Caledonia Mining Corporation Plc: Caledonia’s ‘Central Shaft’ Brought into Operation

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Negative)
Tags
Rhea-AI Summary

Caledonia Mining Corporation Plc (NYSE AMERICAN: CMCL; AIM: CMCL) has announced that its Central Shaft, the deepest in Zimbabwe, is now fully operational. The completion of this $67 million project, funded through internal cash flow, allows daily hoisting of materials, solving previous constraints and supporting an expansion goal of 80,000 ounces of gold production annually. The project took six years and was completed with only two lost time injuries, highlighting the safety of the operation.

Positive
  • Central Shaft is fully operational, enhancing mining capacity.
  • Project completed on budget of $67 million, funded internally.
  • Forecast to increase production target to 80,000 oz of gold annually.
Negative
  • None.

ST HELIER, Jersey, April 06, 2021 (GLOBE NEWSWIRE) -- Caledonia Mining Corporation Plc (“Caledonia” or the “Company”)(NYSE AMERICAN: CMCL; AIM: CMCL) is pleased to announce that its Central Shaft is now fully operational.

Commenting on the announcement, Steve Curtis, Chief Executive Officer, said:

“I am delighted to announce that our new Central Shaft, which is the deepest shaft of any gold mine in Zimbabwe, is fully operational. We can now start to hoist rock, men and material on a daily basis, which will solve our hoisting constraints and facilitate the planned expansion in mine capacity targeting 80,000 oz of gold production per year1.

“Commissioning the Central Shaft has been the culmination of a six-year project costing approximately $67million, all funded through internal cash flow.

“This has been an owner-funded and built project by the Blanket team and I would like to thank everyone for their hard work and especially for achieving the completion of the shaft without any serious accidents, recording only two lost time injuries.”

For further information please contact:

Caledonia Mining Corporation Plc
Mark Learmonth
Camilla Horsfall

Tel: +44 1534 679 802
Tel: +44 7817 841793
  
WH Ireland
Adrian Hadden/James Sinclair-Ford

Tel: +44 20 7220 1751
  
Blytheweigh
Tim Blythe/Megan Ray

Tel: +44 207 138 3204
  
3PPB
Patrick Chidley
Paul Durham

Tel: +1 917 991 7701
Tel: +1 203 940 2538

Note: This announcement contains inside information which is disclosed in accordance with the Market Abuse Regulation (EU) No. 596/2014.

Cautionary Note Concerning Forward-Looking Information
Information and statements contained in this news release that are not historical facts are “forward-looking information” within the meaning of applicable securities legislation that involve risks and uncertainties relating, but not limited, to Caledonia’s current expectations, intentions, plans, and beliefs. Forward-looking information can often be identified by forward-looking words such as “anticipate”, “believe”, “expect”, “goal”, “plan”, “target”, “intend”, “estimate”, “could”, “should”, “may” and “will” or the negative of these terms or similar words suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, intentions or statements about future events or performance. Examples of forward-looking information in this news release include: production guidance, estimates of future/targeted production rates, and our plans and timing regarding further exploration and drilling and development. This forward-looking information is based, in part, on assumptions and factors that may change or prove to be incorrect, thus causing actual results, performance or achievements to be materially different from those expressed or implied by forward-looking information. Such factors and assumptions include, but are not limited to: failure to establish estimated resources and reserves, the grade and recovery of ore which is mined varying from estimates, success of future exploration and drilling programs, reliability of drilling, sampling and assay data, assumptions regarding the representativeness of mineralization being inaccurate, success of planned metallurgical test-work, capital and operating costs varying significantly from estimates, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects and other factors.

Security holders, potential security holders and other prospective investors should be aware that these statements are subject to known and unknown risks, uncertainties and other factors that could cause actual results to differ materially from those suggested by the forward-looking statements. Such factors include, but are not limited to: risks relating to estimates of mineral reserves and mineral resources proving to be inaccurate, fluctuations in gold price, risks and hazards associated with the business of mineral exploration, development and mining, risks relating to the credit worthiness or financial condition of suppliers, refiners and other parties with whom the Company does business; inadequate insurance, or inability to obtain insurance, to cover these risks and hazards, employee relations; relationships with and claims by local communities and indigenous populations; political risk; risks related to natural disasters, terrorism, civil unrest, public health concerns (including health epidemics or outbreaks of communicable diseases such as the coronavirus (COVID-19)); availability and increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development, including the risks of obtaining or maintaining necessary licenses and permits, diminishing quantities or grades of mineral reserves as mining occurs; global financial condition, the actual results of current exploration activities, changes to conclusions of economic evaluations, and changes in project parameters to deal with unanticipated economic or other factors, risks of increased capital and operating costs, environmental, safety or regulatory risks, expropriation, the Company’s title to properties including ownership thereof, increased competition in the mining industry for properties, equipment, qualified personnel and their costs, risks relating to the uncertainty of timing of events including targeted production rate increase and currency fluctuations. Security holders, potential security holders and other prospective investors are cautioned not to place undue reliance on forward-looking information. By its nature, forward-looking information involves numerous assumptions, inherent risks and uncertainties, both general and specific, that contribute to the possibility that the predictions, forecasts, projections and various future events will not occur. Caledonia undertakes no obligation to update publicly or otherwise revise any forward-looking information whether as a result of new information, future events or other such factors which affect this information, except as required by law.

This news release is not an offer of the shares of Caledonia for sale in the United States or elsewhere. This news release shall not constitute an offer to sell or the solicitation of an offer to buy, nor shall there be any sale of the shares of Caledonia, in any province, state or jurisdiction in which such offer, solicitation or sale would be unlawful prior to registration or qualification under the securities laws of such province, state or jurisdiction.

______________________
1 Mr Dana Roets (B Eng (Min.), MBA, Pr.Eng., FSAIMM, AMMSA), Chief Operating Officer, is the Company's qualified person as defined by Canada's National Instrument 43-101 and has approved any scientific or technical information contained in this news release.


FAQ

What is the significance of Caledonia Mining's Central Shaft becoming operational?

The Central Shaft's operation allows Caledonia Mining to hoist materials daily and aims to increase annual gold production to 80,000 ounces.

How much did Caledonia Mining invest in the Central Shaft?

Caledonia Mining invested approximately $67 million in the Central Shaft project.

What safety measures were reported during the Central Shaft's construction?

The project was completed with only two lost time injuries, indicating a strong safety record.

What are the future production targets for Caledonia Mining post Central Shaft operation?

The company is targeting an expansion to 80,000 ounces of gold production per year following the Central Shaft's operational status.

Caledonia Mining Corporation Plc

NYSE:CMCL

CMCL Rankings

CMCL Latest News

CMCL Stock Data

210.40M
16.34M
14.98%
47.82%
0.89%
Gold
Basic Materials
Link
United States of America
Saint Helier