STOCK TITAN

Centerra Gold Announces Thompson Creek Feasibility Study Results and Strategic Plan for US Molybdenum Operations, Including a Restart of the Thompson Creek Mine and Ramp-Up of Langeloth

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Positive)
Tags

Centerra Gold announced results from its Thompson Creek feasibility study and a strategic plan for its US Molybdenum Operations. Key highlights include:

- Integrated value of Thompson Creek and Langeloth expected to have after-tax NPV8% of $472M and IRR of 22%

- Langeloth at full capacity integrated with Thompson Creek expected to generate ~$45M earnings from operations and $50M EBITDA per year

- Thompson Creek restart requires $397M capital investment over 3 years

- Thompson Creek to have 12-year mine life producing ~13M lbs molybdenum annually after ramp-up

- Langeloth plans phased ramp-up to full 40M lbs annual capacity by 2028

The integrated US Moly business shows improved economics compared to previous studies. Centerra aims to unlock value through restarting Thompson Creek and ramping up Langeloth production.

Centerra Gold ha annunciato i risultati del suo studio di fattibilità per Thompson Creek e un piano strategico per le sue Operazioni di Molybdeno negli Stati Uniti. I punti salienti includono:

- Il valore integrato di Thompson Creek e Langeloth si prevede che avrà un NPV8% dopo le tasse di 472 milioni di dollari e un IRR del 22%

- Langeloth, a piena capacità integrato con Thompson Creek, dovrebbe generare circa 45 milioni di dollari di utili operativi e 50 milioni di dollari di EBITDA all'anno

- Il riavvio di Thompson Creek richiede un investimento di capitale di 397 milioni di dollari in 3 anni

- Thompson Creek avrà una vita mineraria di 12 anni producendo circa 13 milioni di libbre di molibdeno all'anno dopo il periodo di ramp-up

- Langeloth prevede un incremento graduale per raggiungere una capacità annuale completa di 40 milioni di libbre entro il 2028

Il business integrato del molibdeno negli Stati Uniti mostra economie migliorate rispetto agli studi precedenti. Centerra punta a sbloccare valore attraverso il riavvio di Thompson Creek e l'aumento della produzione di Langeloth.

Centerra Gold anunció los resultados de su estudio de viabilidad de Thompson Creek y un plan estratégico para sus Operaciones de Molibdeno en Estados Unidos. Los aspectos destacados incluyen:

- Se espera que el valor integrado de Thompson Creek y Langeloth tenga un VPN8% después de impuestos de 472 millones de dólares y una TIR del 22%

- Langeloth, a plena capacidad integrado con Thompson Creek, se espera que genere unos 45 millones de dólares en ganancias operativas y 50 millones de dólares de EBITDA al año

- El reinicio de Thompson Creek requiere una inversión de capital de 397 millones de dólares durante 3 años

- Thompson Creek tendrá una vida útil de 12 años produciendo aproximadamente 13 millones de libras de molibdeno al año después de la fase de ramp-up

- Langeloth planea un aumento gradual para alcanzar una capacidad anual completa de 40 millones de libras para 2028

El negocio integrado de molibdeno en EE. UU. muestra economías mejoradas en comparación con estudios anteriores. Centerra busca desbloquear valor reiniciando Thompson Creek y aumentando la producción de Langeloth.

센터라 골드는 탐슨 크릭의 타당성 조사 결과와 미국 몰리브덴 운영을 위한 전략 계획을 발표했습니다. 주요 내용은 다음과 같습니다:

- 탐슨 크릭과 랭글로스의 통합 가치는 세후 NPV8%가 4억 7천 2백만 달러, IRR이 22%로 예상됩니다.

- 랭글로스는 탐슨 크릭과 통합되어 완전 가동 시 연간 약 4천 5백만 달러의 운영 이익과 5천만 달러의 EBITDA를 창출할 것으로 예상됩니다.

- 탐슨 크릭 재가동을 위해 3년 동안 3억 9천 7백만 달러의 자본투자가 필요합니다.

- 탐슨 크릭은 12년의 광산 수명 동안 매년 약 1천 3백만 파운드의 몰리브덴을 생산합니다. 해당 기간에 상승세를 보인 후입니다.

- 랭글로스는 2028년까지 연간 4천만 파운드의 완전 생산 능력으로 단계적 증가를 계획하고 있습니다.

통합된 미국 몰리브덴 사업은 이전 연구와 비교하여 개선된 경제성을 보여줍니다. 센터라는 탐슨 크릭 재가동 및 랭글로스 생산 증대를 통해 가치를 창출하는 것을 목표로 하고 있습니다.

Centerra Gold a annoncé les résultats de son étude de faisabilité sur Thompson Creek et un plan stratégique pour ses opérations de molybdène aux États-Unis. Les points clés incluent :

- La valeur intégrée de Thompson Creek et de Langeloth devrait avoir un VAN8% après impôts de 472 millions de dollars et un TRI de 22%

- Langeloth, à pleine capacité intégré à Thompson Creek, devrait générer environ 45 millions de dollars de bénéfices opérationnels et 50 millions de dollars d'EBITDA par an

- Le redémarrage de Thompson Creek nécessite un investissement en capital de 397 millions de dollars sur 3 ans

- Thompson Creek aura une durée de vie minière de 12 ans produisant environ 13 millions de livres de molybdène par an après la montée en puissance

- Langeloth prévoit une phase d'augmentation pour atteindre une capacité annuelle complète de 40 millions de livres d'ici 2028

L'activité intégrée de molybdène aux États-Unis montre des économies améliorées par rapport à des études précédentes. Centerra vise à débloquer de la valeur par le redémarrage de Thompson Creek et l'augmentation de la production de Langeloth.

Centerra Gold hat die Ergebnisse seiner Machbarkeitsstudie für Thompson Creek und einen strategischen Plan für seine Molybdänbetriebe in den USA bekannt gegeben. Zu den wichtigsten Punkten gehören:

- Der integrierte Wert von Thompson Creek und Langeloth wird voraussichtlich ein NPV8% nach Steuern von 472 Millionen Dollar und eine IRR von 22% haben.

- Langeloth, das zusammen mit Thompson Creek vollständig integriert ist, wird voraussichtlich jährlich etwa 45 Millionen Dollar an operativen Erträgen und 50 Millionen Dollar EBITDA generieren.

- Der Neustart von Thompson Creek erfordert eine Kapitalinvestition von 397 Millionen Dollar über 3 Jahre.

- Thompson Creek wird eine Bergbaulebensdauer von 12 Jahren haben und jährlich etwa 13 Millionen Pfund Molybdän produzieren. nach der Anlaufphase.

- Langeloth plant eine schrittweise Steigerung auf eine jährliche Gesamtproduktion von 40 Millionen Pfund bis 2028.

Das integrierte Molybdängeschäft in den USA zeigt im Vergleich zu früheren Studien verbesserte wirtschaftliche Bedingungen. Centerra zielt darauf ab, Werte durch den Neustart von Thompson Creek und die Steigerung der Produktion in Langeloth freizusetzen.

Positive
  • Integrated Thompson Creek and Langeloth operations expected to generate after-tax NPV8% of $472M and IRR of 22%
  • Langeloth at full capacity projected to produce $45M in earnings and $50M EBITDA annually when integrated with Thompson Creek
  • Thompson Creek restart has 12-year mine life with average annual production of 13M lbs molybdenum after ramp-up
  • Thompson Creek has proven and probable molybdenum reserves of 161M lbs
  • Langeloth plans phased ramp-up to full 40M lbs annual production capacity by 2028
  • Thompson Creek restart capital costs significantly de-risked due to existing infrastructure
Negative
  • Thompson Creek restart requires $397M capital investment over 3 years
  • Working capital investment required from 2025-2028 to support Langeloth ramp-up
  • Reaching higher Langeloth capacity utilization depends on ability to acquire third-party concentrates on favorable terms

Insights

This announcement represents a significant strategic shift for Centerra Gold's molybdenum business. The decision to restart the Thompson Creek mine and ramp up Langeloth operations is highly impactful, with projected integrated after-tax NPV8% of $472 million and IRR of 22%.

Key financial highlights include:

  • Langeloth at full capacity expected to generate $45 million in earnings and $50 million EBITDA annually
  • Thompson Creek restart requires $397 million capital investment over 3 years
  • 12-year mine life with average annual production of 13 million pounds molybdenum

The phased ramp-up approach and vertical integration strategy appear designed to mitigate risks and capitalize on synergies. However, investors should monitor execution risks and molybdenum price volatility, as the project economics are sensitive to price fluctuations.

The restart of Thompson Creek and ramp-up of Langeloth operations come at an opportune time in the molybdenum market. With current supply deficits and strong demand fundamentals, Centerra is positioning itself to capitalize on favorable market conditions.

Key points for investors:

  • Langeloth's strategic location near US steel markets provides a competitive advantage
  • Flexibility to produce various molybdenum products allows adaptation to market demands
  • Integration of Thompson Creek's high-quality concentrate with third-party sources enhances blending capabilities and potential margins

The phased approach to reaching full capacity by 2028 aligns well with expected market dynamics. However, success will depend on Centerra's ability to secure third-party concentrates on favorable terms, which introduces some uncertainty to the ramp-up plan.

Centerra's decision to restart Thompson Creek represents a significant development in the molybdenum mining sector. The feasibility study results demonstrate a robust project with a 12-year mine life and competitive cost structure.

Notable aspects include:

  • De-risked capital costs due to existing infrastructure and advanced equipment refurbishment
  • Proven and probable reserves of 161 million pounds molybdenum
  • Average LOM operating costs of $9.66 per pound sold

The integration with Langeloth creates a vertically integrated molybdenum business, which should enhance operational flexibility and potentially improve margins. However, investors should be aware that the success of this strategy relies heavily on efficient execution and favorable market conditions. The sensitivity to molybdenum prices highlights both the potential upside and the risks associated with commodity price volatility.

Integrated value of Thompson Creek and Langeloth is expected to have
after-tax NPV8% of $472M and IRR of 22%
Langeloth, at full capacity and integrated with Thompson Creek, is expected to generate
approximately $45M earnings from operations and $50M EBITDANG per year

All figures are in United States dollars. All production figures reflect payable metal quantities and are on a 100% basis, unless otherwise stated. For references denoted with NG, refer to the “Non-GAAP Financial Measures” disclosure at the end of this news release for a description of these measures.

TORONTO, Sept. 12, 2024 (GLOBE NEWSWIRE) -- Centerra Gold Inc. (“Centerra” or the “Company”) (TSX: CG) (NYSE: CGAU) announces the results from its Thompson Creek feasibility study, including a strategic, integrated business plan for its Molybdenum Business Unit (“MBU”) consisting of a restart of the Thompson Creek Mine (“Thompson Creek”) and a commercially optimized plan for the Langeloth Metallurgical Facility (“Langeloth”), collectively the US Molybdenum Operations (“US Moly”). Centerra will host a conference call and webcast to discuss the strategic plan for US Moly on Friday, September 13, 2024, at 9:00 am Eastern Time. Details for the conference call and webcast are included at the end of the news release.

President and CEO, Paul Tomory, commented, “Over the last year, we have developed a value-enhancing strategy for Centerra’s US molybdenum operations, centered around the vertical integration of Thompson Creek and Langeloth, and supported by strong molybdenum market fundamentals. The combined US Moly business is expected to produce an after-tax net present value (8%) (“NPV8%”) of $472 million. A key contributor to this value is Langeloth, which at full capacity, integrated with Thompson Creek, has the potential to generate robust annual EBITDA. Today, we announce the decision to unlock significant value through the restart of operations at Thompson Creek and a progressive ramp-up of production at Langeloth. When Thompson Creek begins production, currently targeted for the second half of 2027, it will provide additional high-grade, high-quality feed to Langeloth, enabling a ramp-up of production towards Langeloth’s full annual capacity of 40 million pounds while improving operational flexibility to meet market demand.”

Paul Tomory continued, “We completed a feasibility study at Thompson Creek that has confirmed the capital estimate from the pre-feasibility study, while adding another year of production. Following significant progress on permitting efforts in the second quarter 2024, we have pivoted from a two-phased approval to a single-phase capital investment of $397 million over three years, from now through mid-2027. Our total project costs guidance at Thompson Creek for the second half of 2024 is expected to be $55 to $65 million. We will provide 2025 guidance for Thompson Creek with our annual guidance that is expected to be published early next year.”

Paul Tomory concluded, “We are continuing to explore strategic options to unlock the full potential of our molybdenum business, in line with Centerra’s strategy to maximize the value of each asset in our portfolio. While Centerra expects to remain a gold-focused company, we acknowledge the significant value of our base metal assets.”

Integrated US Moly Highlights

  • Robust integrated economics of Thompson Creek and Langeloth: Strong project economics due to synergies with the high-quality concentrate blend that could be achieved when Thompson Creek is vertically integrated with Langeloth. Once Thompson Creek resumes full production, the US Moly business is expected to generate sustainable strong annual cash flows.
 US Moly(1)
(Thompson Creek +
Langeloth)
Thompson Creek
Only
(3)
Langeloth
Only
NPV8%$472M$185M$258M
Internal Rate of Return (“IRR”)22%15%n.m.
Additions to PP&E / Non-sustaining capital expendituresNG(2)$397M$397M-


(1)US Moly includes an additional $29M of unattributed tax synergies.
(2)Additions to Property, Plant, and Equipment (“PP&E”) are the same as Capital ExpendituresNG.
(3)The economic assessment for Thompson Creek in the FS (as defined below) has been prepared on a stand-alone basis and does not include integration with Langeloth. The economics for integrating Thompson Creek and Langeloth are extrapolated from the Thompson Creek feasibility study.
NOTE: See “Assumptions” at the end of this news release. “n.m.” stand for not meaningful.


  • Improved integrated economics compared to the pre-feasibility study (“PFS”) in September 2023: Integrated economics based on the FS have improved as compared to the PFS, specifically the Thompson Creek updated life of mine (“LOM”) plan has an additional 12 million pounds of molybdenum being produced, one year of additional mine life, more concentrate produced in the first four years, and a de-risked capital estimate.
 

US Moly: Thompson Creek + Langeloth
FS(1)PFS
NPV8%$472M$218M
NPV5%$692M$373M
IRR22%16%
LOM12 years11 years
Thompson Creek Molybdenum Production146M lbs134M lbs
Additions to PP&E / Non-sustaining capital expendituresNG(2,3)$397M$350M - $400M


(1)The economics for integrating Thompson Creek and Langeloth are extrapolated from the Thompson Creek feasibility study.
(2)Additions to PP&E are the same as Capital ExpendituresNG.
(3)Thompson Creek only; Langeloth additions to PP&E are in the range of $3 to $4 million per year and are considered sustaining capital.


Langeloth Highlights

  • Phased ramp-up to full capacity: Langeloth plans to ramp up production progressively over the next few years to increase production towards its full capacity of 40 million pounds per annum by 2028, which aligns with Thompson Creek’s first full year of production. At full capacity, the molybdenum feed to Langeloth is expected to consist of approximately one third supplied by Thompson Creek and two thirds purchased from third parties.
  • At full capacity, Langeloth is expected to generate approximately $45 million in earnings from operations and $50 million of earnings before interest, taxes, depreciation and amortization (“EBITDA”)NG annually. Significant synergies and margin improvements are expected to result from increased capacity utilization at Langeloth, including improved blending flexibility and more higher margin molybdenum products enabled by the high-quality feed from Thompson Creek.
  • Strategic geographic location: Langeloth is strategically connected to the North American steel supply and sales markets via efficient transportation networks and reliable infrastructure. Being close to several major US east coast ports, Langeloth is also well located for importing molybdenum concentrates and exporting molybdenum products.
  • Flexible and agile operations: With six roasters, the ability to produce a variety of finished molybdenum products and a potential total capacity of approximately 40 million pounds, Langeloth has flexibility to adapt to changing market and commercial conditions. Langeloth has value-added production capabilities, namely for ferromolybdenum and pure molybdenum oxide, positioning the business for opportunities and growth.
  • Strong leadership and people: The Langeloth management team and staff are highly experienced, dedicated and committed to a strong culture of operational excellence and innovation. With 100 years of experience in processing molybdenum, the team at Langeloth has developed a strong commercial network and constructive engagement with local regulators.

Thompson Creek FS Highlights

  • Robust project economics: NPV8% of $185 million and after-tax IRR of 15% using an assumed flat molybdenum price of $20 per pound for the LOM. The economic assessment for Thompson Creek in the FS has been prepared on a stand-alone basis and does not include the benefits of integration with Langeloth.
  • De-risked capital costs: Initial capital investment of approximately $397 million. The capital expenditures needed to restart Thompson Creek are significantly de-risked due to an existing pit, significantly advanced equipment rebuilds and purchases and an existing process plant that requires minimal upgrades and refurbishment. A majority of the anticipated capital expenditures are focused on capitalized stripping, plant refurbishment and mine mobile fleet upgrades.
  • Initial mine life of 12 years: Average annual molybdenum production is estimated to be approximately 13 million pounds after initial ramp-up. The average LOM operating costs are $9.66 per molybdenum pound sold and LOM all-in sustaining costs (“AISC”)NG are $12.46 per molybdenum pound sold.
  • Strong Reserve Base: The FS includes proven and probable molybdenum reserves of 161 million pounds, measured and indicated molybdenum resources of 63 million pounds and inferred molybdenum resources of 17 million pounds, as of September 1, 2024. The average reserve grade is 0.065% molybdenum.

The Company expects to file a technical report for Thompson Creek on its website at www.centerragold.com, on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov/edgar.

US Moly Overview

US Moly, consisting of the Langeloth metallurgical facility near Pittsburgh, Pennsylvania, and the Thompson Creek mine in Idaho, is part of Centerra’s MBU. The molybdenum assets were acquired by Centerra in 2016, along with the Mount Milligan gold-copper mine.

Langeloth

Langeloth is one of three molybdenum conversion facilities in the United States. Its facility and existing permits make it a unique and strategic asset, given its proximity to the North American steel market. Langeloth began commercial molybdenum conversion operations in 1924 and has historically operated at levels significantly higher than today. Over a two-year period prior to the suspension of the Thompson Creek mine in December 2014, the volume of molybdenum roasted at Langeloth was around 37 million pounds per year.

Langeloth operates as a conversion facility of molybdenum concentrate into metallurgical and chemical grade products. These products are sold to steel, other metallurgical, and chemical producers globally. Technical oxide is the main product manufactured by Langeloth due to its role as a key input in the manufacturing of high-performance steels. It can potentially be further processed into value-added products that command a higher margin. Langeloth can also produce ferromolybdenum and pure molybdenum oxide, and it has the capability to produce byproducts such as rhenium, with flexibility to adjust the product mix depending on market demand and the quality of concentrates sourced. The availability of high-quality Thompson Creek concentrate provides significant commercial flexibility to the MBU.

Commercial Optimization of Langeloth

Centerra has completed a commercial optimization plan at Langeloth, geared at increasing profitability and maximizing its future potential by increasing production levels, achieved by a ramp-up in the purchase of third-party concentrates and the restart of the Thompson Creek primary molybdenum mine.

Langeloth is well-positioned to capitalize on the current supply deficit in the molybdenum market and grow the business to meet the market demand. In the recent past Langeloth has operated slightly below its annual breakeven capacity of approximately 14 million pounds. The operation can be ramped up to full capacity to enable production of approximately 40 million pounds per year in a straightforward manner.

At full capacity, significant synergies and margin improvements that will enhance future cash flow generation and profitability from US Moly are expected to result from: (1) ability to leverage fixed costs, related to increased capacity utilization at Langeloth from the current level of approximately one third; (2) ability to blend the high-quality Thompson Creek concentrate with lower quality third-party concentrates; and (3) the ability, enabled by the quality of the Thompson Creek concentrate, to produce an increased volume of higher margin final molybdenum products.

At full production capacity, integrated with Thompson Creek, the molybdenum conversion facility at Langeloth has the potential to generate annually approximately $50 million of EBITDANG, $40 million in cash flow from operations and free cash flowNG of $35 million.

As a result of the compelling value opportunity, Centerra is initiating a progressive ramp-up at Langeloth to allow for commercial optimization. Langeloth is expected to ramp up production progressively towards its full capacity of 40 million pounds per annum by 2028, which aligns with Thompson Creek’s expected first full year of production. At full capacity, the molybdenum feed processed at the Langeloth facility is expected to consist of approximately one third supplied by Thompson Creek and approximately two thirds purchased from third-party providers. Further details on the restart of Thompson Creek are provided below.

Based on an assumed flat price of $20 per pound molybdenum, a working capital investment will be required over the period from 2025 to 2028 to support the ramp-up to full capacity. On a cash flow basis, this increase in working capital is expected to be largely offset by cash flow generated by Langeloth during the same period. The structure of commercial contracts at Langeloth helps to mitigate molybdenum price volatility. Concentrates are purchased at a discount to the prevailing market molybdenum price, while final products are generally sold at prices at or above this benchmark. As a result, the integrated operations of US Moly will be better positioned to withstand future fluctuations in molybdenum prices.

Reaching higher capacity utilization will depend on several factors which are not fully in Centerra’s control, including the ability to acquire third-party concentrates on favourable commercial terms over a significant period of time.

Thompson Creek

The Thompson Creek mine is a large open-pit primary molybdenum mine. It was a producing mine until it was placed on care and maintenance in December 2014. It has an existing open pit, as well as established site infrastructure, processing facilities and equipment fleet.

Feasibility Study

The Company has completed a FS on the restart of mining at Thompson Creek, with the objective of realizing value for the US Moly business. A restart of Thompson Creek, on a stand-alone basis, is expected to result in NPV8% of $185 million and IRR of 15%, based on an assumed flat molybdenum price of $20 per pound. The FS includes an optimized mine plan with a 12-year mine life. A summary of the FS production profile is included in the table below.

Thompson Creek FS Production Profile

 Total Mined
(M tons)
Grade of Ore Processed
(% Mo)
Molybdenum Production(3)
(Mlb)
2024(1)4.9--
202550.0--
202648.0--
2027(2)52.00.054.7
202856.90.0712.4
202951.00.0814.5
203045.00.0814.7
203137.00.0713.7
203257.00.059.7
203340.00.047.8
203436.70.0815.9
203524.20.1019.3
20368.00.0612.2
2037-0.059.1
2038-0.059.1
2039(2)-0.032.4
Total LOM510.70.06145.6


(1)2024 figures for the period from September 1, 2024 to December 31, 2024.
(2)Production is expected for a part of this year.
(3)It is estimated that approximately 4.7% of the recovered molybdenum pounds will be further refined at Thompson Creek and sold as high-performance molybdenum.
NOTE: “Mo” stands for molybdenum, “M tons” stands for millions of short (US) tons, “Mlb” stands for millions of molybdenum pounds. Totals may not sum precisely due to rounding.


The cost profile associated with the FS is largely driven by the grade profile. AISCNG per pound from 2028 to 2031 are expected to be lower than the LOM average due to higher grades and more ore tons mined, which is expected to result in stronger cash flows in these years. The average operating costs over the LOM are detailed in the table below. These operating costs exclude capitalized pre-production costs, which are included in capital costs. Processing costs cover mill, tailings and water management costs.

LOM average operating costs 
Mining$2.03 per ton mined
Processing$4.85 per ton processed
General and administrative (“G&A”)$1.67 per ton processed


Capital Expenditures
NG

Centerra is proceeding with a restart of Thompson Creek, which is expected to require an investment of approximately $397 million in total initial, non-sustaining capital expendituresNG over three years, from September 2024 through mid-2027. In the second quarter of 2024, following environmental studies and regulatory reviews, Centerra obtained mine permit authorizations for additional lands at Thompson Creek, which will enable the proposed pit highwall layback included in the FS. As a result of receiving these mine permit authorizations, a key first step in the overall permitting process, the Company is moving away from a two-phased capital approval previously disclosed to a single-phase capital investment over three years. Thompson Creek is proactively advancing environmental studies which should support future permitting, which will not be required until several years after first production.

Centerra’s capital investment at the Thompson Creek mine is significantly de-risked due to an existing pit, significantly advanced equipment rebuilds and purchases, and an existing process plant that requires some refurbishment. Early works to support the restart of operations at Thompson Creek are underway, progressing on budget and on schedule. The majority of the capital expenditures going forward are expected to be focused on pre-stripping activities and mill refurbishment. Over the first six months of 2024, capital spending at Thompson Creek was primarily related to refurbishment of existing mining mobile equipment and the purchase of additional mobile equipment, stripping activities and technical studies.

Updated 2024 Guidance at Thompson Creek

For the second half of 2024, total project costs at Thompson Creek are expected to be $55 to $65 million, primarily related to pre-production stripping and mine mobile fleet upgrades. Approximately $10 million of these costs will be expensed for accounting purposes, with the remainder treated as capital expenditures. Including the actual amounts spent in the first six months of 2024 of $20.9 million, full year 2024 project development costs guidance at Thompson Creek is $75 to $85 million.

Sensitivity to Molybdenum Prices

The Thompson Creek FS and integration of Langeloth demonstrate strong economics at assumed flat molybdenum prices of $20 per pound. Langeloth provides resilience to low molybdenum prices in the cycle. The sensitivity to changes in molybdenum prices is illustrated in the table below.

FS Economics (Thompson Creek only)

 Molybdenum Price ($/pound)
$17.50$20.00 (FS price)$22.50$25.00
NPV8%($7M)$185M$370M$542M
NPV5%$70M$307M$535M$744M
IRR8%15%21%26%


US Moly Integrated Economics (Thompson Creek plus Langeloth)

 Molybdenum Price ($/pound)
$17.50$20.00 (FS price)$22.50$25.00
NPV8%$313M$472M $628M$782M
NPV5%$496M$692M$885M$1,076M
IRR18%22%26%29%


Mineral Reserve and Mineral Resource Estimates

Thompson Creek is an open pit operation that was active until 2014 when management made the decision to cease operations due to falling molybdenum prices. After approximately 10 years on care and maintenance, the historical mineral resource model needed to be updated. The tables below outline the mineral reserve and resources at Thompson Creek as of September 1, 2024.

Thompson Creek Mineral Molybdenum Reserve and Resource Estimate (September 1, 2024)

 Tons
(M)
Molybdenum
Grade

(%)
Contained Molybdenum
(Mlbs)
Proven490.07675
Probable750.05786
Proven and Probable1250.065161
Measured60.0597
Indicated500.05757
Measured and Indicated550.05763
Inferred120.07217

NOTE: See “Reserve and Resource Notes” at the end of this news release. Totals may not sum precisely due to rounding.

Endako Project

Centerra has a 75% interest in the Endako mine in northern British Columbia, Canada, which is part of the MBU. The remaining 25% interest is held by Moon River Capital Ltd. Endako is expected to remain in care and maintenance while the Company focuses on the Thompson Creek restart. Endako is an important primary molybdenum asset with a large defined resource in a top-tier jurisdiction, with a modern processing plant, providing longer-term optionality. Should Endako be restarted in the future, it has the potential to provide approximately one third of the molybdenum feed supplied to Langeloth, which could either complement or replace the Thompson Creek feed.

Molybdenum Market

Molybdenum is an industrial metal principally used for metallurgical applications such as a ferro-alloy in engineered, stainless, and other speciality steels where high strength, temperature-resistant or corrosion-resistant properties are sought. The addition of molybdenum enhances the strength, toughness and wear and corrosion-resistance in steels. Molybdenum is used in major industries including chemical and petrochemical processing, oil and gas for drilling and pipelines, power generation, automotive and aerospace. It is also required for several green energy applications, especially wind, geothermal and nuclear. Higher purity molybdenum is also widely used in non-metallurgical applications such as petroleum refining catalysts, lubricants, flame-retardants in plastics, water treatment and as a pigment.

According to the World Bank report Minerals for Climate Action: The Mineral Intensity of the Clean Energy Transition (2020), molybdenum is named one of the cross-cutting minerals, like copper, needed across a range of low-carbon technologies, especially wind and geothermal. The report estimates that the cumulative molybdenum demand under the renewable energy roadmap scenario from the International Renewable Energy Agency may grow by 119% through 2050 from green technologies only. Based on data from the International Molybdenum Association, the world used around 630 million pounds of molybdenum in 2023, with the most used in engineered steels (38%), stainless steels (25%) and chemicals (13%). A variety of end uses and limited substitution ensures that molybdenum is not dependent on specific industries, making the demand for it relatively stable.

Conference Call to Discuss the Strategic Plan for US Moly

Centerra will host a conference call and webcast to discuss the strategic plan for US Moly on Friday, September 13, 2024, at 9:00 am Eastern Time. Details for the conference call and webcast are included below.

Webcast

  • Participants can access the webcast at the following link.
  • An archive of the webcast will be available for until end of day December 13, 2024.

Conference Call

  • Participants can register for the conference call at the following registration link. Upon registering, you will receive the dial-in details and a unique PIN to access the call. This process will by-pass the live operator and avoid the queue. Registration will remain open until the end of the live conference call.
  • Participants who prefer to dial-in and speak with a live operator, can access the call by dialing 1-844-763-8274 or 647-484-8814. It is recommended that you call 10 minutes before the scheduled start time.
  • After the call, an audio recording will be made available via telephone for one month, until end of day October 13, 2024. The recording can be accessed by dialing 412-317-0088 or 1-877-344-7529 and using the passcode 1752426. In addition, the webcast will be archived on Centerra’s website at: www.centerragold.com.

About Centerra Gold

Centerra Gold Inc. is a Canadian-based gold mining company focused on operating, developing, exploring and acquiring gold and copper properties in North America, Türkiye, and other markets worldwide. Centerra operates two mines: the Mount Milligan Mine in British Columbia, Canada, and the Öksüt Mine in Türkiye. The Company also owns the Goldfield District Project in Nevada, United States, the Kemess Project in British Columbia, Canada, and owns and operates the Molybdenum Business Unit in the United States and Canada. Centerra’s shares trade on the Toronto Stock Exchange (“TSX”) under the symbol CG and on the New York Stock Exchange (“NYSE”) under the symbol CGAU. The Company is based in Toronto, Ontario, Canada.

For more information:

Lisa Wilkinson 
Vice President, Investor Relations & Corporate Communications 
(416) 204-3780 
lisa.wilkinson@centerragold.com 

Lana Pisarenko 
Senior Manager, Investor Relations  
(416) 204-1957
lana.pisarenko@centerragold.com 

Additional information on Centerra is available on the Company’s website at www.centerragold.com, on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov/edgar.

Reserve and Resource Notes

  1. Mineral Reserves stated in the table above are the economic portion of the Measured and Indicated Mineral Resource contained within the engineered pit design following the selected ultimate Pseudoflow pit shell.
  2. Mineral Reserves are stated in terms of in situ tons and grade before process recovery is applied.
  3. Modifying factors such as dilution and mining loss have been accounted for.
  4. The economic assumptions used for the Mineral Reserve estimate include: ore mining cost of $2.17/ton; waste mining cost of $1.77/ton; mining sustaining cost of $0.06/ton; G&A, processing, and sustaining costs of $7.33/ton ore; and selling cost of $1,460/ton metal in concentrate.
  5. Mineral Reserves are based upon a 0.030% Mo internal cut-off grade with some marginal material included, using a $16.00/lb Mo price with a variable molybdenum recovery.
  6. Mineral Resources are reported exclusive of Mineral Reserves; Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
  7. Mineral Resources are considered for open pit extraction.
  8. Resources are reported using a 0.025% Mo cut-off grade within a conceptual pit shell and are exclusive of Mineral Reserves. Economic parameters for the determination of the resource cut-off grade include: (i) Molybdenum price of US$18.50/lb; (ii) Mining cost of $1.77-$2.17/ton and G&A and processing cost of $6.75/ton processed. Sustaining costs were not included in the resource cut-off grade calculation; (iii) At the cut-off grade an 82% recovery was assumed.
  9. Mineral Resources are classified and have been estimated in accordance with CIM Definition Standards.
  10. As required by reporting guidelines, rounding may result in apparent summation differences between tons, grade, and metal content.
  11. Refer to the full technical report for the Thompson Creek mine at www.centerragold.com, on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov/edgar.

Feasibility Study Qualified Persons (“QPs”)

Lars Weiershäuser, PhD, P.Geo, and Centerra’s Director, Geology, has reviewed and approved the scientific and technical information included in this news release related to mineral resource estimates. Dr. Weiershäuser is a Qualified Person within the meaning of the Canadian Securities Administrators’ National Instrument 43-101, Standards of Disclosure for Mineral Projects (“NI 43-101”).

Jean-Francois St-Onge, Professional Engineer, member of the Professional Engineers of Ontario (PEO), has reviewed and approved the scientific and technical information in this news release related to mineral reserve estimates, operating and capital costs. Mr. St-Onge is a Qualified Person within the meaning of NI 43-101. Mr. St-Onge was Centerra’s Senior Director, Technical Services until May 31, 2024, and is now providing services to the Company as an external consultant.

All other scientific and technical information presented in this news release was reviewed and approved by Centerra’s geological and mining staff under the supervision of W. Paul Chawrun, Professional Engineer, member of the Professional Engineers of Ontario (PEO) and Centerra’s Executive Vice President and Chief Operating Officer. Mr. Chawrun is a Qualified Person within the meaning of NI 43-101.

For more information on the FS and the full list of QPs, please refer to the full technical report for the Thompson Creek mine at www.centerragold.com, on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov/edgar.

Assumptions

The economic analysis of the project was performed using the following assumptions and basis:

  1. Economic assessment for Thompson Creek is prepared on a stand-alone basis and does not include any integration with Langeloth.
  2. Pre-tax net cash flows for Thompson Creek include all operating, transport, treatment, capital and reclamation costs.
  3. Economic assessment of the project uses a discounted cash flow approach. Cash flows are taken to occur at the mid-year of each period. NPV is calculated by applying no discounting to 2024 cash flows and by discounting LOM cash flows from the year 2025 to the end of mine life to January 1, 2025, using 8% discount rate.
  4. Project economics are based on a valuation date of September 1, 2024.
  5. A price of $20/lb of molybdenum is assumed throughout the LOM.
  6. All costs presented are in constant US dollars as of Q2 2024 with no price inflation or escalation factors applied.
  7. Ore production is scheduled to begin in Q3 2027.
  8. Mine life is 16 years, including an initial four years of construction and waste stripping from years 2024 to 2027 and 12 years of production activities.
  9. Average annual molybdenum production during production years is 12 million pounds per year. All molybdenum produced by the mine is assumed to be sold in the same year it is produced.
  10. Working capital for Thompson Creek is assumed not to change significantly over the LOM and is not modeled in this economic analysis.
  11. No salvage values are assumed for the capital equipment at the end of mine life.
  12. Reclamation and closure costs for the site were estimated by an external consultant at a total of $202 million. Reclamation and closure activities will start progressively after the end of production in 2039, with the bulk of reclamation work to be completed by 2045, followed by ongoing tailings management costs and monitoring thereafter.
  13. Transportation costs for molybdenite concentrate shipments to Langeloth are estimated at $29 million over the LOM. Treatment costs at Langeloth are estimated at $118 million over the LOM. These costs include all processing and refining expenses necessary to convert the molybdenite concentrate into molybdenum oxide and other marketable products. The estimated costs for transportation to and treatment at Langeloth are based on current trucking quotes and current treatment costs at the facility, respectively.

Caution Regarding Forward-Looking Information
Information contained in this document which is not a statement of historical fact, and the documents incorporated by reference herein, may be “forward-looking information” for the purposes of Canadian securities laws and within the meaning of the United States Private Securities Litigation Reform Act of 1995. Such forward-looking information involves risks, uncertainties and other factors that could cause actual results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward-looking information. The words "achieve", “advance”, “assume”, “anticipate”, “approach”, “believe”, “budget”, “could”, “de-risk”, “develop”, “enhance”, “estimate”, “expect”, “explore”, “focus”, “forecast”, “future”, “generate”, “growth”, “in line”, “improve”, “may”, “maximize”, “offset”, “optimize”, “plan”, "potential", “remaining”, “restart”, “result”, “schedule”, “strategy”, “subject to”, “target”, “understand”, “update”, “will”, and similar expressions identify forward-looking information.

These forward-looking statements relate to, among other things: statements regarding the Company’s strategic plan; any synergies which may arise from, or are expected to arise from, the vertical integration of Thompson Creek and Langeloth including the Company’s ability to source and blend the concentrate from Thompson Creek or third-parties at Langeloth; the proposed pit highwall layback included in the Thompson Creek feasibility study; projections regarding earnings, cash flow from operations, free cash flow, internal rates of return and after-tax net present values for Thompson Creek, Langeloth or US Moly; the 2024 guidance for project spending at Thompson Creek related to capitalized stripping, plant refurbishment, mine mobile fleet upgrades and capital expenditure guidance; fluctuation of, sensitivity to, and assumptions of molybdenum prices and the impact it may have on the future supply and demand of molybdenum and steel; the expected profile of US Moly’s future production and costs; updates to the life of mine plan for Thompson Creek; the expected filing of a technical report for Thompson Creek; Langeloth’s ability to capitalize on growing demand in the molybdenum market; strategic options for the entire MBU and US Moly; future cash flow generation and profitability from Thompson Creek, Langeloth or US Moly; evaluating external opportunities for growth; ongoing evaluations of a restart of Thompson Creek, including integrating Langeloth, its operating capacities and the use of the concentrate from Thompson Creek or third-parties, the ability of the Company successfully advance environmental studies that support future permitting; the Company receiving all necessary permits and authorizations required during the restart and production at Thompson Creek; mineral reserve and mineral resource estimates from Thompson Creek; the ability to ramp-up operations at Langeloth and realizing its full annual capacity; the ability of the Company to obtain the requisite supply to support full capacity at Langeloth from third-parties; future prices of molybdenum including the ability of the Company to purchase concentrate at a discount to the market and being able to sell final products at or above this benchmark; the future of Endako, its ability to supply Langeloth with molybdenum feed if restarted and whether or not this molybdenum feed could complement or replace that feed from Thompson Creek; and the future exploration plans for the Company.

Forward-looking information is necessarily based upon a number of estimates and assumptions that, while considered reasonable by Centerra, are inherently subject to significant technical, political, business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward- looking information. Factors and assumptions that could cause actual results or events to differ materially from current expectations include, among other things: (A) strategic, legal, planning and other risks associated with the Company’s operations, including; the management of external stakeholder expectations; the impact of changes in, or to the more aggressive enforcement of, laws, regulations and government practices; risks that community activism may result in increased contributory demands or business interruptions; potential defects of title in the Company’s properties that are not known as of the date hereof; the imprecision of the Company’s mineral reserves and resources estimates and the assumptions they rely on, including environmental, processing permitting, taxation, socioeconomic, infill and exploration drilling and other factors; key assumptions, parameters and methods used to estimate the mineral reserve and mineral resource estimate in the Thompson Creek feasibility study; Indigenous claims and consultative issues relating to the Company’s properties which are in proximity to Indigenous communities; and (B) risks related to operational matters and geotechnical issues and the Company’s continued ability to successfully manage such matters, including: the ability of the Company to achieve pit slope design angles at Thompson Creek, particularly in the North Wall, which will be based on future drilling and may be impacted by stronger/weaker rock characteristics, favorable/unfavorable geologic structure, and/or variations in pore pressures that could result in an increase or decrease in required depressurization to achieve these slope design angles; the ability of the Company to achieve historical throughput rates at Thompson Creek; the Company receiving the required authorizations and permits for the restart of Thompson Creek; the ability of the Company to source and blend concentrate from Thompson Creek or third-parties at Langeloth; the stability of the pit walls at the Company’s operations, including Thompson Creek; the integrity of tailings storage facilities and the management thereof, including as to stability, seismic activity, compliance with laws, regulations, licenses and permits, controlling seepages and storage of water, where applicable and any future capital expenditures required for active reclamation and tailings storage facilities issues; changes to current remediation plans due to tailings storage facilities structures; the ability of the Company to achieve its commercial optimization plan at Langeloth; changes to, or delays in the Company’s supply chain and transportation routes, including cessation or disruption in rail and shipping networks, whether caused by decisions of third-party providers or force majeure events (including, but not limited to: labour action, flooding, wildfires, earthquakes, pandemics, or other global events such as wars); risks related to future price of molybdenum, inflation and interest rates; the adequacy of the Company’s insurance to mitigate operational and corporate risks; mechanical breakdowns; the occurrence of any labour unrest or disturbance and the ability of the Company to successfully renegotiate collective agreements when required; reliance on a limited number of suppliers for certain consumables, equipment and components; the ability of the Company to address physical and transition risks from climate change; the Company’s ability to accurately predict decommissioning and reclamation costs and the assumptions they rely upon; the Company’s ability to attract and retain qualified personnel; . For additional risk factors, please see section titled “Risks Factors” in the Company’s most recently filed Annual Information Form (“AIF”) available on SEDAR+ at www.sedarplus.com and EDGAR at www.sec.gov/edgar and the “Capital and Operating Costs – Material Assumptions”, “Economic Analysis – Assumptions”, “Interpretation and Conclusions - Risks and Opportunities” sections of the technical report for Thompson Creek which will be available on SEDAR+ at www.sedarplus.com and EDGAR at www.sec.gov/edgar.

There can be no assurances that forward-looking information and statements will prove to be accurate, as many factors and future events, both known and unknown could cause actual results, performance or achievements to vary or differ materially from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements contained herein or incorporated by reference. Accordingly, all such factors should be considered carefully when making decisions with respect to Centerra, and prospective investors should not place undue reliance on forward-looking information. Forward-looking information is as of September 12, 2024. Centerra assumes no obligation to update or revise forward-looking information to reflect changes in assumptions, changes in circumstances or any other events affecting such forward-looking information, except as required by applicable law.

Non-GAAP Financial Measures

This document contains “specified financial measures” within the meaning of NI 52-112, specifically the non-GAAP financial measures and non-GAAP ratios described below. Management believes that the use of these measures assists analysts, investors and other stakeholders of the Company in understanding the costs associated with producing molybdenum, understanding the economics of molybdenum mining, assessing operating performance, the Company’s ability to generate free cash flow from current operations and on an overall Company basis and for planning and forecasting of future periods. However, the measures have limitations as analytical tools as they may be influenced by the point in the life cycle of a specific mine and the level of additional exploration or other expenditures a company has to make to fully develop its properties. The specified financial measures used in this document do not have any standardized meaning prescribed by IFRS and may not be comparable to similar measures presented by other issuers, even as compared to other issuers who may be applying the World Gold Council (“WGC”) guidelines. Accordingly, these specified financial measures should not be considered in isolation, or as a substitute for, analysis of the Company’s recognized measures presented in accordance with IFRS.

Definitions

The following is a description of the non-GAAP financial measures and non-GAAP ratios used in this document:

  • EBITDA is a non-GAAP financial measure that represents earnings before interest, taxes, depreciation, and amortization. It is calculated by adjusting earnings from operations as recorded in the consolidated statements of earnings by depreciation and amortization. Management uses this measure to monitor and plan for the operating performance of the Company in conjunction with other data prepared in accordance with IFRS.
  • Free cash flow (deficit) is a non-GAAP financial measure calculated as cash provided by operating activities from continuing operations less property, plant and equipment additions. A reconciliation of free cash flow to the nearest IFRS measures is set out below. Management uses this measure to monitor the amount of cash available to reinvest in the Company and allocate for shareholder returns.
  • Sustaining capital expenditures and Non-sustaining capital expenditures are non-GAAP financial measures. Sustaining capital expenditures are defined as those expenditures required to sustain current operations and exclude all expenditures incurred at new operations or major projects at existing operations where these projects will materially benefit the operation. Non-sustaining capital expenditures are primarily costs incurred at ‘new operations’ and costs related to ‘major projects at existing operations’ where these projects will materially benefit the operation. A material benefit to an existing operation is considered to be at least a 10% increase in annual or life of mine production, net present value, or reserves compared to the remaining life of mine of the operation. A reconciliation of sustaining capital expenditures and non-sustaining capital expenditures to the nearest IFRS measures is set out below. Management uses the distinction of the sustaining and non-sustaining capital expenditures as an input into the calculation of all-in sustaining costs per ounce and all-in costs per ounce.
  • All-in sustaining costs per molybdenum pound sold is a non-GAAP financial measure that includes all operating costs, comprising of all stripping costs, capital costs and treatment costs. This measure incorporates costs incurred during the production phase. Management uses this measure to monitor and plan for the operating performance of the Company in conjunction with other data prepared in accordance with IFRS.

FAQ

What is the expected NPV and IRR for Centerra's integrated US Molybdenum Operations?

The integrated value of Thompson Creek and Langeloth is expected to have an after-tax NPV8% of $472 million and IRR of 22%.

How much capital investment is required to restart the Thompson Creek mine?

Restarting the Thompson Creek mine requires a capital investment of approximately $397 million over three years, from September 2024 through mid-2027.

What is the expected annual molybdenum production from Thompson Creek after ramp-up?

Thompson Creek is expected to produce approximately 13 million pounds of molybdenum annually after initial ramp-up, with a 12-year mine life.

What is Langeloth's planned annual production capacity by 2028?

Langeloth plans to ramp up production to reach its full capacity of 40 million pounds per annum by 2028.

How much EBITDA is Langeloth expected to generate annually at full capacity?

At full production capacity and integrated with Thompson Creek, Langeloth has the potential to generate approximately $50 million of EBITDA annually.

Centerra Gold Inc.

NYSE:CGAU

CGAU Rankings

CGAU Latest News

CGAU Stock Data

1.32B
208.57M
0.18%
90.94%
1.16%
Gold
Basic Materials
Link
United States of America
Toronto