STOCK TITAN

Brixton Metals Provides Initial Assay Results from its Maiden Drill Program at the Cirque Cu-Mo Porphyry Target

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

Brixton Metals (BBBXF) has announced initial results from its maiden drill program at the Cirque Cu-Mo Porphyry Target on its Thorn Project in NW British Columbia. Highlights include:

  • Hole THN24-292: 87.00m of 0.26% CuEq including 28.50m of 0.29% CuEq
  • Hole THN24-293: 37.50m of 0.28% CuEq within 425.50m of 0.16% CuEq

The drilling targeted a potassic alteration zone with chalcopyrite and molybdenite mineralization at surface, within a larger 3.6 km x 1.6 km area of phyllic to potassic alteration. The Cirque Target is located 3 km NE of the Camp Creek Porphyry Target. Four diamond drill holes totaling 2,704 meters have been completed at Cirque, all intersecting porphyry-style Cu-Mo mineralization.

Brixton Metals (BBBXF) ha annunciato i risultati iniziali del suo programma di perforazione di debutto al Cirque Cu-Mo Porphyry Target nel progetto Thorn nel NW della Columbia Britannica. Tra i punti salienti si segnalano:

  • Foratura THN24-292: 87,00 m di 0,26% CuEq, inclusi 28,50 m di 0,29% CuEq
  • Foratura THN24-293: 37,50 m di 0,28% CuEq all'interno di 425,50 m di 0,16% CuEq

Le perforazioni hanno mirato a una zona di alterazione potassica con mineralizzazione di calcopirite e molibdenite in superficie, all'interno di una zona più ampia di 3,6 km x 1,6 km di alterazione filica a potassica. Il Cirque Target si trova a 3 km a NE del Camp Creek Porphyry Target. Sono stati completati quattro fori di perforazione a diamante per un totale di 2.704 metri al Cirque, tutti in contatto con la mineralizzazione Cu-Mo in stile porfido.

Brixton Metals (BBBXF) ha anunciado los resultados iniciales de su programa de perforación inaugural en el Cirque Cu-Mo Porphyry Target en su proyecto Thorn en el noroeste de Columbia Británica. Los aspectos más destacados incluyen:

  • Perforación THN24-292: 87,00 m de 0,26% CuEq incluyendo 28,50 m de 0,29% CuEq
  • Perforación THN24-293: 37,50 m de 0,28% CuEq dentro de 425,50 m de 0,16% CuEq

La perforación se dirigió a una zona de alteración potásica con mineralización de calcopirita y molibdenita en la superficie, dentro de un área más grande de 3,6 km x 1,6 km de alteración fílmica a potásica. El Cirque Target se encuentra a 3 km al noreste del Camp Creek Porphyry Target. Se han completado cuatro perforaciones de diamante que suman 2,704 metros en Cirque, todas intersectando mineralización Cu-Mo de estilo porfirítico.

Brixton Metals (BBBXF)는 BC주 북서부의 Thorn 프로젝트에 있는 Cirque Cu-Mo Porphyry Target에서 첫 번째 시추 프로그램의 초기 결과를 발표했습니다. 주요 내용은 다음과 같습니다:

  • 홀 THN24-292: 87.00m의 0.26% CuEq, 포함 28.50m의 0.29% CuEq
  • 홀 THN24-293: 37.50m의 0.28% CuEq, 425.50m의 0.16% CuEq 내 포함

시추는 표면의 칼코파이라이트와 몰리브덴 광맥이 있는 고칼륨 화성 zone을 목표로 했으며, 3.6 km x 1.6 km의 넓은 필릭에서 고칼륨 변형 zone 내 위치하고 있습니다. Cirque Target은 Camp Creek Porphyry Target의 북동쪽 3 km 지점에 있습니다. Cirque에서는 총 2,704 미터의 다이아몬드 시추 구멍 4개가 완료되었으며, 모두 포르피리 스타일의 Cu-Mo 광물화와 접촉했습니다.

Brixton Metals (BBBXF) a annoncé les premiers résultats de son programme de forage inaugural sur la Cirque Cu-Mo Porphyry Target dans son projet Thorn, situé au nord-ouest de la Colombie-Britannique. Les points forts incluent :

  • Forage THN24-292 : 87,00 m de 0,26 % CuEq, incluant 28,50 m de 0,29 % CuEq
  • Forage THN24-293 : 37,50 m de 0,28 % CuEq au sein de 425,50 m de 0,16 % CuEq

Le forage a ciblé une zone d'altération potassique avec des minéralisations de chalcopyrite et de molybdène en surface, à l'intérieur d'une zone plus large de 3,6 km x 1,6 km d'altération phyllique à potassique. La cible Cirque se trouve à 3 km au nord-est de la cible porphyrie Camp Creek. Quatre forages diamant ont été réalisés pour un total de 2 704 mètres au Cirque, tous interceptant une minéralisation Cu-Mo de type porphyre.

Brixton Metals (BBBXF) hat die ersten Ergebnisse seines ersten Bohrprogramms am Cirque Cu-Mo Porphyry Target im Thorn-Projekt im Nordwesten von British Columbia angekündigt. Zu den Highlights gehören:

  • Bohrung THN24-292: 87,00 m mit 0,26% CuEq, einschließlich 28,50 m mit 0,29% CuEq
  • Bohrung THN24-293: 37,50 m mit 0,28% CuEq innerhalb von 425,50 m mit 0,16% CuEq

Die Bohrungen zielten auf eine potassische Alterationszone mit Chalcopyrit- und Molybdänitmineralisierung an der Oberfläche, innerhalb eines größeren Gebiets von 3,6 km x 1,6 km mit phyllischer bis potassischer Alteration. Das Cirque Target befindet sich 3 km nordöstlich des Camp Creek Porphyry Target. Insgesamt wurden vier Diamantbohrungen mit einer Gesamtlänge von 2.704 Metern am Cirque abgeschlossen, die alle auf porphyrische Cu-Mo-Mineralisierung gestoßen sind.

Positive
  • Initial drill results show broad zones of copper-molybdenum porphyry mineralization from surface
  • Hole THN24-292 returned 87.00m of 0.26% CuEq including 28.50m of 0.29% CuEq
  • Hole THN24-293 returned 37.50m of 0.28% CuEq within 425.50m of 0.16% CuEq
  • All four drill holes at Cirque intersected porphyry-style Cu-Mo mineralization
  • The Cirque Target is part of a broader 60-kilometer-long northwest trending belt of Late Cretaceous intrusions
Negative
  • None.

VANCOUVER, British Columbia, Sept. 17, 2024 (GLOBE NEWSWIRE) -- Brixton Metals Corporation (TSX-V: BBB, OTCQB: BBBXF) (the “Company” or “Brixton”) is pleased to announce its third drill hole results of the 2024 season from its wholly owned Thorn Project located in NW British Columbia, Canada. The Thorn Project is an underexplored copper-gold porphyry district with 16 large scale exploration target areas identified. Brixton is operating with two diamond drills and will continue drilling until the end of the season.

Highlights

  • Brixton Metals’ maiden drill program at the Cirque Target has intercepted broad zones of Cu-Mo porphyry style mineralization starting from surface, including:
 Hole THN24-292 returned:
 
  • 87.00m of 0.26% CuEq including 28.50m of 0.29% CuEq
 Hole THN24-293 returned:
 
  • 37.50m of 0.28% CuEq within 425.50m of 0.16% CuEq
  • Drilling has targeted a potassic alteration zone with chalcopyrite and molybdenite mineralization at surface, located within a larger 3.6 km x 1.6 km area of phyllic to potassic alteration.
  • The Cirque Porphyry Target is located approximately 3 km NE of the Camp Creek Porphyry Target, on trend along the Camp Creek fault. Geological mapping in 2024 has identified additional areas of porphyry style alteration along this trend.

Vice President of Exploration, Christina Anstey, stated, “The initial drill holes at Cirque have significantly enhanced our understanding of this early-stage drill target. The presence of porphyry style mineralization and alteration is highly encouraging and gives us a strong foundation to build on as we continue to explore and advance this target.”

Project Geologist Leanne Hawkins Highlights the Cirque Target, Thorn Project:

https://www.youtube.com/watch?v=fnXFv7BYMeI

Figure 1. Thorn Project Location Map with Copper Geochemistry.

Figure 1_17Sept2024

Table 1. Select Assay Intervals for Initial Drilling at the Cirque Porphyry Target.

Hole ID From (m) To (m) Interval (m) Cu (%)Au (g/t)Ag (g/t)Mo (ppm)CuEq (%)
THN24-29214.75401.00386.250.100.041.81470.16
including126.00213.0087.000.200.042.61340.26
including135.00163.5028.500.230.033.22300.29
including135.00145.5010.500.370.045.22360.44
THN24-2938.40433.90425.500.110.021.76420.16
including144.00335.50191.500.140.021.91510.19
including145.50223.5078.000.190.022.37340.23
including189.00226.5037.500.240.022.79390.28
THN24-295556.50787.00230.500.050.022.67200.09
including664.50704.0039.500.090.046.28350.18
including667.50686.1018.600.090.059.81330.22
including667.50677.309.800.100.0614.69580.30


HQ size core samples were cut in half and sampled predominantly at 1.5m intervals. Assay values are weighted averages. The true width of the mineralized intervals has not yet been determined.

Copper Equivalent (CuEq) is calculated based on US$ 4.02/lb Cu, US$ 2105.6/oz Au, US$ 25.16/oz Ag, $US 20.99/lb Mo. These prices represent the approximate metal prices and calculations assume 95% metal recoveries.

CuEq % = (Cu % + (0.764486* Au g/t) + (0.009134 * Ag g/t) + (0.000523 * Mo ppm)) * 0.95

Cirque Porphyry Target Mineralization at Thorn Project: https://youtu.be/EsqYbZBTz4I

Figure 2. Plan Map for the Cirque Porphyry Target.

Figure 2_17Sept2024

Figure 3. Cross-Section for the Cirque Porphyry Target.

Figure 3_17Sept2024

Project Geologist Leanne Hawkins on 2024 Exploration at Cirque Target, Thorn Project:
https://www.youtube.com/watch?v=rX77R_OoNEQ

Technical Discussion

The Cirque Porphyry Target is located approximately 3 km northeast of the Camp Creek Porphyry Target and was first explored in 1965 by Julian Mining with an eight-hole diamond drill program totaling 898 meters. The 1965 drilling outlined copper-molybdenum mineralization over a 600 m x 300 m area with no further drilling completed since. The drilled area lies within a larger 3.6 km x 1.6 km alteration zone consisting of phyllic to potassic assemblages.

Similar to the Camp Creek Porphyry Target, intrusions at Cirque are Late Cretaceous in age and are on trend to the northeast along the Camp Creek fault. Evidence of porphyry style veins intruding the Windy Table volcanics suggests that the Cirque system is younger than the Camp Creek porphyry center where the same Windy Table volcanic stratigraphy unconformably overlies Camp Creek porphyry units. Along this trend, additional areas with porphyry-style alteration have been identified during the 2024 field season. With porphyry deposits often occurring in clusters or alignments, further geological mapping, rock sampling, and hyperspectral scanning of core and rock chips will continue along this prospective corridor during the remainder of the field season.

To date, the 2024 drilling at Cirque has consisted of four diamond drill holes totaling 2,704 meters with all four holes intersecting porphyry-style Cu-Mo mineralization. Results for the first three holes are discussed below with results currently pending for THN24-299.

THN24-292 was designed to test under chalcopyrite and molybdenite mineralization identified at surface within potassium feldspar altered volcanics of the Windy Table Group. THN24-292 was collared at an azimuth of 311.5 degrees with a dip of -80.0 degrees to a total depth of 605.00m. The top of hole is dominated by a transitional magmatic-hydrothermal monzodiorite-cemented breccia with clasts of intermediate to felsic volcanic tuffs. Breccia infill comprises chalcopyrite-pyrite-magnetite-actinolite-calcite with orthoclase alteration halos, which is cut by later chalcopyrite-pyrite-molybdenite veinlets. At 211.82m the hole transitions into a potassium feldspar-biotite altered crowded monzodiorite with disseminated pyrite-chalcopyrite and rare quartz-pyrite-chalcopyrite-molybdenite-biotite veins. The crowded porphyry is intruded by a sericite altered megacrystic monzonite porphyry at 339.48m with sparse disseminated and vein-hosted chalcopyrite-molybdenite. All units are cut by post-mineral intermediate to felsic dykes.

Figure 4. Photos of Mineralized HQ-Sized Drill Core from THN24-292

Figure 4_17Sept2024

THN24-293 was collared 70 meters to the southwest of THN24-292 at an azimuth of 118.0 degrees with a dip of -66.0 degrees to a total depth of 605.00m targeting surface porphyry style mineralization. Similar to THN24-292, the top of Hole 293 intersected the magmatic-hydrothermal breccia, the host of stronger mineralization, before transitioning into the crowded monzodiorite at 227.55m which is intruded by the late-mineral megacrystic monzonite porphyry at 354.05m.

Figure 5. Photos of Mineralized HQ-Sized Drill Core from THN24-293.

Figure 5_17Sept2024

THN24-295 was collared 860 meters SSE of THN24-293 at an azimuth of 309.5 degrees with a dip of -72.8 degrees to a total depth of 808.00m. The objective of THN24-295 was to step-out to the southeast along the interpreted trend of porphyry mineralization. Hole 295 intersected a sericite altered crowded quartz monzonite porphyry which is intruded by the megacrystic monzonite starting at 547.55m. Both porphyries host pyrite and lesser chalcopyrite mineralization observed as disseminations and within quartz veins and are cut by post-mineral intermediate to felsic dykes.

Figure 6. Photos of Mineralized HQ-Sized Drill Core from THN24-295.

Figure 6_17Sept2024

The Cirque Porphyry Target sits within a broader 60-kilometer-long northwest trending belt of Late Cretaceous intrusions that span across the Thorn Project and the presence of porphyry-style mineralization at Cirque illustrates the potential for additional mineralized systems at Thorn. At this time, the strongest mineralization identified at the Cirque Target has been observed in the transitional-magmatic-hydrothermal breccia intersected in THN24-292 and THN24-293. Further work will aim to identify higher-grade portions of the breccia, the extents of this unit, and determine whether other mineralized intrusions exist within the larger 3.6 km x 1.6 km alteration zone found at the Cirque Copper Porphyry Target.

Table 2. Collar Information for THN24-292, THN24-293, and THN24-295.

Hole IDEastingNorthingElevation (m) AzimuthDipDepth (m)
THN24-29263131764930151312311.5-80.0605.00
THN24-29363125864929781330118.0-66.0605.00
THN24-29563171764922431437309.5-72.8808.00


Table 3. 2024 Drilling Progress Report as of September 15, 2024: Meters Drilled: 12500.40m.

TargetHole IDDepth (m)Status
Camp Creek (m): 5649
Camp CreekTHN24-2901564Released July 25, 2024
Camp CreekTHN24-2911523Released August 6, 2024
Camp CreekTHN24-2941553Assays Pending
Camp CreekTHN24-297251Assays Pending
Camp CreekTHN24-307758Actively Drilling
Cirque (m): 2704
CirqueTHN24-292605Current Release
CirqueTHN24-293605Current Release
CirqueTHN24-295808Current Release
CirqueTHN24-299686Assays Pending
Trapper (m): 2695.40
TrapperTHN24-300260Assays Pending
TrapperTHN24-301249Assays Pending
TrapperTHN24-302185Assays Pending
TrapperTHN24-303522Assays Pending
TrapperTHN24-304291Assays Pending
TrapperTHN24-30540.4Abandoned Hole
TrapperTHN24-306154Assays Pending
TrapperTHN24-308303Assays Pending
TrapperTHN24-309255Assays Pending
TrapperTHN24-310266Assays Pending
TrapperTHN24-311170Assays Pending
North Target (m): 1452
North TargetTHN24-296530Assays Pending
North TargetTHN24-298665Assays Pending
North TargetTHN24-312257Actively Drilling


Quality Assurance & Quality Control

Quality assurance and quality control protocols for drill core sampling was developed by Brixton. Core samples were mostly taken at 1.5m intervals. Blank, duplicate (lab pulp) and certified reference materials were inserted into the sample stream for at least every 20 drill core samples. Core samples were cut in half, bagged, zip-tied and sent directly to ALS Minerals preparation facility in Whitehorse, Yukon or Langley, British Columbia depending on available lab capacity. ALS Minerals Laboratories is registered to ISO 9001:2008 and ISO 17025 accreditations for laboratory procedures. Samples were analyzed at ALS Laboratory Facilities in North Vancouver, British Columbia for gold by fire assay with an atomic absorption finish, whereas Ag, Pb, Cu and Zn and 48 additional elements were analyzed using four acid digestion with an ICP-MS finish. Over limits for gold were analyzed using fire assay and gravimetric finish. The standards, certified reference materials, were acquired from CDN Resource Laboratories Ltd., of Langley, British Columbia and the standards inserted varied depending on the type and abundance of mineralization visually observed in the primary sample. Blank material used consisted of non-mineralized siliceous landscaping rock. A copy of the QAQC protocols can be viewed at the Company’s website.

Qualified Person (QP)

Mr. Daniel Guestrin, P.Geo., is a Senior Project Geologist for the Company who is a qualified person as defined by National Instrument 43-101. Mr. Guestrin has verified the referenced data and analytical results disclosed in this press release and has approved the technical information presented herein.

About Brixton Metals Corporation

Brixton Metals is a Canadian exploration company focused on the advancement of its mining projects. Brixton wholly owns four exploration projects: Brixton’s flagship Thorn copper-gold-silver-molybdenum Project, the Hog Heaven copper-silver-gold Project in NW Montana, USA, which is optioned to Ivanhoe Electric Inc., the Langis-HudBay silver-cobalt-nickel Project in Ontario and the Atlin Goldfields Project located in northwest BC which is optioned to Eldorado Gold Corporation. Brixton Metals Corporation shares trade on the TSX-V under the ticker symbol BBB, and on the OTCQB under the ticker symbol BBBXF. For more information about Brixton, please visit our website at www.brixtonmetals.com.

On Behalf of the Board of Directors

Mr. Gary R. Thompson, Chairman and CEO

For Investor Relations inquiries please contact: Mr. Michael Rapsch, Senior Manager, Investor Relations. email: michael.rapsch@brixtonmetals.com or call: 604-630-9707

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Information set forth in this news release may involve forward-looking statements under applicable securities laws. Forward-looking statements are statements that relate to future, not past, events. In this context, forward-looking statements often address expected future business and financial performance, and often contain words such as “anticipate”, “believe”, “plan”, “estimate”, “expect”, and “intend”, statements that an action or event “may”, “might”, “could”, “should”, or “will” be taken or occur, including statements that address potential quantity and/or grade of minerals, potential size and expansion of a mineralized zone, proposed timing of exploration and development plans, or other similar expressions. All statements, other than statements of historical fact included herein including, without limitation, statements regarding the use of proceeds. By their nature, forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements, or other future events, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Such factors include, among others, the following risks: the need for additional financing; operational risks associated with mineral exploration; fluctuations in commodity prices; title matters; and the additional risks identified in the annual information form of the Company or other reports and filings with the TSXV and applicable Canadian securities regulators. Forward-looking statements are made based on management’s beliefs, estimates and opinions on the date that statements are made and the Company undertakes no obligation to update forward-looking statements if these beliefs, estimates and opinions or other circumstances should change, except as required by applicable securities laws. Investors are cautioned against attributing undue certainty to forward-looking statements.

Links:

https://www.youtube.com/watch?v=fnXFv7BYMeI

https://youtu.be/EsqYbZBTz4I

https://www.youtube.com/watch?v=rX77R_OoNEQ

https://brixtonmetals.com/wp-content/uploads/2024/09/Figure-1_17Sept2024-scaled.jpeg

https://brixtonmetals.com/wp-content/uploads/2024/09/Figure-2_17Sept2024.jpg

https://brixtonmetals.com/wp-content/uploads/2024/09/Figure-3_17Sept2024.jpg

https://brixtonmetals.com/wp-content/uploads/2024/09/Figure-4_17Sept2024.jpg

https://brixtonmetals.com/wp-content/uploads/2024/09/Figure-5_17Sept2024.jpg

https://brixtonmetals.com/wp-content/uploads/2024/09/Figure-6_17Sept2024.jpg


FAQ

What are the initial drill results from Brixton Metals' Cirque Target (BBBXF)?

Brixton Metals' initial drill results from the Cirque Target include Hole THN24-292 with 87.00m of 0.26% CuEq including 28.50m of 0.29% CuEq, and Hole THN24-293 with 37.50m of 0.28% CuEq within 425.50m of 0.16% CuEq.

Where is the Cirque Cu-Mo Porphyry Target located within Brixton Metals' Thorn Project (BBBXF)?

The Cirque Cu-Mo Porphyry Target is located approximately 3 km northeast of the Camp Creek Porphyry Target within Brixton Metals' Thorn Project in NW British Columbia, Canada.

How many drill holes has Brixton Metals (BBBXF) completed at the Cirque Target in 2024?

Brixton Metals has completed four diamond drill holes totaling 2,704 meters at the Cirque Target in 2024, with all four holes intersecting porphyry-style Cu-Mo mineralization.

What is the size of the alteration zone at Brixton Metals' Cirque Target (BBBXF)?

The Cirque Target at Brixton Metals' Thorn Project has a larger alteration zone measuring 3.6 km x 1.6 km, consisting of phyllic to potassic assemblages.

BRIXTON METALS CORP

OTC:BBBXF

BBBXF Rankings

BBBXF Latest News

BBBXF Stock Data

25.00M
449.39M
15.7%
15.64%
Other Precious Metals & Mining
Basic Materials
Link
United States of America
Vancouver