Boliden: Update expansion project Odda and capital expenditure guidance 2025
Rhea-AI Summary
Boliden's expansion project at the Odda zinc smelter, aimed at increasing annual production from 200 to 350 ktonnes, faces delays primarily in the roasting facility. The ramp-up towards the new production level will now start at the end of Q1 2025, instead of Q4 2024. This delay results in a EUR 100 million cost increase for the project. Despite this setback, Boliden's total capital expenditures for 2024 remain at SEK 15.5 billion, with 2025 expenditures estimated at SEK 13.5 billion.
The investment is still expected to generate EUR 150 million in annual EBITDA. Odda's production capacity will return to 200 ktonnes from Q1 2025, with full production of 350 ktonnes to be achieved progressively during 2025.
Positive
- Investment in Odda zinc smelter still expected to generate EUR 150 million in annual EBITDA
- Odda's production capacity to return to 200 ktonnes from Q1 2025
- Most of the expansion project components are on schedule for completion by end of 2024
Negative
- Delay in Odda expansion project, particularly in the roasting facility
- EUR 100 million cost increase due to project delay
- Ramp-up to new production level postponed from Q4 2024 to end of Q1 2025
- Full production capacity of 350 ktonnes delayed until later in 2025
News Market Reaction 1 Alert
On the day this news was published, BDNNY gained 1.98%, reflecting a mild positive market reaction.
Data tracked by StockTitan Argus on the day of publication.
In addition to enhanced electricity supply and quay infrastructure, the investment in Odda also includes a new roasting facility, a new sulfhuric acid plant, expansion and modernization of the leaching and purification plant, a new tankhouse and expansion of the foundry. In the vast majority of cases, the work follows the original plan, which means completion and commissioning towards the end of 2024. Due to delayed construction works at primarily the roasting facility, the new production capacity 350 ktonnes will be delayed. The start of the ramp-up, originally planned for the fourth quarter 2024, will instead start at the end of the first quarter of 2025 and full production is estimated to be achieved successively during 2025. The delay results in an additional
The investments in Odda is estimated to generate
Boliden's total investments for 2024 are estimated to be
In light of the above, a press and analyst conference will be held today, September 12, at 09:00 CEST, and can be followed via webcast and telephone. The conference will be led by Boliden's President and CEO Mikael Staffas, and CFO Håkan Gabrielsson.
To participate in the webcast, please use the link below:
https://boliden.videosync.fi/2024-09-12-1omnwfqbz5
To participate in the telephone conference, please register 5 minutes before the opening of the conference via the link below. After the registration you will be provided with phone number and a conference ID to access the conference. If you wish to ask a question, please dial *5 on your telephone keypad to enter the queue.
https://service.flikmedia.se/teleconference/?id=100429
After the call, presentation material and the recorded webcast will be available on our website: https://www.boliden.com
For further information, please contact:
Klas Nilsson
Director Group Communications
+46 70 453 65 88
klas.nilsson@boliden.com
This information is information that Boliden AB is obliged to make public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of contact person above, at 07:00 CEST on September 12, 2024.
This information was brought to you by Cision http://news.cision.com
The following files are available for download:
Press release |
View original content:https://www.prnewswire.com/news-releases/boliden-update-expansion-project-odda-and-capital-expenditure-guidance-2025-302246095.html
SOURCE Boliden