Golden Minerals Completes Updated Technical Reports for Two Properties
Golden Minerals Company (AUMN) announced the completion of Technical Reports for its Rodeo open pit gold-silver mine and Velardeña Properties in Mexico, adhering to NI 43-101 standards. The Rodeo project has a pre-tax net present value (NPV) of $22.9 million over a 24-month life of mine, assuming $1,800/oz gold and $25.00/oz silver. Estimated operating costs are $66.68/t. The Velardeña project displays a pre-tax NPV of $119 million over 11 years. Both projects' economic models include inferred resources, emphasizing the speculative nature of these estimates.
- Rodeo project's pre-tax NPV estimated at $22.9 million.
- Velardeña project's pre-tax NPV projected at $119 million.
- No additional capital costs required at the Rodeo mine.
- Preliminary economic models for both projects include inferred resources, which are speculative.
- Operational success is sensitive to fluctuations in gold prices and operating costs.
Each TR has been completed in accordance with Canadian National Instrument 43-101 - Standards of Disclosure of Mineral Projects (“NI 43-101”). The Resources used for each report were developed by the independent engineering firm of Tetra Tech and comply with the requirements of NI 43-101. Preliminary results of each economic analysis are shown in pre-tax
Rodeo
The Rodeo mine is currently in operation and the Rodeo TR assumes a life of mine (“LOM”) starting point of
Estimated Resources
Classification
|
Cutoff Au (g/t)
|
Tonnes
|
Grade Au g/t |
Au (oz)
|
Grade Ag g/t |
Ag (oz)
|
Low-Grade (Stockpile) |
||||||
Measured |
1.0 |
208,500 |
1.24 |
8,350 |
10.03 |
67,200 |
Indicated |
1.0 |
56,400 |
1.18 |
2,140 |
5.18 |
9,400 |
Measured + Indicated |
1.0 |
264,900 |
1.23 |
10,500 |
9.00 |
76,600 |
Inferred |
1.0 |
1,500 |
1.20 |
58 |
4.09 |
198 |
High-Grade |
||||||
Measured |
1.6 |
310,700 |
3.11 |
31,100 |
13.10 |
131,000 |
Indicated |
1.6 |
43,700 |
3.17 |
4,500 |
10.67 |
15,000 |
Measured + Indicated |
1.6 |
354,400 |
3.12 |
35,600 |
12.80 |
146,000 |
Note: Columns may not total due to rounding |
Capital and Operating Costs
Required capital costs for the Rodeo mine consist of an estimated
Description |
LOM Cost
|
Unit Cost
|
||
Mining |
|
|
||
Processing |
|
|
||
G&A |
|
|
||
Total |
|
|
Economic Analysis
The LOM (life of mine) consists of 24 months of operation and assumes 12 months to perform closure and reclamation. The starting point for the LOM is
Description |
Unit Cost
|
Total Value
|
|||
NSR1 |
|
|
|||
Net Revenue |
|
|
|||
Operating Costs |
|||||
Mining |
|
( |
|||
Processing |
|
( |
|||
G&A |
|
( |
|||
Operating Costs |
|
( |
|||
Operating Margin |
|
|
|||
Capital Costs |
|||||
Mining |
- |
|
|||
Process Plant |
|
||||
Infrastructure |
- |
|
|||
Closure |
- |
( |
|||
Capital Costs |
- |
( |
|||
La Cuesta Royalty |
- |
( |
|||
|
|
|
|
||
Mexico |
- |
( |
|||
|
- |
|
|||
Pre-Tax NPV |
- |
|
1 Net smelter revenue |
Sensitivity Analysis
Sensitivity analyses on metal price and operating costs were performed on the economic model results. Due to the lack of capital cost requirements, no sensitivity analysis was conducted on capital costs. Results of sensitivity analyses show that a reduction in gold price of
Velardeña
The Velardeña Technical report (TR) assumes prices of
Estimated Resources
Classification |
Mineral Type |
NSR Cutoff |
Tonnes |
|
|
Grade Pb% |
Grade Zn% |
Ag oz |
Au oz |
Pb lb |
Zn lb |
Measured |
Oxide |
175 |
128,800 |
268 |
5.69 |
1.74 |
1.53 |
1,108,000 |
23,500 |
4,936,000 |
4,333,400 |
Indicated |
Oxide |
175 |
280,300 |
262 |
5.06 |
1.73 |
1.45 |
2,361,200 |
45,600 |
10,681,500 |
8,936,600 |
Measured + Indicated |
Oxide |
175 |
409,100 |
264 |
5.26 |
1.73 |
1.47 |
3,469,200 |
69,100 |
15,617,500 |
13,270,000 |
Inferred |
Oxide |
175 |
351,400 |
417 |
4.95 |
2.55 |
1.45 |
4,714,600 |
56,000 |
19,729,500 |
11,248,200 |
|
|
|
|
|
|
|
|
|
|
|
|
Measured |
Sulfide |
175 |
256,200 |
357 |
5.52 |
1.56 |
1.91 |
2,942,800 |
45,500 |
8,819,300 |
10,769,700 |
Indicated |
Sulfide |
175 |
603,500 |
341 |
4.79 |
1.46 |
1.91 |
6,619,400 |
92,900 |
19,475,600 |
25,408,900 |
Measured + Indicated |
Sulfide |
175 |
859,700 |
346 |
5.01 |
1.49 |
1.91 |
9,562,200 |
138,400 |
28,294,900 |
36,178,600 |
Inferred |
Sulfide |
175 |
1,357,700 |
348 |
4.76 |
1.52 |
1.97 |
15,179,000 |
207,800 |
45,534,200 |
58,952,900 |
|
|
|
|
|
|
|
|
|
|
|
|
Measured |
All |
175 |
385,000 |
327 |
5.58 |
1.62 |
1.78 |
4,050,800 |
69,000 |
13,755,300 |
15,103,100 |
Indicated |
All |
175 |
883,800 |
316 |
4.88 |
1.55 |
1.76 |
8,980,600 |
138,500 |
30,157,100 |
34,345,500 |
Measured + Indicated |
All |
175 |
1,268,800 |
319 |
5.09 |
1.57 |
1.77 |
13,031,400 |
207,500 |
43,912,400 |
49,448,600 |
Inferred |
All |
175 |
1,709,200 |
362 |
4.8 |
1.73 |
1.86 |
19,893,600 |
263,800 |
65,263,700 |
70,201,100 |
Notes: |
||
(1) |
Resources are reported as diluted Tonnes and grade to 0.7 metres fixed width |
|
(2) |
Metal prices for NSR cutoff are: |
|
(3) |
Columns may not total due to rounding |
Economic Analysis
Economic model results are summarized below. The model includes Measured, Indicated, and Inferred resources. Reclamation costs are assumed to be canceled by salvage value and are therefore not included. The LOM is 11 years, with a pre-tax NPV of
Item |
Total
|
Pb
|
Zn
|
Doré |
Gross Payable |
|
|
|
|
TCs, RCs and penalties |
( |
( |
( |
( |
Freight & Insurance |
( |
( |
( |
( |
NSR |
|
|
|
|
Operating Costs |
|
|
|
|
Mining Costs - Stoping |
( |
|
|
|
Mining Costs - Development |
( |
|
|
|
Milling costs |
( |
|
|
|
Contingency and Other |
( |
|
|
|
Federal |
( |
|
|
|
|
( |
|
|
|
$/t-milled |
( |
|
|
|
Operating Margin |
|
|
|
|
Capital Costs |
Full LOM |
Pre-Production |
LOM |
|
|
( |
( |
|
|
Process Plant |
( |
( |
( |
|
Contingency and Other |
( |
( |
( |
|
Cash Flow |
|
|
|
|
Pre-Tax NPV |
|
|
|
|
IRR |
|
|
|
|
Payback (years) |
1 |
|
|
|
Sensitivity Analysis
Results of the sensitivity analyses show the project is most sensitive to operating costs and gold price. A
Cautionary Note Regarding Inferred Resources
The discounted cash flows shown above are prepared in compliance with NI 43-101. There is no certainty that the economic results described above will be realized. The Company proceeded to production at the Rodeo project without completion of customary feasibility studies demonstrating the economic viability of the Rodeo project, and may elect to do likewise at the Velardeña Properties. A mine production decision that is made without a feasibility study carries additional potential risks which include, but are not limited to, (i) increased uncertainty as to projected initial and sustaining capital costs and operating costs, rates of production and average grades, and (ii) the inclusion of Inferred Mineral Resources, as defined by NI 43-101 that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be converted to a Mineral Reserve, as defined by NI 43-101. Mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work and economic analysis and internal studies to ensure satisfactory operational conditions and decisions regarding future targeted production.
No mineral reserves have been estimated for either the Rodeo mine or the Velardeña Properties. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The economic model for each of the Rodeo project and the Velardeña Properties is preliminary in nature and includes inferred mineral resources that are too speculative geologically to have economic considerations applied to them that would enable the inferred mineral resources to be classified as mineral reserves, and there is no certainty that the preliminary economic model for the Rodeo project, the Velardeña Properties, or both, will be realized.
About
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended and Section 21E of the Securities Exchange Act of 1934, as amended, and applicable Canadian securities legislation, including statements regarding estimated resources and projected economic analyses associated with the Rodeo mine and the Velardeña Properties. These statements are subject to risks and uncertainties, including changes in interpretations of geological, geostatistical, metallurgical, mining or processing information, and interpretations of the information resulting from exploration, analysis or mining and processing experience.
Qualified Person:
The following Qualified Persons from Tetra Tech will co‐author the technical report that will be filed on SEDAR within 45 days of this news release: Dr.
View source version on businesswire.com: https://www.businesswire.com/news/home/20220322005495/en/
For additional information please visit http://www.goldenminerals.com/ or contact:
(303) 839-5060
Source:
FAQ
What is the pre-tax net present value of the Rodeo project for AUMN?
What are the expected operating costs for the Rodeo mine of AUMN?
How long is the life of mine for the Rodeo project announced by AUMN?
What is the significance of the Technical Reports for AUMN's Velardeña Properties?