Denarius Metals Announces Third Quarter and First Nine Months 2024 Results
Denarius Metals reported its Q3 and nine months 2024 financial results. The company invested $9.5 million in exploration and development, including $7.4 million for the Zancudo Project construction. They raised $17.2 million through various financing activities in the first nine months, plus an additional $3.2 million in October. The company is finalizing a toll milling arrangement at Zancudo while constructing a 1,000 TPD processing plant, expected to be operational in Q1 2025. They reported a net loss of $9.5 million in Q3 2024 ($0.14 per share) and $12.1 million ($0.18 per share) for the nine-month period.
Denarius Metals ha riportato i risultati finanziari del terzo trimestre e dei nove mesi del 2024. L’azienda ha investito 9,5 milioni di dollari in esplorazione e sviluppo, di cui 7,4 milioni per la costruzione del Progetto Zancudo. Hanno raccolto 17,2 milioni di dollari tramite varie attività di finanziamento nei primi nove mesi, a cui si aggiungono ulteriori 3,2 milioni di dollari in ottobre. L’azienda sta finalizzando un accordo di lavorazione a pagamento a Zancudo mentre costruisce un impianto di trattamento da 1.000 TPD, previsto per essere operativo nel primo trimestre del 2025. Hanno riportato una perdita netta di 9,5 milioni di dollari nel terzo trimestre del 2024 (0,14 dollari per azione) e 12,1 milioni di dollari (0,18 dollari per azione) per il periodo di nove mesi.
Denarius Metals informó sobre sus resultados financieros del tercer trimestre y de los nueve meses de 2024. La empresa invirtió 9,5 millones de dólares en exploración y desarrollo, incluyendo 7,4 millones para la construcción del Proyecto Zancudo. Recaudaron 17,2 millones de dólares a través de diversas actividades de financiamiento en los primeros nueve meses, más 3,2 millones adicionales en octubre. La empresa está finalizando un acuerdo de molienda por contrato en Zancudo mientras construye una planta de procesamiento de 1,000 TPD, que se espera esté operativa en el primer trimestre de 2025. Reportaron una pérdida neta de 9,5 millones de dólares en el tercer trimestre de 2024 (0,14 dólares por acción) y 12,1 millones (0,18 dólares por acción) para el período de nueve meses.
Denarius Metals는 2024년 3분기 및 9개월 재무 결과를 보고했습니다. 이 회사는 탐사 및 개발에 950만 달러를 투자했으며, 그중 740만 달러는 잔쿠도 프로젝트 건설에 사용되었습니다. 그들은 처음 9개월 동안 다양한 자금 조달 활동을 통해 1,720만 달러를 모금했으며, 10월에는 추가로 320만 달러를 모았습니다. 이 회사는 잔쿠도에서 수수료 제분 계약을 최종화하는 한편, 2025년 1분기에 가동될 예정인 하루 1,000톤 처리 능력을 가진 가공 공장을 건설하고 있습니다. 2024년 3분기에는 950만 달러의 순손실(주당 0.14달러)을 보고했고, 9개월 동안에는 1,210만 달러(주당 0.18달러)의 손실을 기록했습니다.
Denarius Metals a communiqué ses résultats financiers pour le troisième trimestre et les neuf mois de 2024. L'entreprise a investi 9,5 millions de dollars dans l'exploration et le développement, dont 7,4 millions pour la construction du Projet Zancudo. Ils ont levé 17,2 millions de dollars grâce à diverses activités de financement au cours des neuf premiers mois, plus 3,2 millions de dollars supplémentaires en octobre. L'entreprise finalise un accord de broyage à façon à Zancudo tout en construisant une usine de traitement de 1 000 TPD, qui devrait être opérationnelle au premier trimestre de 2025. Ils ont rapporté une perte nette de 9,5 millions de dollars au troisième trimestre 2024 (0,14 dollar par action) et 12,1 millions de dollars (0,18 dollar par action) pour la période de neuf mois.
Denarius Metals hat seine Finanzberichte für das dritte Quartal und die neun Monate des Jahres 2024 vorgelegt. Das Unternehmen investierte 9,5 Millionen Dollar in Erkundung und Entwicklung, darunter 7,4 Millionen Dollar für den Bau des Zancudo-Projekts. In den ersten neun Monaten sammelten sie 17,2 Millionen Dollar durch verschiedene Finanzierungsaktivitäten und zusätzlich 3,2 Millionen Dollar im Oktober. Das Unternehmen finalisiert eine Mahlanlage in Zancudo und baut eine Verarbeitungsanlage mit einer Kapazität von 1.000 TPD, die voraussichtlich im ersten Quartal 2025 in Betrieb genommen wird. Sie berichteten über einen Nettoverlust von 9,5 Millionen Dollar im dritten Quartal 2024 (0,14 Dollar pro Aktie) und 12,1 Millionen Dollar (0,18 Dollar pro Aktie) für den Neunmonatszeitraum.
- Raised total net proceeds of $17.2 million in first nine months of 2024
- Processing plant at Zancudo Project expected to be operational in Q1 2025
- Secured offtake contract with Trafigura for Zancudo's gold-silver concentrate
- Finalizing $9.0 million prepayment financing with Trafigura
- Net loss increased to $9.5 million in Q3 2024 vs $1.0 million in Q3 2023
- Nine-month net loss widened to $12.1 million from $5.0 million year-over-year
- Delay in receiving Water Concession approval for Aguablanca Project
- Outstanding EUR 15 million payment due for RNR joint venture acquisition
Toronto, Ontario--(Newsfile Corp. - November 14, 2024) - Denarius Metals Corp. (Cboe CA: DMET) (OTCQX: DNRSF) ("Denarius Metals" or "the Company") announced today that it has filed its unaudited interim condensed consolidated financial statements and accompanying management's discussion and analysis (MD&A) for the three and nine months ended September 30, 2024. These documents can be found on its website at www.denariusmetals.com and by reviewing its profile on SEDAR+ at www.sedarplus.ca. All financial figures contained herein are expressed in U.S. dollars unless otherwise noted.
Denarius Metals is an emerging metals producer with two mines, Zancudo in Colombia and Aguablanca in Spain, expected to be in production within the next 12 months. In March 2024, the Company graduated its listing to Cboe Canada followed by a change of its trading symbol to "DMET". The Company continues to trade on the OTCQX in the United States under the symbol "DNRSF".
In the first nine months of 2024, the Company incurred total exploration, development and capital expenditures of approximately
To fund its investing activities in 2024, the Company raised total net proceeds of
In anticipation of receiving approval of the Environmental Impact Study ("EIS") that will enable it to commence mining operations at its Zancudo Project, the Company is finalizing a toll milling arrangement with a local third party to be able to commence early production while the 1,000 tonnes per day processing plant is being constructed. The processing plant equipment has been arriving at the project site during the third quarter of 2024 and will be fully mobilized prior to the end of the year. Installation and commissioning are expected to be completed with the plant operational in the first quarter of 2025. Earlier this year, the Company arranged a long-term offtake contract for Zancudo's gold-silver concentrate production with Trafigura Pte. Ltd. ("Trafigura"), a leading global commodities group. The Company and Trafigura are also finalizing definitive documentation for a
Denarius Metals commenced a 10,000 meters surface infill diamond drilling program at its Zancudo Project in April 2024 to upgrade Inferred Resources to the Indicated category and to support future mine development. The drilling program is focused on two priority areas, Los Albertos and Las Brisas, and has been designed at 50x50 meters drill centers. The infill drilling program started in the first priority target, Los Albertos, with two drill rigs operating from six purpose-built surface drill platforms. In September, the Company released the results received from the final assays for 32 drill holes from the Los Albertos target, totalling approximately 4,790 meters. Multiple high gold and silver grades have been intersected in most of the drill holes completed on Los Albertos target, confirming the continuity and extending the mineralization on the main structure and also delineating a northwest-southeast-trending ore shoot on the main Manto Antiguo structure, which is still open along strike and to the west. These results confirm the results from previous drilling campaigns and have delineated a high-grade ore shoot, which is still open along strike and to the west, within the main Manto Antiguo structure that could enhance the resource estimate and production grade down the line. Drilling on the second target, Las Brisas, commenced in August and will be completed in the fourth quarter of 2024. The results from the 2024 drilling program will serve as a guide for mine development and offer the potential for additional resource growth and extension of the mine's life.
The acquisition of a
On November 12, 2024, the Company closed the acquisition of
The Company reported a net loss of
About Denarius Metals
Denarius Metals is a Canadian junior company engaged in the acquisition, exploration, development and eventual operation of polymetallic mining projects in high-grade districts. Denarius Metals has two mines expected to be in operation in the next 12 months, the Zancudo Project in Colombia and the Aguablanca Project in Spain.
In Spain, Denarius Metals owns a
In Colombia, Denarius Metals is carrying out construction activities at its
Additional information on Denarius Metals can be found on its website at www.denariusmetals.com and by reviewing its profile on SEDAR+ at www.sedarplus.ca.
Cautionary Statement on Forward-Looking Information
This news release contains "forward-looking information", which may include, but is not limited to, statements with respect to anticipated business plans or strategies, including timing to receive the EIS approval for Zancudo, construction activities and timing to commence mining operations at the Zancudo Project, receipt of the Water Concession at Aguablanca, completion of the Trafigura financing, exploration programs, re-start of operations and timing to commence production at the Aguablanca Project, mine lifespan of Aguablanca, potential integration of the Aguablanca and Lomero Projects, preliminary economic assessments and future financing plans. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "believes" or variations (including negative variations) of such words and phrases, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Denarius Metals to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Factors that could cause actual results to differ materially from those anticipated in these forward-looking statements are described under the caption "Risk Factors" in the Company's Annual Information Form dated April 25, 2024 which is available for view on SEDAR+ at www.sedarplus.ca. Forward-looking statements contained herein are made as of the date of this press release and Denarius Metals disclaims, other than as required by law, any obligation to update any forward-looking statements whether as a result of new information, results, future events, circumstances, or if management's estimates or opinions should change, or otherwise. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, the reader is cautioned not to place undue reliance on forward-looking statements.
For Further Information, Contact:
Michael Davies
Chief Financial Officer
(416) 360-4653
investors@denariusmetals.com
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/230037
FAQ
What was Denarius Metals (DNRSF) Q3 2024 net loss?
How much did Denarius Metals (DNRSF) raise in financing during the first nine months of 2024?
When is the Zancudo Project processing plant expected to be operational?