Measure | Most Directly Comparable IFRS Measure | 2021 |
Cash operating costs (C1) | Production costs | |
Total cash costs (C2) | ||
AISC | ||
Average realized gold price per ounce sold | Revenue | |
EBITDA | Earnings (loss) from continuing operations before income tax | |
Adjusted EBITDA | ||
Adjusted net earnings/(loss) | Net earnings (loss) attributable to shareholders of the Company from continuing operations | |
Adjusted net earnings/(loss) per share | ||
Cash flow from operations before changes in non-cash working capital | Net cash generated from operating activities of continuing operations | |
Free cash flow | ||
Sustaining capital expenditures | Additions to property, plant and equipment during the period | |
Growth capital expenditures |
Cautionary Note About Forward-Looking Statements and Information
Certain of the statements made and information provided in this press release are forward-looking statements or information within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. Often, these forward-looking statements and forward-looking information can be identified by the use of words such as “anticipates”, “believes”, “budgets”, “continue”, “commitment”, “confident”, “estimates”, “expects”, “forecasts”, “guidance”, “intends”, “outlook”, “plans”, “potential”, “projected”, “prospective”, or “schedule” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “can”, “could”, “likely”, “may”, “might”, “will” or “would” be taken, occur or be achieved.
Forward-looking statements or information contained in this press release include, but are not limited to, statements or information with respect to: our guidance and outlook, including expected production, cost and capital expenditure guidance, AISC and cash operating cost guidance, expected future amount mined and processed, mining rate, recoveries and grade, and five year production outlook; expected impacts on cash operating costs and expected use of sustaining capital at Kisladag, Efemcukuru, Lamaque, and Olympias; expected improvements at Kisladag; expected exploration program at Efemcukuru and Lamaque; expected improvements at Olympias; expected project spending and construction at Skouries; commodity and currency price assumptions; planned capital projects, including timing; growth capital projects at its properties, including anticipated timing and benefits; the duration, extent and other implications of production challenges and cost increases, including those in respect of COVID-19, the Russia-Ukraine war and restrictions and suspensions with respect to the Company’s operations; the timing of resource conversion drilling; our expectations regarding the timing and quantity of annual gold production; the sale of the Certej project; the total funding requirements for Skouries, including the sources thereof; the drawdown of the proceeds of the Facility, including the timing thereof; the Company’s ability to fund the remaining
We have made certain assumptions about the forward-looking statements and information, including assumptions about: production and cost expectations; the total funding required to complete Skouries; our ability to meet our timing objectives for first drawdown of the Facility; our ability to execute our plans relating to Skouries, including the timing thereof; our ability to obtain all required approvals and permits; cost estimates in respect of Skouries; no changes in input costs, exchange rates, development and gold; the geopolitical, economic, permitting and legal climate that we operate in, including at Skouries; how the worldwide economic and social impact of COVID-19 is managed and the duration and extent of the COVID-19 pandemic; timing, cost and results of our construction, improvements and exploration; the future price of gold and other commodities; the global concentrate market; exchange rates; anticipated values, costs, expenses and working capital requirements; production and metallurgical recoveries; mineral reserves and resources; and the impact of acquisitions, dispositions, suspensions or delays on our business and the ability to achieve our goals. In addition, except where otherwise stated, we have assumed a continuation of existing business operations on substantially the same basis as exists at the time of this press release.
Even though our management believes that the assumptions made and the expectations represented by such statements or information are reasonable, there can be no assurance that the forward-looking statement or information will prove to be accurate. Many assumptions may be difficult to predict and are beyond our control.
Furthermore, should one or more of the risks, uncertainties or other factors materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements or information. These risks, uncertainties and other factors include, among others, the following: the outcome of planned technical studies, production and exploration, development, optimization and expansion plans at the Company’s projects; possible variations in ore grade or recovery rates; changes in mineral resources and mineral reserves; costs and timing of the development of new deposits; success of exploration activities; increases in financing costs or adverse changes to the Facility; failure or delays to receive necessary approvals or otherwise satisfy the conditions to the drawdown of the Facility; the proceeds of the Facility not being available to the Company or Hellas Gold Single Member S.A.; ability to execute on plans relating to Skouries, including the timing thereof, ability to achieve the social impacts and benefits contemplated; ability to meet production, expenditure and cost guidance; risks relating to the ongoing COVID-19 pandemic and any future pandemic, epidemic, endemic or similar public health threats; timing and cost of construction, and the associated benefits; ability to achieve expected benefits from improvements, recoveries of gold and other metals; risks relating to our operations being located in foreign jurisdictions; community relations and social license; climate change; liquidity and financing risks; development risks; indebtedness, including current and future operating restrictions, implications of a change of control, ability to meet debt service obligations, the implications of defaulting on obligations and change in credit ratings; environmental matters; waste disposal; the global economic environment; government regulation; reliance on a limited number of smelters and off-takers; commodity price risk; mineral tenure; permits; risks relating to environmental sustainability and governance practices and performance; non-governmental organizations; corruption, bribery and sanctions; litigation and contracts; information technology systems; estimation of mineral reserves and mineral resources; production and processing estimates; credit risk; actions of activist shareholders; price volatility, volume fluctuations and dilution risk in respect of our shares; reliance on infrastructure, commodities and consumables; currency risk; inflation risk; interest rate risk; tax matters; dividends; financial reporting, including relating to the carrying value of our assets and changes in reporting standards; labour, including relating to employee/union relations, employee misconduct, key personnel, skilled workforce, expatriates and contractors; reclamation and long-term obligations; regulated substances; necessary equipment; co-ownership of our properties; acquisitions, including integration risks, and dispositions; the unavailability of insurance; conflicts of interest; compliance with privacy legislation; reputational issues; competition, as well as those risk factors discussed in the sections titled “Forward-looking information and risks” and “Risk factors in our business” in our most recent Annual Information Form & Form 40-F. The reader is directed to carefully review the detailed risk discussion in our most recent Annual Information Form & Form 40-F filed on SEDAR and EDGAR under our Company name, which discussion is incorporated by reference in this release, for a fuller understanding of the risks and uncertainties that affect our business and operations.
The inclusion of forward-looking statements and information is designed to help you understand management’s current views of our near- and longer-term prospects, and it may not be appropriate for other purposes.
There can be no assurance that forward-looking statements or information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, you should not place undue reliance on the forward-looking statements or information contained herein. Except as required by law, we do not expect to update forward-looking statements and information continually as conditions change and you are referred to the full discussion of the Company’s business contained in the Company’s reports filed with the securities regulatory authorities in Canada and the United States.
FAQ
What is Eldorado Gold's 2023 gold production forecast?
What are Eldorado Gold's expected cash operating costs for 2023?
When is the first production from the Skouries project expected?
How much capital is allocated for the Skouries project in 2023?