STOCK TITAN

Coastal Virginia Offshore Wind (CVOW) Project, Part of Comprehensive “All of the Above” Energy Strategy to Affordably Meet Growing Energy Needs, Continues on Schedule, Cost Updated

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Very Positive)
Tags

Dominion Energy (NYSE: D) provided updates on its Coastal Virginia Offshore Wind (CVOW) project, which remains on schedule for completion by end of 2026. The 2.6 GW project is approximately 50% complete, having installed the first 16 transition pieces and received its first offshore substation.

The total project cost has increased ~9% from $9.8B to $10.7B, primarily due to higher network upgrade costs assigned by PJM and increased onshore electrical interconnection costs. The project maintains a $222M contingency. Under cost-sharing mechanisms, 50% of costs above $10.3B will be borne by project owners, not customers.

The expected average impact on typical residential customers (1,000 kWh/month) is 43 cents per month. The project's updated levelized cost of energy is ~$62. Stonepeak, a non-controlling equity partner, will fund 50% of project costs up to $11.3B. Dominion Energy expects a Q4 2024 charge of ~$100M but reaffirms its 2025 operating EPS guidance and 5-7% long-term growth through 2029.

Dominion Energy (NYSE: D) ha fornito aggiornamenti sul suo progetto di energia eolica offshore Coastal Virginia (CVOW), che è ancora previsto per il completamento entro la fine del 2026. Il progetto da 2,6 GW è circa completato al 50%, avendo installato i primi 16 pezzi di transizione e ricevuto la sua prima sottostazione offshore.

Il costo totale del progetto è aumentato di circa il 9%, passando da 9,8 miliardi a 10,7 miliardi di dollari, principalmente a causa dei maggiori costi di aggiornamento della rete assegnati da PJM e degli aumentati costi di interconnessione elettrica a terra. Il progetto mantiene una contingenza di 222 milioni di dollari. In base ai meccanismi di condivisione dei costi, il 50% dei costi superiori a 10,3 miliardi sarà coperto dai proprietari del progetto, non dai clienti.

L'impatto medio previsto sui clienti residenziali tipici (1.000 kWh/mese) è di 43 centesimi al mese. Il costo livellato di energia aggiornato del progetto è di circa 62 dollari. Stonepeak, un partner azionario non controllante, finanzierà il 50% dei costi del progetto fino a 11,3 miliardi. Dominion Energy prevede un costo di circa 100 milioni nel quarto trimestre del 2024, ma conferma la sua previsione di utili per azione operativi per il 2025 e una crescita a lungo termine del 5-7% fino al 2029.

Dominion Energy (NYSE: D) proporcionó actualizaciones sobre su proyecto de energía eólica marina Coastal Virginia (CVOW), que sigue programado para completarse a finales de 2026. El proyecto de 2.6 GW está aproximadamente al 50% de su ejecución, habiendo instalado las primeras 16 piezas de transición y recibido su primera subestación offshore.

El costo total del proyecto ha aumentado aproximadamente un 9%, de 9.8 mil millones a 10.7 mil millones de dólares, principalmente debido a los mayores costos de actualización de la red asignados por PJM y mayores costos de interconexión eléctrica en tierra. El proyecto mantiene una contingencia de 222 millones de dólares. Según los mecanismos de compartición de costos, el 50% de los costos que superen los 10.3 mil millones serán asumidos por los propietarios del proyecto, no por los clientes.

El impacto medio esperado en los clientes residenciales típicos (1,000 kWh/mes) es de 43 centavos al mes. El costo nivelado de energía actualizado del proyecto es de aproximadamente 62 dólares. Stonepeak, un socio de capital no controlador, financiará el 50% de los costos del proyecto hasta 11.3 mil millones. Dominion Energy espera un cargo de aproximadamente 100 millones en el cuarto trimestre de 2024, pero reafirma su guía de ganancias por acción operativas para 2025 y un crecimiento a largo plazo del 5-7% hasta 2029.

도미니언 에너지 (NYSE: D)는 2026년 말까지 완료될 예정인 해안 버지니아 해상 풍력(CVOW) 프로젝트에 대한 업데이트를 제공했습니다. 2.6 GW 프로젝트는 약 50% 진행되었으며, 첫 16개의 전이 조각을 설치하고 첫 해상 변전소를 받았습니다.

총 프로젝트 비용은 9% 증가하여 98억 달러에서 107억 달러로 증가했으며, 이는 주로 PJM에서 할당한 네트워크 업그레이드 비용 증가와 육상의 전기 연결 비용 증가 때문입니다. 이 프로젝트는 2억 2천 200만 달러의 유예 규정을 유지하고 있습니다. 비용 공유 메커니즘에 따라 103억 달러를 초과하는 비용의 50%는 고객이 아닌 프로젝트 소유자가 부담합니다.

전형적인 주거 고객(1,000 kWh/월)에 대한 예상 평균 영향은 월 43센트입니다. 프로젝트의 업데이트된 수준화된 에너지 비용은 약 62달러입니다. 비지배적 지분 파트너인 스톤픽은 113억 달러까지 프로젝트 비용의 50%를 자금 지원합니다. 도미니언 에너지는 2024년 4분기에 약 1억 달러의 비용이 발생할 것으로 예상하지만 2025년 운영 EPS 가이던스를 재확인하고 2029년까지 5-7%의 장기 성장을 기대합니다.

Dominion Energy (NYSE: D) a fourni des mises à jour concernant son projet d'énergie éolienne offshore en Virginie côtière (CVOW), qui reste prévu pour être achevé d'ici la fin de 2026. Le projet de 2,6 GW est complété à environ 50 %, avec l'installation des 16 premiers éléments de transition et la réception de sa première sous-station offshore.

Le coût total du projet a augmenté d'environ 9 %, passant de 9,8 milliards de dollars à 10,7 milliards de dollars, principalement en raison des coûts de mise à niveau du réseau plus élevés attribués par PJM et des coûts d'interconnexion électrique à terre augmentés. Le projet maintient une réserve de 222 millions de dollars. Selon les mécanismes de partage des coûts, 50 % des coûts dépassant 10,3 milliards de dollars seront supportés par les propriétaires du projet, et non par les clients.

L'impact moyen attendu sur les clients résidentiels typiques (1 000 kWh/mois) est de 43 cents par mois. Le coût de l'énergie actualisé du projet est d'environ 62 dollars. Stonepeak, un partenaire en capital non contrôlant, financera 50 % des coûts du projet jusqu'à 11,3 milliards de dollars. Dominion Energy s'attend à une charge de 100 millions de dollars au quatrième trimestre de 2024, mais réaffirme ses prévisions de bénéfice par action pour 2025 et une croissance à long terme de 5 à 7 % jusqu'en 2029.

Dominion Energy (NYSE: D) hat Updates zu seinem Projekt für Offshore-Windenergie in Coastal Virginia (CVOW) bereitgestellt, das planmäßig bis Ende 2026 abgeschlossen sein soll. Das 2,6 GW-Projekt ist zu etwa 50% abgeschlossen, nachdem die ersten 16 Übergangsstücke installiert wurden und die erste Offshore-Umspannstation empfangen wurde.

Die Gesamtkosten des Projekts sind um rund 9% gestiegen, von 9,8 Mrd. USD auf 10,7 Mrd. USD, hauptsächlich aufgrund höherer Netzausbaukosten, die von PJM zugewiesen wurden, und gestiegener Kosten für die elektrische Anbindung an Land. Das Projekt hat eine Rücklage von 222 Millionen USD. Nach den Kostenbeteiligungsmechanismen werden 50% der Kosten, die über 10,3 Milliarden USD hinausgehen, von den Projektinhabern und nicht von den Kunden getragen.

Die erwartete durchschnittliche Auswirkung auf typische Haushaltskunden (1.000 kWh/Monat) beträgt 43 Cent pro Monat. Die aktualisierten nivellierten Energiekosten des Projekts liegen bei etwa 62 USD. Stonepeak, ein nicht kontrolierender Eigenkapitalpartner, wird 50% der Projektkosten bis zu 11,3 Mrd. USD finanzieren. Dominion Energy erwartet im vierten Quartal 2024 eine Belastung von etwa 100 Millionen USD, bekräftigt jedoch seine Gewinnprognose für 2025 und ein langfristiges Wachstum von 5-7% bis 2029.

Positive
  • Project remains on schedule for 2026 completion with 50% completion milestone reached
  • Creation of 2,000 direct/indirect jobs and $2B in economic activity
  • Robust cost-sharing mechanisms protect customers from cost overruns
  • Stonepeak partnership reduces shareholder risk by funding 50% of cost increases
  • Company reaffirms 2025 EPS guidance and 5-7% long-term growth targets
Negative
  • Project cost increased by ~9% ($900M) to $10.7B
  • Expected Q4 2024 charge of ~$100M
  • Increased monthly cost impact on residential customers (43 cents/month)
  • Higher levelized cost of energy from $56 to $62

Insights

The CVOW project update presents a nuanced picture of both progress and challenges in one of America's largest offshore wind developments. The 9% cost increase to $10.7 billion warrants careful analysis, particularly given the current challenging environment for offshore wind projects globally.

Several positive indicators stand out: First, the project's ability to maintain its original timeline while achieving 50% completion demonstrates strong execution capabilities, especially considering recent industry-wide challenges that have led to delays or cancellations in other offshore wind projects. The successful installation of transition pieces and delivery of the first substation are important technical milestones that reduce completion risk.

The financial structure presents a sophisticated risk-mitigation approach: The Stonepeak partnership's 50% cost-sharing agreement up to $11.3 billion effectively caps Dominion's exposure, while the SCC-approved settlement ensures customer protection through cost-sharing mechanisms above $10.3 billion. The minimal $0.43 monthly impact on residential customers maintains the project's political and regulatory viability.

The updated LCOE of $62 remains competitive with alternative generation sources, though the increase from $56 reflects broader industry cost pressures. The $222 million contingency buffer, representing 5% of remaining costs, provides reasonable protection against further overruns, though this is relatively thin by industry standards.

Notably, Dominion's ability to maintain its 2025 guidance and 5-7% long-term EPS growth target despite the $100 million Q4 2024 charge demonstrates the project's manageable impact on the company's overall financial position. This suggests effective integration of the project risks into the broader corporate strategy.

  • No change to expected on-time project completion at end of 2026
  • Project achieving significant construction milestones including the successful installation of the first 16 transition pieces
  • Updated project cost reflects revised estimate of network upgrade costs assigned by PJM to CVOW which represented the largest unfixed cost input for the project; contingency now reflects ~5% of remaining project investment
  • Robust cost sharing mechanisms protect customers and shareholders
  • Expected average impact over the life of the project to a typical residential customer bill is 43 cents per month
  • Project has robust bipartisan support from Virginia government and congressional leaders, local communities, defense interests, commercial marine industry, civic, educational, environmental, labor and community partners
  • Dominion Energy reaffirms its existing guidance for 2025 operating EPS (non-GAAP), long-term operating EPS growth rate, and credit

RICHMOND, Va.--(BUSINESS WIRE)-- Dominion Energy, Inc. (NYSE: D), today provided several updates for the Coastal Virginia Offshore Wind (CVOW) project. The 2.6 GW, fully permitted project is now approximately 50% complete and remains on track for on-time completion at the end of 2026. CVOW is credited with creating 2,000 direct and indirect American jobs and $2 billion of economic activity.

Significant construction progress supports on-time completion

CVOW continues to achieve significant construction milestones including the successful installation of the first 16 transition pieces which serve as the junction between the foundation and tower for each of the 176 wind turbines. Delivery of the first of three 4,300-ton offshore substations to the Portsmouth Marine Terminal in Virginia Beach occurred at the end of January. Fully fabricated monopiles, transition pieces, undersea cable and other major components continue to be delivered in preparation for on-schedule installation. Wind turbine tower and blade fabrication is now underway, with nacelle fabrication to begin later this quarter. SiemensGamesa, the project’s wind turbine supplier, is manufacturing the same turbine model for CVOW as has been successfully fabricated, installed, and is now operating at the Moray West offshore wind project. Charybdis, the American built, flagged, and crewed, wind turbine installation vessel (WTIG) is now 96% complete and has commenced sea trials in Brownsville, Texas.

Project cost updated

Estimated total project costs, inclusive of contingency and excluding financing costs, have increased ~9 percent, from $9.8 billion to $10.7 billion. This is the first and only increase since the original project budget was submitted to the Virginia State Corporation Commission (SCC) in November 2021, approximately 39 months ago. Relative to the original budget of $9.8 billion, the cost increase is attributable to higher network upgrade costs which are assigned by PJM, the regional electric grid operator, to CVOW as part of the generator interconnect process and higher onshore electrical interconnection costs. New electric generation resources constructed within PJM, like CVOW, are assigned costs by PJM that are deemed necessary to effectively integrate these resources and ensure the reliability and stability of the electric grid. Higher network upgrade cost estimates by PJM reflect the significant increase in demand growth that require incremental generation and transmission resources across the system. Network upgrades do not impact project construction or timeline and represented the largest unfixed cost input for the project. Aside from changes to onshore costs, aggregate costs for other project costs, including offshore, have remained in-line with the original budget. The project’s current unused contingency of $222 million, up ~$100 million from last update, now represents ~5% of remaining project costs.

Robust cost sharing mechanisms protect customers

The project remains an affordable source of electricity for Dominion Energy Virginia customers with robust cost sharing mechanisms that protect customers and shareholders. As a result of the comprehensive stakeholder settlement approved by the SCC in December 2022, 50% of the updated total project costs above $10.3 billion are unrecoverable from customers and borne by the project owners. As a result of the total project cost update, the expected average impact over the life of the project to a typical residential customer bill using 1,000 kWh per month is a 43 cent per month increase. The project’s updated levelized cost of energy (“LCOE”) of ~$62 (vs. the prior estimate in November 2024 of $56) continues to benchmark very favorably with new generation alternatives including solar, battery and gas-fired generation.

Business review significantly reduced project risk for shareholders

In addition to the existence of robust cost sharing mechanisms for customers, as part of the comprehensive business review, Dominion Energy successfully completed a non-controlling equity financing with Stonepeak. Under terms of that agreement, Stonepeak agreed to fund 50% of project costs up to $11.3 billion, with additional sharing of costs in excess of $11.3 billion. As a result, Stonepeak will fund half, or ~$450 million, of the ~$900 million increase in total project costs. Further, Stonepeak and Dominion Energy will each absorb 50% of increased total projects costs that are not expected to be recovered from customers under the December 2022 settlement order. As a result, Dominion Energy expects its Q4 2024 results will include an ~$100 million charge, which will be excluded from operating earnings (non-GAAP), for such amount. Additional information may be found on the company’s Investor Relations website at https://investors.dominionenergy.com/events-and-presentations

Fourth quarter 2024 earnings call

The company will host its fourth quarter 2024 investor call, as originally scheduled, on February 12, 2025 at 10:00 AM ET. During the call, management will discuss matters of interest to financial and other stakeholders including recent financial results, updated capital investment expectations and financing plans. The company reaffirms its existing 2025 operating earnings per share (EPS) guidance, as well as its long-term operating earnings per share growth guidance of 5% to 7% through 2029 off of 2025 operating earnings per share midpoint excluding RNG 45Z ($3.30). The company also reaffirms its existing credit guidance.

Important note to investors regarding operating, reported earnings

Dominion Energy uses operating earnings (non-GAAP) as the primary performance measurement of its results for public communications with analysts and investors. Operating earnings are defined as reported earnings adjusted for certain items. Dominion Energy also uses operating earnings internally for budgeting, for reporting to the Board of Directors, for the company's incentive compensation plans, and for its targeted dividend payouts and other purposes. Dominion Energy management believes operating earnings provide a more meaningful representation of the company's fundamental earnings power.

About Dominion Energy

Dominion Energy (NYSE: D), headquartered in Richmond, Va., provides regulated electricity service to 3.6 million homes and businesses in Virginia, North Carolina, and South Carolina, and regulated natural gas service to 500,000 customers in South Carolina. The company is one of the nation's leading developers and operators of regulated offshore wind and solar power and the largest producer of carbon-free electricity in New England. The company's mission is to provide the reliable, affordable, and increasingly clean energy that powers its customers every day. Please visit DominionEnergy.com to learn more.

This release contains certain forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995 that are subject to various risks and uncertainties. These factors are identified in Dominion Energy's Forms 10-K and 10-Q filed with the U.S. Securities and Exchange Commission. Dominion Energy refers readers to those reports for further information. Any forward-looking statement speaks only as of the date on which it is made, and Dominion Energy undertakes no obligation to update any forward-looking statement to reflect events or circumstances occurring after the date on which it is made.

News Category: Virginia & North Carolina

For further information: Media: Jeremy Slayton, (804) 297-5247 or Jeremy.L.Slayton@dominionenergy.com;

Investor Relations: David McFarland, (804) 819-2438 or David.M.McFarland@dominionenergy.com

Source: Dominion Energy

FAQ

What is the new total cost of Dominion Energy's CVOW project and how much did it increase?

The CVOW project cost increased by approximately 9% from $9.8 billion to $10.7 billion, primarily due to higher network upgrade costs assigned by PJM and increased onshore electrical interconnection costs.

How will the CVOW cost increase affect Dominion Energy (D) residential customers?

The cost increase will result in an average impact of 43 cents per month for typical residential customers using 1,000 kWh per month over the life of the project.

When is Dominion Energy's CVOW project expected to be completed?

The CVOW project remains on schedule for completion at the end of 2026, with approximately 50% of construction already completed.

How many jobs has Dominion Energy's CVOW project created?

The CVOW project has created 2,000 direct and indirect American jobs and generated $2 billion in economic activity.

How will the cost increase impact Dominion Energy's (D) financial guidance?

Despite the cost increase, Dominion Energy reaffirms its 2025 operating EPS guidance and long-term operating EPS growth rate of 5-7% through 2029.

Dominion Energy, Inc.

NYSE:D

D Rankings

D Latest News

D Stock Data

42.98B
838.85M
0.13%
77.32%
2.21%
Utilities - Regulated Electric
Electric Services
Link
United States of America
RICHMOND