Bayridge Resources Drilling Update at Waterbury East Project
Bayridge Resources has completed its fall 2024 drilling program at the Waterbury East uranium project in Canada's Athabasca Basin. The program consisted of six holes totaling 2,721 metres, testing multiple targets between September 26th and November 6th, 2024. Five out of six holes recorded zones of elevated counts per second. The drilling focused on two key target areas: WAT005 and the 2024 VTEM conductor. The program confirmed the presence of anomalous CPS at the unconformity and within faulted metasedimentary basement rocks. Samples from the first two holes are at the lab with results pending. The company has also announced its decision to discontinue advancing the Sharpe Lake lithium project.
Bayridge Resources ha completato il suo programma di perforazione autunnale 2024 presso il progetto uranium Waterbury East nel bacino di Athabasca, in Canada. Il programma ha incluso sei pozzi per un totale di 2.721 metri, testando più obiettivi tra il 26 settembre e il 6 novembre 2024. Cinque dei sei pozzi hanno registrato zone con conteggi per secondo elevati. La perforazione si è concentrata su due aree chiave: WAT005 e il conduttore VTEM 2024. Il programma ha confermato la presenza di CPS anomali all'inconformità e all'interno delle rocce basali metasedimentarie fratturate. I campioni dei primi due pozzi sono in laboratorio in attesa dei risultati. L'azienda ha anche annunciato la decisione di interrompere l'avanzamento del progetto litio Sharpe Lake.
Bayridge Resources ha completado su programa de perforación de otoño de 2024 en el proyecto de uranio Waterbury East en la cuenca de Athabasca, Canadá. El programa constó de seis pozos que sumaron 2,721 metros, probando múltiples objetivos entre el 26 de septiembre y el 6 de noviembre de 2024. Cinco de los seis pozos registraron zonas con conteos por segundo elevados. La perforación se centró en dos áreas clave: WAT005 y el conductor VTEM 2024. El programa confirmó la presencia de CPS anómalos en la inconformidad y dentro de las rocas metasedimentarias basales falladas. Las muestras de los primeros dos pozos están en el laboratorio a la espera de resultados. La empresa también ha anunciado su decisión de interrumpir el avance del proyecto de litio Sharpe Lake.
베이리지 리소스는 캐나다 아사바스카 분지에 있는 워터버리 이스트 우라늄 프로젝트에서 2024년 가을 채굴 프로그램을 완료했습니다. 이 프로그램은 6개의 구멍을 포함하여 총 2,721미터를 채굴하며, 2024년 9월 26일부터 11월 6일 사이에 여러 목표 지점을 테스트했습니다. 6개의 구멍 중 5개는 초당 높은 계수를 기록했습니다. 채굴은 두 가지 주요 목표 지역인 WAT005와 2024 VTEM 도체에 집중되었습니다. 이 프로그램은 불일치와 단층이 있는 변성 퇴적암 내에서 비정상적인 CPS의 존재를 확인했습니다. 첫 두 개 구멍의 샘플은 실험실에 있으며 결과를 기다리고 있습니다. 회사는 또한 샤프 레이크 리튬 프로젝트를 지속적으로 진행하지 않기로 결정했다고 발표했습니다.
Bayridge Resources a achevé son programme de forage d'automne 2024 sur le projet d'uranium Waterbury East dans le bassin d'Athabasca au Canada. Le programme a consisté en six forets totalisant 2 721 mètres, testant plusieurs cibles entre le 26 septembre et le 6 novembre 2024. Cinq des six forets ont enregistré des zones avec des comptages par seconde élevés. Le forage s'est concentré sur deux zones cibles clés : WAT005 et le conducteur VTEM 2024. Le programme a confirmé la présence de CPS anormaux à l'inconformité et dans les roches métasédimentaires basement fracturées. Des échantillons des deux premiers forets sont au laboratoire, les résultats sont en attente. L'entreprise a également annoncé sa décision de cesser de faire avancer le projet de lithium Sharpe Lake.
Bayridge Resources hat sein Bohrprogramm für den Herbst 2024 im Uranprojekt Waterbury East im kanadischen Athabasca-Becken abgeschlossen. Das Programm umfasste sechs Bohrlöcher mit einer Gesamtlänge von 2.721 Metern, die zwischen dem 26. September und dem 6. November 2024 mehrere Ziele testeten. Fünf der sechs Bohrlöcher zeichneten Bereiche mit erhöhten Zählungen pro Sekunde auf. Das Bohren konzentrierte sich auf zwei Schlüsselzielbereiche: WAT005 und den 2024 VTEM-Leiter. Das Programm bestätigte die Anwesenheit von anomalem CPS an der Unkonformität und innerhalb der gestörten metasedimentären Grundgesteine. Proben aus den ersten beiden Bohrlöchern sind im Labor, die Ergebnisse stehen noch aus. Das Unternehmen hat auch die Entscheidung bekannt gegeben, das Lithiumprojekt Sharpe Lake nicht weiter voranzutreiben.
- Five out of six drill holes showed elevated radioactivity counts
- Successfully completed 2,721 metres of drilling across six holes
- Confirmed presence of uranium-favorable geological structures
- Discontinued advancement of Sharpe Lake lithium project
- No significant uranium mineralization reported yet
- Lab results still pending for initial drill holes
Vancouver, British Columbia--(Newsfile Corp. - November 19, 2024) - Bayridge Resources Corp. (CSE: BYRG) (OTCQB: BYRFF) (FSE: O0k) ("Bayridge") has completed the fall 2024 drilling program at its 1,337 ha Waterbury East uranium project in Canada's Athabasca Basin. Six holes totaling 2,721 metres tested multiple targets between September 26th and November 6th, 2024.
"We are very pleased with our initial 2024 drill program, which largely focussed on two key target areas: WAT005 and the 2024 VTEM conductor," commented Bayridge President & CEO Saf Dhillon. "Zones of elevated counts per second, varying concentrations of graphite, shearing, faulting and alteration make this phase of drilling a strong success and definitely warrant a follow-up drill program in the new year," he continued. "Samples from the first two holes are at the lab and results will be released as they are received and QA/QC'd," he concluded.
Figure 1. 2024 Drill Collar Locations
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/10256/230527_4a8bd439a41f7a89_001full.jpg
The objective of the 2024 diamond drill program was to follow-up historic anomalous uranium results from the 2005-2007 drill campaign completed by CanAlaska Uranium and test conductors and prospective structures outlined by the 2024 VTEM-Mag helicopter-borne geophysical survey completed by Geotech Ltd. All of the drill holes completed during the 2024 program were probed in 0.10m increments in both the up and down direction, with a Mount Sopris 2SNA-1000-S Spectral Gamma probe which records total count per second (CPS). Zones of elevated counts were recorded in 5 out 6 holes.
Table 1: 2024 Collar Information
Hole ID | Easting (NAD83 UTM ZN13N) | Northing (NAD83 UTM ZN13N) | Azimuth (Deg) | Dip (Deg) | Final Depth (m) |
WB24001 | 554010 | 6446497 | 355 | -68 | 380 |
WB24002 | 554126 | 6446495 | 355 | -68 | 392 |
WB24003 | 552858 | 6445599 | 335 | -65 | 729 |
WB24004 | 554074 | 6446451 | 355 | -68 | 467 |
WB24005 | 553881 | 6446320 | 300 | -65 | 350 |
WB24006 | 552817 | 6445703 | 339 | -45 | 403 |
Total meterage | 2721 |
Drill holes WB24001, WB24002 and WB24004 followed up on the historic intersection of 324 ppm uranium over 0.6m in drill hole WAT005, testing the strike extension to the NE and the SW and also testing the up-dip extension. Elevated CPS were recorded at the unconformity and also + 70 metres further downhole in a chlorite-biotite altered psammitic gneiss carrying 1
The three drill holes, WB24001, WB24002, and WB24004, confirmed the presence of anomalous CPS at the unconformity and within the faulted and variably graphitic metasedimentary basement rocks. Preliminary modelling suggests that the deeper anomaly from WB24001, the upper anomaly in WB24002, and the anomaly from WB24004 correlate to the bottom of the fracture zone defined in WAT005. This zone appears to be basement fault-controlled and a shallowly dipping to the southwest.
Table 2: Spectral Gamma Probe Highlights
Hole ID | Best Gamma (cps over 0.1m) | Average cps over: | interval (m) |
WB24001 | 1056 | 517 | 210.44-214.04m |
WB24001 | 1129 | 616 | 279.04-279.64m |
WB24002 | 898 | 541 | 233.68-234.78m |
WB24002 | 408 | 233 | 308.98-309.78m |
WB24003 | 430 | 287 | 44.8-45.5m |
WB24004 | 1530 | 691 | 266.35-268.95m |
WB24006 | 476 | 342 | 328.86-329.16m |
WB24005 was drilled to connect the historic basement hosted mineralization intersected in WAT005 (324 ppm uranium over 0.6m) and WAT001, which displayed 18m of hydrothermally illite clay altered basement rock at 281m depth which returned 12.9ppm U and 371ppm B. While no elevated CPS was noted, 0.4m of strong foliation and strong brick red pervasive and fracture controlled hematization was observed from 287m downhole, indicating a basement structure host to hydrothermal fluids may be nearby.
Two drillholes, WB24003 and WB24006, were completed in the central-southwest portion of the Waterbury East tenure to test the steeply dipping modelled maxwell conductor plate, outlined by the 2024 VTEM-Mag survey.
WB24003, the first hole, tested the conductor 362m below the unconformity. Elevated CPS was noted at the unconformity at 233.3m downhole with a 90
The Waterbury East project is underlain by geology favourable to hosting both unconformity-hosted and basement-hosted uranium deposits. These deposits are typically associated with graphitic metasediments and structural zones that exhibit strong EM conductor responses. Historical airborne EM surveys have defined an ENE-striking conductor across the property, with a depth to unconformity of ~200m. Most of the uranium discoveries in the Athabasca Basin are concentrated along the unconformity edge, where the sedimentary cover is the thinnest (<300m).
Bayridge holds a staged option to earn up to an
Sharpe Lake Project
The Company also announces that, in order to better focus its resources, it has elected to not proceed with advancing the Sharpe Lake lithium project and has provided notice of same to the property owner.
R. Tim Henneberry, P.Geo. (BC) and a consultant to the Company, is the Qualified Person under National Instrument 43-101 who has reviewed and approved the technical contents of this news release
About Bayridge Resources Corp.
Bayridge Resources Corp. is a green energy company advancing its portfolio of Canadian uranium projects. The 1,337 ha Waterbury East project is located 25 km northeast of the Cigar Lake Mine in the northeastern Athabasca Basin region. Geophysical surveys have identified a 7km long conductivity corridor where mid-2000's drilling highlighted faulted and altered basement rock with local uranium enrichment. Large sections of this corridor remain untested. The 11,142 ha Constellation project is located 60 km south of the present-day Athabasca Basin edge in an area of significant exploration activity for basement hosted uranium. Historic airborne radiometric, electromagnetic, and magnetic surveys identified electromagnetic conductors associated with magnetic lows.
For more information, please contact:
Saf Dhillon, President & Chief Executive Officer
E-mail: saf@bayridgeresources.com
Tel: 604-484-3031
Forward-looking information
Certain statements in this news release are forward-looking statements, which reflect the expectations of management regarding follow up drill programs on the Waterbury East uranium project and the completion of the staged option to earn up to an
The CSE has not reviewed, approved, or disapproved the contents of this press release.
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/230527
FAQ
What were the results of Bayridge Resources (BYRFF) 2024 drilling program at Waterbury East?
How many meters did Bayridge Resources (BYRFF) drill at Waterbury East in fall 2024?