CenterPoint Energy Outlines Plan to Minimize May 2024 Derecho Storm Bill Impact for Electric Customers
CenterPoint Energy has filed a securitization plan with the Public Utility Commission of Texas to manage approximately $450 million in emergency response costs from the May 2024 Derecho storm. The plan aims to spread costs over 15 years, resulting in an estimated $1 per month impact on customer bills while saving them over $50 million in interest charges. The Derecho caused about $5 billion in damages across Houston, requiring over 7,700 workers to restore power. The company restored service to 80% of affected customers within 72 hours, replacing 400 miles of electrical wires, 1,600 transformers, and 1,600 power poles. The final PUCT decision is expected in 2025.
CenterPoint Energy ha presentato un piano di cartolarizzazione alla Commissione Pubblica dei Servizi dell'Elettricità del Texas per gestire circa 450 milioni di dollari in costi di risposta alle emergenze causati dalla tempesta di Derecho di maggio 2024. Il piano mira a distribuire i costi su un periodo di 15 anni, comportando un impatto stimato di 1 dollaro al mese sulle bollette dei clienti, risparmiando oltre 50 milioni di dollari in costi per interessi. Il Derecho ha causato danni per circa 5 miliardi di dollari a Houston, richiedendo l'intervento di oltre 7.700 lavoratori per ripristinare l'energia. L'azienda ha ripristinato il servizio all'80% dei clienti colpiti entro 72 ore, sostituendo 400 miglia di cavi elettrici, 1.600 trasformatori e 1.600 pali della luce. La decisione finale della PUCT è prevista per il 2025.
CenterPoint Energy ha presentado un plan de securitización a la Comisión de Utilidades Públicas de Texas para gestionar aproximadamente 450 millones de dólares en costos de respuesta a emergencias derivados de la tormenta Derecho de mayo de 2024. El plan tiene como objetivo distribuir los costos a lo largo de 15 años, resultando en un impacto estimado de 1 dólar al mes en las facturas de los clientes, lo que les ahorrará más de 50 millones de dólares en cargos por intereses. El Derecho causó aproximadamente 5 mil millones de dólares en daños en Houston, necesitando más de 7,700 trabajadores para restaurar la energía. La compañía restableció el servicio al 80% de los clientes afectados en un plazo de 72 horas, reemplazando 400 millas de cables eléctricos, 1,600 transformadores y 1,600 postes de energía. Se espera la decisión final de la PUCT en 2025.
CenterPoint Energy는 2024년 5월 Derecho 폭풍에 따른 약 4억 5천만 달러의 긴급 대응 비용을 관리하기 위해 텍사스 공공 유틸리티 위원회에 유동화 계획을 제출했습니다. 이 계획은 비용을 15년 동안 분산시키는 것을 목표로 하여 고객 청구서에 대한 월 1달러의 영향을 미치고 이자 비용으로 5천만 달러 이상을 절약할 것으로 예상됩니다. Derecho는 휴스턴 전역에 약 50억 달러의 손실을 초래했으며, 전력을 복구하는 데 7,700명 이상의 작업자가 필요했습니다. 회사는 피해를 입은 고객의 80%에게 72시간 이내에 서비스를 복원했으며, 400마일의 전선, 1,600개의 변압기 및 1,600개의 전선주를 교체했습니다. PUCT의 최종 결정은 2025년에 예상됩니다.
CenterPoint Energy a déposé un plan de titrisation auprès de la Commission des services publics du Texas pour gérer environ 450 millions de dollars de coûts d'intervention d'urgence suite à la tempête Derecho de mai 2024. Ce plan vise à répartir les coûts sur 15 ans, entraînant un impact estimé de 1 dollar par mois sur les factures des clients, tout en leur faisant économiser plus de 50 millions de dollars en frais d'intérêts. Le Derecho a causé environ 5 milliards de dollars de dommages à Houston, nécessitant l'intervention de plus de 7 700 travailleurs pour rétablir l'électricité. L'entreprise a rétabli le service pour 80 % des clients touchés dans les 72 heures, remplaçant 400 miles de fils électriques, 1 600 transformateurs et 1 600 poteaux électriques. La décision finale de la PUCT devrait être attendue en 2025.
CenterPoint Energy hat einen Verbriefungsplan bei der Öffentlichen Versorgungs-Kommission von Texas eingereicht, um ungefähr 450 Millionen Dollar an Notfallkosten aufgrund des Derecho-Sturms im Mai 2024 zu verwalten. Der Plan soll die Kosten über einen Zeitraum von 15 Jahren verteilen, was zu einer geschätzten Auswirkung von 1 Dollar pro Monat auf die Kundenrechnungen führt und über 50 Millionen Dollar an Zinsgebühren spart. Der Derecho verursachte Schäden in Höhe von etwa 5 Milliarden Dollar in Houston und erforderte den Einsatz von über 7.700 Arbeitern zur Wiederherstellung der Stromversorgung. Das Unternehmen stellte den Dienst innerhalb von 72 Stunden für 80% der betroffenen Kunden wieder her und ersetzte 400 Meilen elektrische Leitungen, 1.600 Transformatoren und 1.600 Strommasten. Die endgültige Entscheidung der PUCT wird für 2025 erwartet.
- Efficient emergency response with 80% power restoration within 72 hours
- Cost-effective financing strategy saving customers $50 million in interest charges
- Minimal customer impact of approximately $1 per month through 15-year cost spreading
- Significant emergency response costs of $450 million to be passed to customers
- Additional monthly surcharge for customers starting 2025
- Extensive infrastructure damage requiring substantial replacement costs
Insights
The securitization plan for
The company's efficient emergency response and cost recovery strategy demonstrates solid operational and financial planning. By following established industry practices and securing regulatory approval through the PUCT, CNP is likely to maintain stable returns. The securitization approach, previously successful after Hurricane Ike, provides predictable cost recovery while protecting the balance sheet from immediate strain.
The scale of infrastructure damage and rapid restoration metrics are impressive - 80% customer restoration within 72 hours despite massive system damage requiring 400+ miles of wire replacement and 1,600+ transformers. The mobilization of 7,700 workers across eight states showcases robust emergency response capabilities and strong utility partnerships.
The
- Company plans to spread emergency Derecho response costs of approximately
across 15 years; Customer bill impact expected to be about$450 million per month$1 - Financial method expected to save customers more than
in interest charges$50 million - Derecho storm caused more than an estimated
in damages across the$5 billion Greater Houston area unrelated to CenterPoint infrastructure
The May 16th Derecho caused more than an estimated
The fast-moving storm required CenterPoint to activate its emergency operation plan and mobilize over 7,700 employees, contractors, and mutual aid partners to assess damage, repair downed equipment, and restore power.
"The Derecho that struck the
Scope of CenterPoint Emergency Response
In response to the Derecho, CenterPoint mobilized thousands of frontline crews and critical resources and coordinated with government, community and utility partners to address the significant damage to the electrical system. As a result, CenterPoint restored power to more than 80 percent of impacted customers within 72 hours. The scope of the company's emergency response included:
- Mobilizing over 7,700 frontline electrical workers, contractors and mutual aid resources from eight states to assess system damage and repair equipment;
- Replacing more than 400 miles of primary electrical wires, more than1,600 transformers, and approximately 1,600 power poles on its distribution system;
- Deploying 13 emergency generation units to provide temporary power to critical facilities including hospitals, cooling centers, first responder sites, schools and senior centers;
- Establishing nine multi-city staging sites to efficiently deploy crews and equipment for customer restoration efforts to impacted areas of Greater Houston;
- Restoring power to approximately 340,000 impacted customers within the first 24 hours; 550,000 within 48 hours; and 750,000 within 72 hours; and
- Restoring 98 percent of all CenterPoint customers within five days of the Derecho.
CenterPoint Commitment to Customer Affordability: Securitizing for Lower Cost Impact
CenterPoint's plan follows the standard electric sector industry practice used in
By securitizing the cost recovery following major storms, hurricanes or other one-time events, CenterPoint is able spread cost impacts over several years and at a lower cost when compared to traditional financing, which results in a significantly lower monthly impact to customers. CenterPoint's filing will include costs associated with its emergency response for the May storm events, which includes the mobilization of frontline workers, repair and replacement of critical equipment, crew supplies, fuel and other materials.
Today's filing does not include any costs associated with CenterPoint's 2024 Hurricane Beryl response.
Estimated Monthly Customer Bill Impact
CenterPoint's filing seeks stakeholder and PUCT review of approximately
About CenterPoint Energy
As the only investor-owned electric and gas utility based in
Forward-looking Statements
This news release includes forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. When used in this news release the words "anticipate," "believe," "continue," "could," "estimate," "expect," "forecast," "goal," "intend," "may," "objective," "plan," "potential," "predict," "projection," "should," "target," "will" or other similar words are intended to identify forward-looking statements. These forward-looking statements including statements regarding securitization, customer bill impacts and timing of approvals, are based upon assumptions of management which are believed to be reasonable at the time made and are subject to significant risks and uncertainties. Actual events and results may differ materially from those expressed or implied by these forward-looking statements. Any statements in this news release regarding future events that are not historical facts are forward-looking statements. Each forward-looking statement contained in this news release speaks only as of the date of this release. Important factors that could cause actual results to differ materially from those indicated by the provided forward-looking information include risks and uncertainties relating to: (1) the impact of pandemics, including the COVID-19 pandemic; (2) financial market conditions; (3) general economic conditions; (4) the timing and impact of future regulatory and legislative decisions; and (5) other factors, risks and uncertainties discussed in CenterPoint Energy's Annual Report on Form 10-K for the fiscal year ended December 31, 2023 and CenterPoint's Quarterly Reports on Form 10-Q for the quarters ended March 31, 2024, June 30, 2024 and September 30, 2024 and other reports CenterPoint Energy or its subsidiaries may file from time to time with the Securities and Exchange Commission.
For more information, contact
Communications
Media.Relations@CenterPointEnergy.com
View original content to download multimedia:https://www.prnewswire.com/news-releases/centerpoint-energy-outlines-plan-to-minimize-may-2024-derecho-storm-bill-impact-for-electric-customers-302300487.html
SOURCE CenterPoint Energy
FAQ
How much will the May 2024 Derecho storm recovery cost CenterPoint Energy (CNP)?
How much will CenterPoint Energy (CNP) customers pay monthly for the Derecho storm recovery?
When will the PUCT make a final decision on CenterPoint Energy's (CNP) storm recovery plan?